City of Menlo Park

San Mateo County

Verified Aug. 4, 2026

City of Menlo Park is a city authority in the State of California, serving 33,780 residents. 2,304 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Permitting 5 steps · 28 questions

Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Real-time for the automated PRT/SolarAPP+ path; for a non-expedited application, MMC Sec. Q18 Where you file — Accela Citizen Access (ACA); SolarAPP+ is used as the front-end 'Processor' for PRT-eligible residential PV. Q20

Permit required
Yes95% source
What it costs
Fee schedule reads "State Limit" for both the plan-check and permit fee on "Photovoltaic System - Residential" -- i.e., capped by state law rather than set by the City as a flat dollar figure.85% source
Plan review turnaround
Real-time for the automated PRT/SolarAPP+ path; for a non-expedited application, MMC Sec. 12.22.060 sets a statutory 45-day deemed-approved clock (unless denied in writing or a reasonable information…80% source
Key document
portal landing page cited by 8 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes 95% · department page
    • What does this authority permit itself, and what does it delegate? Both 88% · department page
    • Is a permit required for a residential rooftop PV system? Yes 95% · municipal code
    • Is there a separate electrical permit, or is it combined? Combined 75% · department page
    • Is a HOA or architectural approval required first? No 90% · municipal code
    • Is there a historic-district review? Yes, but only for properties within the designated 'H' Historic Site District or a City-designated landmark site (MMC Ch. 16.54); not a citywide requirement. 80% · zoning code
    • Is a Specific Use Permit or Council approval ever required? Yes, conditionally -- the Planning Division may require a use permit if it finds, based on substantial evidence, that the solar system could have a 'specific, adverse impact' on public health and safety; the Building Official may then deny the use permit only on written findings of such impact with no feasible mitigation. 90% · municipal code
    • Is there a system-size cap on residential generation? Two different caps found: (1) the codified 'small residential rooftop solar energy system' definition in MMC Sec. 12.22.020(b)(1) is capped at 10 kW AC nameplate / 30 kW thermal (the AB 2188-era figure, unchanged since 2016); (2) the City's live PRT/SolarAPP+ automated-issuance eligibility page caps eligible systems at 38.4 kW AC or less. These are two different thresholds for two different purposes (statutory 'small system' definition vs. real-time issuance eligibility) and neither has been reconciled with the other in the published material. 88% · municipal code + department page
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Licensed electrician / Either 65% · department page
    • Must the contractor be registered with this authority before applying? Yes 85% · municipal code
    • Is a homeowner permitted to self-install and self-permit? No (for the expedited PRT/SolarAPP+ path) 55% · department page
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Site plan (ESS/disconnect/grounding locations), roof plan (plumbing vents), roof section(s), installation details, electrical one-line (wire sizes, existing bus capacity, main disconnect), PV labeling plan, Building Permit Application form, structural calculations, electrical load calculations, all product specifications, and (if MPFPD review is required) the MPFPD approval letter. 92% · checklist
    • How many copies, and in what format? Electronic/digital submission only, via the Accela Citizen Access (ACA) portal 75% · department page
    • Is a site plan required, and what must it show? Yes -- must show ESS location, dedicated ESS disconnect location, and grounding system location. 90% · checklist
    • Is a one-line / three-line diagram required? Yes 92% · checklist
    • Are string and conductor calculations required? Yes 88% · checklist
    • Is a structural PE stamp required, and at what threshold? Structural calculations are required whenever PV roof-attachment standoff spacing exceeds 72 inches, or whenever roof-framing modifications are proposed; plans generally must carry the seal of a licensed architect or designer (the City's page cites MMC 12.22.050 and Bus. & Prof. Code Sec. 5536.1, though the currently codified text of MMC 12.22.050 itself does not contain this language -- see note). 72% · department page
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Accela Citizen Access (ACA); SolarAPP+ is used as the front-end 'Processor' for PRT-eligible residential PV. 95% · portal landing page
    • Can the whole application be completed online? Yes, for PRT-eligible residential PV (existing single-family, roof-mounted, new PV only, no battery/EV charger, <=38.4 kW, <=400A service, 225A disconnect/busbar, CA-licensed contractor). Batteries and EV chargers are excluded from real-time issuance and must use the standard review path. 92% · department page
    • What does a residential solar permit cost? Fee schedule reads "State Limit" for both the plan-check and permit fee on "Photovoltaic System - Residential" -- i.e., capped by state law rather than set by the City as a flat dollar figure. 85% · fee schedule
    • How is the fee calculated? Tiered 60% · fee schedule
    • Is there a separate plan-check fee? Yes 88% · fee schedule
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? Real-time for the automated PRT/SolarAPP+ path; for a non-expedited application, MMC Sec. 12.22.060 sets a statutory 45-day deemed-approved clock (unless denied in writing or a reasonable information request is pending), and the Building Division was required to stand up its expedited review process within 30 days of the ordinance's effective date. 80% · municipal code
    • How long is an issued permit valid before it expires? Not locally amended -- defaults to the adopted 2025 CBC's standard permit-expiration provision (commonly 180 days). 60% · municipal code
    • Which utility handles interconnection here? PG&E (Pacific Gas & Electric) 60% · department directory (inference)
    • Where does the utility sit in the sequence? After permit -- PG&E Permission to Operate (PTO) is expressly gated on the AHJ's final-inspection clearance. 78% · utility tariff

28 questions answered against City of Menlo Park’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes

Why the confidence is not higherCity's own Photovoltaic and ESS Systems Permit Information page states the Building Division issues the building/electrical permit; confirmed by MMC Ch. 12.22 (streamlined solar permitting chapter).

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both

Why the confidence is not higherCity's Building Division issues both the building and electrical permit as one combined PV/ESS building permit (no stand-alone city electrical-only path found for PV). Fire Code compliance is not 'delegated' by the City but is held independently by MPFPD under its own ordinance -- see jurisdiction block.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes

Why the confidence is not higherMMC Sec. 12.04.040 makes it unlawful to do electrical/building work without a permit; Ch. 12.22 (Streamline Permitting Process for Small Residential Rooftop Solar Systems) governs the PV permit itself.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined

Why the confidence is not higherPV/ESS is issued as a single building permit application (BLD record in Accela) that incorporates the electrical scope; a separate stand-alone electrical fee schedule exists for non-PV electrical work but the PV/PRT process itself is one combined application.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Licensed electrician / Either

Why the confidence is not higherThe expedited PRT/SolarAPP+ path explicitly requires the 'Applicant' to be a California-licensed contractor; the standard (non-PRT) path is not separately addressed on the City's PV pages, so whether an owner-electrician could pull it is unconfirmed for that path.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes

Why the confidence is not higherMMC Sec. 12.04.030: 'No building permit shall be issued to any licensed contractor to do any building, plumbing, heating or electrical work unless that contractor holds a business license duly issued by the city.' This is a City business license, not a separate contractor-registration scheme.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

No (for the expedited PRT/SolarAPP+ path)

Why the confidence is not higherPRT eligibility explicitly requires 'Applicant is a California-licensed contractor,' excluding homeowner self-permit from that path. The standard, non-expedited path is not separately addressed on the City's PV pages for owner-builder solar, so this is not fully resolved city-wide.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q8 What documents make up a complete submittal? Core Submittal package

Site plan (ESS/disconnect/grounding locations), roof plan (plumbing vents), roof section(s), installation details, electrical one-line (wire sizes, existing bus capacity, main disconnect), PV labeling plan, Building Permit Application form, structural calculations, electrical load calculations, all product specifications, and (if MPFPD review is required) the MPFPD approval letter.

Why the confidence is not higherDirectly enumerated as 'Plan Set Requirements' and 'Required Supporting Documents' on the City's PRT submittal-requirements page.

checklist checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q9 How many copies, and in what format? Submittal package

Electronic/digital submission only, via the Accela Citizen Access (ACA) portal

Why the confidence is not higherDepartment page states 'The Building Division is fully digital and uses the Accela Platform to process all aspects of the permitting and inspection process'; PV pages reference the City's own file specifications for submittal but I did not locate the specific file-spec document (page/count/DPI limits).

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes -- must show ESS location, dedicated ESS disconnect location, and grounding system location.

Why the confidence is not higherPRT plan-set requirement list, item 'Site Plan.'

checklist checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes

Why the confidence is not higherPRT plan set requires an 'Electrical Plan - To include an electrical one-line drawing with wire sizes, existing bus capacity and main disconnect.'

checklist checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q12 Are string and conductor calculations required? Drawings & calculations

Yes

Why the confidence is not higherInstallation-requirements page requires 'calculations demonstrating that the existing bus capacity and main disconnect will not be overloaded' and a separate 'Electrical Load Calculations' document.

checklist checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

Structural calculations are required whenever PV roof-attachment standoff spacing exceeds 72 inches, or whenever roof-framing modifications are proposed; plans generally must carry the seal of a licensed architect or designer (the City's page cites MMC 12.22.050 and Bus. & Prof. Code Sec. 5536.1, though the currently codified text of MMC 12.22.050 itself does not contain this language -- see note).

Why the confidence is not higherInstallation-requirements page states the 72-inch threshold and the seal requirement, but the statutory cross-reference on that page does not match the actual codified content of MMC 12.22.050 (which is about submittal-fee compliance, not stamping) when read on eCode360 -- flagging this discrepancy rather than resolving it silently.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Nothing published by this authority.

Where we lookedCity's PV/ESS installation-requirements and PRT pages (electrical requirements sections) -- these list wiring diagrams, load calculations, and grounding details but never state a valuation or capacity threshold requiring an electrical PE stamp.

https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q15 What does a residential solar permit cost? Core Fees

Fee schedule reads "State Limit" for both the plan-check and permit fee on "Photovoltaic System - Residential" -- i.e., capped by state law rather than set by the City as a flat dollar figure.

Why the confidence is not higher2026 Master Fee Schedule (effective mid-2026, ModDate 20 Aug 2026) lists 'Photovoltaic System - Residential ... State Limit / State Limit' under Miscellaneous Construction Fees, and MMC Sec. 12.22.050 cross-references the controlling statutes: Gov. Code Secs. 65850.55, 66015, 66016 and Health & Safety Code Sec. 17951.

fee schedule checked 2026-08-30 https://www.menlopark.gov/files/sharedassets/public/v/2/administrative-services/documents/finance/master-fee-schedule/2026-approved-master-fee-schedule-effective-july-14.pdf

Q16 How is the fee calculated? Core Fees

Tiered

Why the confidence is not higherThe fee is not a flat city figure but a statutory cap (Gov. Code Sec. 65850.55) referenced only as 'State Limit' in the schedule; 'Tiered' is the closest available option to a statutory graduated cap, but the schedule itself does not print the calculation.

fee schedule checked 2026-08-30 https://www.menlopark.gov/files/sharedassets/public/v/2/administrative-services/documents/finance/master-fee-schedule/2026-approved-master-fee-schedule-effective-july-14.pdf

Q17 Is there a separate plan-check fee? Fees

Yes

Why the confidence is not higherFee schedule lists 'Plan Check' and 'Permit' as two separate columns for Photovoltaic System - Residential, both marked 'State Limit.'

fee schedule checked 2026-08-30 https://www.menlopark.gov/files/sharedassets/public/v/2/administrative-services/documents/finance/master-fee-schedule/2026-approved-master-fee-schedule-effective-july-14.pdf

Q18 What is the stated plan-review turnaround? Core Timeline & validity

Real-time for the automated PRT/SolarAPP+ path; for a non-expedited application, MMC Sec. 12.22.060 sets a statutory 45-day deemed-approved clock (unless denied in writing or a reasonable information request is pending), and the Building Division was required to stand up its expedited review process within 30 days of the ordinance's effective date.

Why the confidence is not higherCodified in MMC Ch. 12.22.060; no separate 'X business days' turnaround figure was found published on the department pages I could reach.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q19 How long is an issued permit valid before it expires? Timeline & validity

Not locally amended -- defaults to the adopted 2025 CBC's standard permit-expiration provision (commonly 180 days).

Why the confidence is not higherSearched the full text of MMC Title 12 (Buildings and Construction) for 'expire'/'expiration'/'valid for' with zero hits, confirming no local amendment to permit validity; the 2025 CBC is adopted by reference (MMC 12.04.010) so its own base-code expiration section governs, but I did not pull the CBC's own section text to confirm the exact day count.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q20 Which permit portal does this authority use? Core Portal & process

Accela Citizen Access (ACA); SolarAPP+ is used as the front-end 'Processor' for PRT-eligible residential PV.

Why the confidence is not higherNamed directly on both the general PV page and the PRT-specific page.

portal landing page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q21 Can the whole application be completed online? Core Portal & process

Yes, for PRT-eligible residential PV (existing single-family, roof-mounted, new PV only, no battery/EV charger, <=38.4 kW, <=400A service, 225A disconnect/busbar, CA-licensed contractor). Batteries and EV chargers are excluded from real-time issuance and must use the standard review path.

Why the confidence is not higherPRT eligibility criteria are stated verbatim on the City's PRT page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q22 Which utility handles interconnection here? Core Utility interconnection

PG&E (Pacific Gas & Electric)

Why the confidence is not higherInferred: the City's department directory lists no municipal electric utility (Administrative Services, City Attorney, City Manager, Community Development, Library & Community Services, Police, Public Works only -- Public Works' utility role is limited to the separate Menlo Park Municipal Water system), and San Mateo County sits entirely within PG&E's IOU electric territory. I could not find a City page that names PG&E by name for electric service, so this is inference rather than a direct city statement -- flagged per the brief's rule on utility confirmation.

department directory (inference) checked 2026-08-30 https://www.menlopark.gov/Government/Departments

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After permit -- PG&E Permission to Operate (PTO) is expressly gated on the AHJ's final-inspection clearance.

Why the confidence is not higherPG&E Electric Rule 21 tariff (Sec. D.13.b) confirms interconnection/PTO occurs after the applicant demonstrates final inspection clearance from the AHJ; this is a utility-level tariff fact rather than a Menlo Park-specific statement.

utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No

Why the confidence is not higherMMC Sec. 12.22.060 codifies the Solar Rights Act protection directly: 'The city of Menlo Park shall not provide conditional approval of an application for a small residential rooftop solar energy system on the approval of an association.'

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q25 Is there a historic-district review? Overlays & special cases

Yes, but only for properties within the designated 'H' Historic Site District or a City-designated landmark site (MMC Ch. 16.54); not a citywide requirement.

Why the confidence is not higherMMC Ch. 16.54 (H Historic Site District) establishes a landmark-designation and review process; Sec. 16.54's design-review clause applies to structures on a designated landmark site, not to ordinary single-family parcels.

zoning code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47185712

Q26 Is a wind or windstorm certification required? Overlays & special cases

Nothing published by this authority.

Where we lookedMMC Title 12 (full text search for 'wind' load context) and the PV installation-requirements page, which addresses wind loads only as one factor in the structural-calculation requirement for wide standoff spacing, with no separate 'windstorm certification' document or program named.

https://ecode360.com/print/ME4536?guid=47072961

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Yes, conditionally -- the Planning Division may require a use permit if it finds, based on substantial evidence, that the solar system could have a 'specific, adverse impact' on public health and safety; the Building Official may then deny the use permit only on written findings of such impact with no feasible mitigation.

Why the confidence is not higherDirectly codified in MMC Sec. 12.22.060.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q28 Is there a system-size cap on residential generation? Overlays & special cases

Two different caps found: (1) the codified 'small residential rooftop solar energy system' definition in MMC Sec. 12.22.020(b)(1) is capped at 10 kW AC nameplate / 30 kW thermal (the AB 2188-era figure, unchanged since 2016); (2) the City's live PRT/SolarAPP+ automated-issuance eligibility page caps eligible systems at 38.4 kW AC or less. These are two different thresholds for two different purposes (statutory 'small system' definition vs. real-time issuance eligibility) and neither has been reconciled with the other in the published material.

Why the confidence is not higherBoth figures are quoted directly from City sources -- MMC 12.22.020 (codified 2016, Ord. 1022) and the current (2026) PRT page -- and read exactly as stated; this is the same codified-vs-live discrepancy documented across other CA cities in this survey.

municipal code + department page checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? 2023 NEC (as incorporated into the 2025 California Electrical Code) 90% · adopting ordinance
    • Which building code edition is in force? 2025 California Building Code and 2025 California Residential Code 95% · adopting ordinance
    • Which fire code edition is in force? 2025 California Fire Code, based on the 2024 International Fire Code 90% · adopting ordinance (image-only PDF, OCR'd)
    • Are there local amendments to any of the above? Yes. Local amendments exist to the Building, Residential, Plumbing (Sec. 808.2, single-pass cooling-water ban), Energy (Sec. 12.16.010, an 'Energy Efficient Measures and Electrification' menu for projects with >=$100,000 valuation), and CALGreen codes. By contrast, MMC Ch. 12.10 (Electrical Code Amendments) and Ch. 12.12 (Mechanical Code Amendments) are both explicitly marked '(Reserved)' -- i.e. no local amendments to the CEC or Mechanical Code at all. Notably, Ord. 1124 (8/26/2025) added Energy Code sections 12.16.030 and 12.16.040 -- BEFORE AB 130's 1 Oct 2025 freeze on more-restrictive residential amendments -- and those sections were then repealed by Ord. 1127 (11/4/2025), AFTER the freeze began. The currently codified Ch. 12.16 no longer contains whatever those repealed sections said, so I cannot characterize their content (they may have been an all-electric/gas-restriction provision consistent with Menlo Park's known reach-code history); the repeal itself, occurring after the freeze started, is a relaxation and AB 130 only restricts adopting MORE restrictive standards, so it does not appear to conflict with AB 130 on its face, but I could not find a BSC filing record confirming this reading. 82% · municipal code (editor's note)
    • What is the installation judged against? 2025 CRC Secs. R301.4-R301.8 (roof loads/attachment), 2025 CEC Secs. 690.12 (rapid shutdown), 690.15(A) (disconnect location), 690.31(D)(2) (labeling), and the 2025 CFC as adopted by MPFPD Ordinance 60-2026 for fire-related work. 85% · department page
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    • What ridge setback and access pathways are required? Not locally amended -- governed by the unamended 2025 CFC rooftop-access-pathway/setback provisions as adopted by MPFPD Ordinance 60-2026. I OCR'd all 22 pages of that ordinance's local-amendment sections and found only sprinkler-system and occupancy-classification changes (e.g., a fire-sprinkler exception for independent solar carports); no modification to the CFC's own rooftop PV pathway/setback table was found. 55% · adopting ordinance (image-only PDF, OCR'd)
  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Yes -- rapid shutdown is required per CEC 690.12 (2025 CEC / 2023 NEC basis), or the applicant must justify why it does not apply. 92% · department page
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? A PV-system label at the service equipment per CEC 690.31(D)(2), plus PV and ESS disconnect labeling per CEC 690.15(A)/705; the City's page does not separately name a distinct city-specific 'placard' beyond these CEC-cross-referenced labels. 75% · department page
    • Does the authority specify placard wording of its own? No -- the City does not publish its own custom placard wording; it cross-references the CEC's generic marking requirement (CEC 690.31(D)(2)) rather than specifying exact text. 70% · department page
    • Does it specify letter height, colour or material? Yes -- minimum 3/8-inch height, all capital letters, white text on a red background, using reflective material suitable for the installation environment. 92% · department page
    • Does the UTILITY specify placards beyond the AHJ's? Yes -- PG&E's Electric Rule 21 tariff requires that the visible interconnection/point-of-common-coupling disconnect carry markings or signage that clearly indicate its open and closed positions, on top of whatever the AHJ requires. 75% · utility tariff
    • Where must the labels be placed? At the service equipment/disconnects: the PV/ESS disconnect must be readily accessible, located either within the equipment or within sight and within 10 feet of it (CEC 690.15(A)); the ESS disconnect specifically must be located outside the dwelling (even if the ESS itself is inside a garage) so emergency responders can access it; the City states a POLICY preference (not a hard requirement) that the PV disconnect be independent of the main service disconnect. 88% · department page
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? Per CEC 690.15(A): the disconnect must be readily accessible, located either within the equipment or within sight and within 10 feet of the point-of-connection equipment; the City states a policy PREFERENCE (not mandatory) that the PV disconnect be independent of the main service disconnect. The finer PG&E meter-clearance specification (Greenbook doc TD-2306M) sits behind PG&E's gated Greenbook portal and could not be checked in this run. 78% · department page
    • Must equipment be on a specific approved list? No dedicated City-approved equipment list found; the City requires manufacturer specifications for all proposed equipment and, for ESS units stacked or spaced under 3 feet, a UL 9540 listing plus a UL 9540A test report for AHJ review -- i.e. listing/testing standards rather than a pre-approved product list. 75% · department page
    • Are batteries permitted, and under what conditions? Yes, with conditions: a heat detector is required at the ESS location; if units are stacked or separated by less than 3 feet, the ESS must be UL 9540-listed with a UL 9540A test report supplied for AHJ review; the ESS disconnect must be within 10 feet of, and within sight of, the unit (CEC 690.15(A)) and must be located OUTSIDE the dwelling even if the ESS is installed in a garage; wall-mounted ESS requires structural verification of stud sizing/spacing (or manufacturer installation guidance) per CRC R301.4-R301.8; and any building machinery/equipment (including ESS) must sit above the Design Flood Elevation in flood-prone parcels. 90% · department page
    • Is there a separate ESS permit or inspection? Yes -- ESS is explicitly excluded from the automated PRT/SolarAPP+ real-time issuance path and must go through the standard (non-expedited) building permit process; the City's electrical fee schedule also carries a distinct 'Battery Storage' line item ($229.45 plan check / $319.84 permit) separate from the PV line items. 85% · department page + fee schedule
    • Is a ground mount treated as a structure? Yes, by inference -- there is no PV-specific ground-mount ordinance, but MMC Sec. 12.32.010's general definition of 'Structure' ('that which is built or constructed... or any piece of work artificially built up or composed of parts joined together in some definite manner') is broad enough to capture a ground-mounted PV array, and Title 16 (Zoning) contains ground-mount provisions only for satellite-dish antennae and ground-mounted mechanical equipment, with no PV carve-out either way. 55% · zoning code
    • Is there a local rule on service upgrades or busbar sizing? No local ordinance amendment on busbar sizing/service upgrades -- MMC Ch. 12.10 (California Electrical Code Amendments) is explicitly '(Reserved),' meaning the City has made zero local amendments to the CEC. The 400A-service/225A-disconnect/225A-busbar figures on the PRT page are ELIGIBILITY criteria for the automated real-time path, not a universal local busbar rule that applies to every PV permit. 85% · municipal code
    • Is a specific mounting system or attachment spacing required? Yes -- structural calculations are required for PV roof-attachment standoff spacing wider than 72 inches (dead/point/wind loads), plus a connection detail of the standoff to existing roof framing and verification the roof can carry the loads per CRC R301.4-R301.8. 90% · department page

20 questions answered against City of Menlo Park’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2023 NEC (as incorporated into the 2025 California Electrical Code)

Why the confidence is not higherMMC Sec. 12.04.010(4) adopts 'The 2025 California Electrical Code, Part 3 of the California Building Standards Code'; the 2025 CEC cycle is based on the 2023 NEC per the state cycle (per Title 24 rulemaking, not independently re-verified against the CEC text itself in this run).

adopting ordinance checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q30 Which building code edition is in force? Core Code editions in force

2025 California Building Code and 2025 California Residential Code

Why the confidence is not higherMMC Sec. 12.04.010(2)-(3) adopts both by reference.

adopting ordinance checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q31 Which fire code edition is in force? Code editions in force

2025 California Fire Code, based on the 2024 International Fire Code

Why the confidence is not higherThe City's own Municipal Code contains NO fire-code title at all (confirmed by listing all 16 Titles on eCode360 -- Titles 1-16, none titled 'Fire'). The Fire Code is instead adopted directly by the Menlo Park Fire Protection District via its own Ordinance No. 60-2026, 'District Fire Prevention Code for the City of Menlo Park,' under Health & Safety Code Sec. 13869 et seq. and Sec. 13869.7, with the City agreeing only to 'ratify and implement this adoption by reference.' This is itself the jurisdictional finding: the City does not hold Fire Code adoption authority here at all.

adopting ordinance (image-only PDF, OCR'd) checked 2026-08-30 https://www.menlofire.gov/media/Fire%20Prevention/Guidelines%20and%20Standards/Ordinance%2060-2026%20-%20City%20of%20Menlo%20Park.pdf

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes. Local amendments exist to the Building, Residential, Plumbing (Sec. 808.2, single-pass cooling-water ban), Energy (Sec. 12.16.010, an 'Energy Efficient Measures and Electrification' menu for projects with >=$100,000 valuation), and CALGreen codes. By contrast, MMC Ch. 12.10 (Electrical Code Amendments) and Ch. 12.12 (Mechanical Code Amendments) are both explicitly marked '(Reserved)' -- i.e. no local amendments to the CEC or Mechanical Code at all. Notably, Ord. 1124 (8/26/2025) added Energy Code sections 12.16.030 and 12.16.040 -- BEFORE AB 130's 1 Oct 2025 freeze on more-restrictive residential amendments -- and those sections were then repealed by Ord. 1127 (11/4/2025), AFTER the freeze began. The currently codified Ch. 12.16 no longer contains whatever those repealed sections said, so I cannot characterize their content (they may have been an all-electric/gas-restriction provision consistent with Menlo Park's known reach-code history); the repeal itself, occurring after the freeze started, is a relaxation and AB 130 only restricts adopting MORE restrictive standards, so it does not appear to conflict with AB 130 on its face, but I could not find a BSC filing record confirming this reading.

Why the confidence is not higherDates and ordinance numbers read directly from the eCode360 editor's note on Ch. 12.16; content of the repealed sections themselves is not recoverable from the current codification and I did not attempt a Wayback reconstruction in this run -- flagged as unresolved rather than guessed.

municipal code (editor's note) checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q33 What is the installation judged against? Core Electrical

2025 CRC Secs. R301.4-R301.8 (roof loads/attachment), 2025 CEC Secs. 690.12 (rapid shutdown), 690.15(A) (disconnect location), 690.31(D)(2) (labeling), and the 2025 CFC as adopted by MPFPD Ordinance 60-2026 for fire-related work.

Why the confidence is not higherAll cited directly on the City's PV/ESS installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

No local ordinance amendment on busbar sizing/service upgrades -- MMC Ch. 12.10 (California Electrical Code Amendments) is explicitly '(Reserved),' meaning the City has made zero local amendments to the CEC. The 400A-service/225A-disconnect/225A-busbar figures on the PRT page are ELIGIBILITY criteria for the automated real-time path, not a universal local busbar rule that applies to every PV permit.

Why the confidence is not higherCh. 12.10's '(Reserved)' status confirmed directly on eCode360; PRT eligibility figures confirmed on the PRT page and correctly characterized as an eligibility gate, not a code amendment.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Yes -- structural calculations are required for PV roof-attachment standoff spacing wider than 72 inches (dead/point/wind loads), plus a connection detail of the standoff to existing roof framing and verification the roof can carry the loads per CRC R301.4-R301.8.

Why the confidence is not higherStated directly on the City's PV/ESS installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Not locally amended -- governed by the unamended 2025 CFC rooftop-access-pathway/setback provisions as adopted by MPFPD Ordinance 60-2026. I OCR'd all 22 pages of that ordinance's local-amendment sections and found only sprinkler-system and occupancy-classification changes (e.g., a fire-sprinkler exception for independent solar carports); no modification to the CFC's own rooftop PV pathway/setback table was found.

Why the confidence is not higherThis is a proved absence within the local-amendment ordinance, but I did not separately pull the base 2025 CFC's own pathway table to state the numeric setback itself -- that table lives in the unamended state model code, not in MPFPD's local ordinance.

adopting ordinance (image-only PDF, OCR'd) checked 2026-08-30 https://www.menlofire.gov/media/Fire%20Prevention/Guidelines%20and%20Standards/Ordinance%2060-2026%20-%20City%20of%20Menlo%20Park.pdf

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes -- rapid shutdown is required per CEC 690.12 (2025 CEC / 2023 NEC basis), or the applicant must justify why it does not apply.

Why the confidence is not higherStated verbatim on the City's PV/ESS installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

A PV-system label at the service equipment per CEC 690.31(D)(2), plus PV and ESS disconnect labeling per CEC 690.15(A)/705; the City's page does not separately name a distinct city-specific 'placard' beyond these CEC-cross-referenced labels.

Why the confidence is not higherContent drawn from the 'PV labeling requirements' section of the installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No -- the City does not publish its own custom placard wording; it cross-references the CEC's generic marking requirement (CEC 690.31(D)(2)) rather than specifying exact text.

Why the confidence is not higherThe installation-requirements page states format/material/colour requirements but does not quote specific required wording (contrast with cities like Hollister or Watsonville that print exact wording).

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Yes -- minimum 3/8-inch height, all capital letters, white text on a red background, using reflective material suitable for the installation environment.

Why the confidence is not higherQuoted directly, citing CEC 690.31(D)(2), on the installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedCity's PV/ESS pages for a dedicated site-plan/facility-map PLACARD (as distinct from the site-plan drawing submitted with the plan set) -- only the plan-set 'Site Plan' drawing requirement was found, not a physical facility-map placard spec.

https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes -- PG&E's Electric Rule 21 tariff requires that the visible interconnection/point-of-common-coupling disconnect carry markings or signage that clearly indicate its open and closed positions, on top of whatever the AHJ requires.

Why the confidence is not higherConfirmed by direct text search of the PG&E Rule 21 tariff PDF ('include markings or signage that clearly indicates open and closed'); this is a utility-wide tariff requirement, not Menlo Park-specific.

utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the service equipment/disconnects: the PV/ESS disconnect must be readily accessible, located either within the equipment or within sight and within 10 feet of it (CEC 690.15(A)); the ESS disconnect specifically must be located outside the dwelling (even if the ESS itself is inside a garage) so emergency responders can access it; the City states a POLICY preference (not a hard requirement) that the PV disconnect be independent of the main service disconnect.

Why the confidence is not higherDirectly quoted from the installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q44 Must equipment be on a specific approved list? Equipment listing

No dedicated City-approved equipment list found; the City requires manufacturer specifications for all proposed equipment and, for ESS units stacked or spaced under 3 feet, a UL 9540 listing plus a UL 9540A test report for AHJ review -- i.e. listing/testing standards rather than a pre-approved product list.

Why the confidence is not higherDrawn from the installation-requirements page's 'ESS installation details' and 'Other documents required' sections.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes, with conditions: a heat detector is required at the ESS location; if units are stacked or separated by less than 3 feet, the ESS must be UL 9540-listed with a UL 9540A test report supplied for AHJ review; the ESS disconnect must be within 10 feet of, and within sight of, the unit (CEC 690.15(A)) and must be located OUTSIDE the dwelling even if the ESS is installed in a garage; wall-mounted ESS requires structural verification of stud sizing/spacing (or manufacturer installation guidance) per CRC R301.4-R301.8; and any building machinery/equipment (including ESS) must sit above the Design Flood Elevation in flood-prone parcels.

Why the confidence is not higherAll directly quoted from the 'ESS installation details' section of the installation-requirements page.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Yes -- ESS is explicitly excluded from the automated PRT/SolarAPP+ real-time issuance path and must go through the standard (non-expedited) building permit process; the City's electrical fee schedule also carries a distinct 'Battery Storage' line item ($229.45 plan check / $319.84 permit) separate from the PV line items.

Why the confidence is not higherPRT eligibility exclusion is stated directly on the PRT page; the separate fee line is read directly from the 2026 Master Fee Schedule (Electrical Plan Check and Permit Fees section).

department page + fee schedule checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q47 Is a ground mount treated as a structure? Core Ground mount

Yes, by inference -- there is no PV-specific ground-mount ordinance, but MMC Sec. 12.32.010's general definition of 'Structure' ('that which is built or constructed... or any piece of work artificially built up or composed of parts joined together in some definite manner') is broad enough to capture a ground-mounted PV array, and Title 16 (Zoning) contains ground-mount provisions only for satellite-dish antennae and ground-mounted mechanical equipment, with no PV carve-out either way.

Why the confidence is not higherSearched the full text of Title 16 (Zoning, 765,000+ characters via eCode360 print route) for 'solar' (50 hits, all read -- none are a ground-mount PV rule), 'ground mount'/'ground-mount' (8 hits total, all antennae/mechanical-equipment specific), with positive control 'electrical' (6 hits, confirming the search mechanism works) and fabricated control 'zzqqx' (0 hits). This is an inference from the general Structure definition, not a PV-specific rule.

zoning code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47185712

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Per CEC 690.15(A): the disconnect must be readily accessible, located either within the equipment or within sight and within 10 feet of the point-of-connection equipment; the City states a policy PREFERENCE (not mandatory) that the PV disconnect be independent of the main service disconnect. The finer PG&E meter-clearance specification (Greenbook doc TD-2306M) sits behind PG&E's gated Greenbook portal and could not be checked in this run.

Why the confidence is not higherCEC 690.15(A) language and City policy preference quoted directly from the installation-requirements page; the gated Greenbook document is noted as a genuine gap rather than guessed.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-System-and-ESS-Installation-Requirements

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal 90% · department page
    • Are same-day or AM/PM windows offered? Yes via the ACA portal, which lets the requester choose a morning/afternoon window; the mobile app allows scheduling by day only, with no AM/PM selection. Next-day inspections are not guaranteed. 88% · department page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes, for the building/electrical scope -- the Building Division performs the single required PV inspection itself; fire-related work is separately inspected by MPFPD (see jurisdiction block), so this is best read as 'Yes' for the City's own scope and 'Delegated' for the fire-code scope. 85% · municipal code
    • If delegated, to whom? Menlo Park Fire Protection District (fire-code-related work only) 90% · municipal code
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? MPFPD fire approval (where required) must be obtained and its approval letter uploaded to ACA BEFORE the City will issue the building permit; after issuance, a single combined building/electrical final inspection is performed by the Building Division, with a follow-up/subsequent inspection authorized only if the first fails. 85% · department page + municipal code
    • Is a rough-in or mid-roof inspection required? No 90% · municipal code
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? Yes, for the PRT/SolarAPP+ path -- the SolarAPP+ processor generates a downloadable 'inspection checklist' alongside the approval certificate, which must be uploaded into ACA. No separately published City inspection checklist was found for the standard (non-PRT) path. 75% · department page
    • What must be on site at inspection? General policy: any inspection-relevant document (special inspection reports, structural observation letters, etc.) that is subject to field verification must be available on site -- either electronic or hard copy -- at the time of inspection, per the Building Inspector's direction for the specific permit. No PV-specific 'must have X on site' list was found; this is the City's general inspection-documents policy. 60% · department page
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • Who notifies the utility for PTO? Installer (applicant submits proof of AHJ final-inspection clearance to PG&E to obtain Permission to Operate) 60% · utility tariff
    • Is there a re-inspection fee? $144.25 for the first half hour (and $144.25 for each additional half hour) 88% · fee schedule
    • How are corrections issued and cleared? A written correction notice detailing all deficiencies and any additional information/documentation needed is sent to the applicant for resubmission; for a failed field inspection, a follow-up/subsequent inspection is authorized once corrections are made. 85% · municipal code

14 questions answered against City of Menlo Park’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal

Why the confidence is not higher'The City of Menlo Park accepts inspection requests exclusively through its online system' -- either the 'Menlo Park Inspection Request' mobile app or the Accela Citizen Access (ACA) portal; phone is offered only for day-of rescheduling/urgency, not as a primary booking channel.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections

Q50 How much notice is required? Core Booking & scheduling

Nothing published by this authority.

Where we looked'Scheduling Inspections' and 'Inspections' department pages -- both describe how to book (portal/app) and note inspector availability limits during busy seasons, but neither states a specific number of business days' advance notice required.

https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections/Scheduling-Inspections

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Yes via the ACA portal, which lets the requester choose a morning/afternoon window; the mobile app allows scheduling by day only, with no AM/PM selection. Next-day inspections are not guaranteed.

Why the confidence is not higherDirectly stated on the 'Scheduling Inspections' page, contrasting the two booking channels.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections/Scheduling-Inspections

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes, for the building/electrical scope -- the Building Division performs the single required PV inspection itself; fire-related work is separately inspected by MPFPD (see jurisdiction block), so this is best read as 'Yes' for the City's own scope and 'Delegated' for the fire-code scope.

Why the confidence is not higherMMC Sec. 12.22.060: 'Only one (1) inspection shall be required and performed by the building division for small residential rooftop solar energy systems eligible for expedited review... A separate permit and fire inspection may be required and performed by the Menlo Park Fire Protection District.'

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q53 If delegated, to whom? Core Who inspects

Menlo Park Fire Protection District (fire-code-related work only)

Why the confidence is not higherSame MMC Sec. 12.22.060 citation as Q52/jurisdiction block.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q54 Which inspections are required, and in what order? Core Stages & sequence

MPFPD fire approval (where required) must be obtained and its approval letter uploaded to ACA BEFORE the City will issue the building permit; after issuance, a single combined building/electrical final inspection is performed by the Building Division, with a follow-up/subsequent inspection authorized only if the first fails.

Why the confidence is not higherSequence stated directly across the PV page ('will not be issued until... MPFPD has approved') and MMC 12.22.060 ('Only one (1) inspection shall be required... If a small residential rooftop solar energy system fails inspection, a subsequent inspection is authorized').

department page + municipal code checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

No

Why the confidence is not higherMMC Sec. 12.22.060: 'Only one (1) inspection shall be required and performed by the building division for small residential rooftop solar energy systems eligible for expedited review.'

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q56 Does the inspector verify labels and listings? Core What is checked

Nothing published by this authority.

Where we lookedDepartment inspection pages and MMC 12.22.060 -- the code requires the field inspection to confirm compliance with 'current California Building Code and/or California Electrical Code requirements' generally, but no page explicitly states that labels/listings are checked as a discrete inspection item.

https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections

Q57 Is there a published inspection checklist? Core What is checked

Yes, for the PRT/SolarAPP+ path -- the SolarAPP+ processor generates a downloadable 'inspection checklist' alongside the approval certificate, which must be uploaded into ACA. No separately published City inspection checklist was found for the standard (non-PRT) path.

Why the confidence is not higherStated on the PRT page ('Download the approval document (certificate) and inspection checklist... Inspection checklist from processor application' listed among Required documents).

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Photovoltaic-and-ESS-Systems-Permit-Information/Photovoltaic-Real-Time-PRT-Permit-Submittal-Requirements

Q58 What must be on site at inspection? Core Documents on site

General policy: any inspection-relevant document (special inspection reports, structural observation letters, etc.) that is subject to field verification must be available on site -- either electronic or hard copy -- at the time of inspection, per the Building Inspector's direction for the specific permit. No PV-specific 'must have X on site' list was found; this is the City's general inspection-documents policy.

Why the confidence is not higherDrawn from the 'How to Upload Inspection Documents' page, which is general to all permit types, not solar-specific.

department page checked 2026-08-30 https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections/How-to-Upload-Inspection-Documents

Q59 Is there a re-inspection fee? Corrections & re-inspection

$144.25 for the first half hour (and $144.25 for each additional half hour)

Why the confidence is not higher2026 Master Fee Schedule, 'HOURLY INSPECTION RATES' -- 'Re-Inspection Fee and Inspection Cancellation Fee (first 1/2 hour) $144.25' plus 'Each Additional 1/2 hour $144.25.' Not solar-specific (general Building Division re-inspection fee), so it is likely the fee that would apply to a failed solar final.

fee schedule checked 2026-08-30 https://www.menlopark.gov/files/sharedassets/public/v/2/administrative-services/documents/finance/master-fee-schedule/2026-approved-master-fee-schedule-effective-july-14.pdf

Q60 How are corrections issued and cleared? Corrections & re-inspection

A written correction notice detailing all deficiencies and any additional information/documentation needed is sent to the applicant for resubmission; for a failed field inspection, a follow-up/subsequent inspection is authorized once corrections are made.

Why the confidence is not higherMMC Sec. 12.22.060.

municipal code checked 2026-08-30 https://ecode360.com/print/ME4536?guid=47072961

Q61 What is issued on pass? Core Final sign-off & PTO

Nothing published by this authority.

Where we lookedDepartment inspection and PV pages -- none name what document/status (CO, Final, Green tag, or Letter) is issued on a passed PV final; the ACA portal record status terminology was not directly observable without an actual permit record to inspect.

https://www.menlopark.gov/Government/Departments/Community-Development/Building/Online-services/Inspections

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer (applicant submits proof of AHJ final-inspection clearance to PG&E to obtain Permission to Operate)

Why the confidence is not higherInferred from PG&E's Electric Rule 21 tariff (Sec. D.13.b), which is a utility-wide, not Menlo Park-specific, provision; no City page addresses the PTO-notification step directly.

utility tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Jurisdiction & key facts

The standing 62-question set, answered for City of Menlo Park against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

City of Menlo Park is the authority having jurisdiction 92% confidence
Holds
Building and Electrical (Community Development Department, Building Division)
Delegated to
Menlo Park Fire Protection District (MPFPD) holds all Fire Code review, permitting and inspection for solar PV and ESS installations city-wide
Overridden by
MPFPD approval is a precondition, not a delegation from the City: the City's own Municipal Code contains no Fire Code title at all (Titles 1-16 checked via eCode360 TOC; no 'Fire' title exists), and MPFPD Ordinance No. 60-2026 recites that it adopts the 2025 CFC 'For the City of Menlo Park' under Health & Safety Code Section 13869.7, with the City agreeing only to 'ratify and implement this adoption by reference.' A City building permit will not be issued until MPFPD has approved the project.
Why not higher
MPFPD is confirmed on its own website ('Our Fire District') as an independent special district with its own elected Board of Directors serving Atherton, Menlo Park, East Palo Alto, and unincorporated San Mateo County (~30 sq mi, ~90,000 population) -- not coterminous with the City. The City's own PV/ESS page states in its own words: 'The Menlo Park Fire Protection District (MPFPD) is a separate and independent agency from the City of Menlo Park' and 'A Building permit from the City of Menlo Park will not be issued until the MPFPD has approved the project if a permit is required.' MMC Ch. 12.22.060 (codified) independently confirms: 'A separate permit and fire inspection may be required and performed by the Menlo Park Fire Protection District.' Confidence is not higher only because I could not independently verify whether the City's business-license/permit desk ever second-guesses an MPFPD sign-off.

https://www.menlofire.gov/our-fire-district

Permit required
Yes95%
Permit cost
Fee schedule reads "State Limit" for both the plan-check and permit fee on "Photovoltaic System - Residential" -- i.e.,85%
Plan review
Real-time for the automated PRT/SolarAPP+ path; for a non-expedited application, MMC Sec. 12.22.060 sets a statutory 45-day deemed-approved clock (unless denied in writing or a reasonable…80%
Portal
Accela Citizen Access (ACA); SolarAPP+ is used as the front-end 'Processor' for PRT-eligible residential PV.95%
Electrical code
2023 NEC (as incorporated into the 2025 California Electrical Code)90%
Own placard wording
No -- the City does not publish its own custom placard wording; it cross-references the CEC's generic marking requirement (CEC 690.31(D)(2)) rather than specifying exact text.70%
Booking an inspection
Portal90%
Labels & placards for this authority

Wording 70%

No -- the City does not publish its own custom placard wording; it cross-references the CEC's generic marking requirement (CEC 690.31(D)(2)) rather than specifying exact text.

Size, colour & material 92%

Yes -- minimum 3/8-inch height, all capital letters, white text on a red background, using reflective material suitable for the installation environment.

Where they go 88%

At the service equipment/disconnects: the PV/ESS disconnect must be readily accessible, located either within the equipment or within sight and within 10 feet of it (CEC 690.15(A)); the ESS disconnect specifically must be located outside the dwelling (even if the ESS itself is inside a garage) so emergency responders can access it; the City states a POLICY preference (not a hard requirement) that the PV disconnect be independent of the main service disconnect.

What the utility wants on top 75%

Yes -- PG&E's Electric Rule 21 tariff requires that the visible interconnection/point-of-common-coupling disconnect carry markings or signage that clearly indicate its open and closed positions, on top of whatever the AHJ requires.

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
City
County
San Mateo County
Regions served
1
Regions covered
City of Menlo Park · city
Solar Requirements
Authority Contact
Address
701 Laurel St., Menlo Park, CA 94025
Main Phone
650-330-6600
Building Department
Department
Building Division, Community Development Department
Direct Phone
650-330-6704
Portal Software
Accela
Booking & Scheduling
Preferred channel
online_portal
Book in advance
next business day not guaranteed
Notes
Uses Accela Citizen Access (ACA) portal for all permit applications and inspection scheduling. Residential rooftop solar PV systems up to 38.4 kW use the Photovoltaic Real-Time (PRT) permit process: installers submit via SolarAPP+ (https://gosolarapp.org/login) first, then upload approved docs to ACA portal. Battery ESS and EV charger add-ons are NOT eligible for automated PRT issuance and require standard review. After construction, inspections are scheduled in ACA under My Records > permit record number > Schedule an Inspection. Also available via Menlo Park Inspection Request mobile app (iOS/Android). For expedited inspections call 650-330-6767 (7:30-9:00 AM) or 650-330-6710 (after 9:00 AM). Inspection scheduling phone: 650-330-6767. Menlo Park Fire Protection District may require a separate fire permit (www.menlofire.org, 650-688-8400). Office hours: Mon-Thu 7:30 AM-5:30 PM; every other Friday 8:00 AM-5:00 PM (alternate Fridays closed). General permits/questions: 650-330-6704 or Permitteam@menlopark.gov.