City of Brea

Orange County

Verified Aug. 4, 2026

City of Brea is a city authority in the State of California, serving 47,325 residents. 2,500 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Permitting 5 steps · 28 questions

Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — SolarAPP+ track: automated/instant approval upon eligible submittal. No published business-day turnaround was found for the standard (non-SolarAPP+) plan-check track Q18 Where you file — Accela Citizen Access ('Brea Online Permit Center', aca-prod.accela.com/BREA) for permit application/payment/inspection scheduling; Q20

Permit required
Yes95% source
What it costs
$450 flat (Residential Solar App+ Project)95% source
Plan review turnaround
SolarAPP+ track: automated/instant approval upon eligible submittal. No published business-day turnaround was found for the standard (non-SolarAPP+) plan-check track65% source
Key document
checklist (inference) cited by 10 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes 95% · department page
    • What does this authority permit itself, and what does it delegate? Both (Building and Electrical) via the Building & Safety Division; Brea Fire Department separately reviews/permits fire-code items for Photovoltaic and Battery Systems via its own Fire Permit Application 85% · department page + form
    • Is a permit required for a residential rooftop PV system? Yes 95% · ordinance/checklist
    • Is there a separate electrical permit, or is it combined? Combined 80% · portal + fee schedule
    • Is a HOA or architectural approval required first? No city-required architectural/HOA approval found as a permit precondition; CA Solar Rights Act (Civil Code §714) limits HOA authority to restrict solar generally 55% · municipal code (checked absence)
    • Is there a historic-district review? Yes, but only for locally designated historic resources — BMC §20.60 requires plan review for exterior alterations to a 'designated historic resource'; this would apply to solar on a designated property but not to ordinary residential parcels 78% · municipal code
    • Is a wind or windstorm certification required? Not applicable — California does not use a TDI-style windstorm certification; wind design is handled through the locally-amended CRC Table R301.2 (wind speed/exposure figures) as part of the standard structural plan check 55% · municipal code
    • Is a Specific Use Permit or Council approval ever required? Not required for a standard residential rooftop PV system 55% · department page (inference)
    • Is there a system-size cap on residential generation? No system-size cap found; BMC Ch. 20.08 (Development Standards) contains zero mentions of solar or photovoltaic (checked directly against working positive ('setback', 11 hits) and fabricated ('zzqqx', 0 hits) controls), so any residential generation-size limit is not a Brea zoning creation — sizing is governed by state NEM/interconnection rules and by the plan-check structural/lateral-calc thresholds in Q13 68% · municipal code (checked absence)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Either 75% · checklist + form
    • Must the contractor be registered with this authority before applying? Yes 65% · permit form
    • Is a homeowner permitted to self-install and self-permit? Yes, outside the SolarAPP+ track 65% · department page
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Two sets of plans (min. 11x17"), manufacturer spec sheets, installation instructions and UL listings; roof plan on a site plan showing PV equipment/array location & dimensions and 3-ft clearance to ridges/eaves; partial roof framing plan (or waiver if ≤4 ft support spacing); structural/lateral calcs (or waiver under size thresholds); full electrical submittal (one-line diagram, inverter/module cut sheets, array/OCD/wiring info, rapid-shutdown per NEC 690.12, signage, grounding, disconnect location, VOC/ISC calcs) 90% · published checklist
    • How many copies, and in what format? Two (2) sets minimum, sheet size 11" x 17" 90% · published checklist
    • Is a site plan required, and what must it show? Yes — a roof plan projected on a site plan, showing location/dimensions of all PV equipment and arrays and a minimum 3-ft-wide clearance from roof ridges and gable-end eaves for fire department access 90% · published checklist
    • Is a one-line / three-line diagram required? Yes 95% · published checklist
    • Are string and conductor calculations required? Yes 90% · published checklist
    • Is a structural PE stamp required, and at what threshold? Yes, conditionally: a licensed PE or architect must provide lateral calculations (existing lateral elements no more than 10% overstressed per CBC) unless total array area is under 250 sq ft over a second-story roof or 350 sq ft over a first-story roof; framing calcs are waived entirely if array support spacing is 4 ft or less 90% · published checklist
    • Is an electrical PE stamp required, and at what threshold? No PE stamp threshold specified — plans may be signed by the licensed contractor (A/B/C-46/C-10) or by a licensed electrical engineer; no separate PE-stamp trigger for electrical scope is stated 60% · published checklist
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Accela Citizen Access ('Brea Online Permit Center', aca-prod.accela.com/BREA) for permit application/payment/inspection scheduling; SolarAPP+ (gosolarapp.org) for the automated PV plan-review step 95% · portal landing page
    • Can the whole application be completed online? Yes 88% · portal landing page
    • What does a residential solar permit cost? $450 flat (Residential Solar App+ Project) 95% · fee schedule
    • How is the fee calculated? Flat 95% · fee schedule
    • Is there a separate plan-check fee? No separate city plan-check fee for the residential SolarAPP+ track — the $450 appears to be a single all-inclusive fee (unlike other permit types in the same schedule, which are explicitly split into separate 'Plan Check' and 'Inspection' columns); SolarAPP+ itself charges its own external plan-review fee on the SolarAPP+ platform 70% · fee schedule
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? SolarAPP+ track: automated/instant approval upon eligible submittal. No published business-day turnaround was found for the standard (non-SolarAPP+) plan-check track 65% · department page
    • How long is an issued permit valid before it expires? 12 months to commence work from permit issuance (renewable once, without plan changes, for one additional inspection fee); plan check itself expires after 6 months if no permit is issued 82% · department page
    • Which utility handles interconnection here? Southern California Edison (SCE) 68% · city page (indirect)
    • Where does the utility sit in the sequence? After permit / before activation (utility notified for interconnection/PTO after the system is installed, inspected, and prior to activation) 55% · checklist (inference)

28 questions answered against City of Brea’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes

Why the confidence is not higherCity's own Building & Safety Division and Community and Economic Development pages describe issuance of building/electrical permits and performance of inspections for the city, including the dedicated Solar App+ residential PV permitting page.

department page checked 2026-08-30 https://www.cityofbrea.gov/124/Building-Safety-Division

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both (Building and Electrical) via the Building & Safety Division; Brea Fire Department separately reviews/permits fire-code items for Photovoltaic and Battery Systems via its own Fire Permit Application

Why the confidence is not higherSolar-App page + fee schedule show Building & Safety issuing one combined solar/PV permit; the Fire Permit Application (DocumentCenter/17232) has explicit 'Photovoltaic System' and 'Battery System' checkboxes as a separate permit track. Nothing is delegated to the county — Orange County has no role here.

department page + form checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes

Why the confidence is not higherSolar App+ page and the 'Solar Photo-Voltaic System over Single-Family Dwelling' submittal-requirements handout both presuppose a required permit; fee schedule lists a dedicated 'Residential Solar App+ Project' permit fee.

ordinance/checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined

Why the confidence is not higherAccela portal application type is a single 'Residential Solar Permit with SolarAPP' (per the Solar App+ page's step-by-step instructions), and the fee schedule lists one flat 'Residential Solar App+ Project' fee ($450) rather than separate building and electrical fee lines for solar — electrical scope is folded into the one permit.

portal + fee schedule checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either

Why the confidence is not higherThe Solar PV submittal-requirements handout requires plans to be 'signed by State of California licensed contractor with classifications A, B, C-46, C-10, or licensed electrical engineer' (i.e., not electrician-only); separately, the general Electrical Permit Application form includes an 'Owner' checkbox alongside 'Contractor', and the Owner-Builder-Information page describes homeowner self-permitting rights, so a homeowner may also pull the permit outside the SolarAPP+ track.

checklist + form checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes

Why the confidence is not higherThe Electrical Permit Application form has a required 'Brea Business License #' field for the contractor in addition to the state license number field, implying local business registration; the form does not explicitly state this must precede application submission.

permit form checked 2026-08-30 https://cityofbrea.gov/DocumentCenter/View/18985/ELECTRICAL-PERMIT-APPLICATION-2026

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes, outside the SolarAPP+ track

Why the confidence is not higherOwner-Builder-Information page confirms homeowner self-install/self-permit rights under CA Business & Professions Code exemptions, and the Electrical Permit Application form has an 'Owner' applicant option. However, the Solar App+ page is titled 'Licensed Contractors Can Now Submit Through SolarAPP+' — the automated SolarAPP+ route itself appears contractor-only; a self-installing homeowner would use the standard (non-automated) plan-check path instead.

department page checked 2026-08-30 https://www.cityofbrea.gov/129/Owner-Builder-Information

Q8 What documents make up a complete submittal? Core Submittal package

Two sets of plans (min. 11x17"), manufacturer spec sheets, installation instructions and UL listings; roof plan on a site plan showing PV equipment/array location & dimensions and 3-ft clearance to ridges/eaves; partial roof framing plan (or waiver if ≤4 ft support spacing); structural/lateral calcs (or waiver under size thresholds); full electrical submittal (one-line diagram, inverter/module cut sheets, array/OCD/wiring info, rapid-shutdown per NEC 690.12, signage, grounding, disconnect location, VOC/ISC calcs)

Why the confidence is not higherDirectly from the city's own 'Solar Photo-Voltaic System over Single Family Dwelling Submittal Requirements' handout (doc 648), read in full via pdftotext. Document is dated June 2024 and still cites the 2022 CBC/CEC — now superseded by the 2025 cycle (effective 1/1/2026) — so treat the code-edition citations as stale even though the document list itself is likely still current practice.

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q9 How many copies, and in what format? Submittal package

Two (2) sets minimum, sheet size 11" x 17"

Why the confidence is not higherStated as item 1 of the Administrative section of the city's own Solar PV submittal-requirements handout.

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes — a roof plan projected on a site plan, showing location/dimensions of all PV equipment and arrays and a minimum 3-ft-wide clearance from roof ridges and gable-end eaves for fire department access

Why the confidence is not higherDirectly quoted from the city's Solar PV submittal-requirements handout, Roof Plan item 1.

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes

Why the confidence is not higherElectrical submittal guidelines item 2: 'Single Line Diagram: show array configuration, conduit and conductor sizes with de-rating calculations.'

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q12 Are string and conductor calculations required? Drawings & calculations

Yes

Why the confidence is not higherElectrical submittal items 5, 6 and 11 require array/series-parallel configuration, conductor ampacity with de-rating, and VOC/ISC system calculations (VOC x1.13, ISC x1.25 per NEC 690 / UL 1703).

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

Yes, conditionally: a licensed PE or architect must provide lateral calculations (existing lateral elements no more than 10% overstressed per CBC) unless total array area is under 250 sq ft over a second-story roof or 350 sq ft over a first-story roof; framing calcs are waived entirely if array support spacing is 4 ft or less

Why the confidence is not higherDirectly quoted thresholds from the city's own Solar PV submittal-requirements handout, Roof Plan items 2, 4 and 5. Document cites the (now superseded) 2022 CBC; the physical-support-spacing and area thresholds are administrative practice thresholds that are typically carried forward code cycle to code cycle, but this specific citation has not been re-verified against the 2025 CBC text.

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

No PE stamp threshold specified — plans may be signed by the licensed contractor (A/B/C-46/C-10) or by a licensed electrical engineer; no separate PE-stamp trigger for electrical scope is stated

Why the confidence is not higherInferred from item 2 of the Administrative section of the submittal handout, which treats contractor signature and PE/EE signature as equally acceptable with no valuation or size threshold given for electrical (as opposed to the explicit structural thresholds in item 13).

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q15 What does a residential solar permit cost? Core Fees

$450 flat (Residential Solar App+ Project)

Why the confidence is not higherCurrent Development Fees schedule, internally dated (via PDF metadata and 'Updated 07/01/2026' footer stamps) 30 Jun/1 Jul 2026 — the current document, not a stale copy. A separate 'Residential Energy Storage System' line is also $450.

fee schedule checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q16 How is the fee calculated? Core Fees

Flat

Why the confidence is not higherThe 'Solar Permit' table in the current fee schedule lists a single flat 'Cost' per project type (Residential Solar App+ Project, Residential ESS, Non-Residential Solar, Non-Residential ESS) rather than a valuation, per-kW or per-panel formula.

fee schedule checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q17 Is there a separate plan-check fee? Fees

No separate city plan-check fee for the residential SolarAPP+ track — the $450 appears to be a single all-inclusive fee (unlike other permit types in the same schedule, which are explicitly split into separate 'Plan Check' and 'Inspection' columns); SolarAPP+ itself charges its own external plan-review fee on the SolarAPP+ platform

Why the confidence is not higherStructural comparison within the current fee schedule (Solar Permit table has one 'Cost' column, not the Plan Check/Inspection split used elsewhere in the same document) plus the Solar-App page's statement that 'a processing fee ... will be charged by SolarAPP+ for plan review.'

fee schedule checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q18 What is the stated plan-review turnaround? Core Timeline & validity

SolarAPP+ track: automated/instant approval upon eligible submittal. No published business-day turnaround was found for the standard (non-SolarAPP+) plan-check track

Why the confidence is not higherSolar-App page describes SolarAPP+ as instant, code-compliance-checked automated review. The Plan-Check-Requirements page and fee schedule describe plan-check expiration/renewal rules but state no specific turnaround-time figure for standard review; not claiming an absence beyond what these two pages show.

department page checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q19 How long is an issued permit valid before it expires? Timeline & validity

12 months to commence work from permit issuance (renewable once, without plan changes, for one additional inspection fee); plan check itself expires after 6 months if no permit is issued

Why the confidence is not higherGeneral building-permit expiration/plan-check-expiration rule from the Plan Check Requirements page — not solar-specific, but solar permits are processed as standard building/electrical permits and would fall under this same administrative provision.

department page checked 2026-08-30 https://www.cityofbrea.gov/130/Plan-Check-Requirements

Q20 Which permit portal does this authority use? Core Portal & process

Accela Citizen Access ('Brea Online Permit Center', aca-prod.accela.com/BREA) for permit application/payment/inspection scheduling; SolarAPP+ (gosolarapp.org) for the automated PV plan-review step

Why the confidence is not higherBoth platforms and their exact URLs are named and linked directly from the city's own Solar App+ page.

portal landing page checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q21 Can the whole application be completed online? Core Portal & process

Yes

Why the confidence is not higherSolarAPP+ review, Accela permit application/payment, and online inspection scheduling are all described as done online end-to-end on the Solar App+ and Inspections pages; only revision uploads/emails to the division are mentioned as needed in some cases.

portal landing page checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q22 Which utility handles interconnection here? Core Utility interconnection

Southern California Edison (SCE)

Why the confidence is not higherNo dedicated 'who is your electric utility' page was found; the city's own Police Department crime-prevention page is titled 'New Payment Scam Targets SCE Customers' and addresses Brea residents about SCE billing scams, which is city-side evidence naming SCE as serving this community, though it is not a direct utility-territory statement. Checked for a competing CCA (Orange County Power Authority) but could not independently reach OCPA's own member-city list this run to confirm Brea's exclusion, so treat the CCA-absence part as unconfirmed rather than proven.

city page (indirect) checked 2026-08-30 https://www.cityofbrea.gov/348/New-Payment-Scam-Targets-SCE-Customers

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After permit / before activation (utility notified for interconnection/PTO after the system is installed, inspected, and prior to activation)

Why the confidence is not higherInferred from item 12 of the city's own Solar PV submittal-requirements handout: 'All PV equipment shall be listed... and Notify serving utility before activation of PV system' — sequencing implied, not stated as a formal step diagram.

checklist (inference) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No city-required architectural/HOA approval found as a permit precondition; CA Solar Rights Act (Civil Code §714) limits HOA authority to restrict solar generally

Why the confidence is not higherNo Brea ordinance or checklist item requiring HOA/ARC sign-off was found in the Building & Safety pages, submittal checklist, or Development Standards chapter (BMC Ch. 20.08, checked directly with zero 'solar'/'photovoltaic' hits against working positive ('setback', 11 hits) and fabricated ('zzqqx', 0 hits) controls). Answer partly rests on statewide preemption rather than a Brea-specific statement.

municipal code (checked absence) checked 2026-08-30 https://ecode360.com/47194193

Q25 Is there a historic-district review? Overlays & special cases

Yes, but only for locally designated historic resources — BMC §20.60 requires plan review for exterior alterations to a 'designated historic resource'; this would apply to solar on a designated property but not to ordinary residential parcels

Why the confidence is not higherRead directly from BMC Chapter 20.60 (Historic Preservation) via eCode360: 'Exterior alterations, including but not limited to restoration, rehabilitation, remodeling, additions, demolition, relocation, or subdivision of a designated historic resource shall require a plan review...' No solar-specific carve-out or requirement was found in this chapter (0 'solar'/'photovoltaic' hits, with 'historic' appearing 57 times as a working positive control).

municipal code checked 2026-08-30 https://ecode360.com/47195508

Q26 Is a wind or windstorm certification required? Overlays & special cases

Not applicable — California does not use a TDI-style windstorm certification; wind design is handled through the locally-amended CRC Table R301.2 (wind speed/exposure figures) as part of the standard structural plan check

Why the confidence is not higherBMC §15.10.020 (2025 California Residential Code — Amendments) amends Table R301.2, the wind-design-criteria table, in place of any separate windstorm certificate; no separate certification requirement was found.

municipal code checked 2026-08-30 https://ecode360.com/47190200

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Not required for a standard residential rooftop PV system

Why the confidence is not higherNo CUP/Council-approval trigger for residential rooftop PV was found in the Solar App+ materials, the Building & Safety pages, or the Development Standards chapter (BMC Ch. 20.08, checked with controls per Q24). The Fire Protection Review page describes CUP/Variance/Zone Change as part of the general new-development process, not as a solar-specific trigger.

department page (inference) checked 2026-08-30 https://www.cityofbrea.gov/157/Fire-Protection-Review

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No system-size cap found; BMC Ch. 20.08 (Development Standards) contains zero mentions of solar or photovoltaic (checked directly against working positive ('setback', 11 hits) and fabricated ('zzqqx', 0 hits) controls), so any residential generation-size limit is not a Brea zoning creation — sizing is governed by state NEM/interconnection rules and by the plan-check structural/lateral-calc thresholds in Q13

Why the confidence is not higherDirect absence check of the zoning chapter most likely to hold a size cap, with controls proving the search itself was working.

municipal code (checked absence) checked 2026-08-30 https://ecode360.com/47194193

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? 2023 NEC (as the basis for the 2025 California Electrical Code) 95% · adopting ordinance
    • Which building code edition is in force? 2025 California Building Code (based on the 2024 IBC) and 2025 California Residential Code (based on the 2024 IRC), effective 1 Jan 2026 95% · adopting ordinance
    • Which fire code edition is in force? 2025 California Fire Code (based on the 2024 IFC), plus the 2025 California Wildland-Urban Interface Code, effective 1 Jan 2026 92% · adopting ordinance
    • Are there local amendments to any of the above? Yes for Building and Residential Code (e.g., amended §105.2 permit-exemption list, amended Table R301.2 wind/seismic table) and for the Fire Code (local amendment chapters covering IFC/CFC Chapters 1,2,3,4,5,9,11,56,57 and 80); No current local amendments to the Electrical Code — BMC §15.12.020 is explicitly '[Reserved for future amendments]' 90% · adopting ordinance
    • What is the installation judged against? The 2025 California Electrical Code (2023 NEC basis) for electrical work and the 2025 CBC/CRC for structural work, per BMC Ch.15; the city's own Solar PV submittal handout still directs plan preparers to the superseded 2022 CBC/CEC — an internal contradiction between the current adopting ordinance and the still-linked 2024-dated solar checklist that installers should be aware of 80% · ordinance + checklist (contradiction noted)
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    • What ridge setback and access pathways are required? Minimum 3-ft-wide clearance path between PV arrays and roof ridges and gable-end eaves for fire department access 82% · published checklist
  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Yes, rapid shutdown is required per NEC 690.12; the currently adopted edition is the 2023 NEC (via the 2025 California Electrical Code, effective 1/1/2026) 82% · ordinance (current) vs. stale checklist (flagged)
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? NEC Art. 690 system labels/warnings at service equipment and disconnects, plus a PV roof-layout placard mounted at/on the electrical panel 78% · policy/checklist
    • Does the authority specify placard wording of its own? No 72% · published checklist (checked absence)
    • Does it specify letter height, colour or material? No Brea-specific letter height, color or material specification found — the handout only cross-references NEC/CEC Article 690's own default labeling requirements 55% · published checklist (checked absence)
    • Is a site plan / facility map placard required, and what must it show? Yes — a PV roof-layout placard must be mounted on/at the electrical panel showing the as-built array layout; inspectors check re-installed panels against this placard at final 88% · policy document
    • Where must the labels be placed? At the electrical/service panel (roof-layout placard) and at the AC/DC disconnects and PV system service equipment per NEC Article 690 72% · checklist + policy
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Must equipment be on a specific approved list? Yes 85% · published checklist
    • Are batteries permitted, and under what conditions? Yes, batteries/ESS are permitted (a dedicated 'Residential Energy Storage System' permit fee exists); no Brea-specific amendment to the Fire Code's Energy Systems chapter was found, so ESS conditions follow the unamended 2025 CFC/2024 IFC provisions 68% · fee schedule + ordinance
    • Is there a separate ESS permit or inspection? Yes 80% · fee schedule
    • Is there a local rule on service upgrades or busbar sizing? No local rule found — BMC §15.12.020 (Electrical Code Amendments) is explicitly reserved with no amendments, so service-upgrade/busbar sizing follows the unamended 2023 NEC (e.g., §705.12) with no Brea-specific overlay 82% · adopting ordinance (checked absence)
    • Is a specific mounting system or attachment spacing required? No fixed universal mounting-spacing mandate, but the submittal-review shortcut (skipping framing/lateral calculations) is only available if the array attachment spacing is 4 ft or less 75% · published checklist

20 questions answered against City of Brea’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2023 NEC (as the basis for the 2025 California Electrical Code)

Why the confidence is not higherBMC §15.12.010, adopted by Ord. 1264 (9/16/2025): 'the 2025 California Electrical Code, based on the 2023 National Electrical Code ... is hereby adopted in its entirety.' The city's Building Code Requirements page independently confirms this same 2023-NEC basis, effective 1/1/2026. Note: the city's own June-2024 Solar PV submittal handout still cites the superseded '2022 California Electric Code' — flagged as stale, not used as the answer here.

adopting ordinance checked 2026-08-30 https://ecode360.com/47190203

Q30 Which building code edition is in force? Core Code editions in force

2025 California Building Code (based on the 2024 IBC) and 2025 California Residential Code (based on the 2024 IRC), effective 1 Jan 2026

Why the confidence is not higherBMC §15.08.010 and §15.10.010, adopted by Ord. 1264 (9/16/2025); corroborated by the city's own Building Code Requirements announcement page.

adopting ordinance checked 2026-08-30 https://ecode360.com/47190197

Q31 Which fire code edition is in force? Code editions in force

2025 California Fire Code (based on the 2024 IFC), plus the 2025 California Wildland-Urban Interface Code, effective 1 Jan 2026

Why the confidence is not higherBMC Ch. 16.04 (Brea Fire Code) text read directly via eCode360: 'The 2025 Editions of the California Wildland-Urban Interface Code and the California Fire Code including Appendices... are hereby adopted by reference,' enforced by the Brea Fire Department.

adopting ordinance checked 2026-08-30 https://ecode360.com/47191620

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes for Building and Residential Code (e.g., amended §105.2 permit-exemption list, amended Table R301.2 wind/seismic table) and for the Fire Code (local amendment chapters covering IFC/CFC Chapters 1,2,3,4,5,9,11,56,57 and 80); No current local amendments to the Electrical Code — BMC §15.12.020 is explicitly '[Reserved for future amendments]'

Why the confidence is not higherRead directly from the BMC Title 15/16 chapter pages on eCode360; the Electrical Code amendment section is empty by its own text, a genuine documented absence rather than an unsearched gap.

adopting ordinance checked 2026-08-30 https://ecode360.com/47190203

Q33 What is the installation judged against? Core Electrical

The 2025 California Electrical Code (2023 NEC basis) for electrical work and the 2025 CBC/CRC for structural work, per BMC Ch.15; the city's own Solar PV submittal handout still directs plan preparers to the superseded 2022 CBC/CEC — an internal contradiction between the current adopting ordinance and the still-linked 2024-dated solar checklist that installers should be aware of

Why the confidence is not higherCombines the current ordinance text (Ord. 1264, 9/16/2025) with the still-published Solar PV handout (doc 648, created June 2024) which was not updated for the 2025 code cycle — flagging rather than resolving the contradiction per instructions.

ordinance + checklist (contradiction noted) checked 2026-08-30 https://ecode360.com/47190203

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

No local rule found — BMC §15.12.020 (Electrical Code Amendments) is explicitly reserved with no amendments, so service-upgrade/busbar sizing follows the unamended 2023 NEC (e.g., §705.12) with no Brea-specific overlay

Why the confidence is not higherDirectly read from the current Electrical Code chapter, which has no amendment text at all beyond the placeholder 'Reserved for future amendments.'

adopting ordinance (checked absence) checked 2026-08-30 https://ecode360.com/47190203

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

No fixed universal mounting-spacing mandate, but the submittal-review shortcut (skipping framing/lateral calculations) is only available if the array attachment spacing is 4 ft or less

Why the confidence is not higherSolar PV submittal-requirements handout, Roof Plan items 2 and 4 ('ALTERNATE: Framing information is not required if arrays are supported at a maximum spacing of 4 ft').

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Minimum 3-ft-wide clearance path between PV arrays and roof ridges and gable-end eaves for fire department access

Why the confidence is not higherDirectly quoted from the city's own Solar PV submittal-requirements handout (Roof Plan item 1); matches the statewide CRC/CFC pathway standard that has been stable across recent code cycles, though this specific document itself still cites the superseded 2022 code cycle.

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes, rapid shutdown is required per NEC 690.12; the currently adopted edition is the 2023 NEC (via the 2025 California Electrical Code, effective 1/1/2026)

Why the confidence is not higherThe current adopting ordinance (BMC §15.12.010) sets the 2023-NEC basis; however the city's own solar submittal handout (item 7 of the Electrical Submittal Guidelines) still cites 'Rapid Shut-down per 2022 California Electric Code 690.12' — a stale reference from before the 2025 code cycle took effect. Used the current ordinance, not the stale handout, for the edition in this answer, and flagged the contradiction.

ordinance (current) vs. stale checklist (flagged) checked 2026-08-30 https://ecode360.com/47190203

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

NEC Art. 690 system labels/warnings at service equipment and disconnects, plus a PV roof-layout placard mounted at/on the electrical panel

Why the confidence is not higherCombines the Solar PV submittal handout item 8 ('System Labels and Warnings: show required signage on the plans per ... CEC-Article 690') with the Solar PV Re-roofing Policy (dated March 2026), which explicitly requires a 'PV roof layout placard mounted on the electrical panel' that the final inspector checks against.

policy/checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/18906/Solar-PV-Re-roofing-Policy

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No

Why the confidence is not higherThe submittal handout only instructs applicants to 'show required signage on the plans per [California Electrical Code]-Article 690' — it defers to the adopted NEC's own labeling language rather than prescribing Brea-specific wording.

published checklist (checked absence) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

No Brea-specific letter height, color or material specification found — the handout only cross-references NEC/CEC Article 690's own default labeling requirements

Why the confidence is not higherThe only signage instruction in the city's own submittal handout is the one-line cross-reference to CEC Article 690, with no additional detail on letter height/color/material of Brea's own.

published checklist (checked absence) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Yes — a PV roof-layout placard must be mounted on/at the electrical panel showing the as-built array layout; inspectors check re-installed panels against this placard at final

Why the confidence is not higherDirectly stated in the Solar PV Re-roofing Policy (dated March 2026, per internal PDF timestamp), which describes the final inspector verifying 'the PV panels have been re-installed in the same location as shown on the PV roof layout placard mounted on the electrical panel.'

policy document checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/18906/Solar-PV-Re-roofing-Policy

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedSearched for SCE's DG/Rule 21 interconnection handbook and generic requirements pages to check for placard requirements beyond the AHJ's; the commonly-cited on.sce.com/interconnectionhandbook redirects to sce.com's generic homepage (302) and the direct sce.com business interconnections page 404s (confirmed live via curl this run)

https://on.sce.com/interconnectionhandbook

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the electrical/service panel (roof-layout placard) and at the AC/DC disconnects and PV system service equipment per NEC Article 690

Why the confidence is not higherCombines the Re-roofing Policy's electrical-panel placard requirement with submittal handout items 8 and 10 (disconnect labeling/location requirements per CEC Article 690).

checklist + policy checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q44 Must equipment be on a specific approved list? Equipment listing

Yes

Why the confidence is not higherSubmittal handout item 12: 'All PV equipment shall be listed by a recognized test lab ... before activation of PV system.'

published checklist checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes, batteries/ESS are permitted (a dedicated 'Residential Energy Storage System' permit fee exists); no Brea-specific amendment to the Fire Code's Energy Systems chapter was found, so ESS conditions follow the unamended 2025 CFC/2024 IFC provisions

Why the confidence is not higherFee schedule lists 'Residential Energy Storage System — $450' as its own line; BMC Ch.16.04's list of locally-amended IFC/CFC chapters (1,2,3,4,5,9,11,56,57,80) does not include an Energy Systems chapter amendment, implying the state-default ESS provisions apply without local modification — a checked, not assumed, absence.

fee schedule + ordinance checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Yes

Why the confidence is not higherFee schedule lists 'Residential Energy Storage System' as a distinct $450 line item separate from the 'Residential Solar App+ Project' line; separately, the Fire Department's own Fire Permit Application has a distinct 'Battery System' checkbox separate from 'Photovoltaic System.'

fee schedule checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q47 Is a ground mount treated as a structure? Core Ground mount

Nothing published by this authority.

Where we lookedBMC Ch. 20.08 (Development Standards) checked directly with a working positive control ('setback', 11 hits) and fabricated control ('zzqqx', 0 hits) — zero 'solar'/'photovoltaic'/'ground mount' hits, so no explicit zoning classification of a ground-mounted PV array as a 'structure' was found; also checked the Solar PV submittal handout (doc 648), which addresses roof-mounted systems only and is silent on ground mounts

https://ecode360.com/47194193

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Nothing published by this authority.

Where we lookedSame SCE interconnection documentation search as Q42 — no reachable SCE document found stating AC-disconnect-to-meter placement; Brea's own Building & Safety materials do not address this utility-side spec

https://www.sce.com/business/generating-your-own-power/interconnections

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal 88% · department page
    • How much notice is required? Requests made before 12:00 p.m. are considered for next-business-day inspection (approx. 1 business day notice); current stated turnaround is 'typically twenty-four (24) hours' 85% · department page
    • Are same-day or AM/PM windows offered? AM/PM windows are offered (AM 8:00 a.m.-12:30 p.m.; PM 1:00 p.m.-4:00 p.m.); not a guaranteed exact time 90% · department page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes 88% · department page
    • If delegated, to whom? N/A — not delegated; Building & Safety Division performs its own final inspection 85% · department page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? Not fully documented for a standalone new installation; the closest published sequence (from the re-roof-with-existing-PV policy) is: (1) rack-anchor/rough inspection to confirm structural attachment, then (2) final inspection of all completed components 55% · policy document (adjacent scenario)
    • Is a rough-in or mid-roof inspection required? Yes, in the re-roof/modification scenario ('an initial inspection of the rack anchors is required to ensure they are properly attached to structural framing members'); not confirmed as a requirement for a standalone new install 55% · policy document
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

14 questions answered against City of Brea’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal

Why the confidence is not higherInspections page: 'Online through the permit center' with an 'Online scheduling guide,' cancellations by phone only as an exception path.

department page checked 2026-08-30 https://www.cityofbrea.gov/136/Inspections

Q50 How much notice is required? Core Booking & scheduling

Requests made before 12:00 p.m. are considered for next-business-day inspection (approx. 1 business day notice); current stated turnaround is 'typically twenty-four (24) hours'

Why the confidence is not higherDirectly quoted from the Inspections page.

department page checked 2026-08-30 https://www.cityofbrea.gov/136/Inspections

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

AM/PM windows are offered (AM 8:00 a.m.-12:30 p.m.; PM 1:00 p.m.-4:00 p.m.); not a guaranteed exact time

Why the confidence is not higherDirectly quoted from the Inspections page.

department page checked 2026-08-30 https://www.cityofbrea.gov/136/Inspections

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes

Why the confidence is not higherSolar App+ page Step 3 ('Schedule Your Inspection') routes through the city's own Online Permit Center/Building & Safety Division, with no mention of a delegated third-party inspector for the residential solar track.

department page checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q53 If delegated, to whom? Core Who inspects

N/A — not delegated; Building & Safety Division performs its own final inspection

Why the confidence is not higherSame source as Q52; no third-party or state inspector is referenced for the standard residential solar permit workflow.

department page checked 2026-08-30 https://www.cityofbrea.gov/1796/Solar-App

Q54 Which inspections are required, and in what order? Core Stages & sequence

Not fully documented for a standalone new installation; the closest published sequence (from the re-roof-with-existing-PV policy) is: (1) rack-anchor/rough inspection to confirm structural attachment, then (2) final inspection of all completed components

Why the confidence is not higherThis exact two-stage sequence is explicitly documented only for the re-roof/PV-modification scenario in the Solar PV Re-roofing Policy; no separate published sequence was found for a brand-new (non-reroof) residential PV install, so this is an inference carried over from an adjacent city document, held to lower confidence.

policy document (adjacent scenario) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/18906/Solar-PV-Re-roofing-Policy

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Yes, in the re-roof/modification scenario ('an initial inspection of the rack anchors is required to ensure they are properly attached to structural framing members'); not confirmed as a requirement for a standalone new install

Why the confidence is not higherSame Re-roofing Policy source as Q54; explicit only for that scenario.

policy document checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/18906/Solar-PV-Re-roofing-Policy

Q56 Does the inspector verify labels and listings? Core What is checked

Yes (by inference)

Why the confidence is not higherThe submittal handout requires equipment to be listed by a recognized test lab and requires code-compliant labeling per NEC Art. 690 (items 8 and 12); building final inspections routinely verify listing labels as standard practice, but no published inspection checklist explicitly states this as a checked item.

checklist (inference) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Q57 Is there a published inspection checklist? Core What is checked

Nothing published by this authority.

Where we lookedInspections page (cityofbrea.gov/136) and its linked documents (online scheduling guide, special inspectors list) — no solar-specific published inspection checklist was found distinct from the plan-submittal checklist in doc 648

https://www.cityofbrea.gov/136/Inspections

Q58 What must be on site at inspection? Core Documents on site

Nothing published by this authority.

Where we lookedInspections page and Solar App+ page — neither states what must physically be on site (approved plans, permit card, equipment labels) at the time of a solar inspection

https://www.cityofbrea.gov/136/Inspections

Q59 Is there a re-inspection fee? Corrections & re-inspection

$146/hour (Callback Building Inspections/Re-Inspection rate)

Why the confidence is not higherSolar permits have no dedicated re-inspection line in the current fee schedule; the general Building & Safety 'Callback Building Inspections/Re-Inspection' hourly rate is the applicable published rate for any building permit type including solar.

fee schedule (general rate) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/13483/Development-Processing-Fees---UPDATED-03012026

Q60 How are corrections issued and cleared? Corrections & re-inspection

Nothing published by this authority.

Where we lookedInspections page, Plan-Check-Requirements page, and Solar App+ revisions section — the Solar App+ page describes how SolarAPP+ plan revisions are handled, but no general 'corrections' notice/clearance process for a failed field inspection was documented

https://www.cityofbrea.gov/130/Plan-Check-Requirements

Q61 What is issued on pass? Core Final sign-off & PTO

Final (permit 'finaled')

Why the confidence is not higherThe Solar PV Re-roofing Policy uses 'finaled' language ('the contractor is responsible for scheduling the required inspections and ensuring the permit is "finaled"') consistent with a Final inspection sign-off rather than a new Certificate of Occupancy for an existing single-family dwelling.

policy document checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/18906/Solar-PV-Re-roofing-Policy

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer

Why the confidence is not higherSubmittal handout item 12 instructs the applicant/installer preparing the plans to 'Notify serving utility before activation of PV system' — phrased as an installer responsibility, not an AHJ action; not an explicit statement of who submits SCE's PTO/interconnection paperwork.

checklist (inference) checked 2026-08-30 https://www.cityofbrea.gov/DocumentCenter/View/648

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Jurisdiction & key facts

The standing 62-question set, answered for City of Brea against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

City of Brea is the authority having jurisdiction 92% confidence
Holds
Building and Electrical (Building & Safety Division, within the Community and Economic Development Department) for the construction/electrical permit; Brea Fire Department separately reviews/permits fire-code items — its own Fire Permit Application has explicit checkboxes for 'Photovoltaic System' and 'Battery System', run alongside (not instead of) the Building & Safety permit
Overridden by
State law only: CA Solar Rights Act (Civil Code §714/§4600) limits HOA/architectural restriction of solar; Gov. Code §65850.52 (SolarAPP+ mandate) and AB 130 (Stats. 2025 Ch. 22, freezing more-restrictive local residential amendments 1 Oct 2025-1 Jun 2031) both constrain what Brea may add locally. No other agency claims building/electrical jurisdiction.
Why not higher
The city's own Community and Economic Development page states the department 'issues all building, planning and public works permits' and performs 'building inspections', and its Building & Safety Division page confirms Building & Safety sits under Community and Economic Development (not Public Works, and not a bare 'Community Development' decoy — this is the real, active building department, corroborated by the SolarAPP+ page's identical breadcrumb and by the Development Fees schedule cover page listing 'BUILDING & SAFETY / ECONOMIC DEVELOPMENT / HOUSING / PLANNING / PUBLIC WORKS / BREA FIRE' as the departments covered). Note: two of the city's own PDF forms (Electrical Permit Application, and BMC §3.32.035 cited in the fee schedule) still use the older label 'Community Development Department' / 'Community Development Director' — an internal naming inconsistency, not a different department. Brea runs its OWN fire department: confirmed both directions — Brea Municipal Code §16.04 names the 'Brea Fire Department' as the enforcing agency for the adopted California Fire Code, AND Brea is absent (0 hits, word-boundary-checked, with 'Tustin' as a working positive control returning 7 hits) from OCFA's own live Member Cities page at ocfa.org/about-us/member-cities/ — so Brea is not an OCFA member.

https://www.cityofbrea.gov/122/Community-and-Economic-Development

Permit required
Yes95%
Permit cost
$450 flat (Residential Solar App+ Project)95%
Plan review
SolarAPP+ track: automated/instant approval upon eligible submittal. No published business-day turnaround was found for the standard (non-SolarAPP+) plan-check track65%
Portal
Accela Citizen Access ('Brea Online Permit Center', aca-prod.accela.com/BREA) for permit application/payment/inspection scheduling;95%
Electrical code
2023 NEC (as the basis for the 2025 California Electrical Code)95%
Own placard wording
No72%
Booking an inspection
Portal88%
Labels & placards for this authority

Wording 72%

No

Size, colour & material 55%

No Brea-specific letter height, color or material specification found — the handout only cross-references NEC/CEC Article 690's own default labeling requirements

Where they go 72%

At the electrical/service panel (roof-layout placard) and at the AC/DC disconnects and PV system service equipment per NEC Article 690

What the utility wants on top None%

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
City
County
Orange County
Regions served
1
Regions covered
City of Brea · city
Solar Requirements
Separate fire inspection
Building & Safety Division | Brea, CA - Official Website Skip to Main Content Art Gallery Curtis Theatre Fitness Center Fire Department Police Department /QuickLinks.aspx Search Home City Services Community and Economic Development Building & Safety Division Building & Safety Division Please contact
Authority Contact
Address
1 Civic Center Circle, Brea, CA 92821
Main Phone
(714) 990-7600
Building Department
Department
Building & Safety Division
Direct Phone
(714) 990-7600
Portal Software
Accela
Booking & Scheduling
Preferred channel
online_portal
Book in advance
1
Notes
Uses Accela online permit center for permit applications, payments, status checks, and inspection scheduling (24/7). Solar PV: eligible residential rooftop systems can use SolarAPP+ (https://gosolarapp.org/) for instant automated permitting; after SolarAPP+ approval number is obtained, contractor applies through Accela portal with the SolarAPP+ documents, then schedules inspection via Accela. Non-eligible solar projects follow standard plan check through Accela. Inspections run Mon-Fri (excluding holidays); requests before noon considered for next-day. AM slot 8am-12:30pm, PM slot 1pm-4pm. Inspection schedule posted at 5pm for next working day. Front counter hours: 8am-5pm Mon-Thu and alternate Fridays.