City of Pomona

Los Angeles County

Verified Aug. 5, 2026

City of Pomona is a city authority in the State of California, serving 151,713 residents. 4,911 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Permitting 5 steps · 28 questions

Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Real-time / instant issuance for SolarAPP+-eligible systems (<=38.4 kW AC, no BIPV, no ballasted systems, main-dwelling roof only), per Gov. Q18 Where you file — SolarAPP+ (solarapp.nrel.gov) for automated code review, feeding into the City of Pomona's EnerGov-based 'Civic/Citizen Self Service' portal… Q20

Permit required
Yes95% source
What it costs
$281.05 flat for 0-15 kW (FY2025-26), plus $10.85 per kW over 15 kW, plus a 'BLD - Solar Plan Check' fee of 75% of the permit fee (minimum $132.15)92% source
Plan review turnaround
Real-time / instant issuance for SolarAPP+-eligible systems (<=38.4 kW AC, no BIPV, no ballasted systems, main-dwelling roof only), per Gov.80% source
Key document
authority's own page (citing state statute) cited by 7 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes 95% · authority's own page
    • What does this authority permit itself, and what does it delegate? Both 85% · fee schedule + LACoFD guide
    • Is a permit required for a residential rooftop PV system? Yes 95% · fee schedule
    • Is there a separate electrical permit, or is it combined? Combined 65% · fee schedule
    • Is a HOA or architectural approval required first? No (city does not itself require HOA/architectural approval as a permit precondition) 65% · state law + authority's own process page
    • Is there a historic-district review? Yes, for designated historic properties / historic districts 95% · authority's own form + published decisions
    • Is a wind or windstorm certification required? No separate wind/windstorm certification form; wind design is via standard ASCE7-16 criteria administered through ordinary structural plan review. 88% · authority's own handout
    • Is a Specific Use Permit or Council approval ever required? Not required for typical residential rooftop PV; no Conditional-Use-Permit or Council-approval fee line for solar was found on the Planning Division fee schedule. 55% · fee schedule (indirect)
    • Is there a system-size cap on residential generation? No hard cap on residential system size itself, but the automated/instant SolarAPP+ permitting path is capped at 38.4 kW AC nameplate (with paired ESS also capped at 38.4 kW AC) per Gov. Code Section 65850.52; larger systems must use the standard, non-instant plan-review path. 88% · authority's own page (citing state statute)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? For the SolarAPP+ track: a completed 'Solar App+ Permit Application' (job valuation, solar size/kW, array sf, module/inverter counts, branch circuits, optional battery-storage kW, panel/subpanel upgrade amperage), a 'Licensed Contractors Declaration', and a Workers' Compensation Declaration, plus the automated SolarAPP+ (NREL) code-compliance approval itself. For the standard track: site/roof plan and single-line electrical diagram (see Q10-11). 85% · authority's own form
    • How many copies, and in what format? Digital PDF submittal is accepted/preferred: general plan submittal is by email to Building@pomonaca.gov; for historic-property solar (Minor Certificate of Appropriateness) two (2) hard copies of the site/roof plan are required, or plans may be submitted digitally in PDF format. 70% · authority's own page + form checklist
    • Is a site plan required, and what must it show? Yes. For a historic property, the MINCOA-Solar checklist requires a Site Plan / Roof Plan (Proposed) showing panel locations. For interconnection, SCE separately requires a plot plan showing the AC disconnect location relative to the meter/point of common coupling, spacing dimensions, and line-of-sight. 78% · authority's own form + utility handbook
    • Is a one-line / three-line diagram required? Yes 80% · authority's own handout
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? SolarAPP+ (solarapp.nrel.gov) for automated code review, feeding into the City of Pomona's EnerGov-based 'Civic/Citizen Self Service' portal (connect.pomonaca.gov/energov_prod/selfservice) for permit issuance, payment, document printing, and inspection scheduling. 95% · authority's own page
    • Can the whole application be completed online? Yes 90% · authority's own page
    • What does a residential solar permit cost? $281.05 flat for 0-15 kW (FY2025-26), plus $10.85 per kW over 15 kW, plus a 'BLD - Solar Plan Check' fee of 75% of the permit fee (minimum $132.15) 92% · fee schedule
    • How is the fee calculated? Tiered / per kW 90% · fee schedule
    • Is there a separate plan-check fee? Yes 90% · fee schedule
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? Real-time / instant issuance for SolarAPP+-eligible systems (<=38.4 kW AC, no BIPV, no ballasted systems, main-dwelling roof only), per Gov. Code Section 65850.52 as implemented by the city; no published business-day turnaround figure was found for systems routed through standard (non-SolarAPP+) plan review. 80% · authority's own page
    • How long is an issued permit valid before it expires? 180 days (California statewide default building-permit expiration under CBC/CRC Section 105.5), inferred 60% · inference from CA statewide code + city form list
    • Which utility handles interconnection here? Southern California Edison (SCE) 95% · authority's own page + utility/CCA statement
    • Where does the utility sit in the sequence? Parallel 70% · utility interconnection handbook

28 questions answered against City of Pomona’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes

Why the confidence is not higherPomona's own Building & Safety Division issues residential PV permits directly (via SolarAPP+ + the city's EnerGov self-service portal); this is a general-law city in LA County and the city holds building/electrical permitting for one- and two-family dwellings, not the county. Page fetched via Wayback (23 Aug 2026 capture) because live pomonaca.gov returns Akamai 403 to automated fetches.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both

Why the confidence is not higherCity Building & Safety issues the building AND electrical permit for conventional rooftop PV (single 'BLD - Solar Panels' fee line covers both in the FY2025-26 Master Fee Schedule). However, LA County Fire Department (LACoFD), Pomona's contracted fire-service provider since 1994, retains independent plan review and field inspection for ESS/BIPV, and a separate disconnect-placarding/rapid-shutdown field inspection for ALL PV -- see LACoFD Guide for ESS, PV and Disconnects (Rev 3, 2023-09-01), Section II.A-B.

fee schedule + LACoFD guide checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes

Why the confidence is not higherFY2025-26 Master Fee Schedule lists a dedicated 'BLD - Solar Panels Residential' permit fee (line 75-76), and the city's Solar Permit Streamlining page describes the required permit-issuance path (SolarAPP+ + EnerGov).

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined

Why the confidence is not higherThe Master Fee Schedule prices residential PV under a single Building ('BLD - Solar Panels Residential') fee line with its own 'BLD - Solar Plan Check' companion line; there is no separate 'ELE' fee item for PV specifically (the general 'Electrical Code Permit Fee' section covers non-PV electrical work). Inferred from fee-schedule structure, not an explicit combined/separate statement by the city.

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either

Why the confidence is not higherThe city's SolarAPP+ pathway is restricted to 'Licensed Contractors Only' per the Solar Permit Streamlining page, but the city also publishes an 'Owner Builder Authorization' form and 'Helpful tips for the Owner-Builder' handout in its Building Application & Forms list, confirming the standard (non-SolarAPP+) track allows an owner-builder to pull the permit under CA Contractors' State License Law.

authority's own page + forms list checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes

Why the confidence is not higherCity's own Business License page states: 'If you are a contractor based outside of the City of Pomona and you are pulling permits with Building & Safety, the Business License will be added to the invoice that is prepared when applying for the permits' -- i.e. a Pomona business license (City Code Sec. 50-331 et seq.) is required of every contractor pulling a permit, applied at time of application.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/business/business-with-pomona-city-hall/business-license

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes

Why the confidence is not higherCity publishes a dedicated 'Owner Builder Authorization' / 'Owner-Builder Work Authorization Form' (Building Application & Forms list) that must be signed before a building permit can be issued to a property owner acting as their own builder, consistent with CA Contractors' State License Law.

authority's own form checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2660/637526096828330000

Q8 What documents make up a complete submittal? Core Submittal package

For the SolarAPP+ track: a completed 'Solar App+ Permit Application' (job valuation, solar size/kW, array sf, module/inverter counts, branch circuits, optional battery-storage kW, panel/subpanel upgrade amperage), a 'Licensed Contractors Declaration', and a Workers' Compensation Declaration, plus the automated SolarAPP+ (NREL) code-compliance approval itself. For the standard track: site/roof plan and single-line electrical diagram (see Q10-11).

Why the confidence is not higherCity's own 'Solar App+ Permit Application' PDF (2-page form combining the application, Licensed Contractors Declaration and Workers' Comp Declaration) obtained from the Building Application & Forms page.

authority's own form checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/5639/638399597760830000

Q9 How many copies, and in what format? Submittal package

Digital PDF submittal is accepted/preferred: general plan submittal is by email to Building@pomonaca.gov; for historic-property solar (Minor Certificate of Appropriateness) two (2) hard copies of the site/roof plan are required, or plans may be submitted digitally in PDF format.

Why the confidence is not higherCombines the Building & Safety contact page ('Electronic Plan Submittal via email: Building@pomonaca.gov') with the MINCOA-Solar application's own submittal checklist ('Two (2) copies plans... Plans may be submitted digitally in PDF format').

authority's own page + form checklist checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/6790/638532893269400000

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes. For a historic property, the MINCOA-Solar checklist requires a Site Plan / Roof Plan (Proposed) showing panel locations. For interconnection, SCE separately requires a plot plan showing the AC disconnect location relative to the meter/point of common coupling, spacing dimensions, and line-of-sight.

Why the confidence is not higherMINCOA-Solar application submittal checklist (city) plus SCE NEM/Net Billing Interconnection Handbook v10 (Oct 2025) Section 5.5 plot-plan requirement.

authority's own form + utility handbook checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/6790/638532893269400000

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes

Why the confidence is not higherCity publishes its own 'Electrical Panel Diagram' handout titled 'Single Line Diagram Example' in the Building Application & Forms list, confirming a one-line diagram is a standard submittal expectation for electrical/panel work including PV interconnection.

authority's own handout checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2620/637526105237730000

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedSearched the Solar Permit Streamlining page and its linked SolarAPP+ eligibility bullets, and the Building Application & Forms handout list, for a statement requiring separate string/conductor sizing calculations; none found (SolarAPP+'s automated code check performs conductor sizing internally rather than requiring a submitted calculation package).

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

Nothing published by this authority.

Where we lookedSearched the 'Building Codes & Design Criteria 2025' handout, the 'Structural Observation' handout listing, and the Solar Permit Streamlining/SolarAPP+ eligibility page for a PV-specific structural PE-stamp weight or size threshold; none published. Only a general ASCE7-16 wind/seismic design-criteria sheet was found (no PV-specific trigger).

https://www.pomonaca.gov/home/showpublisheddocument/2614/639034608178870000

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Nothing published by this authority.

Where we lookedSearched the same Building Application & Forms handout list and the Solar Permit Streamlining page for an electrical PE-stamp threshold specific to residential PV; none published.

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/building-application-forms

Q15 What does a residential solar permit cost? Core Fees

$281.05 flat for 0-15 kW (FY2025-26), plus $10.85 per kW over 15 kW, plus a 'BLD - Solar Plan Check' fee of 75% of the permit fee (minimum $132.15)

Why the confidence is not higherFY2025-26 Master Fee Schedule (Development Services - Building and Safety Fees), lines 74-80: 'BLD - Solar Panels Residential' $271.85->$281.05 (0-15kW) and $10.50->$10.85/kW over 15kW; 'BLD - Solar Plan Check' $127.80->$132.15. Positive control ('electrical') and fabricated control ('zzqqx') both behaved correctly in this document (electrical fee lines present, zzqqx absent), confirming the extraction is reliable.

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q16 How is the fee calculated? Core Fees

Tiered / per kW

Why the confidence is not higherFee schedule prices residential PV as a flat fee for the 0-15kW tier plus a per-additional-kW rate above 15kW -- a tiered, per-kW structure rather than flat, valuation-based or per-panel.

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q17 Is there a separate plan-check fee? Fees

Yes

Why the confidence is not higher'BLD - Solar Plan Check' is a distinct fee line ($132.15 / 75% of the permit fee, whichever governs) separate from the 'BLD - Solar Panels Residential' permit-issuance fee.

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q18 What is the stated plan-review turnaround? Core Timeline & validity

Real-time / instant issuance for SolarAPP+-eligible systems (<=38.4 kW AC, no BIPV, no ballasted systems, main-dwelling roof only), per Gov. Code Section 65850.52 as implemented by the city; no published business-day turnaround figure was found for systems routed through standard (non-SolarAPP+) plan review.

Why the confidence is not higherSolar Permit Streamlining page: 'residential roof-mounted photovoltaic designs for automated review through SolarAPP+ and the City's online software (Energov) for an auto-issued permit.'

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q19 How long is an issued permit valid before it expires? Timeline & validity

180 days (California statewide default building-permit expiration under CBC/CRC Section 105.5), inferred

Why the confidence is not higherNo Pomona-specific expiration figure was found on the pages reviewed; the city does publish a 'Permit Extension Request' form (implying permits do expire), but the exact day-count is not stated on any page or handout retrieved. Falling back to the CA statewide default under the 2025 CBC the city adopted.

inference from CA statewide code + city form list checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/building-application-forms

Q20 Which permit portal does this authority use? Core Portal & process

SolarAPP+ (solarapp.nrel.gov) for automated code review, feeding into the City of Pomona's EnerGov-based 'Civic/Citizen Self Service' portal (connect.pomonaca.gov/energov_prod/selfservice) for permit issuance, payment, document printing, and inspection scheduling.

Why the confidence is not higherSolar Permit Streamlining page: step-by-step instructions naming both SolarAPP+ and the 'Civic Self Service Online Permit Portal'.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q21 Can the whole application be completed online? Core Portal & process

Yes

Why the confidence is not higherFor SolarAPP+-eligible systems the page describes online submission through SolarAPP+, online permit application/registration, online payment, online document printing, and online inspection scheduling, all through the two linked online systems.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q22 Which utility handles interconnection here? Core Utility interconnection

Southern California Edison (SCE)

Why the confidence is not higherCity's own 'Requesting Power Service' page under Building & Safety is titled 'FAQs from Southern California Edison' and links SCE resources for meter sets/service upgrades. Pomona Choice Energy (the city's CCA) confirms on its own site that it only purchases generation -- 'SCE is responsible for distributing it... continues to do the billing, maintains the power lines, and handles all new service requests' -- so SCE, not the CCA, is the interconnecting utility. Not taken from a ZIP-code lookup.

authority's own page + utility/CCA statement checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/inspection-requests/requesting-power-service

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Parallel

Why the confidence is not higherSCE's interconnection application (photos of AC disconnect, plot plan) can be prepared alongside city permitting, but Permission to Operate (PTO) is only granted by SCE after the installed system passes both the city's final inspection and SCE's own interconnection review -- i.e. the utility step runs in parallel with, but must close out after, the permit/inspection step.

utility interconnection handbook checked 2026-08-30 https://www.sce.com/sites/default/files/custom-files/PDF_Files/NBT-NEM-Handbook-Version_10_WCAG_Oct2025_ADA.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No (city does not itself require HOA/architectural approval as a permit precondition)

Why the confidence is not higherNo Pomona ordinance or permit-page requirement for HOA sign-off was found; California Civil Code Section 714 preempts HOA solar restrictions statewide, and the city's own solar streamlining page describes no HOA step in the permit process. Inference from state law + absence on the city's own process page rather than an explicit city statement.

state law + authority's own process page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q25 Is there a historic-district review? Overlays & special cases

Yes, for designated historic properties / historic districts

Why the confidence is not higherCity's own 'Solar Panel Installation Application for All Historic Properties' requires a Minor Certificate of Appropriateness (MINCOA) before installing solar on a historic resource; confirmed by actual approved cases (e.g. MINCOA-001105-2024 and MINCOA-001074-2024, both 'Approval to install solar panels') published on the city's Historic Preservation decisions page.

authority's own form + published decisions checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/6790/638532893269400000

Q26 Is a wind or windstorm certification required? Overlays & special cases

No separate wind/windstorm certification form; wind design is via standard ASCE7-16 criteria administered through ordinary structural plan review.

Why the confidence is not higherCity's own 'Building Codes & Design Criteria' handout (dated 9/2025) states Pomona's wind design values under ASCE7-16: Risk Category I 89 mph, II 96 mph, III 102 mph, IV 107 mph, Exposure C -- there is no separate windstorm certificate requirement described anywhere in the city's forms list.

authority's own handout checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2614/639034608178870000

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Not required for typical residential rooftop PV; no Conditional-Use-Permit or Council-approval fee line for solar was found on the Planning Division fee schedule.

Why the confidence is not higherReviewed the Planning Application Fees (FY2025-2026) schedule; the only solar-specific planning fee is the Minor Certificate of Appropriateness (historic properties). No CUP fee item references solar. Confidence limited because the underlying Zoning and Development Code PDF (which would state this definitively) was found corrupted/truncated in every available Wayback capture (see not_found for Q47/Q28 zoning-specific detail).

fee schedule (indirect) checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7949/638877660108730000

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No hard cap on residential system size itself, but the automated/instant SolarAPP+ permitting path is capped at 38.4 kW AC nameplate (with paired ESS also capped at 38.4 kW AC) per Gov. Code Section 65850.52; larger systems must use the standard, non-instant plan-review path.

Why the confidence is not higherCity's own Solar Permit Streamlining page quotes the Gov. Code 65850.52 threshold verbatim as its own SolarAPP+ eligibility limit.

authority's own page (citing state statute) checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? 2023 NEC (as amended, adopted as the 2025 California Electrical Code) 95% · authority's own handout
    • Which building code edition is in force? 2025 California Building Code (based on the 2024 IBC) 95% · authority's own handout
    • Which fire code edition is in force? 2025 California Fire Code (based on the 2024 IFC), as locally amended by the Los Angeles County Fire Code (LACC Title 32) since Pomona contracts fire services to LACoFD 80% · authority's own handout + LACoFD guide (dated)
    • Are there local amendments to any of the above? Yes 85% · LACoFD guide + city historic-preservation form
    • What is the installation judged against? The 2025 California Electrical Code (2023 NEC as amended), manufacturer/NRTL listing (e.g. UL 1741), and -- for disconnects/ESS -- the LA County Fire Code (Title 32) Sections 509 and 1207.11. 82% · LACoFD guide
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for City of Pomona on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Yes, required (PV/BIPV rapid shutdown / 'Hazard Control System'), under the 2023 NEC (Section 690.12) as incorporated into the 2025 California Electrical Code 85% · LACoFD guide + checklist
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? Utility 'Grid Side' / 'Generation Side' disconnect signage (SCE) and LACoFD's 'F.D. - ELECTRICAL BLDG DISCONNECT #X of Y' placards wherever a structure can receive power from more than one source (i.e. utility + PV, in effect nearly every residential PV job), plus standard NEC 690.56/705.10 PV system labeling. 85% · utility handbook + LACoFD guide (both linked from/adopted by the city)
    • Does the authority specify placard wording of its own? Yes, but the wording is authored by LACoFD and SCE (adopted-by-reference through the fire code Pomona enforces and the interconnection rules SCE administers), not separately drafted by Pomona Building & Safety. 75% · LACoFD guide + utility handbook
    • Does it specify letter height, colour or material? Yes. LACoFD: exterior placards min. 2in x 3.5in weather-resistant plastic, red letters engraved into a yellow background, solid all-caps Arial font min. 24pt (28pt bold for 'F.D.'/'#X of Y'), permanent epoxy attachment. SCE: permanently attached machine-engraved laminated phenolic (or equal) tags, font size 3/8in-1in. 90% · LACoFD guide + utility handbook
    • Is a site plan / facility map placard required, and what must it show? Not a separate site-plan/facility-map placard, but an 'Electrical Power Source Disconnect Schedule' is required on the garage floor plan/partial floor plan, listing every power source, its disconnect device, and the '#X of Y' numbering used on the exterior placards. 75% · LACoFD guide
    • Does the UTILITY specify placards beyond the AHJ's? Yes 92% · utility interconnection handbook
    • Where must the labels be placed? AC/isolation disconnect devices carry the 'Grid Side'/'Generation Side' labels (SCE); LACoFD's placards are placed on or immediately adjacent to each panel/enclosure or standalone disconnect switch that must be operated, with panel-interior placards inside panels for specific breakers, all located to be accessible from the exterior of the structure 24/7. 85% · LACoFD guide + utility handbook
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? For load-side connections: single visible-open AC disconnect located near/adjacent to the point of common coupling (typically the meter), with 24/7 SCE access. For line-side connections: disconnect directly adjacent to the PCC, or if infeasible, no more than 10 feet from the PCC subject to engineer approval (SCE Section 10.2 variance). 92% · utility interconnection handbook
    • Must equipment be on a specific approved list? No authority-maintained 'approved equipment list'; standard requirement is NRTL/UL listing (e.g. equipment 'shall be listed and approved') under the adopted electrical/fire code rather than a discretionary city list. 65% · LACoFD guide (inference)
    • Are batteries permitted, and under what conditions? Yes -- paired residential ESS with PV is explicitly supported via the SolarAPP+/EnerGov instant-issuance path up to the Gov. Code 65850.52 eligibility caps (38.4 kW AC); any ESS installation is additionally subject to LACoFD's Fire Prevention Division plan review and field inspection in all cases, with ESS nameplate capacity over 3 kWh specifically triggering LACFC Section 1207.11 spacing/location/disconnect rules. 90% · authority's own form + LACoFD guide/checklist
    • Is there a separate ESS permit or inspection? Yes 92% · LACoFD guide

20 questions answered against City of Pomona’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2023 NEC (as amended, adopted as the 2025 California Electrical Code)

Why the confidence is not higherCity's own 'Building Codes & Design Criteria' handout (9/2025): 'These codes are based upon... 2023 National Electrical Code... adopted by the State of California Building Standards Commission,' with enforcement beginning 1 Jan 2026 per the same handout and Ordinance No. 4364 (adopting the 2025 CA Building Standards Code), confirmed on the city's Recently Adopted Ordinances page.

authority's own handout checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2614/639034608178870000

Q30 Which building code edition is in force? Core Code editions in force

2025 California Building Code (based on the 2024 IBC)

Why the confidence is not higherSame 'Building Codes & Design Criteria' handout lists '2025 California Building Code' among the codes in force, based on the 2024 IBC, effective for projects submitted after 1 Jan 2026; adopted locally via Ordinance No. 4364.

authority's own handout checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2614/639034608178870000

Q31 Which fire code edition is in force? Code editions in force

2025 California Fire Code (based on the 2024 IFC), as locally amended by the Los Angeles County Fire Code (LACC Title 32) since Pomona contracts fire services to LACoFD

Why the confidence is not higherCity's Design Criteria handout lists '2025 California Fire Code' among adopted codes. Note: LACoFD's own PV/ESS guide (dated 2023-09-01) still cites the 2022 CFC / 2023 LACFC cycle and does not yet visibly reflect the 2025 cycle -- flagging a likely documentation lag between the city's Jan-2026 CBSC adoption and LACoFD's county-wide fire-code amendment cycle.

authority's own handout + LACoFD guide (dated) checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/2614/639034608178870000

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes

Why the confidence is not higherLA County Fire Code (Title 32) amendments to the CFC apply in Pomona because the city contracts fire services to LACoFD (since 1994); Pomona also layers its own Zoning/Historic-Preservation solar rules (Minor Certificate of Appropriateness) on top of the base state codes.

LACoFD guide + city historic-preservation form checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q33 What is the installation judged against? Core Electrical

The 2025 California Electrical Code (2023 NEC as amended), manufacturer/NRTL listing (e.g. UL 1741), and -- for disconnects/ESS -- the LA County Fire Code (Title 32) Sections 509 and 1207.11.

Why the confidence is not higherComposite of the city's Design Criteria handout (code editions) and LACoFD's Guide for ESS, PV and Disconnects (Rev 3, 2023-09-01), which cites 2022 CEC Sections 225.37, 230.70, 230.85, 705.10, 705.20 and LACFC Sections 509-509.3, 1207.11.5.1 as its stated authority.

LACoFD guide checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedSearched the city's own 'Electrical Panel Diagram' handout (a single-line-diagram template) for a stated busbar-sizing or service-upgrade rule specific to solar backfeed (e.g. a 120%-rule statement); the handout is a generic blank template with no such text. Also checked the 'Electrical Permit' info handout (11/2024) -- general permit-exemption list only, no busbar rule.

https://www.pomonaca.gov/home/showpublisheddocument/2620/637526105237730000

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Nothing published by this authority.

Where we lookedSearched the Solar Permit Streamlining page and its SolarAPP+ eligibility bullets (main-dwelling roof, no ballasted systems, no BIPV) for a specific mounting-system or attachment-spacing requirement; none published by the city itself (mounting is governed by the manufacturer's engineering under SolarAPP+'s national standard, not a Pomona-specific spec).

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedSearched the LACoFD Guide for ESS, PV and Disconnects (Rev 3, 2023-09-01) full text (positive control 'electrical' = 39 hits, fabricated control 'zzqqx' = 0 hits, confirming the search was live) for a ridge-setback / roof-access-pathway table; the guide covers ESS spacing and disconnect placarding but does not reproduce the CFC 1204 rooftop-access-pathway table, and no Pomona-specific ridge-setback publication was found elsewhere.

https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes, required (PV/BIPV rapid shutdown / 'Hazard Control System'), under the 2023 NEC (Section 690.12) as incorporated into the 2025 California Electrical Code

Why the confidence is not higherLACoFD's Guide for ESS, PV and Disconnects defines 'Rapid Shutdown (RSD)' and requires an initiation device for it to be included among the placarded disconnects (Appendix B.A.4, D.3); the LACoFD Expedited-Permitting inspection checklist explicitly checks 'PV Rapid Shutdown function activation... is encompassed.' NEC edition per the city's own Design Criteria handout (2023 NEC).

LACoFD guide + checklist checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

Utility 'Grid Side' / 'Generation Side' disconnect signage (SCE) and LACoFD's 'F.D. - ELECTRICAL BLDG DISCONNECT #X of Y' placards wherever a structure can receive power from more than one source (i.e. utility + PV, in effect nearly every residential PV job), plus standard NEC 690.56/705.10 PV system labeling.

Why the confidence is not higherSCE NEM/Net Billing Interconnection Handbook v10 (Oct 2025) Appendix H (signage) and LACoFD Guide Appendix B (Disconnect Placarding), both cited by the city -- LACoFD's guide is directly linked from Pomona's own Solar Permit Streamlining page for ESS projects and applies its placarding system whenever the Department reviews a multi-source electrical project.

utility handbook + LACoFD guide (both linked from/adopted by the city) checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

Yes, but the wording is authored by LACoFD and SCE (adopted-by-reference through the fire code Pomona enforces and the interconnection rules SCE administers), not separately drafted by Pomona Building & Safety.

Why the confidence is not higherLACoFD Guide Appendix B.B.5 specifies exact verbiage ('F.D. - ELECTRICAL BLDG DISCONNECT #X of Y'); SCE's handbook Appendix H specifies 'Grid Side' / 'Generation Side' wording. No independent Pomona-authored placard-wording document was found.

LACoFD guide + utility handbook checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Yes. LACoFD: exterior placards min. 2in x 3.5in weather-resistant plastic, red letters engraved into a yellow background, solid all-caps Arial font min. 24pt (28pt bold for 'F.D.'/'#X of Y'), permanent epoxy attachment. SCE: permanently attached machine-engraved laminated phenolic (or equal) tags, font size 3/8in-1in.

Why the confidence is not higherLACoFD Guide for ESS, PV and Disconnects, Appendix B, Section B (Specifications and Placement of the Placards); SCE NEM/Net Billing Interconnection Handbook v10 (Oct 2025), Appendix H.

LACoFD guide + utility handbook checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Not a separate site-plan/facility-map placard, but an 'Electrical Power Source Disconnect Schedule' is required on the garage floor plan/partial floor plan, listing every power source, its disconnect device, and the '#X of Y' numbering used on the exterior placards.

Why the confidence is not higherLACoFD Guide for ESS, PV and Disconnects, Section (E) 'Wall Elevations and/or Details' / 'Required Disconnect Schedule and Notes,' including a worked example schedule (Utility, ESS, New/Existing Solar PV, Generator).

LACoFD guide checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes

Why the confidence is not higherSCE's Net Billing Tariff / Net Energy Metering Interconnection Handbook, Version 10 (Oct 2025), Appendix H specifies signage beyond anything the AHJ requires: 'Grid Side' / 'Generation Side' labeling on isolation devices and net-output generation metering, via permanently attached machine-engraved laminated phenolic tags, font size 3/8in-1in.

utility interconnection handbook checked 2026-08-30 https://www.sce.com/sites/default/files/custom-files/PDF_Files/NBT-NEM-Handbook-Version_10_WCAG_Oct2025_ADA.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

AC/isolation disconnect devices carry the 'Grid Side'/'Generation Side' labels (SCE); LACoFD's placards are placed on or immediately adjacent to each panel/enclosure or standalone disconnect switch that must be operated, with panel-interior placards inside panels for specific breakers, all located to be accessible from the exterior of the structure 24/7.

Why the confidence is not higherSCE NEM/Net Billing Handbook v10 Appendix H; LACoFD Guide Appendix B, Section B.7 (Placard Locations).

LACoFD guide + utility handbook checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q44 Must equipment be on a specific approved list? Equipment listing

No authority-maintained 'approved equipment list'; standard requirement is NRTL/UL listing (e.g. equipment 'shall be listed and approved') under the adopted electrical/fire code rather than a discretionary city list.

Why the confidence is not higherLACoFD Guide repeatedly states devices 'shall be listed and approved' (e.g. disconnect devices in the Disconnect Schedule notes) rather than referencing a Pomona-specific approved-products list; no such list was found on any Pomona Building & Safety page.

LACoFD guide (inference) checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes -- paired residential ESS with PV is explicitly supported via the SolarAPP+/EnerGov instant-issuance path up to the Gov. Code 65850.52 eligibility caps (38.4 kW AC); any ESS installation is additionally subject to LACoFD's Fire Prevention Division plan review and field inspection in all cases, with ESS nameplate capacity over 3 kWh specifically triggering LACFC Section 1207.11 spacing/location/disconnect rules.

Why the confidence is not higherCity's own 'Solar App+ Permit Application' form includes a 'Battery Storage Size (kW)' field; LACoFD's Guide (Section II.A-B) and Expedited-Permitting Checklist (Section 2.b.i, citing the 3 kWh nameplate threshold under 2023 LACFC Section 1207.11) both confirm the ESS-specific review layer.

authority's own form + LACoFD guide/checklist checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/5639/638399597760830000

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Yes

Why the confidence is not higherLACoFD's Guide states that even where an ESS/BIPV project 'is/was submitted for plan-review by, and/or is/was installed and then inspected by either a city or county Building and Safety... they are also required to have LACoFD approval... in all cases, LACoFD field inspection and approval' -- i.e. a separate ESS permit-review and inspection layer beyond the city's own permit, regardless of who issued the underlying building permit.

LACoFD guide checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q47 Is a ground mount treated as a structure? Core Ground mount

Nothing published by this authority.

Where we lookedSearched the Pomona Zoning and Development Code PDF (in effect since 31 Jul 2024) for its ground-mount/accessory-structure solar provisions; every available capture (live site 403s; the only two Wayback captures found, both sourced from a Sept-2025 Common Crawl crawl, are truncated by Wayback's own 'content truncated by length' limit at exactly 5,242,880 bytes and will not open in pdftotext -- 'Internal Error: xref num ... not found,' 'Top-level pages object is wrong type'). This is a PDF-unreadable absence, not a code absence -- do not infer ground-mount treatment from this.

https://www.pomonaca.gov/government/departments/development-services/planning-division/zoning-and-development-code

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

For load-side connections: single visible-open AC disconnect located near/adjacent to the point of common coupling (typically the meter), with 24/7 SCE access. For line-side connections: disconnect directly adjacent to the PCC, or if infeasible, no more than 10 feet from the PCC subject to engineer approval (SCE Section 10.2 variance).

Why the confidence is not higherSCE Net Billing Tariff / NEM Interconnection Handbook, Version 10 (Oct 2025), Section 5.5.3 'AC Disconnect Type and Location Requirements.'

utility interconnection handbook checked 2026-08-30 https://www.sce.com/sites/default/files/custom-files/PDF_Files/NBT-NEM-Handbook-Version_10_WCAG_Oct2025_ADA.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal (online inspection-request form) or the EnerGov self-service portal; phone/counter also available. 90% · authority's own page
    • How much notice is required? Next business day if the request is submitted before 4:00pm; submitted after 4:00pm is scheduled 2 business days out. Monday inspections require submission by Thursday 4:00pm (City Hall is closed Fridays). 92% · authority's own page
    • Are same-day or AM/PM windows offered? No same-day inspections; next-business-day is the fastest option, and even the requested time-of-day window is 'NOT guaranteed' per the city's own page. 85% · authority's own page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Delegated (split) 88% · LACoFD guide
    • If delegated, to whom? Los Angeles County Fire Department (LACoFD), Fire Prevention Division -- for ESS/BIPV plan review and field inspection in all cases, and for disconnect-placarding/rapid-shutdown field verification on all PV projects. Pomona has contracted fire services to LACoFD since 1994 (Pomona Fire Department was dissolved). 88% · authority's own page (linking to LACoFD) + LACoFD guide
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? 1) City permit issuance (SolarAPP+ auto-issue or standard plan check); 2) City Building & Safety final building/electrical inspection; 3) where applicable (ESS, or disconnect/rapid-shutdown verification), a separate LACoFD Fire Prevention field inspection scheduled by the applicant directly with the jurisdictional LACoFD regional office, invoiced and paid before the inspection occurs. 68% · city page + LACoFD checklist
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? Yes 88% · LACoFD checklist (linked by the city)
    • What must be on site at inspection? Digital proof of the construction permit obtained via the city's SolarAPP+/expedited process (including any inspection checklist issued with it), the project address and occupancy classification, and -- per general city practice -- the printed permit/job card (the Solar Permit Streamlining page includes 'Print your Documents -- How to print your permit/job card'). 78% · LACoFD checklist + city page
    • Does the inspector verify labels and listings? Yes 90% · LACoFD checklist
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? Final (inspection sign-off on the permit/job card); a Certificate of Occupancy is not typically issued for a PV retrofit on an existing dwelling (CofO forms in the city's own form list are tied to new construction/ADU/JADU, not solar retrofits). 70% · inference from authority's own forms list
    • Who notifies the utility for PTO? Installer (applicant-driven) 78% · utility interconnection handbook (inference)
    • Is there a re-inspection fee? $132.15 (FY2025-26) per request 92% · fee schedule

14 questions answered against City of Pomona’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal (online inspection-request form) or the EnerGov self-service portal; phone/counter also available.

Why the confidence is not higherCity's 'Inspection Requests' page: 'Welcome to the City of Pomona Building & Safety's Online Inspection Request... complete the form below,' plus the EnerGov Citizen Self Service link ('How to schedule an Online Inspection') on the Solar Permit Streamlining page.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/inspection-requests

Q50 How much notice is required? Core Booking & scheduling

Next business day if the request is submitted before 4:00pm; submitted after 4:00pm is scheduled 2 business days out. Monday inspections require submission by Thursday 4:00pm (City Hall is closed Fridays).

Why the confidence is not higherCity's Inspection Requests page states these exact cutoff rules.

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/inspection-requests

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

No same-day inspections; next-business-day is the fastest option, and even the requested time-of-day window is 'NOT guaranteed' per the city's own page.

Why the confidence is not higherInspection Requests page: 'Depending on the amount of inspections, the Requested Time Frame is NOT guaranteed. We will try to accommodate your request.'

authority's own page checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/inspection-requests

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Delegated (split)

Why the confidence is not higherCity of Pomona Building & Safety performs the final building/electrical inspection for conventional rooftop PV under fire-official authority historically delegated by LACoFD for R-3/R-4 occupancies. LACoFD's own Fire Prevention Division independently performs a field inspection of disconnect placarding and rapid-shutdown devices on ALL PV (not just ESS), and full plan review plus field inspection on any ESS/BIPV project, 'in all cases' regardless of who issued the underlying permit.

LACoFD guide checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/LACoFD-Guide-for-ESS-PV-and-Disconnects-Rev-3-2023-09-01-w-Appendices-SECURED.pdf

Q53 If delegated, to whom? Core Who inspects

Los Angeles County Fire Department (LACoFD), Fire Prevention Division -- for ESS/BIPV plan review and field inspection in all cases, and for disconnect-placarding/rapid-shutdown field verification on all PV projects. Pomona has contracted fire services to LACoFD since 1994 (Pomona Fire Department was dissolved).

Why the confidence is not higherLACoFD Guide for ESS, PV and Disconnects and Expedited-Permitting Checklist, both linked directly from Pomona's own Solar Permit Streamlining page ('For projects with Energy Storage Systems... please see this link for LA County Fire Department requirements').

authority's own page (linking to LACoFD) + LACoFD guide checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q54 Which inspections are required, and in what order? Core Stages & sequence

1) City permit issuance (SolarAPP+ auto-issue or standard plan check); 2) City Building & Safety final building/electrical inspection; 3) where applicable (ESS, or disconnect/rapid-shutdown verification), a separate LACoFD Fire Prevention field inspection scheduled by the applicant directly with the jurisdictional LACoFD regional office, invoiced and paid before the inspection occurs.

Why the confidence is not higherComposite of the city's Solar Permit Streamlining page sequence (permit -> inspection scheduling) and LACoFD's Expedited-Permitting Checklist Section I ('Before Making Request for FD Inspection... Digital Proof of Construction Permit... Schedule the inspection... Pay the invoice').

city page + LACoFD checklist checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/Expedited-Permitting-Checklist-LACoFD-ESS-PV-Disconnects-2023-09-01-SECURED.pdf

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedSearched the Solar Permit Streamlining page, SolarAPP+ eligibility bullets, and the Building Application & Forms handout list for a rough-in or mid-roof PV inspection requirement; none published (only a single final inspection is described for the SolarAPP+ path).

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Q56 Does the inspector verify labels and listings? Core What is checked

Yes

Why the confidence is not higherLACoFD's Expedited-Permitting Checklist explicitly checks (Section IV) 'Disconnect Placarding in Place' and 'PV Rapid Shutdown function activation (where present) is encompassed' as inspection line items.

LACoFD checklist checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/Expedited-Permitting-Checklist-LACoFD-ESS-PV-Disconnects-2023-09-01-SECURED.pdf

Q57 Is there a published inspection checklist? Core What is checked

Yes

Why the confidence is not higherLACoFD publishes an 'Expedited-Permitting Checklist for LACoFD ESS/PV Disconnects' (2023-09-01), linked directly from Pomona's own Solar Permit Streamlining page for ESS/PV projects; no separate Pomona Building & Safety PV-specific inspection checklist was found beyond SolarAPP+'s own automated review.

LACoFD checklist (linked by the city) checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/Expedited-Permitting-Checklist-LACoFD-ESS-PV-Disconnects-2023-09-01-SECURED.pdf

Q58 What must be on site at inspection? Core Documents on site

Digital proof of the construction permit obtained via the city's SolarAPP+/expedited process (including any inspection checklist issued with it), the project address and occupancy classification, and -- per general city practice -- the printed permit/job card (the Solar Permit Streamlining page includes 'Print your Documents -- How to print your permit/job card').

Why the confidence is not higherLACoFD Expedited-Permitting Checklist Section I.a; Solar Permit Streamlining page 'Print your Documents' step.

LACoFD checklist + city page checked 2026-08-30 https://fire.lacounty.gov/wp-content/uploads/2023/09/Expedited-Permitting-Checklist-LACoFD-ESS-PV-Disconnects-2023-09-01-SECURED.pdf

Q59 Is there a re-inspection fee? Corrections & re-inspection

$132.15 (FY2025-26) per request

Why the confidence is not higherFY2025-26 Master Fee Schedule: 'BLD - Re-Inspection' $127.80 (FY24-25) -> $132.15 (FY25-26), per Request.

fee schedule checked 2026-08-30 https://www.pomonaca.gov/home/showpublisheddocument/7941/638877315370370000

Q60 How are corrections issued and cleared? Corrections & re-inspection

Nothing published by this authority.

Where we lookedSearched the Inspection Requests page and the Building Application & Forms handout list for a published corrections/re-inspection process specific to solar; none found beyond the existence of the flat re-inspection fee (Q59).

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/inspection-requests

Q61 What is issued on pass? Core Final sign-off & PTO

Final (inspection sign-off on the permit/job card); a Certificate of Occupancy is not typically issued for a PV retrofit on an existing dwelling (CofO forms in the city's own form list are tied to new construction/ADU/JADU, not solar retrofits).

Why the confidence is not higherInferred from the Building Application & Forms list (CofO forms are described only for 'New ADU & JADU' and 'with New Business License' contexts) plus the Solar Permit Streamlining page's job-card language ('Print your permit/job card').

inference from authority's own forms list checked 2026-08-30 https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/building-application-forms

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer (applicant-driven)

Why the confidence is not higherSCE's NEM/Net Billing Interconnection Handbook describes an applicant/installer-submitted interconnection application, AC-disconnect photos, and plot plan as the trigger for SCE's Permission-to-Operate review; the city's own pages describe no step where Building & Safety itself notifies SCE.

utility interconnection handbook (inference) checked 2026-08-30 https://www.sce.com/sites/default/files/custom-files/PDF_Files/NBT-NEM-Handbook-Version_10_WCAG_Oct2025_ADA.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Jurisdiction & key facts

The standing 62-question set, answered for City of Pomona against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

City of Pomona is the authority having jurisdiction 90% confidence
Holds
Building and Electrical (city); Fire/ESS partially retained by LA County Fire Department (LACoFD)
Overridden by
LACoFD retains independent plan review AND field inspection for ESS/BIPV in all cases, plus a disconnect-placarding/rapid-shutdown field inspection on ALL residential PV, per LACoFD's Guide for ESS, PV and Disconnects (Rev 3, 2023-09-01) -- Pomona has contracted fire services to LACoFD since 1994, so this is not a discretionary city choice. Southern California Edison (not Pomona Choice Energy, the city's generation-only CCA) governs interconnection sequencing, AC-disconnect placement, and utility-side signage under Rule 21/NEM-NBT.
Why not higher
City's own Solar Permit Streamlining page confirms Building & Safety issues the building/electrical permit directly via SolarAPP+ + EnerGov for one- and two-family dwellings (Pomona is a general-law city; the county has no role in city building/electrical permitting here, unlike the county's OWN unincorporated-area survey record). Pomona's own page links directly to LACoFD's ESS/PV requirements for any project with battery storage, confirming the fire-jurisdiction split at the source. Utility identity confirmed from the city's own 'Requesting Power Service' page (titled 'FAQs from Southern California Edison') and Pomona Choice Energy's own explanation that SCE distributes/bills/maintains lines while the CCA only purchases generation -- not from a ZIP-code lookup tool.

https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Permit required
Yes95%
Permit cost
$281.05 flat for 0-15 kW (FY2025-26), plus $10.85 per kW over 15 kW, plus a 'BLD - Solar Plan Check' fee of 75% of the permit fee (minimum $132.15)92%
Plan review
Real-time / instant issuance for SolarAPP+-eligible systems (<=38.4 kW AC, no BIPV, no ballasted systems, main-dwelling roof only), per Gov.80%
Portal
SolarAPP+ (solarapp.nrel.gov) for automated code review, feeding into the City of Pomona's EnerGov-based 'Civic/Citizen Self Service' portal (connect.pomonaca.gov/energov_prod/selfservice)…95%
Electrical code
2023 NEC (as amended, adopted as the 2025 California Electrical Code)95%
Own placard wording
Yes, but the wording is authored by LACoFD and SCE (adopted-by-reference through the fire code Pomona enforces and the interconnection rules SCE administers),75%
Booking an inspection
Portal (online inspection-request form) or the EnerGov self-service portal; phone/counter also available.90%
Labels & placards for this authority

City of Pomona writes its own placard wording. A standard NEC label set will not satisfy it — the exact text, and in most cases the size, colour and font, are specified below.

Wording 75%

Yes, but the wording is authored by LACoFD and SCE (adopted-by-reference through the fire code Pomona enforces and the interconnection rules SCE administers), not separately drafted by Pomona Building & Safety.

Size, colour & material 90%

Yes. LACoFD: exterior placards min. 2in x 3.5in weather-resistant plastic, red letters engraved into a yellow background, solid all-caps Arial font min. 24pt (28pt bold for 'F.D.'/'#X of Y'), permanent epoxy attachment. SCE: permanently attached machine-engraved laminated phenolic (or equal) tags, font size 3/8in-1in.

Where they go 85%

AC/isolation disconnect devices carry the 'Grid Side'/'Generation Side' labels (SCE); LACoFD's placards are placed on or immediately adjacent to each panel/enclosure or standalone disconnect switch that must be operated, with panel-interior placards inside panels for specific breakers, all located to be accessible from the exterior of the structure 24/7.

What the utility wants on top 92%

Yes

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
City
County
Los Angeles County
Regions served
1
Regions covered
City of Pomona · city
Solar Requirements
Notes
Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division
Authority Contact
Address
505 S Garey Ave, Pomona, CA 91766
Main Phone
Office Hours
7:30 a.m. – 6 p.m.
Closed Friday
Building Department
Department
Building and Safety Division
Direct Phone
909-620-2371
Portal Software
EnerGov (Tyler)
Booking & Scheduling
Preferred channel
online
Book in advance
1
Booking phone
Notes
Submit inspection request before 4:00 PM for next business day; after 4:00 PM schedules 2 business days out. For Monday inspections, request must be submitted by Thursday at 4:00 PM. Inspections conducted Monday–Thursday 8:00 AM–4:00 PM; City Hall closed Fridays. Walk-in counter hours: Monday–Thursday 7:30 AM–6:00 PM. Inspection request phone line: 909-620-2422. Online booking via EnerGov self-service portal at connect.pomonaca.gov. Uses SolarAPP+ for automated residential PV (up to 38.4 kW AC) permit auto-issuance. Solar permit submittals email: solarsubmittals@pomonaca.gov. Provide permit number and project address when scheduling. (collected Jul 2026)