City of Burbank
Los Angeles County
City of Burbank is a city authority in the State of California, serving 107,337 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Same day to a few days for Symbium instant permits (issued in real time); the state 'small residential rooftop solar' ordinance requires the checklist-based… Q18 Where you file — Burbank Online Permits (BOP) for issuance/payment/inspections; Symbium for the instant residential solar permit application itself; Q20
- Permit required
- Yes95% source
- What it costs
- $308.24 flat (Residential Photovoltaic System, electrical permit fee)85% source
- Plan review turnaround
- Same day to a few days for Symbium instant permits (issued in real time); the state 'small residential rooftop solar' ordinance requires the checklist-based application be processed for…75% source
- Key document
- department page + utility FAQ cited by 6 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- What does this authority permit itself, and what does it delegate? Both 90% · department page
- Is a permit required for a residential rooftop PV system? Yes 95% · department page
- Is there a separate electrical permit, or is it combined? Combined 75% · fee schedule + permit log
- Is a HOA or architectural approval required first? No -- HOA/architectural approval is not a City permitting precondition; the local ordinance's definition of a qualifying small system explicitly cross-references Civil Code Section 714 (the CA Solar Rights Act, which bars HOA denial of solar). 65% · ordinance
- Is there a system-size cap on residential generation? No zoning-based system-size cap found in Title 9; the effective cap for the Symbium instant-permit track is 38.4kW (program eligibility, not a legal ceiling), and BWP separately caps net-billing eligibility at 150% of the customer's trailing 12-month energy use for systems interconnecting after 1 Jan 2026. 75% · department page + utility FAQ
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Licensed electrician 70% · adopting ordinance (Title 9 admin code)
- Must the contractor be registered with this authority before applying? No dedicated solar-contractor registry, but out-of-town contractors must register for Burbank business tax before permitting 60% · department page
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? For the Symbium instant residential permit: address, system size, equipment make/model entered into Symbium's online tool plus the BWP Solar Confirmation Number obtained from BWP first; for traditional (Tier 2 / commercial) review, a full plan set is required through ProjectDox. 55% · department page
- Is a site plan required, and what must it show? For the BWP Confirmation of Electric Service, a full set of solar PV plans (including a single-line diagram) must be emailed to BWP's Electric Service Planner before a Confirmation of Electric Service is issued; BWP schedules a site visit to verify the meter/backyard access. 70% · utility form/instructions
- Is a one-line / three-line diagram required? Yes for BWP's Confirmation of Electric Service review ('sample solar single line drawing' referenced); for the Symbium instant permit itself no separate uploaded one-line is described on the city's page. 60% · utility form
- Is a structural PE stamp required, and at what threshold? Structural review is required but no PE-stamp threshold is stated; for the state-defined 'small residential rooftop solar energy system' (<=10kW AC / 30kW thermal, single/duplex family), the applicant need only verify structural adequacy 'through standard engineering evaluation techniques' before submittal -- no PE stamp is mandated by the local ordinance text itself. 75% · ordinance (BMC 9-1-3-80.99)
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? Burbank Online Permits (BOP) for issuance/payment/inspections; Symbium for the instant residential solar permit application itself; ProjectDox for Tier 2/commercial plan check. 90% · portal landing page
- Can the whole application be completed online? Yes, for qualifying single-family systems (<=38.4kW) via Symbium -- 'permit applications submitted using Symbium will be issued in real time.' 90% · department page
- What does a residential solar permit cost? $308.24 flat (Residential Photovoltaic System, electrical permit fee) 85% · fee schedule
- How is the fee calculated? Flat 85% · fee schedule
- Is there a separate plan-check fee? No separate line item for residential PV plan check (unlike Energy Storage System and EV Charger, which list Permit Fee + Plan Check Fee separately); the $308.24 appears to be an all-in electrical permit fee for instant/Tier-1 residential PV. 60% · fee schedule
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? Same day to a few days for Symbium instant permits (issued in real time); the state 'small residential rooftop solar' ordinance requires the checklist-based application be processed for expedited/administrative approval; BWP's own Confirmation of Electric Service review (a precondition to permitting) is separately quoted at 4-7 business days. 75% · monthly permit log (city's own data)
- How long is an issued permit valid before it expires? 365 days from date of application for residential occupancies (per AB 2913); work must otherwise commence within 180 days of issuance or the permit expires. 90% · adopting ordinance
- Which utility handles interconnection here? Burbank Water and Power (BWP) -- a municipally owned utility, not an investor-owned utility. PowerToChoose-style third-party utility lookups would be wrong here; confirmed directly from the city's and utility's own pages. 95% · utility's own page
- Where does the utility sit in the sequence? Before permit 95% · department page
28 questions answered against City of Burbank’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Nothing published by this authority.
Where we lookedCommunity Development / Building & Safety and Solar pages state the City issues permits, but no explicit 'AHJ statement' sentence was found; answered under jurisdiction.is_ahj instead based on the totality of the permitting-page evidence.
https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherCity of Burbank Community Development, Building & Safety Division issues the single BS-series permit covering both building and electrical for solar; Burbank Water and Power (a municipal utility) separately controls interconnection, but that is a utility gate, not a permit delegation.
department page checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherSolar page and BWP installer instructions both state a building permit is required for any solar installation in Burbank.
department page checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Combined
Why the confidence is not higherSolar PV is processed as a single Building & Safety (BS-number) permit; the fee schedule lists 'Residential Photovoltaic System' as one line item under the Electrical Permit fee section, and the monthly permit log shows one BS permit number per install with no separate paired electrical permit number.
fee schedule + permit log checked 2026-08-30 https://web.archive.org/web/20260418010847/https://www.burbankca.gov/documents/d/community-development/2026-feb-spv
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Licensed electrician
Why the confidence is not higherTitle 9 admin code: 'No permit shall be issued to any person doing any work regulated by the California Building Code except to a person holding a valid, unexpired and unrevoked State license to do such work' (9-1-1-105.6). Applies to the electrical trade generally; homeowner/owner-builder exception exists under state law but is not spelled out solar-specific here.
adopting ordinance (Title 9 admin code) checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
No dedicated solar-contractor registry, but out-of-town contractors must register for Burbank business tax before permitting
Why the confidence is not higherBuilding Permit Applications page lists a 'Contractor's Business Tax (For out-of-town contractors)' authorization form as part of the permit packet; no separate solar-specific contractor registration list was found.
department page checked 2026-08-30 https://web.archive.org/web/20260418004315/https://www.burbankca.gov/web/community-development/building-permit-applications
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Nothing published by this authority.
Where we lookedBuilding Permit Applications page (Residential Permit Application form listing) and Title 9 admin code Section 9-1-1-105.6 (contractor licensing); no explicit owner-builder self-permit statement for solar specifically was found, only the general state-licensee permit-issuance rule.
Q8 What documents make up a complete submittal? Core Submittal package
For the Symbium instant residential permit: address, system size, equipment make/model entered into Symbium's online tool plus the BWP Solar Confirmation Number obtained from BWP first; for traditional (Tier 2 / commercial) review, a full plan set is required through ProjectDox.
Why the confidence is not higherSymbium generates the ready-to-issue permit from data entry rather than uploaded plan sheets for qualifying systems (<=38.4kW, single-family); the exact data fields Symbium requires are not published in full detail on burbankca.gov, only the workflow steps.
department page checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q9 How many copies, and in what format? Submittal package
Nothing published by this authority.
Where we lookedBuilding Permit Applications page and Solar Online Permit page; Symbium is a fully digital workflow so 'copies and format' language (common to paper-plan-check cities) does not appear to apply, but no explicit statement of digital file format/quantity requirements was found.
https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q10 Is a site plan required, and what must it show? Core Submittal package
For the BWP Confirmation of Electric Service, a full set of solar PV plans (including a single-line diagram) must be emailed to BWP's Electric Service Planner before a Confirmation of Electric Service is issued; BWP schedules a site visit to verify the meter/backyard access.
Why the confidence is not higherBWP's Confirmation of Electric Service form states plans are reviewed and a site visit is scheduled; it does not itemize every sheet required in a site plan.
utility form/instructions checked 2026-08-30 https://www.burbankwaterandpower.com/documents/d/guest/BWP-ConfirmationOfElectricServices-Solar-07-21-23
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Yes for BWP's Confirmation of Electric Service review ('sample solar single line drawing' referenced); for the Symbium instant permit itself no separate uploaded one-line is described on the city's page.
Why the confidence is not higherBWP's form explicitly references a solar single-line drawing attachment; Burbank's own solar permit page does not describe Symbium's internal document requirements in detail.
utility form checked 2026-08-30 https://www.burbankwaterandpower.com/documents/d/guest/BWP-ConfirmationOfElectricServices-Solar-07-21-23
Q12 Are string and conductor calculations required? Drawings & calculations
Nothing published by this authority.
Where we lookedBMC 9-1-3-80.99 (small residential solar ordinance) and BWP's Confirmation of Electric Service form; neither explicitly requires string/conductor calculations as a named submittal item.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Structural review is required but no PE-stamp threshold is stated; for the state-defined 'small residential rooftop solar energy system' (<=10kW AC / 30kW thermal, single/duplex family), the applicant need only verify structural adequacy 'through standard engineering evaluation techniques' before submittal -- no PE stamp is mandated by the local ordinance text itself.
Why the confidence is not higherMunicipal Code 9-1-3-80.99(D)(1) sets this out; it does not use the words 'PE stamp,' so whether Symbium or plan check independently demands a stamp above some size was not found.
ordinance (BMC 9-1-3-80.99) checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Nothing published by this authority.
Where we lookedBMC Title 9 Article 3 (California Electrical Code, adopted without local amendments) and Article 1 (Building Administrative Standards); no electrical PE-stamp threshold specific to solar was found.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q15 What does a residential solar permit cost? Core Fees
$308.24 flat (Residential Photovoltaic System, electrical permit fee)
Why the confidence is not higherFY2025-26 Citywide Fee Schedule, Building Division Electrical Permit fee table, item (K) 'Residential Photovoltaic System' = $308.24 each. Document is titled 'PROPOSED' on its cover page though the URL slug says 'final'; could not independently confirm Council adoption date, so this may be superseded.
fee schedule checked 2026-08-30 https://web.archive.org/web/20250716111356/https://www.burbankca.gov/documents/d/financial-services/proposed-fy-2025-26-fee-schedule-final
Q16 How is the fee calculated? Core Fees
Flat
Why the confidence is not higherFee schedule lists a single flat 'Each' amount ($308.24) for Residential Photovoltaic System, not tiered by valuation, kW, or panel count.
fee schedule checked 2026-08-30 https://web.archive.org/web/20250716111356/https://www.burbankca.gov/documents/d/financial-services/proposed-fy-2025-26-fee-schedule-final
Q17 Is there a separate plan-check fee? Fees
No separate line item for residential PV plan check (unlike Energy Storage System and EV Charger, which list Permit Fee + Plan Check Fee separately); the $308.24 appears to be an all-in electrical permit fee for instant/Tier-1 residential PV.
Why the confidence is not higherAdjacent fee-schedule rows (L) ESS and (M) EV Charger explicitly split Permit Fee and Plan Check Fee, but (K) Residential PV lists only one amount -- inferred rather than stated outright that no separate PV plan-check fee exists.
fee schedule checked 2026-08-30 https://web.archive.org/web/20250716111356/https://www.burbankca.gov/documents/d/financial-services/proposed-fy-2025-26-fee-schedule-final
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Same day to a few days for Symbium instant permits (issued in real time); the state 'small residential rooftop solar' ordinance requires the checklist-based application be processed for expedited/administrative approval; BWP's own Confirmation of Electric Service review (a precondition to permitting) is separately quoted at 4-7 business days.
Why the confidence is not higherThe Feb-2026 solar permit log shows numerous permits with Applied date = Issued date the same day via Symbium; BWP's own stated average for its pre-permit step is 4-7 business days, which sits outside and before the city's own review clock.
monthly permit log (city's own data) checked 2026-08-30 https://web.archive.org/web/20260418010847/https://www.burbankca.gov/documents/d/community-development/2026-feb-spv
Q19 How long is an issued permit valid before it expires? Timeline & validity
365 days from date of application for residential occupancies (per AB 2913); work must otherwise commence within 180 days of issuance or the permit expires.
Why the confidence is not higherStated plainly in BMC 9-1-1-105.5.1 Permit Expiration, part A.
adopting ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q20 Which permit portal does this authority use? Core Portal & process
Burbank Online Permits (BOP) for issuance/payment/inspections; Symbium for the instant residential solar permit application itself; ProjectDox for Tier 2/commercial plan check.
Why the confidence is not higherAll three named explicitly and consistently across the Solar page, Building & Safety page, and BWP installer instructions.
portal landing page checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q21 Can the whole application be completed online? Core Portal & process
Yes, for qualifying single-family systems (<=38.4kW) via Symbium -- 'permit applications submitted using Symbium will be issued in real time.'
Why the confidence is not higherDirectly stated on the city's Solar page.
department page checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q22 Which utility handles interconnection here? Core Utility interconnection
Burbank Water and Power (BWP) -- a municipally owned utility, not an investor-owned utility. PowerToChoose-style third-party utility lookups would be wrong here; confirmed directly from the city's and utility's own pages.
Why the confidence is not higherBWP is a department of the City of Burbank; its own site and the Solar Online Permit page both name it as the interconnecting utility.
utility's own page checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Q23 Where does the utility sit in the sequence? Core Utility interconnection
Before permit
Why the confidence is not higherThe city's own 5-step sequence puts 'Contact Burbank Water & Power' (Step 2, to obtain a Solar Confirmation Number) before 'Apply for the Instant Solar Permit with Symbium' (Step 4); the confirmation number is a required field in the Symbium application. BWP's installer instructions confirm the same order.
department page checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Q24 Is a HOA or architectural approval required first? Overlays & special cases
No -- HOA/architectural approval is not a City permitting precondition; the local ordinance's definition of a qualifying small system explicitly cross-references Civil Code Section 714 (the CA Solar Rights Act, which bars HOA denial of solar).
Why the confidence is not higherInferred from BMC 9-1-3-80.99(A) citing Civil Code 714 in its own definitions; no city document was found stating HOA approval either is or is not required as a submittal item.
ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q25 Is there a historic-district review? Overlays & special cases
Nothing published by this authority.
Where we lookedSearched Title 9 (Building/Fire) full text for 'historic'; term does not appear there. Historic Preservation is a Planning Division function (separate nav tab from Building & Safety) and its page was not reachable through burbankca.gov (Cloudflare-gated) or found archived; genuinely not checked at the Planning-division level.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q26 Is a wind or windstorm certification required? Overlays & special cases
Nothing published by this authority.
Where we lookedSearched Title 9 full text for 'wind' certification language beyond the standard CBC/CRC wind-load design provisions; no separate windstorm-certification requirement (of the type seen in Texas coastal jurisdictions) was found, consistent with California using seismic rather than wind-zone certification as its structural driver -- but no city document affirmatively states 'no wind certification is required.'
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Nothing published by this authority.
Where we lookedTitle 9 Article 1 (Building Administrative Standards) and the small-residential-solar ordinance (9-1-3-80.99); neither mentions a Specific Use Permit or Council approval step for residential solar. Zoning code (Title 10) was not reached (burbankca.gov Cloudflare-gated, no archived capture located for the zoning ordinance itself) to confirm from the zoning side.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q28 Is there a system-size cap on residential generation? Overlays & special cases
No zoning-based system-size cap found in Title 9; the effective cap for the Symbium instant-permit track is 38.4kW (program eligibility, not a legal ceiling), and BWP separately caps net-billing eligibility at 150% of the customer's trailing 12-month energy use for systems interconnecting after 1 Jan 2026.
Why the confidence is not higher38.4kW figure is a Symbium/city program threshold (above it, traditional plan review applies, not a hard prohibition); the 150% figure is BWP's net billing/interconnection sizing rule, sourced from BWP's own FAQ.
department page + utility FAQ checked 2026-08-30 https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 NEC (adopted into the 2025 California Electrical Code, Title 24 Part 3) 90% · adopting ordinance
- Which building code edition is in force? 2025 California Building Code (and 2025 California Residential Code), effective 1 Jan 2026, with local amendments in BMC Title 9 (Ord. No. 25-4,034) 95% · department page + adopting ordinance
- Which fire code edition is in force? 2025 California Fire Code (based on the 2024 IFC), effective 1 Jan 2026, with local amendments (BMC 9-1-9, Ord. No. 25-4,034) 90% · adopting ordinance
- Are there local amendments to any of the above? Yes 95% · adopting ordinance
- What is the installation judged against? The 2025 CEC (2023 NEC base) unamended for electrical work, plus the 2025 CBC/CRC as locally amended for structural attachment, and BWP's Rules & Regulations / Electric Service Specifications (drawings S-0812, S-0813, S-0819) for the utility interconnection point. 75% · adopting ordinance + utility spec index
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? Not locally amended -- Burbank's Fire Code amendments (BMC 9-1-9) contain no additions or changes to CFC Chapter 12 (Energy Systems), the chapter that sets rooftop PV setbacks and access pathways, so the unamended 2025 CFC Section 1204 standard applies as published by the state. 80% · adopting ordinance (absence proved by full-text search)
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes, per the 2025 CEC (2023 NEC), Article 690.12 rapid shutdown -- adopted without local amendment. 70% · adopting ordinance
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? Standard NEC/CFC-required service equipment placards (main disconnect, PV disconnect, rapid shutdown label) plus a BWP-required solar performance meter and, for multi-family buildings specifically, BWP Drawing S-825A labeling. 60% · utility installer instructions
- Does the UTILITY specify placards beyond the AHJ's? Yes for multi-family buildings (BWP Drawing S-825A, labeling requirements referenced explicitly); no separate placard drawing is listed for single-family residential in BWP's own Electric Service Specifications index -- only single-line diagrams (S-0812/S-0813/S-0819) are listed under 'Solar and Battery Standards.' 75% · utility spec index (absence proved by reading full drawing list)
- Where must the labels be placed? Not found as a single stated location beyond standard NEC placement (at the service equipment / point of interconnection); BWP requires the solar performance meter socket and AC disconnect to be wired between the inverter output and the service-entrance revenue meter. 55% · utility form
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Where must the AC disconnect be, relative to the meter? The AC disconnect (and the solar performance meter socket) must be wired between the output of the inverter and the service-entrance revenue (net) meter; detached structures with their own PV array must have their own ground-level, readily-accessible disconnect. AC/DC disconnects must be lever-actuated and lockable in the open position; built-in inverter disconnects are not an acceptable substitute. 90% · utility DG manual/form
- Are batteries permitted, and under what conditions? Yes, permitted; governed by the unamended 2025 CFC Chapter 12 (Energy Systems / ESS) since Burbank's local fire amendments do not touch that chapter. Separately, BWP allows AC- and DC-coupled battery configurations per its own single-line diagram standards S-0812/S-0813/S-0819. 75% · adopting ordinance (absence proved) + utility spec index
- Is there a separate ESS permit or inspection? Yes -- Energy Storage System has its own separate fee schedule line: Permit Fee $249.19 plus Plan Check Fee $280.21, distinct from the PV permit fee. 85% · fee schedule
20 questions answered against City of Burbank’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023 NEC (adopted into the 2025 California Electrical Code, Title 24 Part 3)
Why the confidence is not higherBurbank Municipal Code 9-1-3 adopts the '2025 California Electrical Code... without local amendments,' effective 1/1/26; the 2025 CEC is based on the 2023 NFPA 70 per the CA Building Standards Commission's own code text.
adopting ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code (and 2025 California Residential Code), effective 1 Jan 2026, with local amendments in BMC Title 9 (Ord. No. 25-4,034)
Why the confidence is not higherStated directly on the Building Codes and Building & Safety pages and confirmed in the ordinance text itself.
department page + adopting ordinance checked 2026-08-30 https://web.archive.org/web/20260418014842/https://www.burbankca.gov/web/community-development/building-codes
Q31 Which fire code edition is in force? Code editions in force
2025 California Fire Code (based on the 2024 IFC), effective 1 Jan 2026, with local amendments (BMC 9-1-9, Ord. No. 25-4,034)
Why the confidence is not higherDirectly stated in Article 9 of Title 9 ('Adoption of 2025 California Fire Code'); the article recites it is 'based on the 2024 International Fire Code.'
adopting ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes
Why the confidence is not higherTitle 9 contains extensive local amendments to the CBC and CFC (structural, seismic, fire access, building ID, sprinkler rules); by contrast the CEC (electrical) was adopted 'without local amendments.'
adopting ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q33 What is the installation judged against? Core Electrical
The 2025 CEC (2023 NEC base) unamended for electrical work, plus the 2025 CBC/CRC as locally amended for structural attachment, and BWP's Rules & Regulations / Electric Service Specifications (drawings S-0812, S-0813, S-0819) for the utility interconnection point.
Why the confidence is not higherSynthesized from the three adopting-ordinance articles plus BWP's own drawing index; no single document states this as one sentence.
adopting ordinance + utility spec index checked 2026-08-30 https://www.burbankwaterandpower.com/electric-specifications
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
Nothing published by this authority.
Where we lookedSearched Title 9 Article 3 (California Electrical Code, adopted without local amendments) for service-upgrade or busbar-sizing amendments; found none -- but did not separately check whether BWP's own Rules & Regulations (a lengthy separate tariff document referenced via Granicus, not retrieved) impose a busbar/service-upgrade rule.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedSearched Title 9 Article 2/2R (CBC/CRC amendments) full text for mounting-system/attachment-spacing language specific to solar; none found. The state small-system ordinance requires only a general structural-adequacy verification, not a named spacing standard.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Not locally amended -- Burbank's Fire Code amendments (BMC 9-1-9) contain no additions or changes to CFC Chapter 12 (Energy Systems), the chapter that sets rooftop PV setbacks and access pathways, so the unamended 2025 CFC Section 1204 standard applies as published by the state.
Why the confidence is not higherSearched the full text of Article 9 (all ~340 lines of local fire amendments) for 'photovoltaic,' 'solar,' 'rooftop,' 'setback,' 'pathway' and found none inside the fire-code article; a positive control ('electrical', 39 hits) and fabricated control ('zzqqx', 0 hits) confirmed the search itself was working.
adopting ordinance (absence proved by full-text search) checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes, per the 2025 CEC (2023 NEC), Article 690.12 rapid shutdown -- adopted without local amendment.
Why the confidence is not higherInferred from the fact that Burbank adopted the 2025 CEC 'without local amendments'; the ordinance text does not separately restate Article 690.12, so this is standard state-law inheritance rather than a Burbank-specific statement.
adopting ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Standard NEC/CFC-required service equipment placards (main disconnect, PV disconnect, rapid shutdown label) plus a BWP-required solar performance meter and, for multi-family buildings specifically, BWP Drawing S-825A labeling.
Why the confidence is not higherNo Burbank-specific single-family placard wording/spec document was located; the multi-family reference (Drawing S-825A) is explicit in BWP's installer instructions but that drawing itself was not retrievable (not indexed on the public specifications page, which only lists 'S-0825 - Multi-unit apartments' without an 'A' suffix).
utility installer instructions checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSearched BMC Title 9 Article 9 (Fire) and Article 3 (Electrical) full text for placard wording language and found none; BWP references a labeling drawing (S-825A) for multi-family only, and the drawing file itself could not be retrieved to check for city-specific wording.
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame search as q38/39 -- no letter-height/colour/material specification for solar placards found in BMC Title 9 Articles 3 or 9, and BWP's Drawing S-825A (which might contain this) could not be retrieved (not on the public specifications index, no working direct link found).
https://www.burbankwaterandpower.com/electric-specifications
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSearched BMC Title 9 (Fire, Electrical) and BWP's Confirmation of Electric Service form for a site-plan/facility-map placard requirement (NEC 705.10-style); none found. BWP's form describes a single-line electrical drawing but not a facility/roof map placard.
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Yes for multi-family buildings (BWP Drawing S-825A, labeling requirements referenced explicitly); no separate placard drawing is listed for single-family residential in BWP's own Electric Service Specifications index -- only single-line diagrams (S-0812/S-0813/S-0819) are listed under 'Solar and Battery Standards.'
Why the confidence is not higherBWP's full Electric Service Specifications drawing index (7 categories, dozens of drawings, checked in full) lists no dedicated placard/label drawing for single-family PV, only wiring diagrams; the S-825A reference for multi-family came from a separate installer-instructions page.
utility spec index (absence proved by reading full drawing list) checked 2026-08-30 https://www.burbankwaterandpower.com/electric-specifications
Q43 Where must the labels be placed? Core Labels Signage & labelling
Not found as a single stated location beyond standard NEC placement (at the service equipment / point of interconnection); BWP requires the solar performance meter socket and AC disconnect to be wired between the inverter output and the service-entrance revenue meter.
Why the confidence is not higherBWP's Confirmation of Electric Service form describes physical equipment placement (disconnect between inverter and meter) but does not separately describe where paper/placard labels must be affixed.
utility form checked 2026-08-30 https://www.burbankwaterandpower.com/documents/d/guest/BWP-ConfirmationOfElectricServices-Solar-07-21-23
Q44 Must equipment be on a specific approved list? Equipment listing
Nothing published by this authority.
Where we lookedBMC Title 9 Article 3 (Electrical) and the fee schedule; found only the general CEC requirement that 'all service equipment installed must be UL approved' (from BWP's form) -- no equipment-specific approved-products list was found.
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Yes, permitted; governed by the unamended 2025 CFC Chapter 12 (Energy Systems / ESS) since Burbank's local fire amendments do not touch that chapter. Separately, BWP allows AC- and DC-coupled battery configurations per its own single-line diagram standards S-0812/S-0813/S-0819.
Why the confidence is not higherSame full-text search of the local Fire Code amendments (Article 9) found zero ESS/battery-specific local changes; BWP's drawing index independently confirms it has standard drawings for battery-coupled solar.
adopting ordinance (absence proved) + utility spec index checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Yes -- Energy Storage System has its own separate fee schedule line: Permit Fee $249.19 plus Plan Check Fee $280.21, distinct from the PV permit fee.
Why the confidence is not higherFY2025-26 Fee Schedule, item (L) Energy Storage System, immediately below the Residential Photovoltaic line, lists two separate fees.
fee schedule checked 2026-08-30 https://web.archive.org/web/20250716111356/https://www.burbankca.gov/documents/d/financial-services/proposed-fy-2025-26-fee-schedule-final
Q47 Is a ground mount treated as a structure? Core Ground mount
Nothing published by this authority.
Where we lookedSearched Title 9 (Building/Fire regulations) full text for 'ground mount' / 'accessory structure' language; zero hits. Ground-mount setback/structure classification is typically a zoning (Title 10) matter, which was not reachable (burbankca.gov Cloudflare-gated; no archived zoning-code capture located).
https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
The AC disconnect (and the solar performance meter socket) must be wired between the output of the inverter and the service-entrance revenue (net) meter; detached structures with their own PV array must have their own ground-level, readily-accessible disconnect. AC/DC disconnects must be lever-actuated and lockable in the open position; built-in inverter disconnects are not an acceptable substitute.
Why the confidence is not higherExtracted directly (via pdftotext, not the fetch tool's summary) from BWP's Confirmation of Electric Service instructions -- the AHJ-facing utility DG document that q48 asks for.
utility DG manual/form checked 2026-08-30 https://www.burbankwaterandpower.com/documents/d/guest/BWP-ConfirmationOfElectricServices-Solar-07-21-23
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Portal 90% · department page
- How much notice is required? 1 business day minimum (can be scheduled up to 3 days in advance, excluding weekends/holidays) 90% · department page
- Are same-day or AM/PM windows offered? No stated AM/PM window; applicants call inspection staff between 7:00-7:45am the morning of the inspection to confirm a time. 85% · department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes 85% · department + utility pages
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? For the state-defined small residential rooftop solar system (<=10kW AC), only one consolidated inspection is required (may include both Building Official and Fire Official); a subsequent re-inspection is allowed if it fails. Larger/traditional systems follow normal rough/final building and electrical inspection sequencing. 75% · ordinance
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Does the inspector verify labels and listings? Yes (implied) 65% · utility installer instructions
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- What is issued on pass? Final (permit finaled in the Burbank Online Permits system) 70% · city's own permit log
- Who notifies the utility for PTO? AHJ 90% · utility installer instructions
- Is there a re-inspection fee? $184.93 per hour (general Building Division reinspection penalty fee; not solar-specific) 60% · fee schedule
14 questions answered against City of Burbank’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Portal
Why the confidence is not higherBuilding Inspections page: 'Request your next-day Building Inspection online from the Burbank Online Permits portal.'
department page checked 2026-08-30 https://web.archive.org/web/20260306063150/https://www.burbankca.gov/web/community-development/building-inspections
Q50 How much notice is required? Core Booking & scheduling
1 business day minimum (can be scheduled up to 3 days in advance, excluding weekends/holidays)
Why the confidence is not higherSame page: 'Request your Building Inspection one day in advance' and 'You may schedule an inspection up to three days in advance, except for weekends and holidays.'
department page checked 2026-08-30 https://web.archive.org/web/20260306063150/https://www.burbankca.gov/web/community-development/building-inspections
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
No stated AM/PM window; applicants call inspection staff between 7:00-7:45am the morning of the inspection to confirm a time.
Why the confidence is not higher'Please call Building Inspection staff between 7:00 a.m. - 7:45 a.m. the morning of your inspection... to confirm a time for your inspection' -- no fixed window is offered up front.
department page checked 2026-08-30 https://web.archive.org/web/20260306063150/https://www.burbankca.gov/web/community-development/building-inspections
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes
Why the confidence is not higherBuilding & Safety Division performs its own building/electrical inspections and notifies BWP only afterward for the separate utility performance-meter/safety-test step, which is not a code inspection.
department + utility pages checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Q53 If delegated, to whom? Core Who inspects
Nothing published by this authority.
Where we lookedN/A -- q52 answered 'Yes, AHJ performs its own inspection,' so q53 (delegation) does not apply; recorded here rather than invented.
https://www.burbankwaterandpower.com/solar-installer-instructions
Q54 Which inspections are required, and in what order? Core Stages & sequence
For the state-defined small residential rooftop solar system (<=10kW AC), only one consolidated inspection is required (may include both Building Official and Fire Official); a subsequent re-inspection is allowed if it fails. Larger/traditional systems follow normal rough/final building and electrical inspection sequencing.
Why the confidence is not higherBMC 9-1-3-80.99(E) states this plainly for the state-size-defined 'small' system; the sequence for systems above that size (up to the 38.4kW Symbium ceiling) was not separately documented.
ordinance checked 2026-08-30 https://www.codepublishing.com/CA/Burbank/html/Burbank09/Burbank0901.html
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
Nothing published by this authority.
Where we lookedBuilding Inspections page and BWP installer instructions describe only a single final solar inspection scheduled through Burbank Online Permits; no mid-roof/rough-in inspection stage is named for PV specifically, but no document affirmatively states one is NOT required either.
Q56 Does the inspector verify labels and listings? Core What is checked
Yes (implied)
Why the confidence is not higherBWP's installer instructions warn installers to 'pay close attention to labeling requirements for solar systems to avoid additional inspection costs and delays,' implying labels/listings are checked at inspection, but no city inspection checklist was found stating this explicitly.
utility installer instructions checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Q57 Is there a published inspection checklist? Core What is checked
Nothing published by this authority.
Where we lookedBuilding Permit Applications page lists a 'Residential Correction List' (a plan-check correction list, not explicitly labeled an inspection checklist); could not confirm a separate published field-inspection checklist exists for solar specifically -- the underlying PDF link could not be resolved to a working URL through burbankca.gov's Cloudflare gate or Wayback.
Q58 What must be on site at inspection? Core Documents on site
Nothing published by this authority.
Where we lookedBuilding Inspections page describes how to schedule/request inspections but does not list required on-site documents (e.g., approved plan set, permit card) for solar specifically; general CBC practice was not cited here to avoid guessing a Burbank-specific answer.
Q59 Is there a re-inspection fee? Corrections & re-inspection
$184.93 per hour (general Building Division reinspection penalty fee; not solar-specific)
Why the confidence is not higherFY2025-26 Fee Schedule, Building Permits section (C)(2) Reinspection = $184.93/hour; this is the general building reinspection fee, no solar-specific reinspection fee line was found separately.
fee schedule checked 2026-08-30 https://web.archive.org/web/20250716111356/https://www.burbankca.gov/documents/d/financial-services/proposed-fy-2025-26-fee-schedule-final
Q60 How are corrections issued and cleared? Corrections & re-inspection
Nothing published by this authority.
Where we lookedBuilding Permit Applications page names correction-list documents (e.g., 'Residential Correction List,' 'Plan Revision Form') and an 'Extension or Reinstatement Request' process, but no document was found describing how field-inspection corrections specifically (as opposed to plan-check corrections) are issued and cleared.
Q61 What is issued on pass? Core Final sign-off & PTO
Final (permit finaled in the Burbank Online Permits system)
Why the confidence is not higherThe monthly 'Solar Photovoltaic Permits Issued' log tracks Applied/Issued/Final columns per permit, consistent with a 'Final' sign-off rather than a separate CO or green tag for these single-family alteration permits.
city's own permit log checked 2026-08-30 https://web.archive.org/web/20260418010847/https://www.burbankca.gov/documents/d/community-development/2026-feb-spv
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
AHJ
Why the confidence is not higherBWP's installer instructions state plainly: 'The Building & Safety Division will notify BWP once a final permit is issued. BWP will schedule an onsite visit to install the performance meter...' -- the city notifies the utility, not the installer.
utility installer instructions checked 2026-08-30 https://www.burbankwaterandpower.com/solar-installer-instructions
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of Burbank against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Burbank is the authority having jurisdiction 90% confidence
- Holds
- building and electrical (single combined BS permit through Community Development's Building & Safety Division); Burbank Water and Power, a municipally owned utility, separately and independently controls interconnection and requires its own Confirmation of Electric Service and Interconnection & Metering Agreement BEFORE a city permit can even be applied for
- Overridden by
- State law sets the floor: Gov. Code Section 65850.5 / Civil Code Section 714 (Solar Rights Act) require an expedited/administrative process for small residential rooftop systems and prohibit denial via HOA/architectural review; Burbank has codified this at BMC 9-1-3-80.99. BWP's own interconnection and net-billing sizing rules (150% of trailing annual usage, effective for permits applied after 1 Jan 2026) function as a gate the City's permitting process depends on but does not itself set.
- Why not higher
- City of Burbank's Community Development / Building & Safety Division page states plainly that it issues solar permits ('Instant Residential Solar Permits... via our partnership with Symbium Corp'), and BWP's own site confirms the City permit and BWP interconnection are two distinct, sequenced steps. No county or other agency claims jurisdiction here -- Burbank is a full-service charter city with its own building department and its own municipal electric utility (BWP), not served by LA County or an investor-owned utility.
https://web.archive.org/web/20260608135016/https://www.burbankca.gov/web/community-development/solar
- Permit required
- Yes95%
- Permit cost
- $308.24 flat (Residential Photovoltaic System, electrical permit fee)85%
- Plan review
- Same day to a few days for Symbium instant permits (issued in real time); the state 'small residential rooftop solar' ordinance requires the checklist-based application be processed for…75%
- Portal
- Burbank Online Permits (BOP) for issuance/payment/inspections; Symbium for the instant residential solar permit application itself; ProjectDox for Tier 2/commercial plan check.90%
- Electrical code
- 2023 NEC (adopted into the 2025 California Electrical Code, Title 24 Part 3)90%
- Booking an inspection
- Portal90%
Labels & placards for this authority
Wording None%
Size, colour & material None%
Where they go 55%
Not found as a single stated location beyond standard NEC placement (at the service equipment / point of interconnection); BWP requires the solar performance meter socket and AC disconnect to be wired between the inverter output and the service-entrance revenue meter.
What the utility wants on top 75%
Yes for multi-family buildings (BWP Drawing S-825A, labeling requirements referenced explicitly); no separate placard drawing is listed for single-family residential in BWP's own Electric Service Specifications index -- only single-line diagrams (S-0812/S-0813/S-0819) are listed under 'Solar and Battery Standards.'
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.