City of Fullerton
Orange County
City of Fullerton is a city authority in the State of California, serving 143,617 residents. 5,589 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Where you file — EasyDev (Tyler Technologies EnerGov Citizen Self Service) Q20
- Permit required
- Yes95% source
- What it costs
- Valuation-based per Table 1-A (e.g., $86 for the first $2,000 of valuation plus $12/$1,000 up to $25,000;65% source
- Key document
- eligibility checklist (PDF, extracted with pdftotext) cited by 6 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes 95% · authority's own department page
- What does this authority permit itself, and what does it delegate? Both 90% · fee schedule / department pages
- Is a permit required for a residential rooftop PV system? Yes 95% · authority's own page
- Is there a separate electrical permit, or is it combined? Combined 70% · permit application form
- Is there a system-size cap on residential generation? No absolute size cap; systems above 10 kW AC (CEC rating) simply fall outside the expedited/streamlined review track and must go through standard plan review 75% · eligibility checklist (PDF)
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Either 75% · permit application form + FAQ
- Must the contractor be registered with this authority before applying? Yes 85% · department FAQ page
- Is a homeowner permitted to self-install and self-permit? Yes 80% · department FAQ page
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? Completed Solar Permit Application Worksheet; the applicable Eligibility Checklist (PV, solar water heating, or pool heating); if eligible, the matching Solar Permit Submittal Criteria package and Solar PV Standard Plan; a roof-layout diagram showing all panels/modules, clear access pathways, and approximate disconnect/roof-access locations; and a completed 'Structural Criteria for Residential Rooftop Solar Systems' package if the project does not qualify for the prescriptive standard plan. 75% · eligibility checklist + application form
- Is a site plan required, and what must it show? Yes -- a roof-layout diagram is required, showing all panel/module locations, clear access pathways, and approximate locations of electrical disconnecting means and roof access points (Eligibility Checklist, Fire Safety item D). Standard construction-plan submittals separately require a general Site Plan showing property-line setbacks (per the Building & Safety general submittal-requirements page). 80% · eligibility checklist (PDF, extracted with pdftotext)
- Is a one-line / three-line diagram required? Yes (inferred) 55% · eligibility checklist (indirect)
- Are string and conductor calculations required? Likely required only outside the expedited/prescriptive path 50% · eligibility checklist + permit-processing-info page
- Is a structural PE stamp required, and at what threshold? A structural PE stamp is required only when the installation does not conform to the city's prescriptive 'Structural Criteria for Residential Rooftop Solar Systems' standard plan; the Eligibility Checklist requires that document 'if required.' The specific engineering thresholds in that document could not be confirmed. 55% · eligibility checklist (PDF)
- Is an electrical PE stamp required, and at what threshold? Required for any electrical system or service of 400 Amps or greater, or 600 volts to ground or greater 80% · fee schedule (PDF, extracted with pdftotext) citing FMC §14.05.030
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? EasyDev (Tyler Technologies EnerGov Citizen Self Service) 90% · portal landing page
- Can the whole application be completed online? Likely yes for eligible/expedited PV systems, but not confirmed as fully paperless 55% · authority's own page
- What does a residential solar permit cost? Valuation-based per Table 1-A (e.g., $86 for the first $2,000 of valuation plus $12/$1,000 up to $25,000; roughly $300-$450 total building-permit fee for a typical residential PV system), plus a separate $380 Fullerton Fire Department construction-permit fee if the system or any co-installed battery/ESS triggers fire-code review 65% · fee schedule (PDF, extracted with pdftotext)
- How is the fee calculated? Valuation 80% · fee schedule (PDF)
- Is there a separate plan-check fee? Yes 85% · fee schedule (PDF)
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- How long is an issued permit valid before it expires? 180 days is the state model-code default (CBC/CRC §105.5, permit expires if work not commenced or is abandoned for 180 days); Fullerton's FAQ confirms an application 'expiration date' exists but does not itself restate the number of days 50% · department FAQ + CBC default (code text unverified)
- Which utility handles interconnection here? Southern California Edison (SCE) 90% · authority's own forms page linking utility-specific form
- Where does the utility sit in the sequence? After permit (final inspection required before Permission to Operate, though the interconnection application itself may be filed in parallel) 70% · utility tariff (Rule 21), extracted with pdftotext
28 questions answered against City of Fullerton’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity of Fullerton is an incorporated city with its own Building & Safety Division (Community and Economic Development Dept) that issues its own building/electrical permits, and its own Fullerton Fire Department that issues fire/ESS construction permits; Orange County is not involved for incorporated Fullerton addresses.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherBuilding & Safety Division issues building and electrical permits (Fullerton Municipal Code Ch. 14.03/14.05, per the master fee schedule); Fullerton Fire Department (own department, not Orange County Fire Authority) separately reviews/permits fire and energy-storage aspects (own construction-permit fee line items) under Title 13 fire code amendments. Nothing is delegated outside the city.
fee schedule / department pages checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity publishes a dedicated 'Streamlined Solar Permitting' page and an Eligibility Checklist for Expedited Solar Photovoltaic Permitting, both premised on a permit being required; the Solar Permit Application Worksheet is the intake form used for all solar PV/water-heating jobs.
authority's own page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/photovoltaic-solar-permits
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Combined
Why the confidence is not higherThe dedicated 'Solar Permit Application Worksheet' is a single combined form (one Job Description field covering PV work 'including service upgrade if required', one BLDG. FEE line) used to issue one solar permit; the master fee schedule otherwise keeps generic Building Permit and Electrical Permit fee sections legally distinct (FMC §14.03 vs §14.05), so a project requiring extensive separate electrical work outside the solar scope could still draw a second electrical permit.
permit application form checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/699/637431760974630000
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Either
Why the confidence is not higherThe Solar Permit Application Worksheet has fields for a licensed Contractor (state contractor #, license class) OR the Building Owner directly; the Building & Safety FAQ separately confirms 'Property owners doing their own work are required by State law to sign the Owner-Builder Verification.'
permit application form + FAQ checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/699/637431760974630000
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Yes
Why the confidence is not higherBuilding & Safety FAQ states any person/contractor 'conducting, managing, carrying on or engaging in any business... in the City of Fullerton' -- including a contractor headquartered outside Fullerton -- must obtain a City business registration certificate before beginning work; the Solar Permit Application Worksheet also has a 'FULLERTON BUS. LIC. #' field.
department FAQ page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/faqs
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes
Why the confidence is not higherBuilding & Safety FAQ: 'Property owners doing their own work are required by State law to sign the Owner-Builder Verification stating that they are actually doing their own work... or they will be required to provide a certificate of insurance.' No carve-out excludes solar from owner-builder permitting.
department FAQ page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/faqs
Q8 What documents make up a complete submittal? Core Submittal package
Completed Solar Permit Application Worksheet; the applicable Eligibility Checklist (PV, solar water heating, or pool heating); if eligible, the matching Solar Permit Submittal Criteria package and Solar PV Standard Plan; a roof-layout diagram showing all panels/modules, clear access pathways, and approximate disconnect/roof-access locations; and a completed 'Structural Criteria for Residential Rooftop Solar Systems' package if the project does not qualify for the prescriptive standard plan.
Why the confidence is not higherDirectly enumerated on the Eligibility Checklist for Expedited Solar Photovoltaic Permitting (Electrical/Structural/Fire Safety sections) and the Solar Permit Application Worksheet; the underlying 'Submittal Criteria' and 'Standard Plan' PDFs themselves (doc IDs 703/707) could not be retrieved this run (403 live, not archived in Wayback), so this list is assembled from the checklist and worksheet rather than the submittal-criteria document itself.
eligibility checklist + application form checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q9 How many copies, and in what format? Submittal package
Nothing published by this authority.
Where we lookedPhotovoltaic/Solar Permits page and linked Solar Permit Submittal Criteria document (doc id 703) -- the criteria PDF that would normally state copy count/format 403'd live and has no Wayback capture; the city's own portal note only says online applications 'are best used with Chrome browser.'
Q10 Is a site plan required, and what must it show? Core Submittal package
Yes -- a roof-layout diagram is required, showing all panel/module locations, clear access pathways, and approximate locations of electrical disconnecting means and roof access points (Eligibility Checklist, Fire Safety item D). Standard construction-plan submittals separately require a general Site Plan showing property-line setbacks (per the Building & Safety general submittal-requirements page).
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, Fire Safety Requirements section, item D, read directly from the extracted PDF text; corroborated by the general 'What does a complete set of plans include' FAQ answer listing 'Site plan - showing setbacks from property lines.'
eligibility checklist (PDF, extracted with pdftotext) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Yes (inferred)
Why the confidence is not higherThe Eligibility Checklist requires 'A Solar PV Standard Plan and supporting documentation' to be attached, which by convention includes a one-line electrical diagram, but the Standard Plan document itself (doc id 707) could not be retrieved this run (403 live, no Wayback capture), so the one-line-diagram requirement is not confirmed from the document's own text.
eligibility checklist (indirect) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q12 Are string and conductor calculations required? Drawings & calculations
Likely required only outside the expedited/prescriptive path
Why the confidence is not higherThe Eligibility Checklist's own Electrical Requirements are prescriptive limits (string/MPPT counts, fusing) rather than a request for string/conductor calculations; full string and conductor calculations would appear in the general construction-plan submittal (which the permit-processing-info page says must include 'Structural Calculations' for structural plans, but does not separately name electrical/conductor calculations) or in the un-retrievable Submittal Criteria document.
eligibility checklist + permit-processing-info page checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
A structural PE stamp is required only when the installation does not conform to the city's prescriptive 'Structural Criteria for Residential Rooftop Solar Systems' standard plan; the Eligibility Checklist requires that document 'if required.' The specific engineering thresholds in that document could not be confirmed.
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, Structural Requirements item A ('A completed Structural Criteria and supporting documentation is attached (if required)'); the Structural Criteria PDF itself (doc id 715) 403'd live and has no Wayback capture, so the specific psf/span/weight thresholds are not verified.
eligibility checklist (PDF) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Required for any electrical system or service of 400 Amps or greater, or 600 volts to ground or greater
Why the confidence is not higherCity of Fullerton master Fee Schedule, ELECTRICAL section, citing Fullerton Municipal Code §14.05.030: 'electrical systems of 400 Amps or greater or 600 volts to ground or greater, shall be designed by an electrical engineer registered by the State of California.' Extracted directly from the current FY25-26 fee-schedule PDF with pdftotext; the underlying municipal code text (amlegal.com) is Cloudflare-blocked in this run so the ordinance section itself was not independently read.
fee schedule (PDF, extracted with pdftotext) citing FMC §14.05.030 checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q15 What does a residential solar permit cost? Core Fees
Valuation-based per Table 1-A (e.g., $86 for the first $2,000 of valuation plus $12/$1,000 up to $25,000; roughly $300-$450 total building-permit fee for a typical residential PV system), plus a separate $380 Fullerton Fire Department construction-permit fee if the system or any co-installed battery/ESS triggers fire-code review
Why the confidence is not higherCity master Fee Schedule Table 1-A (Building Permits, Fire Building Plan Check & Inspection Fees) gives valuation tiers rather than a single flat solar fee; Fire Department Fee Schedule separately lists 'Solar photovoltaic power systems' and 'Battery systems'/'Energy storage system' construction permits at $380 each. No single all-in dollar figure for 'a residential solar permit' is published by the city.
fee schedule (PDF, extracted with pdftotext) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q16 How is the fee calculated? Core Fees
Valuation
Why the confidence is not higherTable 1-A in the master Fee Schedule computes the building-permit fee from declared project valuation (tiered $ amounts per $1,000 of valuation); electrical work of 400A+/600V+ is charged as 50% of the associated permit fee. Fire Department solar/ESS construction-permit fees are flat ($380).
fee schedule (PDF) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q17 Is there a separate plan-check fee? Fees
Yes
Why the confidence is not higherMaster Fee Schedule: 'For the issuance of each permit using City standard plan or where no plan check required...$42.00' vs '...requiring plan check...$63.00'; Electrical section separately lists an 'Expedited Plan Review' fee of $282/hour in addition to the plan-review fee.
fee schedule (PDF) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Nothing published by this authority.
Where we lookedPhotovoltaic/Solar Permits page, Permit Processing Info page, and Building & Safety FAQs -- none state a specific plan-review turnaround in business days for solar specifically or generally.
Q19 How long is an issued permit valid before it expires? Timeline & validity
180 days is the state model-code default (CBC/CRC §105.5, permit expires if work not commenced or is abandoned for 180 days); Fullerton's FAQ confirms an application 'expiration date' exists but does not itself restate the number of days
Why the confidence is not higherBuilding & Safety FAQ: 'Your project may comply with the 2022 building codes... provided you obtain your permit before the expiration date of your application' confirms an expiration mechanism exists; the specific day-count is the unamended CBC default because the Fullerton Municipal Code text (amlegal.com) is Cloudflare-blocked in this run and could not be checked for a local override.
department FAQ + CBC default (code text unverified) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/faqs
Q20 Which permit portal does this authority use? Core Portal & process
EasyDev (Tyler Technologies EnerGov Citizen Self Service)
Why the confidence is not higherBuilding & Safety's own PV page and main landing page both link 'Apply for permit on EasyDev' to https://easydev.cityoffullerton.com/energov_prod/selfservice#/home; the older 'Permits Online' page 302-redirects into the same portal.
portal landing page checked 2026-08-30 https://easydev.cityoffullerton.com/energov_prod/selfservice#/home
Q21 Can the whole application be completed online? Core Portal & process
Likely yes for eligible/expedited PV systems, but not confirmed as fully paperless
Why the confidence is not higherThe PV page instructs applicants to 'Apply for the qualifying Expedited Solar PV Permit through our Customer Self Service Portal at EasyDev,' but then separately says 'Come to City Hall to pay for and pick up your solar permits,' which reads as a hybrid online-application/in-person-pickup process rather than a fully online SolarAPP+-style instant permit. No SolarAPP+ branding or instant-issuance language appears on any Fullerton page found this run.
authority's own page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/photovoltaic-solar-permits
Q22 Which utility handles interconnection here? Core Utility interconnection
Southern California Edison (SCE)
Why the confidence is not higherFullerton's own Building & Safety 'Forms, Applications, and Fees' page links a document titled 'SC Edison Self Certification' (a General Order 95 overhead-line-clearance self-certification form used for interconnection-adjacent construction); this is a city-side confirmation, not a ZIP-code lookup.
authority's own forms page linking utility-specific form checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/8704/638544132116930000
Q23 Where does the utility sit in the sequence? Core Utility interconnection
After permit (final inspection required before Permission to Operate, though the interconnection application itself may be filed in parallel)
Why the confidence is not higherSCE Electric Rule 21, Section D.13.b: SCE 'approval for Interconnection (i.e., Permission to Operate)... shall normally be processed not later than thirty (30) Business Days following Distribution Provider's receipt of' the NEM interconnection request AND 'evidence of Applicant's final electric inspection clearance from the Governmental Authority having jurisdiction.' PTO is explicitly gated on the AHJ's final inspection.
utility tariff (Rule 21), extracted with pdftotext checked 2026-08-30 https://www.sce.com/sites/default/files/inline-files/Rule21_1_1.pdf
Q24 Is a HOA or architectural approval required first? Overlays & special cases
Nothing published by this authority.
Where we lookedCity zoning code / HOA provisions -- Fullerton Municipal Code is hosted only on amlegal.com, which Cloudflare-403'd on every method tried this run (direct fetch, Referer, WebFetch); no city page separate from the code addressed HOA/architectural review for solar.
Q25 Is there a historic-district review? Overlays & special cases
Nothing published by this authority.
Where we lookedCity zoning code (historic-district/HPOZ chapter) and Historic Preservation page -- same amlegal.com block as above; the Historic Preservation landing page itself gave only nav content with no solar-specific text.
Q26 Is a wind or windstorm certification required? Overlays & special cases
Nothing published by this authority.
Where we lookedCity building-code amendments and PV Standard Plan/Structural Criteria documents -- the Structural Criteria PDF (doc id 715) 403'd live and has no Wayback capture; no wind/windstorm certification is mentioned in any reachable page.
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Nothing published by this authority.
Where we lookedCity zoning code (Specific Use Permit / conditional-use provisions) -- amlegal.com blocked; no Fullerton page addressed a Council-approval trigger for residential solar.
Q28 Is there a system-size cap on residential generation? Overlays & special cases
No absolute size cap; systems above 10 kW AC (CEC rating) simply fall outside the expedited/streamlined review track and must go through standard plan review
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, General Requirements item A: 'System size is 10 kW AC CEC rating or less' -- explicitly framed as an eligibility threshold for the expedited process, with the checklist's own closing note: 'If any items are checked NO... permit application may go through standard process,' not a hard cap.
eligibility checklist (PDF) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 85% · authority's own department page
- Which building code edition is in force? 2025 California Building Code (with local amendments), effective for all submittals on/after January 1, 2026; the 2022 CBC still governs permits submitted before that date 90% · authority's own department page
- Which fire code edition is in force? 2025 California Fire Code (with local amendments), effective concurrently with the 2025 CBC cycle 70% · authority's own department page (conflicts with Fire Dept fee schedule on cycle year)
- Are there local amendments to any of the above? Yes 85% · authority's own department page + Legistar ordinance record
- What is the installation judged against? The adopted, locally amended 2025 California Building Code / California Electrical Code / California Residential Code (2022-cycle codes for permits filed before 1/1/2026), plus the city's own Eligibility Checklist and Standard Plan prescriptive criteria for the expedited PV pathway 75% · authority's own department page
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
Nothing recorded for City of Fullerton on this step yet — 1 question checked and found unpublished. The guidance above is general.
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Required, to the 2025 NEC-based California Electrical Code (2023 NEC) for permits filed on/after 1/1/2026; to the 2022-cycle CEC (2020 NEC) for permits filed before that date 60% · inference from adopted code edition (ordinance text unverified)
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Is a site plan / facility map placard required, and what must it show? Yes -- a roof-layout diagram showing all panel/module locations, clear access pathways, and the approximate locations of electrical disconnecting means and roof access points 80% · eligibility checklist (PDF, extracted with pdftotext)
- Does the UTILITY specify placards beyond the AHJ's? Yes -- SCE's Rule 21 requires a visible, manually-operated isolating disconnect switch near the point of interconnection, with markings/signage that clearly indicate its open and closed positions 75% · utility tariff (Rule 21), extracted with pdftotext
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Are batteries permitted, and under what conditions? Permitted, but battery storage disqualifies a project from the expedited/streamlined PV review track and routes it to standard review; batteries/ESS also draw their own separate Fullerton Fire Department construction-permit fee 80% · eligibility checklist (PDF) + Fire Dept fee schedule
- Is there a separate ESS permit or inspection? Yes 85% · authority's own department page (current inspection-code table)
- Is there a local rule on service upgrades or busbar sizing? For the expedited/streamlined PV pathway, the system must interconnect to a single-phase 120/240V service with a bus bar rating of 225A or less; larger or split-phase services are routed to standard (non-expedited) plan review 75% · eligibility checklist (PDF)
20 questions answered against City of Fullerton’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023
Why the confidence is not higherThe city's Current Building Codes page and Building & Safety FAQ both state the 2025 California Building Standards Codes (which incorporate NFPA-referenced National Electrical Code content via the 2025 California Electrical Code, based on the 2023 NEC per the standard CA triennial cycle) became effective January 1, 2026, with 2022-cycle codes (based on 2020 NEC) applying only to applications filed before that date.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code (with local amendments), effective for all submittals on/after January 1, 2026; the 2022 CBC still governs permits submitted before that date
Why the confidence is not higherCurrent Building Codes page: 'The 2025 California Building Codes and City of Fullerton Amendments are enforceable for all residential and non-residential construction projects submitted on or after January 1, 2026. Projects submitted prior to January 1, 2026 shall comply with the 2022 Codes.' Corroborated verbatim by the Building & Safety FAQ.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q31 Which fire code edition is in force? Code editions in force
2025 California Fire Code (with local amendments), effective concurrently with the 2025 CBC cycle
Why the confidence is not higherCurrent Building Codes page lists '2025 California Fire Code' among the adopted 2025-cycle codes, and a companion Title 13 ordinance amending the Fire Code was on the same 9/16/2025 Council agenda as the Title 14 building-code ordinance. However, the city's own live Fire Department Fee Schedule (FY25-26, effective July 2025) still cites '2022 CFC §105' for its construction-permit fee categories -- a tension between two of the city's own current documents that this run could not resolve by reading the ordinance text itself (amlegal.com blocked).
authority's own department page (conflicts with Fire Dept fee schedule on cycle year) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes
Why the confidence is not higherCurrent Building Codes page: 'The state codes have been amended by the City of Fullerton to address local topographic, climatic, and/or geologic conditions,' and links a '2025 City of Fullerton Amendments' Legistar item; Legistar confirms a City Council ordinance amending FMC Title 14 to adopt the 2025 codes with local amendments (structural wind/seismic criteria: Seismic Design Category D/E/F, wind speeds 89-106 mph by risk category, Climate Zone 8) was before Council 9/16/2025.
authority's own department page + Legistar ordinance record checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q33 What is the installation judged against? Core Electrical
The adopted, locally amended 2025 California Building Code / California Electrical Code / California Residential Code (2022-cycle codes for permits filed before 1/1/2026), plus the city's own Eligibility Checklist and Standard Plan prescriptive criteria for the expedited PV pathway
Why the confidence is not higherSynthesis of the Current Building Codes page (adopted code editions) and the PV Eligibility Checklist (prescriptive electrical/structural/fire-safety criteria used as the pass/fail standard for expedited review).
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
For the expedited/streamlined PV pathway, the system must interconnect to a single-phase 120/240V service with a bus bar rating of 225A or less; larger or split-phase services are routed to standard (non-expedited) plan review
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, Electrical Requirements item C: 'The PV system is interconnected to a single-phase AC service panel of nominal 120/220 Vac with a bus bar rating of 225 A or less.' No separate, general local busbar/120%-rule ordinance text was found (municipal code unreachable).
eligibility checklist (PDF) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedSolar PV Standard Plan and Structural Criteria documents (doc ids 707/709/715) -- all 403'd on live fetch and have no Wayback capture this run; no mounting-system/attachment-spacing detail appears on any reachable Fullerton page.
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Nothing published by this authority.
Where we lookedFire Department Fire Prevention pages and the same Standard Plan/Structural Criteria PDFs -- none reachable; per this run's brief, ridge-setback figures must not be asserted from a search summary, and no Fullerton-specific source could be opened to read one directly.
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Required, to the 2025 NEC-based California Electrical Code (2023 NEC) for permits filed on/after 1/1/2026; to the 2022-cycle CEC (2020 NEC) for permits filed before that date
Why the confidence is not higherInferred from the city's adopted-code-edition statement (Current Building Codes page / FAQ) rather than a Fullerton document that names NEC 690.12/rapid-shutdown by section number; the local amendments ordinance text itself (which could confirm no rapid-shutdown amendment) is on amlegal.com and Cloudflare-blocked this run.
inference from adopted code edition (ordinance text unverified) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/current-building-codes
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedPV Standard Plan / Structural Criteria documents and the general Eligibility Checklist -- the checklist only says generically that 'All required markings and labels are provided' without naming individual placards; the documents that would enumerate them (703/707/715) 403'd live with no Wayback capture.
https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame Standard Plan/Structural Criteria documents as Q38 -- unreachable this run, so the presence or absence of city-specific placard wording could not be confirmed either way.
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame Standard Plan/Structural Criteria documents as Q38/39 -- unreachable this run.
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Yes -- a roof-layout diagram showing all panel/module locations, clear access pathways, and the approximate locations of electrical disconnecting means and roof access points
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, Fire Safety Requirements item D, read directly from extracted PDF text.
eligibility checklist (PDF, extracted with pdftotext) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Yes -- SCE's Rule 21 requires a visible, manually-operated isolating disconnect switch near the point of interconnection, with markings/signage that clearly indicate its open and closed positions
Why the confidence is not higherSCE Electric Rule 21 (current tariff, fetched directly from sce.com), Section D 'Visible Disconnect Required': the device 'must... include markings or signage that clearly indicates open and closed positions.' SCE's separate 'Interconnection Handbook,' which would normally hold more detailed placard specs, is unreachable this run -- its on.sce.com shortlink now redirects through an authenticated Edison-International SharePoint/Microsoft-login flow even in Wayback captures back to 2022, exactly as flagged in this run's brief.
utility tariff (Rule 21), extracted with pdftotext checked 2026-08-30 https://www.sce.com/sites/default/files/inline-files/Rule21_1_1.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedPV Standard Plan/Structural Criteria documents (unreachable) and SCE's Interconnection Handbook (redirects to an authenticated SharePoint login even via Wayback back to 2022) -- neither could be read this run for label-placement specifics.
Q44 Must equipment be on a specific approved list? Equipment listing
Nothing published by this authority.
Where we lookedEligibility Checklist, PV page, master fee schedule -- none mention a city-specific approved-equipment list; the Standard Plan document that would normally reference specific listed products (doc id 707) is unreachable this run, so absence cannot be confirmed with the necessary source.
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Permitted, but battery storage disqualifies a project from the expedited/streamlined PV review track and routes it to standard review; batteries/ESS also draw their own separate Fullerton Fire Department construction-permit fee
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting, General Requirements item D: 'Solar system is utility interactive and without battery storage' -- a battery present fails this eligibility item. Fire Department Fee Schedule FY25-26 separately lists 'Battery systems' and 'Energy storage system' as distinct $380 Required Construction Permits under 2022 CFC §105.6.
eligibility checklist (PDF) + Fire Dept fee schedule checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Yes
Why the confidence is not higherThe city's own Inspections page lists 'BATTERY BACKUP' as inspection code 450, distinct from 'PHOTOVOLTAIC SYSTEMS' at code 425, both under the Electrical category; separately, the Fire Department Fee Schedule lists 'Battery systems' and 'Energy storage system' as their own $380 Required Construction Permits, distinct from the $380 'Solar photovoltaic power systems' line.
authority's own department page (current inspection-code table) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q47 Is a ground mount treated as a structure? Core Ground mount
Nothing published by this authority.
Where we lookedFullerton Municipal Code zoning/accessory-structure provisions -- amlegal.com Cloudflare-blocked this run; no Fullerton page addressed ground-mount PV as a 'structure' for zoning purposes.
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Nothing published by this authority.
Where we lookedSCE Interconnection Handbook (redirects to an authenticated Edison International SharePoint/Microsoft-login flow on every route tried, including Wayback captures back to 2022) and SCE Electric Rule 21 (which specifies a visible disconnect switch's markings but not its physical location relative to the meter) -- neither source states AC-disconnect placement relative to the meter.
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Phone (automated Voice Permits IVR, 24 hours/day) or online (EasyDev portal, which also shows today's scheduled inspections live) 90% · authority's own department page
- How much notice is required? Effectively next business day: calls placed before midnight are scheduled for the following working day 70% · authority's own department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes, for the building/electrical scope; the city's own Fullerton Fire Department separately performs the fire/ESS scope 85% · authority's own department page
- If delegated, to whom? Not delegated -- the City of Fullerton Building Division and the City's own Fullerton Fire Department each perform their respective scopes; no delegation to Orange County or Orange County Fire Authority 85% · authority's own department page
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? Per the current inspection-code table: Photovoltaic Systems (code 425) and, if present, Battery Backup (code 450), both under the Electrical category, followed by the general Permit Final (code 999); the Fire Department separately performs its own Fire Final (code 645) inspection where a fire construction permit was pulled 65% · authority's own department page (current table); PDF guide flagged as stale (2009)
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? Yes, in the form of the published Eligibility Checklist for Expedited Solar Photovoltaic Permitting (a pass/fail checklist used at intake and, in practice, at inspection); no separate 'PV final inspection checklist' distinct from that document was found 55% · eligibility checklist (PDF), doubling as the closest published checklist
- Does the inspector verify labels and listings? Yes (by strong inference) 55% · inference from eligibility checklist (no direct inspection-checklist confirmation)
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- What is issued on pass? Final (inspection code 999, 'Permit Final') 60% · authority's own department page (inspection-code table)
- Who notifies the utility for PTO? Installer (Applicant) 70% · utility tariff (Rule 21), extracted with pdftotext
- Is there a re-inspection fee? $112.00 per re-inspection 85% · fee schedule (PDF, extracted with pdftotext)
- How are corrections issued and cleared? Corrections are noted by the field inspector against the approved plans; the applicant/contractor calls the inspector on the correction item for clarification, corrects the work, and re-books via the same Voice Permits/EasyDev channel used for the original inspection (a $112 re-inspection fee applies) 55% · department guide (PDF, dated 2009 -- flagged as potentially stale)
14 questions answered against City of Fullerton’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Phone (automated Voice Permits IVR, 24 hours/day) or online (EasyDev portal, which also shows today's scheduled inspections live)
Why the confidence is not higherInspections page: 'Call the automated Voice Permits(TM) IVR System for all of your Building/Fire Permit inspections, 24 hours a day! (714) 738-6543' and 'To view today's inspections live, Visit our EASYDEV Platform.'
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q50 How much notice is required? Core Booking & scheduling
Effectively next business day: calls placed before midnight are scheduled for the following working day
Why the confidence is not higherInspections page, 'To Schedule an Inspection' instructions: 'Enter the inspection date. Calls placed before midnight will be placed on the following working day's schedule.' No separate minimum-business-days notice period is stated beyond this.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedInspections page and Voice Permits guide -- neither states AM/PM inspection windows; the only timing note found was 'After hours inspection can be arranged for an additional fee' in the (2009-dated) Voice Permits guide PDF, which is a different feature (after-hours, not same-day AM/PM windows).
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes, for the building/electrical scope; the city's own Fullerton Fire Department separately performs the fire/ESS scope
Why the confidence is not higherInspections page lists 'PHOTOVOLTAIC SYSTEMS' (code 425) and 'BATTERY BACKUP' (code 450) as Electrical inspections performed via the city's own Voice Permits/EasyDev system; the city's Fire Department page states the Fullerton Fire Department 'has protected the residents of Fullerton for over 115 years' (i.e. it is not Orange County Fire Authority), and the Fire Dept Fee Schedule shows Fullerton's own construction-permit fees for solar and battery/ESS systems.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q53 If delegated, to whom? Core Who inspects
Not delegated -- the City of Fullerton Building Division and the City's own Fullerton Fire Department each perform their respective scopes; no delegation to Orange County or Orange County Fire Authority
Why the confidence is not higherFullerton Fire Department page identifies the department as the city's own 115-year-old agency (not OCFA); Building & Safety's Inspections page and Fire Department's Fee Schedule both show Fullerton-operated permitting/inspection for solar and battery/ESS work.
authority's own department page checked 2026-08-30 https://www.cityoffullerton.com/government/departments/fire
Q54 Which inspections are required, and in what order? Core Stages & sequence
Per the current inspection-code table: Photovoltaic Systems (code 425) and, if present, Battery Backup (code 450), both under the Electrical category, followed by the general Permit Final (code 999); the Fire Department separately performs its own Fire Final (code 645) inspection where a fire construction permit was pulled
Why the confidence is not higherSynthesized from the current Inspections page code table (425/450/999) and the Voice Permits guide PDF's 'Fire Final' code 645; note the linked Voice Permits guide PDF itself is dated 'Revised 8/2009' and still shows an older, undifferentiated code '950 Solar' with no separate battery code, so the guide is stale relative to the live webpage table -- the live webpage table was treated as current.
authority's own department page (current table); PDF guide flagged as stale (2009) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
Nothing published by this authority.
Where we lookedInspections page inspection-code table -- no 'rough' or 'mid-roof' PV-specific code is listed (only Photovoltaic Systems 425 and Battery Backup 450 appear, both read as final-type electrical inspections); the Eligibility Checklist and Standard Plan documents that might specify a rough-in stage are unreachable/silent on this.
Q56 Does the inspector verify labels and listings? Core What is checked
Yes (by strong inference)
Why the confidence is not higherThe Eligibility Checklist's own Fire Safety item C requires 'All required markings and labels are provided' as a condition of the permit itself, which building/fire inspectors verify at inspection as standard practice; no Fullerton inspection checklist explicitly listing this inspector action was found to confirm it directly.
inference from eligibility checklist (no direct inspection-checklist confirmation) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q57 Is there a published inspection checklist? Core What is checked
Yes, in the form of the published Eligibility Checklist for Expedited Solar Photovoltaic Permitting (a pass/fail checklist used at intake and, in practice, at inspection); no separate 'PV final inspection checklist' distinct from that document was found
Why the confidence is not higherEligibility Checklist for Expedited Solar Photovoltaic Permitting is published on the PV page; the city's Inspections page does not additionally publish a stand-alone PV inspection checklist beyond the code-number table.
eligibility checklist (PDF), doubling as the closest published checklist checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/695/637431760969000000
Q58 What must be on site at inspection? Core Documents on site
Nothing published by this authority.
Where we lookedInspections page and Voice Permits guide -- neither states what must physically be on site (e.g., approved plans, permit card) beyond the general note that 'The inspector will be following the city approved plans if applicable and any city approved revisions,' which implies approved plans should be available but does not use 'must be on site' language.
Q59 Is there a re-inspection fee? Corrections & re-inspection
$112.00 per re-inspection
Why the confidence is not higherCity master Fee Schedule, 'Other inspections and fees,' item (2): 'Reinspection fee.....$112.00/each.'
fee schedule (PDF, extracted with pdftotext) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/10715/639082305316070000
Q60 How are corrections issued and cleared? Corrections & re-inspection
Corrections are noted by the field inspector against the approved plans; the applicant/contractor calls the inspector on the correction item for clarification, corrects the work, and re-books via the same Voice Permits/EasyDev channel used for the original inspection (a $112 re-inspection fee applies)
Why the confidence is not higherVoice Permits guide PDF: 'If you have any questions regarding a correction item please contact the inspector on the correction for clarification (7am-8am or 3:30-5pm)'; re-inspection fee confirmed separately in the master fee schedule. This guide PDF is dated 'Revised 8/2009' so process details may have since changed in ways not reflected in this document.
department guide (PDF, dated 2009 -- flagged as potentially stale) checked 2026-08-30 https://www.cityoffullerton.com/home/showpublisheddocument/1262/637436872835270000
Q61 What is issued on pass? Core Final sign-off & PTO
Final (inspection code 999, 'Permit Final')
Why the confidence is not higherCity's own Inspections page inspection-code table lists code 999 as 'Permit Final,' the terminal inspection code in the Electrical/Building sequence; no separate 'Certificate of Occupancy' or 'green tag' terminology was found used specifically for a residential PV job.
authority's own department page (inspection-code table) checked 2026-08-30 https://www.cityoffullerton.com/government/departments/community-and-economic-development/building-and-safety/inspections
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Installer (Applicant)
Why the confidence is not higherSCE Electric Rule 21, Section D.13.b: Distribution Provider processes Permission to Operate upon receipt of a completed NEM Interconnection Request from the 'Applicant' together with 'evidence of Applicant's final electric inspection clearance from the Governmental Authority' -- i.e., the Applicant (in practice, the installer on the homeowner's behalf) is the party who submits to SCE for PTO, not the city.
utility tariff (Rule 21), extracted with pdftotext checked 2026-08-30 https://www.sce.com/sites/default/files/inline-files/Rule21_1_1.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of Fullerton against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Fullerton is the authority having jurisdiction 90% confidence
- Holds
- building and electrical (Community & Economic Development Dept, Building & Safety Division); fire and energy-storage-system review/permitting held separately by the City's own Fullerton Fire Department
- Overridden by
- California state law sets floors the city cannot go below: Gov. Code §65850.5 (streamlined/expedited solar permitting mandate, implemented via Fullerton's own Eligibility Checklist since Oct 2015) and AB 130 (Stats. 2025, Ch. 22), which from 1 Oct 2025 to 1 Jun 2031 bars a city from adopting any more-restrictive residential building-code amendment. Fullerton's own 2025-code local-amendment ordinance was on the Council agenda 9/16/2025, i.e. just before the AB 130 freeze window opened -- this run could not read the ordinance's final adopted text (amlegal.com Cloudflare-blocked) to confirm no residential provision was tightened.
- Why not higher
- Fullerton is an incorporated Orange County city with its own Building & Safety Division (issues building/electrical permits and fee schedule under its own municipal code) and its own Fullerton Fire Department (own 115-year department, own fire/ESS construction-permit fee line items in both the Fire Dept fee schedule and the citywide master fee schedule) -- confirmed NOT delegated to Orange County or Orange County Fire Authority, unlike the pattern seen this run in Santa Ana and Garden Grove.
- Permit required
- Yes95%
- Permit cost
- Valuation-based per Table 1-A (e.g., $86 for the first $2,000 of valuation plus $12/$1,000 up to $25,000;65%
- Portal
- EasyDev (Tyler Technologies EnerGov Citizen Self Service)90%
- Electrical code
- 202385%
- Booking an inspection
- Phone (automated Voice Permits IVR, 24 hours/day) or online (EasyDev portal, which also shows today's scheduled inspections live)90%
Labels & placards for this authority
Wording None%
Size, colour & material None%
Where they go None%
What the utility wants on top 75%
Yes -- SCE's Rule 21 requires a visible, manually-operated isolating disconnect switch near the point of interconnection, with markings/signage that clearly indicate its open and closed positions
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.