City of Seal Beach
Orange County
City of Seal Beach is a city authority in the State of California, serving 25,242 residents. 865 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Plan review takes approximately 3-4 weeks after plans are accepted for review; initial fee/scope confirmation after application submittal takes 1-3 business days. Q18 Where you file — Three linked systems: SolarAPP+ (NREL) for automated PV plan review; the city's Tyler/EnerGov 'Civic Access Portal' (sealbeachca-energovpub.tylerhost.net) for the… Q20
- Permit required
- Yes98% source
- What it costs
- $344 flat for systems ≤15 kW; above 15 kW, $344 base + $15 per kW above 15 kW (residential). Commercial is a separate, higher tiered schedule.92% source
- Plan review turnaround
- Plan review takes approximately 3-4 weeks after plans are accepted for review; initial fee/scope confirmation after application submittal takes 1-3 business days.85% source
- Key document
- ordinance cited by 10 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes 95% · department page
- What does this authority permit itself, and what does it delegate? Both 90% · ordinance
- Is a permit required for a residential rooftop PV system? Yes 98% · ordinance
- Is there a separate electrical permit, or is it combined? Combined 82% · department page
- Is a HOA or architectural approval required first? Conditional: No for most single-family parcels (Solar Rights Act protections apply, and SBMC §9.60.050 has no general HOA-approval gate), but Yes specifically inside Leisure World — the city's own SolarAPP+ page states 'Individual users in Leisure World shall obtain Golden Rain Foundation permits to the City prior to submission on SolarAPP+.' 88% · department page
- Is there a historic-district review? No dedicated historic-district design review found reaching solar. 60% · ordinance
- Is a wind or windstorm certification required? No 65% · ordinance
- Is a Specific Use Permit or Council approval ever required? Only if the Building Official makes a written finding, based on substantial evidence, that the system 'could have a specific, adverse impact upon the public health or safety' — otherwise no Use Permit or Council approval is required. 85% · ordinance
- Is there a system-size cap on residential generation? No absolute residential cap. The AB 2188-era 10 kW AC / 30 kW thermal figure only gates eligibility for the streamlined 'small residential rooftop solar energy system' administrative-approval pathway (also limited to single- or duplex-family dwellings, and to the max legal building height). The city's own fee schedule shows tiered residential fees running well past 15 kW with no stated ceiling, so larger single-family systems are permitted, just outside the expedited track. 82% · ordinance
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Either 85% · department page
- Must the contractor be registered with this authority before applying? Yes 85% · department page
- Is a homeowner permitted to self-install and self-permit? Yes 80% · department page
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? Completed permit application; electrical plan (main disconnect location, module/string count, inverter/combiner make-model, one-line diagram, grounding/bonding and conductor/conduit sizing, battery locations if any, equipment cut sheets, CEC 690/705 labeling); site diagram (panel layout, north arrow, lot dimensions, existing shading, distances to property lines/buildings); structural support info for roof-mounted systems (roof covering/framing, panel weight, attachment method, racking documentation, calculations if required). 92% · published checklist
- How many copies, and in what format? Fully electronic — PDF upload only; no physical copies required. 85% · department page
- Is a site plan required, and what must it show? Yes — must show arrangement of panels on the roof/ground, north arrow, lot dimensions, existing shading elements, and distances from property lines to adjacent buildings/structures (existing and proposed). 92% · published checklist
- Is a one-line / three-line diagram required? Yes 90% · published checklist
- Are string and conductor calculations required? Yes 75% · published checklist
- Is a structural PE stamp required, and at what threshold? No PV-specific stamp threshold published; the general locally-amended residential stamp rule (SBMC 9.60.020, CRC amendment) requires a CA-licensed architect/engineer's stamp on construction documents for wood-frame dwellings more than 2 stories + basement in Seismic Design Category A/B/C, or more than 1 story/with a basement in Category D0/D1/D2/E. The PV handout itself only says to 'demonstrate compliance with structural requirements if needed.' 60% · ordinance
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? Three linked systems: SolarAPP+ (NREL) for automated PV plan review; the city's Tyler/EnerGov 'Civic Access Portal' (sealbeachca-energovpub.tylerhost.net) for the building permit application, fees, and inspection scheduling; and 'GoPost' (Transtech-hosted, gopost-transtech.eplansoftreview.com) for electronic plan-set submittal/plan check. 88% · portal landing page
- Can the whole application be completed online? Yes 85% · portal
- What does a residential solar permit cost? $344 flat for systems ≤15 kW; above 15 kW, $344 base + $15 per kW above 15 kW (residential). Commercial is a separate, higher tiered schedule. 92% · fee schedule
- How is the fee calculated? Tiered 90% · fee schedule
- Is there a separate plan-check fee? No 85% · fee schedule
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? Plan review takes approximately 3-4 weeks after plans are accepted for review; initial fee/scope confirmation after application submittal takes 1-3 business days. 85% · department page
- How long is an issued permit valid before it expires? 365 days (1 year) 90% · ordinance
- Which utility handles interconnection here? Southern California Edison (SCE) 78% · ordinance
- Where does the utility sit in the sequence? After permit 65% · ordinance
28 questions answered against City of Seal Beach’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity of Seal Beach Community Development / Building & Safety Division administers building and electrical permits for residential solar; codified at SBMC Ch. 9.60 (Building Code). Fire (OCFA) and, in the Coastal Zone, the CA Coastal Commission also have roles (see jurisdiction block).
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherBuilding & Safety self-performs building and electrical review/inspection for standard residential PV under one combined permit (SBMC 9.60.050). Fire is delegated to OCFA but ONLY for battery/ESS and PV needing 'Alternative Compliance' (deviation) — OCFA's own current fee schedule and its Jan-2026 SFR Plan Screening Form confirm standard residential rooftop PV is not an OCFA plan-review trigger.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherSBMC §9.60.050 codifies a permitting process for 'small residential rooftop solar energy systems'; the Cost Recovery Schedule lists a dedicated Building Permit fee for 'Residential Solar Photovoltaic System.'
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Combined
Why the confidence is not higherThe city's own SolarAPP+ page instructs applicants to 'Apply for a City of Seal Beach Electrical Photovoltaic Building permit' (singular, EnerGov category) and the fee schedule lists one 'Residential Solar Photovoltaic System - Solar Permit' line rather than separate building and electrical lines.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/SOLARAPP
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Either
Why the confidence is not higherContractors need an active Seal Beach business license to pull the permit, but the Permit/Contractor's License page states 'If you are a property owner and plan to do the work yourself, you do not need a contractor's license' — owner-builder self-permitting is allowed.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/Permit-Contractors-License
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Yes
Why the confidence is not higherPermit/Contractor's License page: 'If you are a contractor, you must have the proper license to obtain a permit' and directs contractors to the Seal Beach Contractor Business License application before permitting.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/Permit-Contractors-License
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes
Why the confidence is not higherSame page: property owners performing their own work do not need a contractor's license, implying self-install/self-permit is allowed for owner-builders.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/Permit-Contractors-License
Q8 What documents make up a complete submittal? Core Submittal package
Completed permit application; electrical plan (main disconnect location, module/string count, inverter/combiner make-model, one-line diagram, grounding/bonding and conductor/conduit sizing, battery locations if any, equipment cut sheets, CEC 690/705 labeling); site diagram (panel layout, north arrow, lot dimensions, existing shading, distances to property lines/buildings); structural support info for roof-mounted systems (roof covering/framing, panel weight, attachment method, racking documentation, calculations if required).
Why the confidence is not higherFull itemized list from the city's own 'Solar Photovoltaic Installation Guidelines' handout (Community Development Dept, 'Toolkit Document #1'), Section 2.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q9 How many copies, and in what format? Submittal package
Fully electronic — PDF upload only; no physical copies required.
Why the confidence is not higherForm B ('How to Submit Electronic Plans for Building Permits') instructs applicants to upload plans and supporting docs as PDF through the GoPost electronic plan submittal portal after applying/paying in the Civic Access Portal; no paper-copy count is specified anywhere.
department page checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Users/027/27/27/FORM%20B-Getting%20Started%20for%20Electronic%20Plan%20Submittal-Seal%20Beach%201-17-25.pdf?ver=2025-03-14-143028-330
Q10 Is a site plan required, and what must it show? Core Submittal package
Yes — must show arrangement of panels on the roof/ground, north arrow, lot dimensions, existing shading elements, and distances from property lines to adjacent buildings/structures (existing and proposed).
Why the confidence is not higherSolar PV handout, Section 2(c) site-diagram bullet.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Yes
Why the confidence is not higherSolar PV handout requires 'One-line diagram of system' as part of the required electrical plan.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q12 Are string and conductor calculations required? Drawings & calculations
Yes
Why the confidence is not higherHandout requires 'Total number of modules, number of modules per string, and the total number of strings' and full conductor/conduit type-and-size specification for each conduit run — string/conductor sizing information, though not phrased as a formal 'calculation.'
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
No PV-specific stamp threshold published; the general locally-amended residential stamp rule (SBMC 9.60.020, CRC amendment) requires a CA-licensed architect/engineer's stamp on construction documents for wood-frame dwellings more than 2 stories + basement in Seismic Design Category A/B/C, or more than 1 story/with a basement in Category D0/D1/D2/E. The PV handout itself only says to 'demonstrate compliance with structural requirements if needed.'
Why the confidence is not higherGeneral provision found in the local CRC amendment inside SBMC Ch. 9.60; not solar-specific, so applied by inference to PV racking/attachment structural pages.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Nothing published by this authority.
Where we lookedSolar PV handout (structural/electrical requirements sections), SBMC Ch. 9.60 (Building Code chapter, incl. local amendments in §9.60.020 and the solar-specific §9.60.050) — no distinct electrical PE-stamp threshold for PV is stated anywhere in either.
Q15 What does a residential solar permit cost? Core Fees
$344 flat for systems ≤15 kW; above 15 kW, $344 base + $15 per kW above 15 kW (residential). Commercial is a separate, higher tiered schedule.
Why the confidence is not higherCity of Seal Beach Cost Recovery Schedule, effective 1 Jul 2025 (current FY2025-26), Building Fees §A.3 'Residential Solar Photovoltaic System - Solar Permit.' Confirmed against the prior FY2023-24 schedule ($322/$16 per kW), so this is a real annual update, not a stale figure.
fee schedule checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Finance/Cost%20Recovery%20Schedule%20FY%202025-2026.pdf?ver=2025-10-16-094407-650
Q16 How is the fee calculated? Core Fees
Tiered
Why the confidence is not higherSame fee-schedule line: flat fee up to a 15kW threshold, then a base fee plus a per-kW rate above it.
fee schedule checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Finance/Cost%20Recovery%20Schedule%20FY%202025-2026.pdf?ver=2025-10-16-094407-650
Q17 Is there a separate plan-check fee? Fees
No
Why the confidence is not higherThe Building Fees Section A header states fees in that section 'include all applicable inspection, and plan review fees' — the $344 solar permit line is inclusive, not a separate plan-check line (though small statutory add-ons — SMI, SB1473, 2% plan-archival — apply on top, as they do to every building permit).
fee schedule checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Finance/Cost%20Recovery%20Schedule%20FY%202025-2026.pdf?ver=2025-10-16-094407-650
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Plan review takes approximately 3-4 weeks after plans are accepted for review; initial fee/scope confirmation after application submittal takes 1-3 business days.
Why the confidence is not higherCity's own 'How to Apply for a Building Permit' guide (Form A), steps 2 and 4.
department page checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Users/027/27/27/FORM%20A-HOW%20TO%20APPLY%20FOR%20E-PERMIT.pdf?ver=2025-03-14-142944-190
Q19 How long is an issued permit valid before it expires? Timeline & validity
365 days (1 year)
Why the confidence is not higherSBMC §9.60.020 (locally amended CBC §105.7): a permit expires if work is not commenced within 1 year of issuance, or if no required inspection is approved within 1 year of the last approved inspection. The Building Official may grant extensions of up to 180 days each.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q20 Which permit portal does this authority use? Core Portal & process
Three linked systems: SolarAPP+ (NREL) for automated PV plan review; the city's Tyler/EnerGov 'Civic Access Portal' (sealbeachca-energovpub.tylerhost.net) for the building permit application, fees, and inspection scheduling; and 'GoPost' (Transtech-hosted, gopost-transtech.eplansoftreview.com) for electronic plan-set submittal/plan check.
Why the confidence is not higherSolarAPP+ page names the SolarAPP+ workflow and 'Electrical Photovoltaic Building permit'; Forms/Permit-License pages link the EnerGov selfservice Civic Access Portal for applications/inspections and the GoPost portal for plan submittal.
portal landing page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/SOLARAPP
Q21 Can the whole application be completed online? Core Portal & process
Yes
Why the confidence is not higherSolarAPP+ registration, the Civic Access Portal application/fee payment, GoPost plan upload, and inspection requests are all done online end-to-end per the city's own instructions.
portal checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/SOLARAPP
Q22 Which utility handles interconnection here? Core Utility interconnection
Southern California Edison (SCE)
Why the confidence is not higherSeal Beach's own Municipal Code (Title 6, Wireless Communication Facilities provisions) names 'Southern California Edison' as an example of an existing electric utility structure owner in the city's public right-of-way — first-party confirmation of the incumbent electric utility, though it is an illustrative 'e.g.' reference rather than a franchise grant naming SCE outright.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q23 Where does the utility sit in the sequence? Core Utility interconnection
After permit
Why the confidence is not higherSBMC §9.60.050.060.D: city approval/permit issuance 'does not authorize an applicant to connect the small residential rooftop energy system to the local utility provider's electricity grid. The applicant is responsible for obtaining such approval or permission from the local utility provider' — utility interconnection/PTO approval is a separate step, obtained after the city permits/installs the system.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q24 Is a HOA or architectural approval required first? Overlays & special cases
Conditional: No for most single-family parcels (Solar Rights Act protections apply, and SBMC §9.60.050 has no general HOA-approval gate), but Yes specifically inside Leisure World — the city's own SolarAPP+ page states 'Individual users in Leisure World shall obtain Golden Rain Foundation permits to the City prior to submission on SolarAPP+.'
Why the confidence is not higherCity's own SOLARAPP+ page, verbatim Leisure World sentence. Note the codified solar ordinance (§9.60.050.030) defines 'Association' and 'common interest development' but never operationally uses those defined terms elsewhere in the section — the actual GRF requirement lives only on the webpage, not in the ordinance.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety/SOLARAPP
Q25 Is there a historic-district review? Overlays & special cases
No dedicated historic-district design review found reaching solar.
Why the confidence is not higherTitle 11 (Zoning) has no distinct Historic Overlay District chapter; the only historic mechanism (§11.4.40.055 'Nonconforming Historic Buildings') is a discretionary CUP route for a building found to have 'local historic significance,' with no solar-specific trigger or carve-out found on a search of the full Title 11 text for 'historic.'
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q26 Is a wind or windstorm certification required? Overlays & special cases
No
Why the confidence is not higherNo windstorm/wind-certification requirement appears in SBMC Ch. 9.60 or its local amendments (§9.60.020) — searched with a passing positive control ('electrical', 39 hits) and a fabricated control ('zzqqx', 0 hits) on the same extracted text; standard unamended ASCE 7-22 wind provisions in the 2025 CBC/CRC apply.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Only if the Building Official makes a written finding, based on substantial evidence, that the system 'could have a specific, adverse impact upon the public health or safety' — otherwise no Use Permit or Council approval is required.
Why the confidence is not higherSBMC §9.60.050.060.F.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q28 Is there a system-size cap on residential generation? Overlays & special cases
No absolute residential cap. The AB 2188-era 10 kW AC / 30 kW thermal figure only gates eligibility for the streamlined 'small residential rooftop solar energy system' administrative-approval pathway (also limited to single- or duplex-family dwellings, and to the max legal building height). The city's own fee schedule shows tiered residential fees running well past 15 kW with no stated ceiling, so larger single-family systems are permitted, just outside the expedited track.
Why the confidence is not higherSBMC §9.60.050.030 (definition) cross-checked against the Cost Recovery Schedule's uncapped tiered residential PV fee table.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 (adopted as part of the 2025 California Electrical Code, effective under the 2025 Title 24 cycle) 88% · ordinance
- Which building code edition is in force? 2025 California Building Code (and 2025 California Residential Code for detached 1-2 family dwellings and townhomes ≤3 stories) 92% · ordinance
- Which fire code edition is in force? 2025 California Fire Code, as amended by the State Fire Marshal and OCFA 90% · ordinance
- Are there local amendments to any of the above? Yes 90% · ordinance
- What is the installation judged against? The 2025 California Building/Residential/Electrical/Fire Codes as locally amended by SBMC Ch. 9.60, with PV-specific electrical work additionally judged against CEC Sections 690 and 705 per the city's own solar handout. 88% · ordinance
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
Nothing recorded for City of Seal Beach on this step yet — 1 question checked and found unpublished. The guidance above is general.
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes, rapid shutdown is required under the 2023 NEC/2025 CEC §690.12, applied unamended — no local text on 690.12 was found in SBMC Ch. 9.60 (searched with the same passing controls used for Q34/36), consistent with the city simply adopting the state code's rapid-shutdown mandate without local elaboration. 75% · ordinance
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? Functionally described, not itself the wording: a sign at the DC disconnect identifying 'PV power source system attributes', a sign identifying the AC point of connection, and a sign identifying the 'switch for alternative power system' — matching CEC 690/705 labeling, which the handout cites directly. 75% · published checklist
- Does the authority specify placard wording of its own? No 70% · published checklist
- Is a site plan / facility map placard required, and what must it show? Not locally elaborated — the handout cites 'Labeling of equipment as required by CEC, Sections 690 and 705' generally, which includes the CEC 705.10 rapid-shutdown map/label, but no city-specific facility-map placard format is described. 60% · published checklist
- Where must the labels be placed? At the main service/utility disconnect, the DC (PV) disconnect, and the AC point of connection to the electrical system — the locations the handout requires the electrical plan to show and the inspector to verify. 70% · published checklist
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Must equipment be on a specific approved list? No closed 'approved product list' — equipment must be submitted with cut sheets (inverters, modules, disconnects, combiners) and meet CEC/UL/IEEE standards per SBMC §9.60.050.040(C), but there is no city-maintained pre-approved equipment list referenced anywhere. 65% · published checklist
- Are batteries permitted, and under what conditions? Batteries/ESS are permitted under the unamended 2025 CRC/CFC energy-storage provisions (no local ESS-specific ordinance was found in SBMC Ch. 9.60), and OCFA plan review/inspection is required for all battery/stationary-storage systems (fee code PR375) regardless of size. 70% · fee schedule
- Is there a separate ESS permit or inspection? Yes, at the fire-authority level — OCFA's own fee schedule carries a dedicated 'Battery Systems, stationary storage and cell sites' plan review ($963, FY2025-26 adopted / $965 FY2026-27 proposed effective 1 Sep 2026) plus a $233 inspection fee (code PR375), separate from the PV line (PR362). The city's own Building Fees schedule has no distinct ESS line — batteries are folded into the standard electrical/building valuation fee on the city side. 75% · fee schedule
- Is a ground mount treated as a structure? Likely yes, by inference — ground- and wall-mounted collectors must be 'screened from public view' per SBMC §11.4.10.045.A.2, and the zoning code's general site-development-standards table treats solar under the same row structure as other 'Accessory Structures,' but no PV-specific ground-mount setback/height table or explicit 'is a structure' statement was found in Title 11. 58% · ordinance
20 questions answered against City of Seal Beach’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023 (adopted as part of the 2025 California Electrical Code, effective under the 2025 Title 24 cycle)
Why the confidence is not higherSBMC §9.60.020 adopts the '2025 California Electrical Code' by reference; the 2025 CEC is statewide based on the 2023 NEC (there is no separate '2025 NEC').
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code (and 2025 California Residential Code for detached 1-2 family dwellings and townhomes ≤3 stories)
Why the confidence is not higherSBMC §9.60.020/§9.60.010, Sections 101.4.1-101.4.2.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q31 Which fire code edition is in force? Code editions in force
2025 California Fire Code, as amended by the State Fire Marshal and OCFA
Why the confidence is not higherSBMC §9.60.010, Section 101.4.7 adopts 'the mandatory provisions of the California Fire Code as adopted and amended by City of Seal Beach'; §9.60.020's Fire Code amendments repeatedly cite '2025' editions and reference OCFA guidelines by number.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes
Why the confidence is not higherSBMC §9.60.020 contains substantial local amendments across all adopted codes (stamp thresholds, permit-expiration rules, Fire Code Section 202 OCFA definition, etc.).
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q33 What is the installation judged against? Core Electrical
The 2025 California Building/Residential/Electrical/Fire Codes as locally amended by SBMC Ch. 9.60, with PV-specific electrical work additionally judged against CEC Sections 690 and 705 per the city's own solar handout.
Why the confidence is not higherSBMC §9.60.010/.020 plus Solar PV handout Section 2(c).
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
Nothing published by this authority.
Where we lookedSBMC §9.60.020 (local CBC/CEC amendments) — searched full text (39 'electrical' positive-control hits, 0 fabricated-control hits) for 'busbar', '225', '200 amp', 'service upgrade'; no local rule found.
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedSolar PV handout Section 2(e) (structural support requirements) and SBMC Ch. 9.60 — the handout requires generic racking documentation ('attachment method,' 'maximum allowable weight') but no numeric spacing/attachment-interval standard is published.
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Nothing published by this authority.
Where we lookedSBMC §9.60.020 Fire Code amendments — searched full extracted text for 'ridge' and found no PV-specific ridge-setback or access-pathway rule (control-checked: 'electrical' appears 8 times in the same amendment block, 'zzqqx' zero times); technical ridge/pathway requirements appear to come from the unamended 2025 CFC §1205 series.
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes, rapid shutdown is required under the 2023 NEC/2025 CEC §690.12, applied unamended — no local text on 690.12 was found in SBMC Ch. 9.60 (searched with the same passing controls used for Q34/36), consistent with the city simply adopting the state code's rapid-shutdown mandate without local elaboration.
Why the confidence is not higherInference from adoption of the unamended 2025 CEC plus a control-checked absence of local 690.12 text.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Functionally described, not itself the wording: a sign at the DC disconnect identifying 'PV power source system attributes', a sign identifying the AC point of connection, and a sign identifying the 'switch for alternative power system' — matching CEC 690/705 labeling, which the handout cites directly.
Why the confidence is not higherSolar PV handout, Section 4 inspection checklist.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
No
Why the confidence is not higherThe handout only describes what each required sign must identify (functionally, per CEC 690/705); it does not give the city's own custom wording, unlike e.g. Hollister's or Manhattan Beach's handouts.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSolar PV handout Section 4 and SBMC Ch. 9.60 — no letter-height, colour, or material spec for placards is published anywhere found; the handout only requires signs to be 'properly constructed, installed, and displayed.'
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Not locally elaborated — the handout cites 'Labeling of equipment as required by CEC, Sections 690 and 705' generally, which includes the CEC 705.10 rapid-shutdown map/label, but no city-specific facility-map placard format is described.
Why the confidence is not higherSolar PV handout Section 2(c).
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSCE's own DG/interconnection and Rule 21 pages — sce.com's solar/DG landing pages returned soft-404/generic content on this run, consistent with other GovBot runs; per standing guidance this is booked not_found rather than borrowed from another utility's documents.
https://www.sce.com/business/generating-your-own-power/interconnections
Q43 Where must the labels be placed? Core Labels Signage & labelling
At the main service/utility disconnect, the DC (PV) disconnect, and the AC point of connection to the electrical system — the locations the handout requires the electrical plan to show and the inspector to verify.
Why the confidence is not higherSolar PV handout Sections 2(c) and 4.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q44 Must equipment be on a specific approved list? Equipment listing
No closed 'approved product list' — equipment must be submitted with cut sheets (inverters, modules, disconnects, combiners) and meet CEC/UL/IEEE standards per SBMC §9.60.050.040(C), but there is no city-maintained pre-approved equipment list referenced anywhere.
Why the confidence is not higherSolar PV handout Section 2(c) equipment cut-sheet requirement, plus SBMC §9.60.050.040(C).
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Batteries/ESS are permitted under the unamended 2025 CRC/CFC energy-storage provisions (no local ESS-specific ordinance was found in SBMC Ch. 9.60), and OCFA plan review/inspection is required for all battery/stationary-storage systems (fee code PR375) regardless of size.
Why the confidence is not higherControl-checked absence of local 'battery'/'energy storage' text in SBMC Ch. 9.60, cross-checked against OCFA's own current fee schedule.
fee schedule checked 2026-08-31 https://storageocfaprod001.blob.core.windows.net/blobocfaprod01/2026/06/OCFA-Proposed-Fee-Schedule-Prevention-Field-Services.pdf
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Yes, at the fire-authority level — OCFA's own fee schedule carries a dedicated 'Battery Systems, stationary storage and cell sites' plan review ($963, FY2025-26 adopted / $965 FY2026-27 proposed effective 1 Sep 2026) plus a $233 inspection fee (code PR375), separate from the PV line (PR362). The city's own Building Fees schedule has no distinct ESS line — batteries are folded into the standard electrical/building valuation fee on the city side.
Why the confidence is not higherOCFA Proposed Fee Schedule - Prevention Field Services (2026-27), PR375/PR375i lines, cross-checked against the city's Cost Recovery Schedule which has no battery/ESS line (searched and confirmed absent).
fee schedule checked 2026-08-31 https://storageocfaprod001.blob.core.windows.net/blobocfaprod01/2026/06/OCFA-Proposed-Fee-Schedule-Prevention-Field-Services.pdf
Q47 Is a ground mount treated as a structure? Core Ground mount
Likely yes, by inference — ground- and wall-mounted collectors must be 'screened from public view' per SBMC §11.4.10.045.A.2, and the zoning code's general site-development-standards table treats solar under the same row structure as other 'Accessory Structures,' but no PV-specific ground-mount setback/height table or explicit 'is a structure' statement was found in Title 11.
Why the confidence is not higherSBMC §11.4.10.045 (Solar Energy Systems) and the Title 11 development-standards table; inference flagged as inference.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Nothing published by this authority.
Where we lookedSCE's own DG/interconnection pages — no reachable SCE document specifying AC-disconnect location relative to the meter for Seal Beach; per standing guidance, not substituted with another utility's spec.
https://www.sce.com/business/generating-your-own-power/interconnections
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Portal 90% · department page
- How much notice is required? Approximately 2 business days 85% · department page
- Are same-day or AM/PM windows offered? A requested timeframe (not a guaranteed slot) is chosen via a dropdown when booking; the day's inspection schedule/timeframes are posted on the city website the evening before the requested date. 75% · department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes 85% · ordinance
- If delegated, to whom? Not delegated away for standard building/electrical — self-performed by the city's Building Official, jointly with the OCFA Fire Chief only where a consolidated inspection is used for expedited small residential rooftop solar. 80% · ordinance
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? For an eligible 'small residential rooftop solar energy system' (≤10 kW AC/30 kW thermal, single/duplex dwelling): only one inspection, at completion, potentially consolidated between Building and Fire. The general Solar PV handout describes this as a single final inspection checking modules, grounding, conductors, attachment, and signage. Larger/non-expedited systems are not separately documented and likely follow the standard CBC electrical rough-in + final sequence. 72% · ordinance
- Is a rough-in or mid-roof inspection required? No — for systems eligible for the expedited path, SBMC §9.60.050.060.B states 'only one inspection shall be required,' i.e., no separate rough-in/mid-roof inspection. 80% · ordinance
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? Yes 88% · published checklist
- What must be on site at inspection? Approved plans and equipment specification/cut sheets matching what's installed — the handout requires the number and model of PV modules and specification sheets to 'match plans' at inspection, implying both must be available on site. 70% · published checklist
- Does the inspector verify labels and listings? Yes 88% · published checklist
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- What is issued on pass? Final (approved final inspection) rather than a Certificate of Occupancy — the locally amended CBC states the Building Official 'may not issue certificate of occupancies for remodels and additions to owner-occupied dwellings,' which covers a typical residential PV retrofit. 68% · ordinance
- Who notifies the utility for PTO? Installer 85% · ordinance
- Is there a re-inspection fee? $98 per re-inspection (3rd time or more); $98 missed-inspection fee. 78% · fee schedule
- How are corrections issued and cleared? A written correction notice detailing all deficiencies and any additional information required is issued to the applicant for resubmission; this is spelled out for the expedited solar pathway specifically. 78% · ordinance
14 questions answered against City of Seal Beach’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Portal
Why the confidence is not higherBuilding-Safety page: 'ALL INSPECTIONS SHALL BE SUBMITTED THROUGH THE PORTAL' (the Civic Access Portal); phone is available for general inquiries only.
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety
Q50 How much notice is required? Core Booking & scheduling
Approximately 2 business days
Why the confidence is not higherBuilding-Safety page: 'Inspection requests are responded to at the end of the day, and typically executed within two business days.'
department page checked 2026-08-31 https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
A requested timeframe (not a guaranteed slot) is chosen via a dropdown when booking; the day's inspection schedule/timeframes are posted on the city website the evening before the requested date.
Why the confidence is not higherCity's 'Inspection Step by Step Guide' PDF.
department page checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Users/027/27/27/Inspection%20Step%20by%20Step%20Guide.pdf?ver=2025-03-14-143225-900
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes
Why the confidence is not higherBuilding & Safety self-performs building/electrical inspections; for eligible expedited residential solar, SBMC §9.60.050.060.B allows 'a consolidated inspection by the building official and fire chief' rather than delegating away from the city.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q53 If delegated, to whom? Core Who inspects
Not delegated away for standard building/electrical — self-performed by the city's Building Official, jointly with the OCFA Fire Chief only where a consolidated inspection is used for expedited small residential rooftop solar.
Why the confidence is not higherSBMC §9.60.050.060.B.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q54 Which inspections are required, and in what order? Core Stages & sequence
For an eligible 'small residential rooftop solar energy system' (≤10 kW AC/30 kW thermal, single/duplex dwelling): only one inspection, at completion, potentially consolidated between Building and Fire. The general Solar PV handout describes this as a single final inspection checking modules, grounding, conductors, attachment, and signage. Larger/non-expedited systems are not separately documented and likely follow the standard CBC electrical rough-in + final sequence.
Why the confidence is not higherSBMC §9.60.050.060.B and Solar PV handout Section 4.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
No — for systems eligible for the expedited path, SBMC §9.60.050.060.B states 'only one inspection shall be required,' i.e., no separate rough-in/mid-roof inspection.
Why the confidence is not higherSBMC §9.60.050.060.B.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q56 Does the inspector verify labels and listings? Core What is checked
Yes
Why the confidence is not higherSolar PV handout's inspection checklist explicitly includes 'Appropriate signs are properly constructed, installed, and displayed' and equipment-rating-vs-sign cross-checks.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q57 Is there a published inspection checklist? Core What is checked
Yes
Why the confidence is not higherThe Solar PV Installation Guidelines handout's Section 4 is itself a published, itemized inspection checklist.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q58 What must be on site at inspection? Core Documents on site
Approved plans and equipment specification/cut sheets matching what's installed — the handout requires the number and model of PV modules and specification sheets to 'match plans' at inspection, implying both must be available on site.
Why the confidence is not higherSolar PV handout Section 4.
published checklist checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Solar%20Photovoltaic%20Installation%20-new.pdf?ver=2022-01-24-175625-587
Q59 Is there a re-inspection fee? Corrections & re-inspection
$98 per re-inspection (3rd time or more); $98 missed-inspection fee.
Why the confidence is not higherCost Recovery Schedule, Building Fees §G 'Re-inspection Fee (3rd Time or More)' and 'Missed Inspection Fee' — general building-fee lines, not solar-specific, but apply to all building permits including solar.
fee schedule checked 2026-08-31 https://www.sealbeachca.gov/Portals/0/Documents/Finance/Cost%20Recovery%20Schedule%20FY%202025-2026.pdf?ver=2025-10-16-094407-650
Q60 How are corrections issued and cleared? Corrections & re-inspection
A written correction notice detailing all deficiencies and any additional information required is issued to the applicant for resubmission; this is spelled out for the expedited solar pathway specifically.
Why the confidence is not higherSBMC §9.60.050.060.C and .E.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q61 What is issued on pass? Core Final sign-off & PTO
Final (approved final inspection) rather than a Certificate of Occupancy — the locally amended CBC states the Building Official 'may not issue certificate of occupancies for remodels and additions to owner-occupied dwellings,' which covers a typical residential PV retrofit.
Why the confidence is not higherSBMC §9.60.020 (CBC §110 amendment).
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Installer
Why the confidence is not higherSBMC §9.60.050.060.D: city approval 'does not authorize' grid connection — 'the applicant is responsible for obtaining such approval or permission from the local utility provider,' i.e., the installer/applicant, not the AHJ, deals with the utility for PTO.
ordinance checked 2026-08-31 https://www.ecode360.com/SE5012
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of Seal Beach against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Seal Beach is the authority having jurisdiction 85% confidence
- Holds
- Building and Electrical (self-performed by the City of Seal Beach Community Development Dept, Building & Safety Division, under one combined solar permit). Fire is delegated to the Orange County Fire Authority (OCFA), but only for battery/ESS systems and PV needing 'Alternative Compliance' — OCFA's own current fee schedule (PR362 'Photovoltaic System – Residential Alternative Compliance' $223/$175, PR375 'Battery Systems...' $963-965/$233) and its January-2026 Single-Family Plan Screening Form confirm standard residential rooftop PV is NOT an OCFA plan-review trigger. Within the Coastal Zone (all of Seal Beach), Coastal Development Permit authority is retained directly by the California Coastal Commission, NOT the city, because Seal Beach has never certified a Local Coastal Program — its own zoning code chapter 11.4.35 'Coastal Development Permit' is codified as '(RESERVED)' and the city's own LCP project page confirms the 2008 LCP was 'Not Certified' and a revised Draft Land Use Plan was still with the Coastal Commission as of the most recent posted update (May 2023).
- Delegated to
- Orange County Fire Authority (fire, ESS/Alternative-Compliance PV only); California Coastal Commission (Coastal Development Permits, citywide, due to no certified LCP)
- Overridden by
- In the Coastal Zone, CA Coastal Commission jurisdiction (Pub. Res. Code / Coastal Act) sits above the city because there is no certified LCP; however, most existing single-family rooftop PV retrofits likely still qualify for the Coastal Act's own statewide exemption for improvements to existing single-family residences (Pub. Res. Code §30610, 14 CCR §13250) unless the parcel is on the beach/wetland or within 50 ft of a bluff edge — and parts of the city's coastal zone are separately covered by a Coastal Commission 'Categorical Exclusion Area' (per the city's own Zoning Code definition citing CCC Maps 143 'Los Alamitos' and 144 'Seal Beach') where no CDP is required at all. This CDP layer is a genuine correction to the brief: the city administers building/electrical, but does NOT administer its own coastal permits.
- Why not higher
- Building/Electrical: SBMC Ch. 9.60 and the city's own Building-Safety/SolarAPP+ pages. Fire: OCFA's own member-cities page lists Seal Beach; SBMC §9.60.020 Fire Code Section 202 amendment independently defines 'OCFA: Orange County Fire Authority, authority having jurisdiction' inside the city's own code (the Stanton-style codified hook), and OCFA's own current SFR Plan Screening Form (updated 01/01/2026) has no PV/battery trigger question, matching its fee-schedule wording. Coastal: SBMC Title 11 Ch. 11.4.35 codified as RESERVED, and the city's own Local Coastal Plan (LCP) Project page states the 2008 LCP was 'Not Certified' with a 2023 draft still pending Coastal Commission review — a genuinely unusual, sourced finding since most CA coastal cities in this survey have a certified LCP.
https://www.sealbeachca.gov/Departments/Community-Development/Building-Safety
- Permit required
- Yes98%
- Permit cost
- $344 flat for systems ≤15 kW; above 15 kW, $344 base + $15 per kW above 15 kW (residential). Commercial is a separate, higher tiered schedule.92%
- Plan review
- Plan review takes approximately 3-4 weeks after plans are accepted for review; initial fee/scope confirmation after application submittal takes 1-3 business days.85%
- Portal
- Three linked systems: SolarAPP+ (NREL) for automated PV plan review; the city's Tyler/EnerGov 'Civic Access Portal' (sealbeachca-energovpub.tylerhost.net) for the building permit…88%
- Electrical code
- 2023 (adopted as part of the 2025 California Electrical Code, effective under the 2025 Title 24 cycle)88%
- Own placard wording
- No70%
- Booking an inspection
- Portal90%
Labels & placards for this authority
Wording 70%
No
Size, colour & material None%
Where they go 70%
At the main service/utility disconnect, the DC (PV) disconnect, and the AC point of connection to the electrical system — the locations the handout requires the electrical plan to show and the inspector to verify.
What the utility wants on top None%
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.