City of San Juan Bautista
San Benito County
City of San Juan Bautista is a city authority in the State of California, serving 2,089 residents. 296 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Same day for over-the-counter applications; 1 to 3 business days for electronic applications Q18 Where you file — No dedicated online permit portal found — permits are processed via a downloadable/fillable PDF Building Permit Application submitted to City Hall (311 Second… Q20
- Permit required
- Yes95% source
- What it costs
- $549 flat (residential, roof-mounted); $783 flat (non-residential)92% source
- Plan review turnaround
- Same day for over-the-counter applications; 1 to 3 business days for electronic applications92% source
- Key document
- municipal code (eCode360) cited by 4 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes 95% · municipal code (eCode360)
- What does this authority permit itself, and what does it delegate? Both 78% · municipal code definitions section
- Is a permit required for a residential rooftop PV system? Yes 95% · municipal code (eCode360)
- Is there a separate electrical permit, or is it combined? Combined 78% · city permit application form
- Is a HOA or architectural approval required first? Conditionally Yes — NOT required for a standard qualifying small residential rooftop solar system, but IS required (site plan and design review, potentially with Historic Resources Board and Planning Commission review) if the property is more than 45 years old, listed on the City's Register of Historic Resources, or located in a designated historic district. No general citywide HOA-approval requirement was found. 85% · municipal code (eCode360), full chapter text extracted
- Is there a historic-district review? Yes — and it is in direct, unresolved tension with the City's own AB 2188 ministerial solar chapter. 90% · municipal code (eCode360) + adopted fee schedule
- Is a Specific Use Permit or Council approval ever required? Conditionally Yes. (1) Under Ch. 10-7 itself, the City Manager may require an applicant to obtain an administrative use permit if the system 'could have a specific, adverse impact upon the public health and safety' (§10-7-060(A)), appealable to the Planning Commission. (2) Independently, a major alteration to a historic-Register-listed property is routed to the Historic Resources Board with the Planning Commission holding final discretionary authority (§11-06-120(C)(5)), and the Master Fee Schedule's 'Historic Resources Review — Commission' tier ($5,000 deposit) confirms this is a live, priced process. 82% · municipal code (eCode360)
- Is there a system-size cap on residential generation? 10 kW AC nameplate rating or 30 kW thermal, on a single- or two-family dwelling only, panel/module array not to exceed the maximum legal building height 95% · municipal code (eCode360)
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Either 75% · city permit application form
- Is a homeowner permitted to self-install and self-permit? Yes 85% · city permit addendum form
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? A completed Building Permit Application (with 'Solar' checked under Project Type, project valuation, owner/applicant/contractor information, and design-professional information if used). NOTE: SJBMC §10-7-050(C) itself REQUIRES the City's Building Division to 'adopt a standard plan and checklist of all requirements with which small residential rooftop solar energy systems shall comply to be eligible for expedited review,' and §10-7-050(D) requires that checklist to substantially conform to the State's Solar Permitting Guidebook. No such solar-specific checklist or standard plan is published on the City's site: the Planning & Building Applications document center lists exactly 10 building-related forms (ADU, permit extension, building permit application, owner/builder declaration, plan revision, EV charging, window/skylight, recycling guide, smoke/CO affidavit, special inspection) and none is a PV/solar checklist. 82% · department document-center listing + ordinance requirement
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? No dedicated online permit portal found — permits are processed via a downloadable/fillable PDF Building Permit Application submitted to City Hall (311 Second Street / P.O. Box 1420) in person, by mail, or (for Planning applications) by email to planning@san-juan-bautista.ca.us. No SolarAPP+, OpenGov, Accela, eTRAKiT, iWorq or similar portal was found anywhere on the City's site. 78% · absence check across department pages
- Can the whole application be completed online? No 75% · city permit application form
- What does a residential solar permit cost? $549 flat (residential, roof-mounted); $783 flat (non-residential) 92% · adopted fee schedule
- How is the fee calculated? Flat 90% · adopted fee schedule
- Is there a separate plan-check fee? No 60% · adopted fee schedule
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? Same day for over-the-counter applications; 1 to 3 business days for electronic applications 92% · municipal code (eCode360)
- Which utility handles interconnection here? PG&E (Pacific Gas & Electric) 90% · city-published service-provider directory
28 questions answered against City of San Juan Bautista’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes
Why the confidence is not higherSJBMC §10-1-100(B) states the building-code chapter applies to 'all buildings or structures in the incorporated territory of the City of San Juan Bautista,' and SJBMC Ch. 10-7 (Ord. 2015-23) separately governs 'the permitting of all small residential rooftop solar energy systems in the City.' The City's own Building Permit Application form (downloaded and read) has a 'Solar' checkbox under Project Type. The City is the AHJ for building/electrical; fire is delegated (see jurisdiction block).
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50527669
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherSJBMC §10-1-105(A) defines 'Building Official,' 'Plumbing Official,' 'Administrative Authority,' AND 'Chief Electrical Inspector' all as one single in-house title: 'the Building Inspector of the City of San Juan Bautista.' No contract-firm name (Willdan, 4Leaf, CSG, Interwest, Bureau Veritas, Transtech, EsGil, etc.) appears anywhere: staff directory shows Community Development staff on the city's own sanjuanbautista.ca.gov/san-juan-bautista.ca.gov domains with no firm names, and the Master Fee Schedule (adopted 6/16/2026) has no staffing appendix naming a contractor. Fire, however, IS delegated — the City's own FHSZ page says the City is 'working with the Hollister Fire Department,' and the city's own Service Providers directory lists 'Hollister FD #4' with a San Juan Bautista street address as the fire department. Engineering standards are also adopted by reference from the City of Hollister (§10-1-110(B)). Confidence is not higher because no staff directory entry carries an explicit 'Building Official' job title (only department name 'Community Development' is shown), so the in-house finding rests on the code's own definition section rather than a named person.
municipal code definitions section checked 2026-08-31 https://ecode360.com/50527669
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherSJBMC §10-7-030(A): 'This Chapter applies to the permitting of all small residential rooftop solar energy systems in the City.' The City's own Building Permit Application form has a 'Solar' checkbox confirming a permit is pulled through the standard building-permit process.
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Combined
Why the confidence is not higherThe City's own fillable Building Permit Application (downloaded, read with pdftotext) lists 'Solar' and 'Electrical' as checkboxes under one single 'Project Type' section of one application form — not as two separate applications. The Master Fee Schedule prices an 'Electrical Sub-Permit' as 15% of the Building Permit Fee, i.e. a sub-permit under the same permit rather than a wholly separate electrical permit application/fee track.
city permit application form checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/forms/SJB%20Building%20Permit%20Application%20%28Fillable%29.pdf
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Either
Why the confidence is not higherThe City's own Building Permit Application, Section 5 (Contractor Information), offers checkboxes for '⬜ Owner/Builder ⬜ Contractor ⬜ TBD' with no restriction specific to solar or electrical work, and the City separately publishes an 'Owner/Builder Declaration' (Permit Addendum for Owner-Builders) confirming owner-builder permits are issued. This is a general building-permit-process finding, not a solar-specific statement, since SJBMC Ch. 10-7 does not separately address who may pull the electrical/solar permit.
city permit application form checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/forms/SJB%20Building%20Permit%20Application%20%28Fillable%29.pdf
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Nothing published by this authority.
Where we lookedCity's own Building Permit Application form (Sections 1-5) and Master Fee Schedule (Business License Fee line, $204) — neither states that a City business license is a precondition to permit issuance for a contractor; no dedicated out-of-town/non-resident contractor licensing rule (like Avenal's 'Non-Fixed Place of Business' fee category) was found.
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes
Why the confidence is not higherThe City publishes a dedicated 'Owner/Builder Declaration' — 'PERMIT ADDENDUM FOR OWNER-BUILDERS' — that a permit applicant listing themselves as the builder must read, initial and sign before a permit is issued, confirming the City does allow and process owner-builder self-permitted work. General building-permit document, not solar-specific.
city permit addendum form checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Planning%20%26%20Building%20Applications/171006%20Owner%20Builder%20Declaration%20100617.pdf
Q8 What documents make up a complete submittal? Core Submittal package
A completed Building Permit Application (with 'Solar' checked under Project Type, project valuation, owner/applicant/contractor information, and design-professional information if used). NOTE: SJBMC §10-7-050(C) itself REQUIRES the City's Building Division to 'adopt a standard plan and checklist of all requirements with which small residential rooftop solar energy systems shall comply to be eligible for expedited review,' and §10-7-050(D) requires that checklist to substantially conform to the State's Solar Permitting Guidebook. No such solar-specific checklist or standard plan is published on the City's site: the Planning & Building Applications document center lists exactly 10 building-related forms (ADU, permit extension, building permit application, owner/builder declaration, plan revision, EV charging, window/skylight, recycling guide, smoke/CO affidavit, special inspection) and none is a PV/solar checklist.
Why the confidence is not higherPositive/absence finding sourced two ways: the City's own document-center listing (checked directly, 10 named files, none PV-related) and the ordinance's own mandate that such a checklist be adopted (§10-7-050(C)-(D)), which the City has apparently not fulfilled on its public-facing site. This is a real gap, not a search failure — reported as such rather than invented.
department document-center listing + ordinance requirement checked 2026-08-31 https://www.san-juan-bautista.ca.us/departments/planning/planning_and_building_applications.php
Q9 How many copies, and in what format? Submittal package
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (solar chapter, full text) and the City's Planning & Building Applications document center (10 named forms) — no statement of how many copies or in what format a solar submittal must be made; §10-7-050(B) only says electronic submittal 'shall be made available,' without specifying a copy count for either track.
Q10 Is a site plan required, and what must it show? Core Submittal package
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) and the general Building Permit Application form — neither states a site-plan requirement or content list specific to solar; no city 'Homeowner's Guide' or PV checklist (of the kind other CA cities publish) was found on the site.
https://www.san-juan-bautista.ca.us/departments/planning/planning_and_building_applications.php
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text, all sections §10-7-010 through -060) — no mention of a one-line/three-line diagram requirement; the chapter only requires 'documents' generally and defers detail to a checklist that §10-7-050(C) requires but which is not published (see Q8/Q57).
Q12 Are string and conductor calculations required? Drawings & calculations
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text, all sections) — no mention of string or conductor calculations; the chapter defers technical submittal detail entirely to a Building Division checklist required by §10-7-050(C) that is not published on the City's site (see Q8/Q57).
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7, Title 10-1 Article 1 (code adoption), and the City's 'Special Inspection & Testing' packet (downloaded and read) — the special-inspection form is a generic, stale reprint of the 2016 CBC §1705 special-inspection trigger list with no solar-specific or kW/valuation PE-stamp threshold stated anywhere.
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Nothing published by this authority.
Where we lookedSame documents as Q13 — no electrical PE-stamp threshold stated anywhere in the City's own materials.
Q15 What does a residential solar permit cost? Core Fees
$549 flat (residential, roof-mounted); $783 flat (non-residential)
Why the confidence is not higherMaster Fee Schedule, 'Adopted 6.16.2026 – Fee Schedule Final Draft.pdf' (downloaded, extracted with pdftotext -layout), page 2: 'Photovoltaic Roof Mounted — Residential: $549 / Non-Residential: $783,' listed as flat 'Each' fees alongside other standalone permit-fee lines (re-roof $408, kitchen remodel $657, etc.). This is the City's own current adopted fee schedule.
adopted fee schedule checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Master%20Fee%20Schedule/Adopted%206.16.2026-%20%20Fee%20Schedule%20Final%20Draft.pdf
Q16 How is the fee calculated? Core Fees
Flat
Why the confidence is not higherThe 'Photovoltaic Roof Mounted' line in the Master Fee Schedule is a flat 'Each' fee ($549 residential), not a valuation-, per-kW-, or per-panel-based figure, distinct from the general Building Permit Fee Table (which IS valuation-based for other work).
adopted fee schedule checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Master%20Fee%20Schedule/Adopted%206.16.2026-%20%20Fee%20Schedule%20Final%20Draft.pdf
Q17 Is there a separate plan-check fee? Fees
No
Why the confidence is not higherThe Master Fee Schedule lists 'Photovoltaic Roof Mounted' as a single flat line ($549 residential / $783 non-residential) grouped among other single-line 'Miscellaneous Standalone Fees' (re-roof, kitchen remodel, etc.) that do not carry a companion plan-check line, unlike the general valuation-based Building Permit Fee Table which is paired with a separate 'Structural and Architectural Plan Review — 65% of Bldg Permit Fee' line. Moderate confidence because the schedule does not explicitly state that the PV flat fee is plan-check-inclusive.
adopted fee schedule checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Master%20Fee%20Schedule/Adopted%206.16.2026-%20%20Fee%20Schedule%20Final%20Draft.pdf
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Same day for over-the-counter applications; 1 to 3 business days for electronic applications
Why the confidence is not higherSJBMC §10-7-060(A): 'The City shall issue a building permit, the issuance of which is nondiscretionary, on the same day for over-the-counter applications or within one (1) to three (3) business days for electronic applications upon receipt of a complete application that meets the requirements of the approved checklist and standard plan.'
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q19 How long is an issued permit valid before it expires? Timeline & validity
Nothing published by this authority.
Where we lookedSJBMC Title 10-1 Article 1 (§10-1-100–120, code adoption) and Ch. 10-7 (solar chapter) — neither states a locally-set permit-validity/expiration period; the 2025 CBC's own default expiration rule (§105.5, typically 180 days) was not independently re-confirmed as adopted without local override, so this is left unconfirmed rather than assumed.
Q20 Which permit portal does this authority use? Core Portal & process
No dedicated online permit portal found — permits are processed via a downloadable/fillable PDF Building Permit Application submitted to City Hall (311 Second Street / P.O. Box 1420) in person, by mail, or (for Planning applications) by email to planning@san-juan-bautista.ca.us. No SolarAPP+, OpenGov, Accela, eTRAKiT, iWorq or similar portal was found anywhere on the City's site.
Why the confidence is not higherSearched every page fetched from the City's site (Home, Planning index, Planning & Building Applications, Public Safety, Fire, Utility Billing, Staff Directory, Municipal Code) for 'OpenGov,' 'Accela,' 'eTRAKiT,' 'SolarAPP,' 'CitizenServe,' 'iWorq,' 'GeoCivix,' and 'permit portal' — zero hits across the whole downloaded corpus. Not full-site absolute proof (a portal could theoretically exist unlinked), but consistent across every page found.
absence check across department pages checked 2026-08-31 https://www.san-juan-bautista.ca.us/departments/planning/planning_and_building_applications.php
Q21 Can the whole application be completed online? Core Portal & process
No
Why the confidence is not higherSame absence finding as Q20 — the Building Permit Application is a fillable PDF with a signature line, meant to be submitted physically or by mail/email, not an online application system.
city permit application form checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/forms/SJB%20Building%20Permit%20Application%20%28Fillable%29.pdf
Q22 Which utility handles interconnection here? Core Utility interconnection
PG&E (Pacific Gas & Electric)
Why the confidence is not higherThe City's own 'Service Providers' document (San Juan Bautista Service Providers list, hosted on the City's Document Center) lists 'Gas & Electricity: PG&E, 401 McCray Street A-1, Hollister, CA 95023' as the utility serving the City. Document's own printed revision stamp reads 'Rev. 2/12/2018,' so dated but city-hosted and not contradicted by anything newer found; not sourced from PowerToChoose, per the playbook's warning about that tool.
city-published service-provider directory checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Service%20Providers.pdf
Q23 Where does the utility sit in the sequence? Core Utility interconnection
Nothing published by this authority.
Where we lookedCity's own Utility Billing and Service Providers pages (water/sewer-only city utility; PG&E named only as gas/electric provider, no interconnection-sequence detail) and attempted direct fetch of PG&E's own interconnection/Rule 21 pages (both attempted URLs returned HTTP 404) — no source could be reached stating where PG&E interconnection falls relative to the City's permit/inspection sequence.
https://www.san-juan-bautista.ca.us/document_center/Service%20Providers.pdf
Q24 Is a HOA or architectural approval required first? Overlays & special cases
Conditionally Yes — NOT required for a standard qualifying small residential rooftop solar system, but IS required (site plan and design review, potentially with Historic Resources Board and Planning Commission review) if the property is more than 45 years old, listed on the City's Register of Historic Resources, or located in a designated historic district. No general citywide HOA-approval requirement was found.
Why the confidence is not higherSJBMC §10-7-030(C) (within the solar chapter itself): 'A use permit and/or design review may be required for properties on the City's list of historic resources as deemed necessary by the City Manager.' Separately and more broadly, SJBMC §11-06-120(A) requires that '[w]hen a property owner wishes to make an alteration to a property that is more than forty-five (45) years old, the owner shall submit an application to the City Planning Department for a site plan and design review permit' — with NO exception anywhere in Ch. 11-06 for solar energy systems (confirmed: zero hits for 'solar' across the full text of Ch. 11-06, control-checked against 'electrical' which does appear once and 'zzqqx' which appears zero times). See jurisdiction block and Q25 for the conflict this creates with the state's ministerial mandate under Gov. Code §65850.5.
municipal code (eCode360), full chapter text extracted checked 2026-08-31 https://ecode360.com/50528988
Q25 Is there a historic-district review? Overlays & special cases
Yes — and it is in direct, unresolved tension with the City's own AB 2188 ministerial solar chapter.
Why the confidence is not higherSJBMC Ch. 11-06 (Historic Resources Preservation, Ord. 2008-03) and Ch. 11-18 (Site Plan and Design Review, Ord. 2007-03/2007-23) together require: (1) ANY 'alteration' (defined broadly to include anything that 'alters the exterior appearance,' §11-06-020) to a property over 45 years old triggers a mandatory Planning Department application (§11-06-120(A)); (2) minor alterations to Register-listed or historic-district properties that don't meet the City's Design Guidelines go to the Historic Resources Board AND Planning Commission with full DISCRETIONARY approval authority (§11-06-120(C)(3)-(4)); (3) major alterations to Register-listed properties require a historic-resource evaluation/impact report and discretionary Planning Commission approval (§11-06-120(C)(5)). NOWHERE in Ch. 11-06 or Ch. 11-18 is there any exception, carve-out, or even a mention of 'solar' or 'photovoltaic' — confirmed by a full-text search of both chapters (0 hits for 'solar' in Ch. 11-06 across ~95,000 characters of extracted text; 0 hits in Ch. 11-18). This sits directly against Gov. Code §65850.5 (AB 2188), which itself contains NO historic-property exemption (confirmed by reading the enacted statute text) and only permits discretionary review via a narrow 'specific, adverse impact' administrative-use-permit process limited to health/safety findings — not aesthetic/historic-character findings. SJBMC §10-7-030(C)'s own text ('design review may be required... as deemed necessary') appears to reach for exactly the broader aesthetic-review authority that §65850.5 does not grant. The City's own Master Fee Schedule prices this discretionary track concretely: 'Historic Resources Review (including demolition/significant alteration/registration of property) — Administrative $1,500 / Commission $5,000 / Evaluation Actual Cost' — real dollar exposure for a rooftop solar job on a historic-listed property, against the $549 flat fee for the ministerial path. Reported as a genuine, unresolved conflict per the brief's instruction, not flattened into a single answer.
municipal code (eCode360) + adopted fee schedule checked 2026-08-31 https://ecode360.com/50528988
Q26 Is a wind or windstorm certification required? Overlays & special cases
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) and Title 10-1 (code adoption) — no mention of a wind/windstorm certification requirement anywhere; California is not a Texas-style wind-pool state so this may simply not exist as a category here, but no city document was found stating so directly.
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Conditionally Yes. (1) Under Ch. 10-7 itself, the City Manager may require an applicant to obtain an administrative use permit if the system 'could have a specific, adverse impact upon the public health and safety' (§10-7-060(A)), appealable to the Planning Commission. (2) Independently, a major alteration to a historic-Register-listed property is routed to the Historic Resources Board with the Planning Commission holding final discretionary authority (§11-06-120(C)(5)), and the Master Fee Schedule's 'Historic Resources Review — Commission' tier ($5,000 deposit) confirms this is a live, priced process.
Why the confidence is not higherBoth routes are stated directly in the City's own code and fee schedule (see Q24/Q25 for full citations); no instance of an actual Council-level approval requirement for solar specifically was found (appeals from the Planning Commission's use-permit or historic decisions go to City Council per §11-06-120(C)(5)(b), so Council involvement is possible only on appeal).
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q28 Is there a system-size cap on residential generation? Overlays & special cases
10 kW AC nameplate rating or 30 kW thermal, on a single- or two-family dwelling only, panel/module array not to exceed the maximum legal building height
Why the confidence is not higherSJBMC §10-7-020(B): 'Small residential rooftop solar energy system' means a system 'no larger than ten (10) kilowatts alternating current nameplate rating or thirty (30) kilowatts thermal... installed on a single- or two (2) family dwelling... [and] a solar panel or module array that does not exceed the maximum legal building height.' This is the AB 2188-era (2015) figure, unchanged since original adoption (Ord. 2015-23) — consistent with the playbook's finding that many CA cities never updated this cap. This is a scope-defining cap for the EXPEDITED path; larger systems are not barred, they simply fall outside Ch. 10-7's ministerial process and go through standard plan check.
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 NEC (adopted as Part 3, California Electrical Code, of the 2025 California Building Standards Code, Title 24) 78% · municipal code adoption ordinance
- Which building code edition is in force? 2025 California Building Code and 2025 California Residential Code (2025 edition, Title 24, Parts 2 and 2.5), adopted by Ord. 2025-02, effective 11/18/2025 92% · municipal code adoption ordinance
- Which fire code edition is in force? 2025 California Fire Code, adopted by Ord. 2025-03, effective 11/18/2025 95% · municipal code (eCode360)
- Are there local amendments to any of the above? Yes for the Fire Code (extensive local amendments, including PV-specific placarding and module-layout rules — see Q36/Q38-40). No substantive amendments were found to the Building/Residential/Electrical Code beyond adoption-by-reference (the only building-title change noted was repeal of the old UBC Chapter 70 appendix by Ord. 2023-03). 80% · municipal code (eCode360), fire code amendments article
- What is the installation judged against? The 2025 California Building Code, California Residential Code and California Electrical Code (Title 24, Parts 2/2.5/3) as adopted by SJBMC §10-1-110, plus SJBMC Ch. 10-7's own solar-specific requirements (§10-7-040): compliance with 'the California Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories.' 82% · municipal code (eCode360)
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? Hip-and-valley module layout only: modules must be no closer than 1.5 feet (1'-6") to a hip or valley if modules are placed on both sides of it; modules on only one side of a hip or valley of equal length may be placed directly adjacent to it. No separate ridge-setback or 3-foot perimeter access-pathway local amendment was found beyond this — the unamended base 2025 CFC pathway/setback provisions would otherwise apply. 75% · municipal code (eCode360), fire code amendments article
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes, rapid shutdown is required under NEC/CEC §690.12 as adopted via the 2025 California Electrical Code (Title 24, Part 3); no local amendment or exception to §690.12 was found. 65% · inference from code adoption + absence check
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? Main service disconnect panel placard reading 'SOLAR DISCONNECT INSIDE PANEL'; a separate label at the inverter/PV circuit breaker reading 'SOLAR DISCONNECT'; additional signage for any secondary power source (battery/generator) shutoff switch location; installer-identification signage (name + emergency phone number) at the main disconnect; and, where applicable, 'FUEL CELL' and 'BESS' interior equipment-location placards. 92% · municipal code (eCode360), fire code amendments article
- Does the authority specify placard wording of its own? Yes 95% · municipal code (eCode360), fire code amendments article
- Does it specify letter height, colour or material? Main panel placard: red background, white capital letters ≥ 1/2" high, non-serif font, weather-resistant durable plastic with engraved letters. Circuit-disconnect label: contrasting-color capital letters ≥ 3/8" high, non-serif font, durable adhesive material. 'FUEL CELL' and 'BESS' interior placards: block letters 6" high with a 3/4" stroke on a contrasting background. 95% · municipal code (eCode360), fire code amendments article
- Where must the labels be placed? Main disconnect placard: permanently affixed to the main service disconnect panel. Circuit-disconnect label: affixed adjacent to the circuit breaker controlling the inverter/PV electrical controller. Installer-information signage: adjacent to the main disconnect. Secondary-power-source signage: at the secondary power source shutoff switch location. 'FUEL CELL'/'BESS' signage: at the interior location of that equipment. ESS disconnect: located at or adjacent to the main electrical panel. 90% · municipal code (eCode360), fire code amendments article
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Are batteries permitted, and under what conditions? Yes, batteries/ESS are permitted under the adopted 2025 California Fire Code as locally amended. Local amendments require: ESS disconnect located at or adjacent to the main electrical panel with placarding showing equipment location and all shutdowns (§1207.4.1.1); and, where a battery energy storage system is installed inside any structure, interior signage reading 'BESS' in 6" block letters with 3/4" stroke on a contrasting background (§1207.4.8-6). 80% · municipal code (eCode360), fire code amendments article
20 questions answered against City of San Juan Bautista’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023 NEC (adopted as Part 3, California Electrical Code, of the 2025 California Building Standards Code, Title 24)
Why the confidence is not higherSJBMC §10-1-110(A) (Ord. 2025-02, adopted 11/18/2025) adopts 'the 2025 Edition of the California Building Standards, Title 24... in its entirety consisting of... Part 3 California Electrical Code' by reference, without further amendment stated. The city's own text does not spell out 'NEC 2023' explicitly — that mapping is inferred from California's standard code-cycle correlation (each CBSC 3-year cycle's CEC is based on the NFPA 70/NEC edition two years prior: 2022 CBSC→NEC 2020, 2025 CBSC→NEC 2023), which is well-established but not itself stated in this ordinance.
municipal code adoption ordinance checked 2026-08-31 https://ecode360.com/50527670
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code and 2025 California Residential Code (2025 edition, Title 24, Parts 2 and 2.5), adopted by Ord. 2025-02, effective 11/18/2025
Why the confidence is not higherSJBMC §10-1-110(A) lists the full 2025 Title 24 suite adopted verbatim: Part 1 (Administrative), Part 2 (CBC), Part 2.5 (CRC), Part 4 (CMC), Part 5 (CPC), Part 6 (Energy Code), Part 7 (WUI Code), Part 8 (Historical Building Code), Part 10 (Existing Building Code), Part 11 (CALGreen), Part 12 (Referenced Standards), plus the 2024 International Property Maintenance Code.
municipal code adoption ordinance checked 2026-08-31 https://ecode360.com/50527670
Q31 Which fire code edition is in force? Code editions in force
2025 California Fire Code, adopted by Ord. 2025-03, effective 11/18/2025
Why the confidence is not higherSJBMC Chapter 5-1 is titled 'CALIFORNIA FIRE CODE, 2025 EDITION,' with history line '(Ord. 2003-04, 10/21/2003; Ord. 2023-02, 4/18/2023; Ord. 2025-03, 11/18/2025)' — confirmed as the current, most-recent adoption (the eCode360 site itself states 'Includes legislation through 11-18-2025').
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50523187
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes for the Fire Code (extensive local amendments, including PV-specific placarding and module-layout rules — see Q36/Q38-40). No substantive amendments were found to the Building/Residential/Electrical Code beyond adoption-by-reference (the only building-title change noted was repeal of the old UBC Chapter 70 appendix by Ord. 2023-03).
Why the confidence is not higherFire Code amendments confirmed directly from the ordinance's own 'amendments, additions and deletions to the California Fire Code, 2025 Edition' section (Article 1, extracted in full). Building Code (Title 10-1, Article 1, §10-1-100–120) was read in full and contains only the adoption-by-reference clause, definitions, and a repealed UBC appendix — no separate 'amendments' article was found in that chapter's table of contents.
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q33 What is the installation judged against? Core Electrical
The 2025 California Building Code, California Residential Code and California Electrical Code (Title 24, Parts 2/2.5/3) as adopted by SJBMC §10-1-110, plus SJBMC Ch. 10-7's own solar-specific requirements (§10-7-040): compliance with 'the California Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories.'
Why the confidence is not higherCombines the general code-adoption section with Ch. 10-7's own solar-specific standards clause, both read directly from the municipal code.
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
Nothing published by this authority.
Where we lookedSJBMC Title 10-1 Article 1 (code adoption) and Ch. 10-7 (solar chapter) — no local rule on service-panel/busbar sizing for solar interconnection was found; only the state-adopted 2025 CEC would govern, unamended locally as far as could be confirmed.
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7, Title 10-1, and the local Fire Code amendments article (Ch. 5-1) — the only mounting-related local rule found is the fire-code hip/valley module-spacing rule recorded under Q36; no separate structural attachment-system or fastener-spacing requirement was found.
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Hip-and-valley module layout only: modules must be no closer than 1.5 feet (1'-6") to a hip or valley if modules are placed on both sides of it; modules on only one side of a hip or valley of equal length may be placed directly adjacent to it. No separate ridge-setback or 3-foot perimeter access-pathway local amendment was found beyond this — the unamended base 2025 CFC pathway/setback provisions would otherwise apply.
Why the confidence is not higherSJBMC §1205.2.1.4 (local Fire Code amendment, extracted directly from the ordinance's amendments article): 'Hip and Valley Layout. Modules shall be located no closer than one and one-half feet (1-1/2') to a hip or valley if modules are to be placed on both sides of a hip or valley...' A full-text search of the same amendments article for 'ridge,' 'setback' and 'pathway' found no additional PV-specific access-pathway rule (the 'ridge' hits that appeared were all false positives from the word 'bridge').
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes, rapid shutdown is required under NEC/CEC §690.12 as adopted via the 2025 California Electrical Code (Title 24, Part 3); no local amendment or exception to §690.12 was found.
Why the confidence is not higherInferred from (a) the City's adoption of the full, unamended 2025 CEC (§10-1-110(A)), and (b) a full-text search of the City's own locally-amended Fire Code article for 'rapid shutdown' and '690.12,' which returned zero hits — i.e., the City has not carved out or modified the state rapid-shutdown requirement. No city document explicitly restates or cites §690.12 by number, so this is inference from adoption plus a control-checked absence of any override, not a direct local citation.
inference from code adoption + absence check checked 2026-08-31 https://ecode360.com/50527670
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Main service disconnect panel placard reading 'SOLAR DISCONNECT INSIDE PANEL'; a separate label at the inverter/PV circuit breaker reading 'SOLAR DISCONNECT'; additional signage for any secondary power source (battery/generator) shutoff switch location; installer-identification signage (name + emergency phone number) at the main disconnect; and, where applicable, 'FUEL CELL' and 'BESS' interior equipment-location placards.
Why the confidence is not higherSJBMC local Fire Code amendments §1205.1.1.1 through §1205.1.1.4, plus §1206.14 and §1207.4.8-6, read directly from the City's own amendments-to-the-2025-CFC article (Ord. 2025-03, effective 11/18/2025).
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
Yes
Why the confidence is not higherThe ordinance specifies exact required wording verbatim: 'SOLAR DISCONNECT INSIDE PANEL' (§1205.1.1.1), 'SOLAR DISCONNECT' (§1205.1.1.2), 'FUEL CELL' (§1206.14), and 'BESS' (§1207.4.8-6).
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Main panel placard: red background, white capital letters ≥ 1/2" high, non-serif font, weather-resistant durable plastic with engraved letters. Circuit-disconnect label: contrasting-color capital letters ≥ 3/8" high, non-serif font, durable adhesive material. 'FUEL CELL' and 'BESS' interior placards: block letters 6" high with a 3/4" stroke on a contrasting background.
Why the confidence is not higherVerbatim specifications from SJBMC's local Fire Code amendments §1205.1.1.1, §1205.1.1.2, §1206.14 and §1207.4.8-6.
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSJBMC's local Fire Code amendments article (Ch. 5-1) — searched for a site-plan/facility-map placard requirement tied to CFC/NEC §705.10; none of the located amendment sections (§1205.x, §1206.14, §1207.x) mention a facility map or site-plan placard.
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedAttempted direct fetch of PG&E's own interconnection/DG-manual pages for utility-specific placard requirements (both attempted URLs returned HTTP 404); the City's own Service Providers document names PG&E as the utility but contains no placard specification.
https://www.san-juan-bautista.ca.us/document_center/Service%20Providers.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
Main disconnect placard: permanently affixed to the main service disconnect panel. Circuit-disconnect label: affixed adjacent to the circuit breaker controlling the inverter/PV electrical controller. Installer-information signage: adjacent to the main disconnect. Secondary-power-source signage: at the secondary power source shutoff switch location. 'FUEL CELL'/'BESS' signage: at the interior location of that equipment. ESS disconnect: located at or adjacent to the main electrical panel.
Why the confidence is not higherLocations specified verbatim in SJBMC's local Fire Code amendments §1205.1.1.1–.4 and §1207.4.1.1.
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q44 Must equipment be on a specific approved list? Equipment listing
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 and the local Fire Code amendments article — no statement requiring equipment to be on a specific approved list (beyond generic CEC/UL/IEEE listing standards already recorded under Q33).
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Yes, batteries/ESS are permitted under the adopted 2025 California Fire Code as locally amended. Local amendments require: ESS disconnect located at or adjacent to the main electrical panel with placarding showing equipment location and all shutdowns (§1207.4.1.1); and, where a battery energy storage system is installed inside any structure, interior signage reading 'BESS' in 6" block letters with 3/4" stroke on a contrasting background (§1207.4.8-6).
Why the confidence is not higherDrawn directly from the City's own locally-amended Fire Code article. No separate SJBMC chapter specifically addresses residential ESS beyond these two amendment sections — SJBMC Ch. 10-7 (the solar permitting chapter) does not mention batteries or ESS at all (confirmed: zero hits for 'battery'/'ESS'/'energy storage' in the full text of Ch. 10-7).
municipal code (eCode360), fire code amendments article checked 2026-08-31 https://ecode360.com/50523188
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (zero mentions of batteries/ESS in the solar chapter) and the local Fire Code amendments article (§1207.4.1.1, §1207.4.8-6, which address disconnect location and signage but do not state whether a SEPARATE ESS permit or inspection, distinct from the base CFC process, is required).
Q47 Is a ground mount treated as a structure? Core Ground mount
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (scoped only to ROOFTOP solar, zero mentions of ground-mount) and Ch. 11-04 (Additional Development Standards, full text extracted — the only 'ground-mounted' hits found relate to satellite/antenna equipment, not solar), control-checked against 'zzqqx' (0 hits).
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 and the local Fire Code amendments article — no city document specifies AC-disconnect placement relative to the meter; attempted direct fetch of PG&E's own DG-manual/interconnection pages for this detail returned HTTP 404 on both attempted URLs.
https://www.san-juan-bautista.ca.us/document_center/Service%20Providers.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
Nothing recorded for City of San Juan Bautista on this step yet — 3 questions checked and found unpublished. The guidance above is general.
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes 92% · municipal code (eCode360)
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? One consolidated final inspection, performed by the Building Division, done 'in a timely manner' and 'should include consolidated inspections.' 88% · municipal code (eCode360)
- Is a rough-in or mid-roof inspection required? No 88% · municipal code (eCode360)
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? No 78% · department document-center listing (absence check)
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- Is there a re-inspection fee? $182 per re-inspection 85% · adopted fee schedule
- How are corrections issued and cleared? At the APPLICATION stage: if an application is deemed incomplete, the City sends 'a written correction notice detailing all deficiencies in the application and any additional information or documentation required,' for resubmission (SJBMC §10-7-060(F)). No City document was found describing how corrections identified at a FAILED INSPECTION are issued/cleared beyond §10-7-060(I) authorizing 're-inspection' after a failure. 55% · municipal code (eCode360), partial answer
14 questions answered against City of San Juan Bautista’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) and every fetched City department page — no statement of how an inspection is booked (portal/phone/email/walk-in); only the City's general phone number (831) 623-4661 is published.
Q50 How much notice is required? Core Booking & scheduling
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) — §10-7-060(H) only says inspection 'shall be done in a timely manner,' with no stated notice period in business days.
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) and every fetched City department page — no mention of same-day or AM/PM inspection windows.
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes
Why the confidence is not higherSJBMC §10-7-060(G): 'Only one (1) inspection shall be required and performed by the building division for small residential rooftop solar energy systems eligible for expedited review.'
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q53 If delegated, to whom? Core Who inspects
Nothing published by this authority.
Where we lookedN/A — Q52 establishes that the Building Division performs its own final solar inspection in-house per §10-7-060(G); there is no delegation to identify.
Q54 Which inspections are required, and in what order? Core Stages & sequence
One consolidated final inspection, performed by the Building Division, done 'in a timely manner' and 'should include consolidated inspections.'
Why the confidence is not higherSJBMC §10-7-060(G)-(H): 'Only one (1) inspection shall be required and performed by the building division... The inspection shall be done in a timely manner and should include consolidated inspections.'
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
No
Why the confidence is not higherSJBMC §10-7-060(G) explicitly limits expedited-path solar systems to a single required inspection ('Only one (1) inspection shall be required'), which by its terms excludes a separate rough-in/mid-roof inspection for qualifying systems.
municipal code (eCode360) checked 2026-08-31 https://ecode360.com/50528306
Q56 Does the inspector verify labels and listings? Core What is checked
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 and the local Fire Code amendments article — neither states explicitly that the inspector verifies labels/listings as part of the required inspection, though the fire-code amendments do require specific placards to exist (Q38-40); no document states this is checked at inspection.
Q57 Is there a published inspection checklist? Core What is checked
No
Why the confidence is not higherSJBMC §10-7-050(C) requires the Building Division to 'adopt a standard plan and checklist' for expedited solar review, but no such checklist is published in the City's own Planning & Building Applications document center (10 named documents checked directly, none PV-related). This is recorded as a proved absence of a published checklist — not proof the City has never adopted one internally — since the ordinance mandates one exist.
department document-center listing (absence check) checked 2026-08-31 https://www.san-juan-bautista.ca.us/departments/planning/planning_and_building_applications.php
Q58 What must be on site at inspection? Core Documents on site
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) and the general Building Permit Application — no published list of documents required to be on-site at the time of inspection.
Q59 Is there a re-inspection fee? Corrections & re-inspection
$182 per re-inspection
Why the confidence is not higherMaster Fee Schedule, 'Reinspection Fees — Per re-inspection — $182' (Building section). SJBMC §10-7-060(I) separately confirms 'If a small residential rooftop solar energy system fails inspection, a subsequent inspection is authorized,' consistent with this fee applying to solar.
adopted fee schedule checked 2026-08-31 https://www.san-juan-bautista.ca.us/document_center/Master%20Fee%20Schedule/Adopted%206.16.2026-%20%20Fee%20Schedule%20Final%20Draft.pdf
Q60 How are corrections issued and cleared? Corrections & re-inspection
At the APPLICATION stage: if an application is deemed incomplete, the City sends 'a written correction notice detailing all deficiencies in the application and any additional information or documentation required,' for resubmission (SJBMC §10-7-060(F)). No City document was found describing how corrections identified at a FAILED INSPECTION are issued/cleared beyond §10-7-060(I) authorizing 're-inspection' after a failure.
Why the confidence is not higherThe only correction-notice process stated in the City's own code is at the pre-permit application-completeness stage, not the post-inspection stage the question is really asking about; recorded at reduced confidence because it only partially answers the question, and the true post-inspection process was not found published anywhere.
municipal code (eCode360), partial answer checked 2026-08-31 https://ecode360.com/50528306
Q61 What is issued on pass? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text) — the chapter describes only the inspection process (§10-7-060(G)-(I)); it does not name what is issued upon a passed inspection (CO / Final / Green tag / Letter).
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedSJBMC Ch. 10-7 (full text), the City's Service Providers directory, and attempted direct fetch of PG&E's own interconnection pages (both attempted URLs returned HTTP 404) — no source found stating who notifies PG&E for Permission to Operate.
https://www.san-juan-bautista.ca.us/document_center/Service%20Providers.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of San Juan Bautista against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of San Juan Bautista is the authority having jurisdiction 88% confidence
- Holds
- Building and Electrical (self-performed in-house; SJBMC §10-1-105(A) defines 'Building Official' and 'Chief Electrical Inspector' as one title, 'the Building Inspector of the City of San Juan Bautista'). Fire prevention/suppression is DELEGATED to the City of Hollister Fire Department (a neighbouring independent city's department, not a county or district) — confirmed by the City's own FHSZ page ('working with the Hollister Fire Department') and its own Service Providers directory, which lists 'Hollister FD #4' at a Polk Street address inside San Juan Bautista. Engineering design standards are also adopted by reference from the City of Hollister (SJBMC §10-1-110(B)).
- Delegated to
- City of Hollister Fire Department (fire prevention, plan review and suppression); City of Hollister Engineering Design Standards (adopted by reference for engineering standards, not a delegation of permitting authority itself)
- Overridden by
- California Gov. Code §65850.5 (AB 2188) mandates a ministerial, nondiscretionary review process for qualifying small residential rooftop solar systems, codified locally as SJBMC Ch. 10-7 (same-day/1-3-business-day permit issuance, one inspection). BUT SJBMC Ch. 11-06 (Historic Resources Preservation) and Ch. 11-18 (Site Plan and Design Review) independently require a mandatory, often DISCRETIONARY site-plan/design-review application — with Historic Resources Board and Planning Commission approval authority — for any 'alteration' to a property over 45 years old or in a designated historic district, with NO exception anywhere in either chapter for solar energy systems (confirmed by a full-text search: zero 'solar' hits in Ch. 11-06, control-checked against 'electrical' [1 hit] and a fabricated term 'zzqqx' [0 hits]; likewise zero 'solar' hits in Ch. 11-18). Ch. 10-7's own §10-7-030(C) tries to reserve 'design review... as deemed necessary by the City Manager' for historic-listed properties, but Gov. Code §65850.5 itself (read directly from the enacted statute) contains no historic-property carve-out and permits discretionary review only through a narrow, health/safety-based 'specific, adverse impact' administrative process — not an aesthetic/historic-character design-review process. This is reported as a live, unresolved conflict per the brief's instruction, not resolved in either direction. The City's own Master Fee Schedule prices the historic-review track concretely (Historic Resources Review: Administrative $1,500 / Commission $5,000 deposit), which is real cost exposure that could attach to a rooftop solar job on a historic property well beyond the $549 ministerial-path fee.
- Why not higher
- Directly sourced from the City's own eCode360-hosted municipal code (Chs. 5-1, 10-1, 10-7, 11-06, 11-18), its own Master Fee Schedule (adopted 6/16/2026), its own FHSZ department page, and its own Service Providers directory — all fetched and read in full (not summarized) in this run. The historic/solar conflict is the central jurisdictional finding this brief specifically asked to surface for San Juan Bautista given its state-historic-park/mission historic district.
- Permit required
- Yes95%
- Permit cost
- $549 flat (residential, roof-mounted); $783 flat (non-residential)92%
- Plan review
- Same day for over-the-counter applications; 1 to 3 business days for electronic applications92%
- Portal
- No dedicated online permit portal found — permits are processed via a downloadable/fillable PDF Building Permit Application submitted to City Hall (311 Second Street / P.O.78%
- Electrical code
- 2023 NEC (adopted as Part 3, California Electrical Code, of the 2025 California Building Standards Code, Title 24)78%
- Own placard wording
- Yes95%
Labels & placards for this authority
City of San Juan Bautista writes its own placard wording. A standard NEC label set will not satisfy it — the exact text, and in most cases the size, colour and font, are specified below.
Wording 95%
Yes
Size, colour & material 95%
Main panel placard: red background, white capital letters ≥ 1/2" high, non-serif font, weather-resistant durable plastic with engraved letters. Circuit-disconnect label: contrasting-color capital letters ≥ 3/8" high, non-serif font, durable adhesive material. 'FUEL CELL' and 'BESS' interior placards: block letters 6" high with a 3/4" stroke on a contrasting background.
Where they go 90%
Main disconnect placard: permanently affixed to the main service disconnect panel. Circuit-disconnect label: affixed adjacent to the circuit breaker controlling the inverter/PV electrical controller. Installer-information signage: adjacent to the main disconnect. Secondary-power-source signage: at the secondary power source shutoff switch location. 'FUEL CELL'/'BESS' signage: at the interior location of that equipment. ESS disconnect: located at or adjacent to the main electrical panel.
What the utility wants on top None%
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.