City of Burlingame
San Mateo County
City of Burlingame is a city authority in the State of California, serving 31,386 residents. 1,283 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Separate Q4 Plan review — Branded 'instantaneous' plan review via Symbium (SB 379); statutory backstop of 45 days deemed-approved if not denied in writing Q18 Where you file — Symbium (residential PV/ESS, expedited); eTRAKiT (general building/electrical permitting) Q20
- Permit required
- Yes97% source
- What it costs
- $0 (residential); $650 permit / $350 plan check (commercial)95% source
- Plan review turnaround
- Branded 'instantaneous' plan review via Symbium (SB 379); statutory backstop of 45 days deemed-approved if not denied in writing80% source
- Key document
- ordinance (absence) cited by 5 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes 96% · department page
- What does this authority permit itself, and what does it delegate? Both 90% · department page + ordinance
- Is a permit required for a residential rooftop PV system? Yes 97% · department page
- Is there a separate electrical permit, or is it combined? Separate 82% · fee schedule
- Is a HOA or architectural approval required first? No 78% · ordinance
- Is there a historic-district review? No 85% · ordinance
- Is a wind or windstorm certification required? No 75% · ordinance (absence)
- Is a Specific Use Permit or Council approval ever required? Yes, conditionally — the Planning Division may require a use permit if it finds a specific, adverse impact on public health/safety 88% · ordinance
- Is there a system-size cap on residential generation? 10 kW AC / 30 kW thermal, for the expedited/no-design-review pathway; scoped to single-family or duplex dwellings and capped at the max legal building height — a gate on the streamlined process, not an absolute residential ceiling 92% · ordinance
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Either (licensed contractor or homeowner owner-builder) 58% · form
- Must the contractor be registered with this authority before applying? No 55% · department page
- Is a homeowner permitted to self-install and self-permit? Yes 72% · form
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- How many copies, and in what format? Electronic/PDF submittal (email or online); a front-counter paper alternative exists 68% · ordinance
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? Symbium (residential PV/ESS, expedited); eTRAKiT (general building/electrical permitting) 90% · department page
- Can the whole application be completed online? Yes 88% · department page
- What does a residential solar permit cost? $0 (residential); $650 permit / $350 plan check (commercial) 95% · fee schedule
- How is the fee calculated? Flat 90% · fee schedule
- Is there a separate plan-check fee? Yes 92% · fee schedule
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? Branded 'instantaneous' plan review via Symbium (SB 379); statutory backstop of 45 days deemed-approved if not denied in writing 80% · department page + ordinance
- How long is an issued permit valid before it expires? No local amendment found; default (unamended) 2025 CBC permit-expiration provision applies 55% · ordinance (absence)
- Which utility handles interconnection here? PG&E (Pacific Gas & Electric) 92% · department page
- Where does the utility sit in the sequence? After Permit — Permission to Operate is gated on the City's own final-inspection clearance 85% · utility tariff
28 questions answered against City of Burlingame’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity's own Building Division page: responsible for 'permit issuance, and field inspections of most buildings and structures built within the City'; BMC Title 18 Article 7 (§1-701 et seq.) codifies the City's own streamlined residential-solar permitting process.
department page checked 2026-08-30 https://www.burlingame.org/157/Building
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherBuilding and Electrical are both self-performed in-house by the Building Division (same staff, same contact emails, both permit types listed on the same online-permitting-instructions page). Fire is delegated to CCFD, but only for the fire-specific component and 'if required' per BMC §18.07.015 (§1-706) — noted here, not folded into the Building/Electrical answer.
department page + ordinance checked 2026-08-30 https://www.burlingame.org/1231/Online-Permitting-Portal-Submittal-Instr
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity's own Solar Resources page states plainly: 'Electrical permits are required for all solar PV installations.'
department page checked 2026-08-30 https://www.burlingame.org/642/Solar-Resources
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Separate
Why the confidence is not higherSolar PV is issued as its own Electrical permit, not bundled with a Building permit — the FY26-27 Master Fee Schedule lists 'Photo voltaic systems' as its own sub-line under 'ELECTRICAL PERMIT FEES' (Residential/Commercial), and the City's Solar Resources page states 'Solar projects do not require zoning permits or design review,' i.e. only the electrical permit applies.
fee schedule checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/9097/Master-Fee-Schedule-FY-26-27-PDF
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Either (licensed contractor or homeowner owner-builder)
Why the confidence is not higherNo PV-specific restriction found on the Symbium, portal, or Building pages. The City's standard 'Owner-Builder Declaration' package is a general precondition for any owner-signed construction permit and is not excluded for electrical/solar; this is an inference from the general owner-builder process, not a solar-specific statement.
form checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/179/Owner-Builder-Declaration-PDF
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
No
Why the confidence is not higherNo pre-registration/pre-qualification step is described anywhere in the Symbium page or the Online Permitting Portal & Submittal Instructions page before a contractor may apply; only standard CSLB license-number entry at application. Absence-based inference from the full submittal-instructions page, moderate confidence.
department page checked 2026-08-30 https://www.burlingame.org/1231/Online-Permitting-Portal-Submittal-Instr
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes
Why the confidence is not higherCity publishes a general 'Owner-Builder Declaration' / Property Owner's Package for any 'construction permit' filed by the owner; it is not solar-specific but nothing in the electrical/solar workflow excludes it, and the California Solar Rights Act does not bar self-installation.
form checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/179/Owner-Builder-Declaration-PDF
Q8 What documents make up a complete submittal? Core Submittal package
Nothing published by this authority.
Where we looked'Forms & Documents' page (182) lists ~35 named permit checklists by topic with none titled Solar/Photovoltaic; the Symbium page and Online Permitting Portal & Submittal Instructions page describe eligibility narratively but do not enumerate a document list; BMC §1-705 requires the City to publish 'a standard plan and checklist' but that specific document was not locatable outside the (login-gated) Symbium application flow itself.
Q9 How many copies, and in what format? Submittal package
Electronic/PDF submittal (email or online); a front-counter paper alternative exists
Why the confidence is not higherBMC §18.07.015 (§1-705): 'Electronic submittal of the required permit application and associated documents for small, residential rooftop solar energy system permits shall be by email, or the Internet. As an alternative an applicant may submit a permit application and associated documents at the Building Division front counter.' General portal guidance elsewhere on the site requires PDF format.
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q10 Is a site plan required, and what must it show? Core Submittal package
Nothing published by this authority.
Where we lookedCommercial Electrical section of the Online Permitting Portal page lists 'Site plan' among required documents for solar PV, but that section is explicitly Commercial, not Residential; the Residential pathway routes through Symbium, whose internal checklist is not independently viewable pre-application.
https://www.burlingame.org/1231/Online-Permitting-Portal-Submittal-Instr
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Nothing published by this authority.
Where we lookedNo Burlingame document states a one-line/three-line diagram requirement by name for residential PV; BMC §1-705 only requires the City's standard plan/checklist to 'substantially conform to' the state Solar Permitting Guidebook, which is a step removed from a direct city-side statement.
Q12 Are string and conductor calculations required? Drawings & calculations
Nothing published by this authority.
Where we lookedSame Title 18 Article 7 text and Commercial Electrical submittal list — neither mentions string or conductor calculations.
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Nothing published by this authority.
Where we lookedCommercial Electrical submittal list mentions 'Structural calculations, as necessary, for new solar PV systems' with no stated threshold (weight, span, or valuation) triggering a PE stamp; no residential-specific threshold found.
https://www.burlingame.org/1231/Online-Permitting-Portal-Submittal-Instr
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Nothing published by this authority.
Where we lookedTitle 18 Article 7 (§1-701 et seq.) and the Electrical chapter — no electrical PE-stamp threshold stated anywhere for residential PV.
Q15 What does a residential solar permit cost? Core Fees
$0 (residential); $650 permit / $350 plan check (commercial)
Why the confidence is not higherFY2026-27 Master Fee Schedule (own document, PDF creation stamp 26 May 2026 / mod 1 Jun 2026), p.3: 'Photo voltaic systems: Residential Systems** — Permit $0, Plan Check $0. Commercial Systems — Permit $650, Plan Check $350,' with footnote '*Residential Solar Permit fees are currently waived to incentivize solar permits.'
fee schedule checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/9097/Master-Fee-Schedule-FY-26-27-PDF
Q16 How is the fee calculated? Core Fees
Flat
Why the confidence is not higherFee schedule lists PV permit and plan-check fees as flat 'Each' amounts (currently $0 residential via waiver, not per-kW or per-panel), not a valuation- or per-kW-based formula.
fee schedule checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/9097/Master-Fee-Schedule-FY-26-27-PDF
Q17 Is there a separate plan-check fee? Fees
Yes
Why the confidence is not higherFee schedule lists 'Plan Check' as its own line item separate from 'Permit' for both Residential ($0/$0) and Commercial ($650/$350) photovoltaic systems.
fee schedule checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/9097/Master-Fee-Schedule-FY-26-27-PDF
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Branded 'instantaneous' plan review via Symbium (SB 379); statutory backstop of 45 days deemed-approved if not denied in writing
Why the confidence is not higherCity's own Symbium page: partnered with Symbium 'to establish an automated permitting platform' providing 'instantaneous plan review.' BMC §18.07.015 (§1-706) codifies the statutory backstop: 'If an application for the installation of a solar system is not denied in writing within 45 days of receipt of a complete application the application shall be deemed approved.' No separate business-day figure is published for the residential solar pathway specifically (contrast: Commercial Demo elsewhere on the same portal page states '15 working days' — a different, non-solar permit type, not to be confused with solar's turnaround).
department page + ordinance checked 2026-08-30 https://www.burlingame.org/1200/Symbium-for-Instant-Residential-PV-and-E
Q19 How long is an issued permit valid before it expires? Timeline & validity
No local amendment found; default (unamended) 2025 CBC permit-expiration provision applies
Why the confidence is not higherSearched Title 18 (Building Construction) for 'permit expiration,' 'expiration of permit,' and '105.5' — zero hits (positive controls 'electrical'=24 and 'fire'=77 occurrences passed; fabricated control 'zzqqx'=0). No Burlingame-specific permit-validity period is stated on the Building Division page beyond noting the expiration date appears on the printed permit card.
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q20 Which permit portal does this authority use? Core Portal & process
Symbium (residential PV/ESS, expedited); eTRAKiT (general building/electrical permitting)
Why the confidence is not higherCity's own dedicated page 'Symbium for Instant Residential PV and ESS Permits' names the platform; the Building Division page and Online Permitting Portal page name eTRAKiT (hosted at burlg.csqrcloud.com/community-etrakit/) as the general portal for all other permit types including Residential/Commercial Electrical.
department page checked 2026-08-30 https://www.burlingame.org/1200/Symbium-for-Instant-Residential-PV-and-E
Q21 Can the whole application be completed online? Core Portal & process
Yes
Why the confidence is not higherSymbium page: 'Contractors and homeowners seeking to pull permits under SB 379 are able to apply for instantaneous plan review via this Symbium portal' after 'verifying the address is within Burlingame's city limits' — a fully online flow for eligible PV/ESS. The general Online Permitting Portal page states 'Building permit applications may now be submitted online for all permit types through the online portal, eTRAKiT.'
department page checked 2026-08-30 https://www.burlingame.org/1200/Symbium-for-Instant-Residential-PV-and-E
Q22 Which utility handles interconnection here? Core Utility interconnection
PG&E (Pacific Gas & Electric)
Why the confidence is not higherCity's own Rebates page names 'PG&E' directly and links its rebate programs; CCFD (the JPA whose member city is Burlingame) publishes its own 'PG&E — Public Safety Power Shut-off Information (PSPS)' page. No municipal electric utility exists for Burlingame; PowerToChoose was not used per instruction.
department page checked 2026-08-30 https://www.burlingame.org/641/Rebates
Q23 Where does the utility sit in the sequence? Core Utility interconnection
After Permit — Permission to Operate is gated on the City's own final-inspection clearance
Why the confidence is not higherPG&E Electric Rule 21, Advice 7692-E (effective 29 Aug 2025, current — independently downloaded and grepped, not taken from a secondary source), Sheet 45, §D.13.b: Distribution Provider approval for interconnection (Permission to Operate) requires, among other things, '3) evidence of Applicant's final electric inspection clearance from the Governmental Authority having jurisdiction over the Generating Facility.' The utility step can run in parallel with permitting but PTO itself cannot precede the City's final sign-off.
utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Q24 Is a HOA or architectural approval required first? Overlays & special cases
No
Why the confidence is not higherThe City's own Design Review chapter (BMC §25.68.020.D.2) exempts 'solar panels or other energy efficient installations which are pre-empted from such review by State or Federal law' from Design Review; the California Solar Rights Act (Civil Code §714) separately bars an HOA from conditioning approval. The City does not require or condition its own permit on HOA sign-off.
ordinance checked 2026-08-30 https://ecode360.com/44514176
Q25 Is there a historic-district review? Overlays & special cases
No
Why the confidence is not higherBurlingame's Historic Resources chapter (BMC §25.35) is a voluntary, opt-in local register — inclusion 'shall only occur upon request of the property owner' (§25.35.040.D) and non-designated properties are unaffected. Even for an officially-designated historic resource, exterior-alteration review (§25.35.070) routes through the Design Review chapter, and §25.68.020.D.2 explicitly exempts 'solar panels or other energy efficient installations' from Design Review as pre-empted by state/federal law. This is a different shape from either West Hollywood's standalone solar exemption or Los Gatos' blanket pre-1941 reach: Burlingame's carve-out is embedded in its generic Design Review exemption and applies regardless of whether the structure is designated.
ordinance checked 2026-08-30 https://ecode360.com/44514176
Q26 Is a wind or windstorm certification required? Overlays & special cases
No
Why the confidence is not higherSearched Title 18 (Building Construction) for 'windstorm,' 'wind certification,' 'wind speed,' and 'ASCE 7' — zero hits (positive/fabricated controls as above). No TDI-style wind/windstorm certification exists in this California Bay Area jurisdiction; wind loading is addressed only through the unamended state structural code (ASCE 7 via CBC).
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Yes, conditionally — the Planning Division may require a use permit if it finds a specific, adverse impact on public health/safety
Why the confidence is not higherBMC §18.07.015 (§1-706): 'the Burlingame Planning Division may require an applicant to apply for a use permit if the Planning Division finds, based on substantial evidence, that the solar energy system could have a specific, adverse impact upon the public health and safety. Such decisions may be appealed to City of Burlingame Planning Commission.'
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q28 Is there a system-size cap on residential generation? Overlays & special cases
10 kW AC / 30 kW thermal, for the expedited/no-design-review pathway; scoped to single-family or duplex dwellings and capped at the max legal building height — a gate on the streamlined process, not an absolute residential ceiling
Why the confidence is not higherBMC §18.07.015 (§1-702) 'Small residential rooftop solar energy system' definition: 'no larger than 10 kilowatts alternating current nameplate rating or 30 kilowatts thermal... installed on a single-family or duplex-family dwelling... does not exceed the maximum legal building height.' Same AB 2188-era figure found in 15+ other CA authorities; separately, §25.30.040.A.5.b allows solar collectors compatible with the roofline to exceed the district height limit even where other rooftop mechanical equipment cannot.
ordinance checked 2026-08-30 https://ecode360.com/44512920
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 96% · adopting ordinance
- Which building code edition is in force? 2025 California Building Code (based on 2024 IBC) and 2025 California Residential Code (based on 2024 IRC), both Ord. 2041, 11/3/2025 96% · adopting ordinance
- Which fire code edition is in force? 2025 California Fire Code (based on 2024 IFC, as amended by the State of California) 95% · adopting ordinance
- Are there local amendments to any of the above? Yes 88% · ordinance
- What is the installation judged against? The 2025 CEC/CBC/CRC/CFC as locally amended by Ord. 2041/2042 (11/3/2025); BMC §1-704 additionally requires PV systems to meet CEC, IEEE, and UL (or other accredited testing lab) standards 88% · ordinance
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? No local ridge-setback or fire-access-pathway amendment found; the unamended 2025 CFC default applies 75% · ordinance (absence)
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes, per NEC §690.12 as adopted (2023 NEC / 2025 CEC), unmodified locally 78% · ordinance (state code, no local amendment found)
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? No Burlingame-specific placard beyond the unamended 2025 CEC (Art. 690/705) and CFC signage requirements 72% · ordinance (absence)
- Does the authority specify placard wording of its own? No 80% · department page (absence)
- Does it specify letter height, colour or material? No 78% · ordinance (absence)
- Is a site plan / facility map placard required, and what must it show? No Burlingame-specific supplement found; governed by the unamended CEC §705.10 default 68% · ordinance (absence)
- Does the UTILITY specify placards beyond the AHJ's? PG&E requires a visible, manually-operated isolating disconnect near the point of interconnection with markings clearly indicating open/closed positions; the exact meter-proximity distance and any placard wording live in PG&E's internal Greenbook (not publicly published) 65% · utility tariff
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Where must the AC disconnect be, relative to the meter? Near the point of interconnection, visible, and marked open/closed per PG&E Rule 21; exact meter-proximity distance not publicly published 62% · utility tariff
- Must equipment be on a specific approved list? No 75% · ordinance
- Are batteries permitted, and under what conditions? Permitted, governed by the unamended 2025 CFC Chapter 12 (Energy Systems/ESS) — no Burlingame-specific condition found 65% · ordinance (absence) + fee schedule
- Is there a separate ESS permit or inspection? Likely yes at the fire level — CCFD's own fee schedule lists a distinct 'Battery System' permit ($530), separate from any PV line (which has none) 60% · fee schedule
- Is a ground mount treated as a structure? No PV-specific ground-mount provision found; likely 'not contemplated' given Burlingame's small urban residential lots 55% · ordinance (absence)
- Is there a local rule on service upgrades or busbar sizing? No 82% · ordinance (absence)
- Is a specific mounting system or attachment spacing required? No local mounting/attachment-spacing rule found; governed by the unamended CBC/CRC and manufacturer engineering 68% · ordinance (absence)
20 questions answered against City of Burlingame’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023
Why the confidence is not higherBMC §18.16.010 (Ord. 2041, 11/3/2025): adopts '2023 National Electrical Code' with amendments as the '2025 California Electrical Code.'
adopting ordinance checked 2026-08-30 https://ecode360.com/44512920
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code (based on 2024 IBC) and 2025 California Residential Code (based on 2024 IRC), both Ord. 2041, 11/3/2025
Why the confidence is not higherBMC §18.08.005: 'Adoption of 2025 California Building Code, Part 2, Volume 1... published under the title "2024 International Building Code Volume 1."' BMC §18.10.010: 'Adoption of 2025 California Residential Code... "2024 International Residential Code."'
adopting ordinance checked 2026-08-30 https://ecode360.com/44512920
Q31 Which fire code edition is in force? Code editions in force
2025 California Fire Code (based on 2024 IFC, as amended by the State of California)
Why the confidence is not higherBMC §17.04.010 (Ord. 2042, 11/3/2025): adopts 'the 2025 California Fire Code (International Fire Code, 2024 Edition, as amended by the State of California)... together with all appendices, except Appendices A, D, J, and P.' Enforced by Central County Fire Department per the same title.
adopting ordinance checked 2026-08-30 https://ecode360.com/44512849
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes
Why the confidence is not higherOrd. 2041 and Ord. 2042 (both 11/3/2025) contain extensive local amendments across Titles 17-19 (e.g. the Article 7 small-residential-solar chapter itself, Article 8 EV-charging chapter, CFC §903.2/§903.2.10.3 sprinkler amendments, CBC roof-drainage §1502.3.1, etc.). Note, however, that a targeted search found NO local amendment specifically touching NEC §690.12, CRC R324, CFC Ch. 12 (ESS), or CFC 1204/1205 ridge-setback/pathway provisions — the general 'local amendments exist' answer should not be read as covering the solar-technical sections themselves (see Q34/Q36/Q37/Q45).
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q33 What is the installation judged against? Core Electrical
The 2025 CEC/CBC/CRC/CFC as locally amended by Ord. 2041/2042 (11/3/2025); BMC §1-704 additionally requires PV systems to meet CEC, IEEE, and UL (or other accredited testing lab) standards
Why the confidence is not higherBMC §18.07.015 (§1-704): 'Solar energy systems for producing electricity shall meet all applicable safety and performance standards established by the California Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories and, where applicable, rules of the Public Utilities Commission.'
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
No
Why the confidence is not higherSearched Title 18 for 'busbar' and 'service upgrade' — zero hits (positive controls 'electrical'=24, 'fire'=77 passed; fabricated 'zzqqx'=0). No local rule found beyond the unamended 2025 CEC service-disconnect amendment (§230.70(A)(1), which only concerns exterior accessibility of the main switch, not busbar sizing).
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
No local mounting/attachment-spacing rule found; governed by the unamended CBC/CRC and manufacturer engineering
Why the confidence is not higherSearched Title 18 for 'mounting system,' 'attachment spacing,' 'racking,' and 'attachment point' — zero true hits (one apparent 'racking' hit was a substring of 'tracking' in an unrelated landscape-water clause). Positive/fabricated controls as above passed.
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
No local ridge-setback or fire-access-pathway amendment found; the unamended 2025 CFC default applies
Why the confidence is not higherSearched Title 17 (Fire) and Title 18 for 'ridge,' 'CFC 1204,' 'CFC 1205,' and '705.10'/'705.12' — zero relevant hits (all 'ridge' hits in Title 18 were flood-hazard-map terminology, not roof pathways). Positive/fabricated controls passed on both titles.
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512849
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes, per NEC §690.12 as adopted (2023 NEC / 2025 CEC), unmodified locally
Why the confidence is not higherRapid shutdown is a 2023 NEC Article 690.12 requirement carried into the unamended 2025 CEC (Ord. 2041, §18.16.010). Searched Title 18 for '690.12' and 'rapid shutdown' — zero hits, i.e. no local amendment loosens or tightens it (positive/fabricated controls passed).
ordinance (state code, no local amendment found) checked 2026-08-30 https://ecode360.com/44512920
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
No Burlingame-specific placard beyond the unamended 2025 CEC (Art. 690/705) and CFC signage requirements
Why the confidence is not higherSearched Title 17 and Title 18 in full for any placard/label specification tied to solar/PV/ESS — none found beyond the general adopted (not locally amended) state code. CCFD's own site (construction-permits, plan-submittals pages) has no PV/ESS-specific handout either (checked directly, zero hits for 'solar', 'photovoltaic', 'battery', 'rapid shutdown').
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
No
Why the confidence is not higherNo wording specified anywhere in Title 17/18 or on the CCFD construction-permits/plan-submittals pages (checked directly, zero 'solar'/'photovoltaic' hits on either CCFD page). Only the unamended state code's generic label content applies.
department page (absence) checked 2026-08-30 https://www.ccfd.org/construction-permits
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
No
Why the confidence is not higherNo letter-height/colour/material specification found in the City's or CCFD's own code or handout pages for solar signage; both were checked directly with zero relevant hits.
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
No Burlingame-specific supplement found; governed by the unamended CEC §705.10 default
Why the confidence is not higherTitle 18 contains no local addition to CEC 705.10 (zero hits on '705.10' across Titles 17-19).
ordinance (absence) checked 2026-08-30 https://ecode360.com/44512920
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
PG&E requires a visible, manually-operated isolating disconnect near the point of interconnection with markings clearly indicating open/closed positions; the exact meter-proximity distance and any placard wording live in PG&E's internal Greenbook (not publicly published)
Why the confidence is not higherPG&E Electric Rule 21, Sheet 171, §H.1.d 'Visible Disconnect Required': device must 'allow visible verification that separation has been accomplished' and 'include markings or signage that clearly indicates open and closed positions.' The more granular meter-distance figure is understood (per prior GovBot PG&E-territory findings) to sit in PG&E's gated internal Greenbook/TD document, which is not publicly accessible — not claimed here as read.
utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedTitle 17/18 (no local label-placement rule) and CCFD's construction-permits/plan-submittals pages (checked directly, zero 'solar'/'photovoltaic' hits) — no Burlingame- or CCFD-specific label-placement rule found beyond the unamended state code.
Q44 Must equipment be on a specific approved list? Equipment listing
No
Why the confidence is not higherBMC §1-704 requires equipment to meet CEC/IEEE standards and be tested by 'accredited testing laboratories such as Underwriters Laboratories' — a UL-listing requirement, not a city-curated approved equipment list.
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Permitted, governed by the unamended 2025 CFC Chapter 12 (Energy Systems/ESS) — no Burlingame-specific condition found
Why the confidence is not higherSearched Title 17 for 'battery,' 'energy storage system,' 'lithium,' '1206' and '1207' — the only hit was an unrelated EV-charging-station sprinkler-density amendment (§903.2.10.3), not a residential ESS rule; positive/fabricated controls passed. CCFD's own FY26-27 fee schedule separately lists a 'Battery System' general fire permit ($530), implying batteries are permitted subject to that fire permit.
ordinance (absence) + fee schedule checked 2026-08-30 https://ecode360.com/44512849
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Likely yes at the fire level — CCFD's own fee schedule lists a distinct 'Battery System' permit ($530), separate from any PV line (which has none)
Why the confidence is not higherCCFD FY26-27 Master Fee Schedule, 'General Permits': 'Battery System — $530,' with no corresponding photovoltaic line anywhere in the same schedule (control-proven absence: positive control 'fire'/'electrical' found repeatedly, fabricated 'zzqqx' absent). The fee implies a distinct operational/construction permit process for battery systems but no city document explicitly describes a separate ESS *inspection* step beyond that permit.
fee schedule checked 2026-08-30 https://www.ccfd.org/files/e23e64e51/FEE+SCHEDULE+CCFD+FY26-27+Adopted.pdf
Q47 Is a ground mount treated as a structure? Core Ground mount
No PV-specific ground-mount provision found; likely 'not contemplated' given Burlingame's small urban residential lots
Why the confidence is not higherTitle 25 (Zoning) contains only 6 total 'solar' hits (all read and accounted for: near-zero-net-energy incentive credits, a building-mounted-equipment projection allowance, the Minor Design Review solar exemption, and the rooftop height-exception clause) — none address ground-mounted systems. Positive controls ('electrical'=18, 'fire'=45) and fabricated control ('zzqqx'=0) passed, so this is a control-proven absence, not a failed search. A ground-mounted array would default to Burlingame's general accessory-structure/setback rules.
ordinance (absence) checked 2026-08-30 https://ecode360.com/44514176
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Near the point of interconnection, visible, and marked open/closed per PG&E Rule 21; exact meter-proximity distance not publicly published
Why the confidence is not higherPG&E Electric Rule 21 §H.1.d requires the visible disconnect be installed 'near the Point of Interconnection' and be reachable by utility personnel, but does not give a specific linear distance from the meter in the publicly filed tariff text; that figure is believed to live in PG&E's gated internal Greenbook/TD document.
utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Phone or Email 85% · department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? No 85% · department page + form (absence)
- What must be on site at inspection? The printed permit card and approved plans/documents 68% · department page
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- Who notifies the utility for PTO? Installer (Applicant) 68% · utility tariff
- Is there a re-inspection fee? $230.35/hour (one-hour minimum) 75% · fee schedule
- How are corrections issued and cleared? A subsequent (re-)inspection is authorized and required if the system fails; no separate written-correction-notice process is described for solar specifically 62% · ordinance
14 questions answered against City of Burlingame’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Phone or Email
Why the confidence is not higherBuilding Division page: 'Building inspections may be requested by calling 650-558-7260, or by emailing buildinginspections@burlingame.org.' No portal-based self-scheduling is described on this page.
department page checked 2026-08-30 https://www.burlingame.org/157/Building
Q50 How much notice is required? Core Booking & scheduling
Nothing published by this authority.
Where we lookedBuilding Division page (157/Building) states only the phone number and email for requesting an inspection; no stated advance-notice period found anywhere on the site.
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedSame Building Division page — no mention of same-day service or AM/PM window options.
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes
Why the confidence is not higherBMC §18.07.015 (§1-706): 'Only one inspection shall be required and performed by the Building Division for small residential rooftop solar energy systems eligible for expedited review.' A separate fire inspection is delegated to CCFD only 'if required' (see Q53).
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q53 If delegated, to whom? Core Who inspects
Central County Fire Department (fire-specific component only, when required)
Why the confidence is not higherSame §1-706 text: 'A separate fire inspection may be performed by the Central County Fire Department, if required. The inspection shall be done within three business days and may include consolidated inspections.'
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q54 Which inspections are required, and in what order? Core Stages & sequence
One Building Division inspection (final) for eligible small residential rooftop solar; a separate CCFD fire inspection only if required, within 3 business days
Why the confidence is not higherDirect quote of BMC §18.07.015 (§1-706), same citation as Q52/53.
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
No
Why the confidence is not higher§1-706's 'Only one inspection shall be required' language for eligible small residential rooftop solar systems forecloses a separate rough-in/mid-roof step for the expedited pathway.
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q56 Does the inspector verify labels and listings? Core What is checked
Nothing published by this authority.
Where we lookedNo City or CCFD document states explicitly that the inspector verifies labels/listings; this is standard practice generally but not documented in writing for Burlingame specifically, so not recorded as a sourced fact.
Q57 Is there a published inspection checklist? Core What is checked
No
Why the confidence is not higherThe City's 'Forms & Documents' page lists ~35 named checklists/forms (roofing, decks, kitchen/bath remodel, EV charging, etc.) with none titled Solar or Photovoltaic; its own 'Residential Inspection Checklist' PDF (dated 18 Dec 2025, extracted with pdftotext) contains zero mentions of 'solar' or 'photovoltaic.' Positive control ('electrical' appears in the checklist) and fabricated control ('zzqqx' absent) both passed.
department page + form (absence) checked 2026-08-30 https://www.burlingame.org/182/Forms-Documents
Q58 What must be on site at inspection? Core Documents on site
The printed permit card and approved plans/documents
Why the confidence is not higherBuilding Division page: after fee payment 'you will receive detailed instructions about printing out the plans, permit, and documents. These need to be at the job site during inspections.' Not solar-specific but this is the City's general, stated practice for all permits.
department page checked 2026-08-30 https://www.burlingame.org/157/Building
Q59 Is there a re-inspection fee? Corrections & re-inspection
$230.35/hour (one-hour minimum)
Why the confidence is not higherFY2026-27 Master Fee Schedule, 'BUILDING INSPECTION FEES': 'Re-inspection fees (minimum – one hour) — Per Hour — $230.35.' This is the City's general re-inspection fee (not solar-specific, but the applicable schedule for any failed Building Division inspection including the single solar inspection).
fee schedule checked 2026-08-30 https://www.burlingame.org/DocumentCenter/View/9097/Master-Fee-Schedule-FY-26-27-PDF
Q60 How are corrections issued and cleared? Corrections & re-inspection
A subsequent (re-)inspection is authorized and required if the system fails; no separate written-correction-notice process is described for solar specifically
Why the confidence is not higherBMC §18.07.015 (§1-706): 'If a small residential rooftop solar energy system fails inspection, a subsequent inspection is authorized and required but need not conform to the requirements of this section.'
ordinance checked 2026-08-30 https://ecode360.com/44512920
Q61 What is issued on pass? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedBuilding Division page references a 'permit card' generally but never states what is issued specifically on a passed final inspection (no 'Final'/'Green tag'/'CO'/'Letter' language found); insufficient to select one of the four choices with a genuine source.
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Installer (Applicant)
Why the confidence is not higherPG&E Electric Rule 21 §D.13.b frames Permission-to-Operate as processed upon Distribution Provider's receipt of the 'Applicant's' completed Interconnection Request/Agreement plus 'evidence of Applicant's final electric inspection clearance' — i.e. the customer/installer, not the City, submits the PTO package to PG&E. This is a utility-level fact (PG&E), not an authority-level one.
utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of Burlingame against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Burlingame is the authority having jurisdiction 92% confidence
- Holds
- Building and Electrical (self-performed, in-house Building Division); Fire review/inspection delegated to Central County Fire Department (CCFD), a JPA of Burlingame, Hillsborough and Millbrae, and only 'if required'
- Delegated to
- Central County Fire Department (fire-code review and any required separate fire inspection only)
- Overridden by
- State law sets the ceiling on process: Gov. Code §65850.5/§65850.52 (SB 379) mandates the City's expedited/instantaneous review pathway (implemented via Symbium), and PG&E Electric Rule 21 §D.13.b gates the utility's Permission-to-Operate on the City's own final-inspection clearance rather than the reverse
- Why not higher
- The City's own Building Division page states it is 'responsible for plan checking construction documents, permit issuance, and field inspections of most buildings and structures built within the City' (in-house staff, buildingpermits@ and buildinginspections@ on the city domain, no third-party plan-check firm found anywhere in the portal/forms pages). Burlingame Municipal Code Title 17 (Fire), Ord. 2042 (11/3/2025), names 'Central County Fire Department' as the enforcing fire agency repeatedly in its own adopted CFC amendments, and CCFD's own 'About CCFD' page confirms it 'serves the communities of Burlingame, Hillsborough, and Millbrae' (formed 2004, not merged/dissolved). BMC Title 18 §18.07.015 (Article 7, §1-706) explicitly splits the two: 'Only one inspection shall be required and performed by the Building Division for small residential rooftop solar energy systems eligible for expedited review... A separate fire inspection may be performed by the Central County Fire Department, if required.' The brief's premise (CCFD as likely fire AHJ) is confirmed, not overturned.
- Permit required
- Yes97%
- Permit cost
- $0 (residential); $650 permit / $350 plan check (commercial)95%
- Plan review
- Branded 'instantaneous' plan review via Symbium (SB 379); statutory backstop of 45 days deemed-approved if not denied in writing80%
- Portal
- Symbium (residential PV/ESS, expedited); eTRAKiT (general building/electrical permitting)90%
- Electrical code
- 202396%
- Own placard wording
- No80%
- Booking an inspection
- Phone or Email85%
Labels & placards for this authority
Wording 80%
No
Size, colour & material 78%
No
Where they go None%
What the utility wants on top 65%
PG&E requires a visible, manually-operated isolating disconnect near the point of interconnection with markings clearly indicating open/closed positions; the exact meter-proximity distance and any placard wording live in PG&E's internal Greenbook (not publicly published)
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.