City of Woodland
Yolo County
City of Woodland is a city authority in the State of California, serving 61,032 residents. 7,566 residential solar installs are on record here. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Plan review — Not solar-specific: general residential plan review is quoted as '2 to 4 weeks' for initial plan-check activities; Q18 Where you file — SolarAPP+ (gosolarapp.org) for eligible systems; no dedicated online permitting portal for the standard track — applications and approval documents are submitted by… Q20
- Permit required
- Yes95% source
- What it costs
- $280 for residential rooftop OR ground-mount PV up to 15 kW AC, plus $10 per additional kW or fraction thereof (combined plan review & inspection fee, Building Division).80% source
- Plan review turnaround
- Not solar-specific: general residential plan review is quoted as '2 to 4 weeks' for initial plan-check activities; Fire's ESS-specific plan review has a stated 14-business-day turnaround;70% source
- Key document
- fee schedule cited by 5 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes 95% · department page
- What does this authority permit itself, and what does it delegate? Both 85% · department page
- Is a permit required for a residential rooftop PV system? Yes 95% · department page
- Is there a separate electrical permit, or is it combined? Combined 78% · fee schedule
- Is a HOA or architectural approval required first? No city-imposed HOA/architectural review requirement found for standard residential rooftop PV; where an HOA exists, California's Solar Rights Act (Civil Code §714) preempts denial and limits HOAs to narrow 'reasonable restrictions.' 60% · checklist
- Is there a historic-district review? Potentially yes within the Downtown National Register Historic District 60% · department page
- Is a wind or windstorm certification required? No 55% · ordinance / department page
- Is there a system-size cap on residential generation? No hard cap on system size found for standard permitting; the tiered fee schedule scales indefinitely ($280 base + $10/kW beyond 15 kW) rather than capping at a maximum. A stale 2015 'Conditions of Approval' / eligibility checklist limited the EXPEDITED review track to systems ≤10 kW AC without battery storage, but the current live SolarAPP+ page states no kW ceiling and explicitly supports ADUs; systems outside SolarAPP+/expedited eligibility simply route to standard (non-expedited) review rather than being capped. 70% · fee schedule
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? Either 65% · department page
- Is a homeowner permitted to self-install and self-permit? Yes 60% · checklist
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? For SolarAPP+: contractor license info plus automated review output ('SolarAPP+ approval documents') emailed to CDD-Building. For the standard track, the 2015 'Solar Checklist' (eligibility checklist for the expedited program) lists: completed permit application, a 'Solar PV Standard Plan' with supporting documentation, structural criteria documentation (if required), and a roof-layout diagram showing panel/module locations, clear access pathways, and approximate disconnect/roof-access locations. 82% · checklist
- How many copies, and in what format? Digital PDF submittal by email; no paper-copy count specified 65% · department page
- Is a site plan required, and what must it show? Yes — a roof-layout/site diagram showing all panels/modules, clear access pathways, and approximate locations of electrical disconnecting means and roof access points 82% · checklist
- Is a one-line / three-line diagram required? Yes 75% · checklist / guideline
- Are string and conductor calculations required? Yes (implied) 55% · checklist
- Is an electrical PE stamp required, and at what threshold? No PE electrical stamp requirement found for standard residential PV 50% · department page
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? SolarAPP+ (gosolarapp.org) for eligible systems; no dedicated online permitting portal for the standard track — applications and approval documents are submitted by email to cdd-building@cityofwoodland.gov. services.cityofwoodland.gov is a separate Tyler-based utility-BILLING portal only (no permitting module). 82% · portal landing page
- Can the whole application be completed online? Yes, for SolarAPP+-eligible systems (apply, submit contractor license info, pay, and download approval documents entirely at gosolarapp.org, then email the approval to the city for a permit number). No for the standard track — that pathway's own page section is marked '[Under construction]' as of this check. 80% · portal
- What does a residential solar permit cost? $280 for residential rooftop OR ground-mount PV up to 15 kW AC, plus $10 per additional kW or fraction thereof (combined plan review & inspection fee, Building Division). Separately, Woodland Fire Dept bills $394 for Residential Solar (Ground) only (no dedicated fire fee line for residential rooftop PV) and $664 for Residential ESS. 80% · fee schedule
- How is the fee calculated? Per kW (tiered) 90% · fee schedule
- Is there a separate plan-check fee? No 75% · fee schedule
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? Not solar-specific: general residential plan review is quoted as '2 to 4 weeks' for initial plan-check activities; Fire's ESS-specific plan review has a stated 14-business-day turnaround; SolarAPP+ eligible submittals get automated (same-day) review. 70% · department page
- How long is an issued permit valid before it expires? 365 days (12 months) from issuance, with one allowed 180-day extension if requested before expiration 95% · department page
- Which utility handles interconnection here? PG&E (Pacific Gas & Electric) 90% · utility's own page
- Where does the utility sit in the sequence? After permit (for Permission to Operate) 82% · utility DG manual / tariff
28 questions answered against City of Woodland’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes
Why the confidence is not higherCity's own Community Development Building Division page and dedicated Residential Solar page identify Woodland as the permitting authority for residential PV; confirmed distinct from Yolo County, which is AHJ only for unincorporated territory.
department page checked 2026-08-30 https://www.cityofwoodland.gov/259/Building-Division
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both
Why the confidence is not higherBuilding Division (Community Development Dept) issues building/electrical/mechanical/plumbing permits itself; Woodland Fire Department (its own department, not contracted/JPA) reviews and inspects ESS/solar-adjacent fire items and its final gates the building final. Not delegated to Yolo County.
department page checked 2026-08-30 https://www.cityofwoodland.gov/259/Building-Division
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherResidential Solar page and SolarAPP+ page both describe a required permit process; fee schedule carries a dedicated Solar Energy Permit Fees table.
department page checked 2026-08-30 https://www.cityofwoodland.gov/303/Residential-Solar
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Combined
Why the confidence is not higherFee schedule's Solar Energy Permit Fees table lists one 'Residential Plan Review & Inspection Fee' (not split building vs electrical), and the SolarAPP+ page shows a single BLDG-prefixed permit number example (BLDG-14-00001) used for solar. No separate electrical-only permit fee line found for PV.
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q5 Who is allowed to pull the electrical permit? Core Who may apply
Either
Why the confidence is not higherSolarAPP+ pathway explicitly requires 'Licensed contractors only.' The standard (non-SolarAPP+) pathway has no solar-specific exclusion of owner-builders; the city publishes a generic 'Application for Building Permit - Owner Builder' form used for all building permit types including alterations, and no Woodland document was found excluding solar from owner-builder eligibility outside the SolarAPP+ track.
department page checked 2026-08-30 https://www.cityofwoodland.gov/1615/SolarAPP
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Nothing published by this authority.
Where we lookedChecked the city's Business License page (cityofwoodland.gov/406/Business-License) for a stated requirement that a contractor register/obtain a city business license before a building permit is issued; the page describes how to apply for a business license but does not state permit-issuance is contingent on it, and no solar- or contractor-specific registration requirement was found.
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes
Why the confidence is not higherNo Woodland document excludes owner-builder self-permitting for residential solar on the standard (non-SolarAPP+) track; the city publishes standard CSLB owner-builder disclosure/consent forms used for all permit types. SolarAPP+ itself is licensed-contractor-only, so self-install/self-permit would have to go through the standard track.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/534/Owner-Builder-Take-Note-PDF
Q8 What documents make up a complete submittal? Core Submittal package
For SolarAPP+: contractor license info plus automated review output ('SolarAPP+ approval documents') emailed to CDD-Building. For the standard track, the 2015 'Solar Checklist' (eligibility checklist for the expedited program) lists: completed permit application, a 'Solar PV Standard Plan' with supporting documentation, structural criteria documentation (if required), and a roof-layout diagram showing panel/module locations, clear access pathways, and approximate disconnect/roof-access locations.
Why the confidence is not higherThe Solar Checklist PDF is dated 2015 (CreationDate confirmed via pdfinfo) and is explicitly framed as the EXPEDITED-permit eligibility checklist; the live 'Apply for solar without SolarAPP+' section of the current SolarAPP+ page is marked '[Under construction]', so a current general submittal checklist for the standard track is not published as of this check.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q9 How many copies, and in what format? Submittal package
Digital PDF submittal by email; no paper-copy count specified
Why the confidence is not higherGeneral residential permit page states 'All documents must be submitted digitally as PDFs' to cdd-building@cityofwoodland.gov, and SolarAPP+ instructions likewise call for emailing approval-document PDFs. No copy-count requirement found (consistent with digital-only submittal).
department page checked 2026-08-30 https://www.cityofwoodland.gov/342/Residential
Q10 Is a site plan required, and what must it show? Core Submittal package
Yes — a roof-layout/site diagram showing all panels/modules, clear access pathways, and approximate locations of electrical disconnecting means and roof access points
Why the confidence is not higherExplicit item D under FIRE SAFETY REQUIREMENTS on the Solar Checklist; CRR-002 (ESS Guideline, current, rev. 10/2025) separately requires a detailed site plan showing ESS unit location(s) and equipment for battery installations.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Yes
Why the confidence is not higherCRR-002 (Residential ESS Guideline, current) requires the emergency disconnect location to 'be shown on all plan submittals, including one-line diagrams and site plans.' The 2015 Solar Checklist's 'Solar PV Standard Plan' requirement is the pre-SolarAPP+-era equivalent for PV-only systems.
checklist / guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q12 Are string and conductor calculations required? Drawings & calculations
Yes (implied)
Why the confidence is not higherThe Solar Checklist's electrical-requirements section enumerates MPPT/string-count and fuse-rating limits as pass/fail eligibility items and requires a 'Solar PV Standard Plan and supporting documentation,' which functions as string/conductor compliance documentation, but the checklist does not use the phrase 'string and conductor calculations' verbatim.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Nothing published by this authority.
Where we lookedChecked the Structural Design page (general seismic/wind/soil design-criteria page, no PE-stamp threshold stated) and the Special Inspection Information and Form PDF (doc 544) for any PV-specific structural PE-stamp trigger; neither document mentions solar/photovoltaic or gives a threshold.
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
No PE electrical stamp requirement found for standard residential PV
Why the confidence is not higherSolarAPP+ and the Solar Checklist eligibility framework (aimed at 1-2 family dwellings, standard string inverter systems) do not call for an electrical PE stamp; no Woodland document requires one for residential-scale systems. Not stated as an explicit rule, so treated as inference from absence.
department page checked 2026-08-30 https://www.cityofwoodland.gov/1615/SolarAPP
Q15 What does a residential solar permit cost? Core Fees
$280 for residential rooftop OR ground-mount PV up to 15 kW AC, plus $10 per additional kW or fraction thereof (combined plan review & inspection fee, Building Division). Separately, Woodland Fire Dept bills $394 for Residential Solar (Ground) only (no dedicated fire fee line for residential rooftop PV) and $664 for Residential ESS.
Why the confidence is not higherFee Schedule PDF, 77 pages. The SOLAR ENERGY PERMIT FEES table itself is stamped 'Effective Date August 8, 2016' even though the overall PDF was regenerated 30 Jun 2026 (pdfinfo CreationDate) — the $ amounts may be stale relative to the rest of the 2026 schedule. Fire's SOLAR & ESS table is explicitly dated 'Effective 7/1/2026' and is current.
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q16 How is the fee calculated? Core Fees
Per kW (tiered)
Why the confidence is not higherFee table: '$280 for 15 kW or less' then '$10 each additional kW or fraction of kW' — a flat base plus per-kW tier, not a valuation-based calculation.
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q17 Is there a separate plan-check fee? Fees
No
Why the confidence is not higherThe Solar Energy Permit Fees table combines 'Plan Review & Inspection Fee' into a single line item per tier; no separate plan-check line for solar is listed elsewhere in the 77-page fee schedule (checked via full-text search of extracted PDF).
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Not solar-specific: general residential plan review is quoted as '2 to 4 weeks' for initial plan-check activities; Fire's ESS-specific plan review has a stated 14-business-day turnaround; SolarAPP+ eligible submittals get automated (same-day) review.
Why the confidence is not higherGeneral timeline is from the Residential permitting page (not solar-specific); ESS timeline from CRR-008 (Fire, current).
department page checked 2026-08-30 https://www.cityofwoodland.gov/342/Residential
Q19 How long is an issued permit valid before it expires? Timeline & validity
365 days (12 months) from issuance, with one allowed 180-day extension if requested before expiration
Why the confidence is not higherExtensions/Expirations page: 'A building permit is valid for 12 months from the date of issuance...you may request a one-time extension of an additional 180 days.'
department page checked 2026-08-30 https://www.cityofwoodland.gov/341/Extensions-Expirations
Q20 Which permit portal does this authority use? Core Portal & process
SolarAPP+ (gosolarapp.org) for eligible systems; no dedicated online permitting portal for the standard track — applications and approval documents are submitted by email to cdd-building@cityofwoodland.gov. services.cityofwoodland.gov is a separate Tyler-based utility-BILLING portal only (no permitting module).
Why the confidence is not higherSolarAPP+ page names gosolarapp.org and the CDD-Building email route; confirmed services.cityofwoodland.gov (checked directly) is billing/HR/business-services only, with no permit content.
portal landing page checked 2026-08-30 https://www.cityofwoodland.gov/1615/SolarAPP
Q21 Can the whole application be completed online? Core Portal & process
Yes, for SolarAPP+-eligible systems (apply, submit contractor license info, pay, and download approval documents entirely at gosolarapp.org, then email the approval to the city for a permit number). No for the standard track — that pathway's own page section is marked '[Under construction]' as of this check.
Why the confidence is not higherSolarAPP+ page, Step 2 and 'Apply for solar without SolarAPP+' section.
portal checked 2026-08-30 https://www.cityofwoodland.gov/1615/SolarAPP
Q22 Which utility handles interconnection here? Core Utility interconnection
PG&E (Pacific Gas & Electric)
Why the confidence is not higherWoodland's Public Works 'Electrical' page covers only municipal streetlights/traffic signals/pump stations — the city runs no electric utility of its own. Valley Clean Energy (the Yolo County CCA that includes Woodland) states on its own About page: 'VCE buys cleaner electricity, and PG&E delivers it, maintains the lines and provides billing and maintenance services, just as they always have' — confirming PG&E remains the wires-owning/interconnecting utility; VCE is the generation-only CCA layered on top and is not part of the interconnection chain.
utility's own page checked 2026-08-30 https://valleycleanenergy.org/about/
Q23 Where does the utility sit in the sequence? Core Utility interconnection
After permit (for Permission to Operate)
Why the confidence is not higherPG&E Electric Rule No. 21 (Sheet 45, Section D.13.b, Advice Ltr 7692-E, effective 8/29/2025) requires, before PTO for NEM Generating Facilities ≤1MW, 'evidence of Applicant's final electric inspection clearance from the Governmental Authority having jurisdiction' — i.e., the AHJ's final inspection must be complete before PG&E issues Permission to Operate, though the interconnection application itself may be filed in parallel with permitting.
utility DG manual / tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Q24 Is a HOA or architectural approval required first? Overlays & special cases
No city-imposed HOA/architectural review requirement found for standard residential rooftop PV; where an HOA exists, California's Solar Rights Act (Civil Code §714) preempts denial and limits HOAs to narrow 'reasonable restrictions.'
Why the confidence is not higherNot listed as a submittal item on the Solar Checklist or SolarAPP+ eligibility page; conclusion partly rests on statewide law rather than a Woodland-specific document.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q25 Is there a historic-district review? Overlays & special cases
Potentially yes within the Downtown National Register Historic District
Why the confidence is not higherCity's Historic Preservation page confirms Woodland has adopted a Historic Landmarks, Districts and Resources Ordinance (Title 15) and that Downtown Woodland is a National Register Historic District overseen by the Planning Commission; no solar-specific carve-out or exterior-alteration review procedure for PV was found on that page, and most single-family residential parcels are outside the downtown district.
department page checked 2026-08-30 https://www.cityofwoodland.gov/673/Historic-Preservation
Q26 Is a wind or windstorm certification required? Overlays & special cases
No
Why the confidence is not higherNo wind/windstorm certification requirement was found in Woodland's structural design page or solar checklist; California's design basis is seismic/wind-load per the adopted CBC/CRC rather than a separate windstorm certification regime (unlike coastal/hurricane states).
ordinance / department page checked 2026-08-30 https://www.cityofwoodland.gov/306/Structural-Design
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Nothing published by this authority.
Where we lookedChecked the Solar Checklist, SolarAPP+ page, and Residential Solar page for any statement that a Specific Use Permit, variance, or Council approval is ever triggered (e.g., by ground-mount size, setback exception, or historic-district location); none of these documents mention a discretionary/Council-level approval path for residential PV.
Q28 Is there a system-size cap on residential generation? Overlays & special cases
No hard cap on system size found for standard permitting; the tiered fee schedule scales indefinitely ($280 base + $10/kW beyond 15 kW) rather than capping at a maximum. A stale 2015 'Conditions of Approval' / eligibility checklist limited the EXPEDITED review track to systems ≤10 kW AC without battery storage, but the current live SolarAPP+ page states no kW ceiling and explicitly supports ADUs; systems outside SolarAPP+/expedited eligibility simply route to standard (non-expedited) review rather than being capped.
Why the confidence is not higherFee schedule shows uncapped per-kW tiering; SolarAPP+ live page has no stated kW limit; 2015 Solar Checklist and 2015 Conditions-of-Approval PDF (pdfinfo-confirmed dates) show the old 10kW/no-battery ceiling applied only to the expedited track, not to permitting generally.
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2023 NEC (adopted as the 2025 California Electrical Code) 90% · department FAQ
- Which building code edition is in force? 2025 California Building Code (CBC) and 2025 California Residential Code (CRC) 92% · department page
- Which fire code edition is in force? Uncertain — likely still the 2022 California Fire Code as locally amended, not yet confirmed updated to 2025 55% · ordinance
- Are there local amendments to any of the above? Yes 95% · ordinance
- What is the installation judged against? The 2025 CBC/CRC/CEC/CMC/CPC as amended locally by Woodland (Title 15 and Title 8.20 of the Municipal Code), plus Woodland Fire Department guideline CRR-002 for any ESS component 75% · ordinance
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? Clear roof access pathways are required (Solar Checklist item A under Fire Safety Requirements: 'Clear access pathways provided'), consistent with the statewide adopted Fire Code's residential rooftop PV pathway/ridge-setback provisions; Woodland's own checklist does not restate the numeric pathway widths or ridge-setback distances itself. 62% · checklist
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes, rapid shutdown is required per NEC 690.12 as adopted in the 2025 CEC 75% · adopting ordinance / inference
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? For ESS: DC conduit/raceway/enclosure/junction-box labels (every 10 ft, at turns, above/below penetrations), an emergency-disconnect label with distance markings, an operations/maintenance-contact label, and NFPA-855/UL-9540/UL-1741 equipment labels. For PV-only systems, only the generic Solar Checklist item 'All required markings and labels are provided' was found — no separate itemized PV-only placard list beyond what NEC 690/705 already requires. 78% · guideline / checklist
- Does the authority specify placard wording of its own? No custom wording found — CRR-002 governs label durability, permanence and legibility ('Labels shall be permanently affixed...and shall not be hand written') and cross-references NEC 2022 Art. 110.21(B), but does not prescribe its own custom placard text. 60% · guideline
- Does it specify letter height, colour or material? For ESS warning labels exposed to sunlight/outdoors: 'Engraved or Etched Plastic Placards with Red Background and White Lettering.' No separate letter-height/colour/material spec was found for PV-only (non-ESS) labels beyond code-default NEC durability language. 80% · guideline
- Is a site plan / facility map placard required, and what must it show? Yes — Woodland requires a 'residential image directory placard' that must show the location of any Energy Storage System installed on or in the residence (per CRR-002). The base document establishing the general (non-ESS) content/format requirements of this placard was not separately located. 62% · guideline
- Where must the labels be placed? For ESS: emergency disconnect 10-15 ft from the battery, mounted at 5 ft on center above grade, in a clear path of travel not requiring passage through the ESS area; DC labels every 10 ft/at turns/above-below penetrations/at combiner-junction boxes. For general PV, no Woodland-specific placement rule beyond standard NEC 690/705 disconnect and rapid-shutdown label locations was found. 75% · guideline
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Must equipment be on a specific approved list? Yes (implied via listing requirements) 68% · guideline
- Are batteries permitted, and under what conditions? Yes, extensively regulated. Per CRR-002 (current, rev. 10/2025): individual ESS units capped at 20 kWh; aggregate ratings capped at 40 kWh (utility closets/storage), 80 kWh (attached/detached garages, accessory structures, exterior walls, or outdoors on the ground); must be UL 9540 listed, inverters UL 1741 listed; 3 ft minimum separation between units and from doors/windows (or UL 9540A testing to reduce it); prohibited in sleeping rooms/closets/habitable spaces (CFC 1207.11.3); vehicle impact protection required per CFC Fig. 1207.11.7.1 unless garage clear height ≤7'6" and unit mounted ≥36in above floor; smoke/heat alarm requirements for unconditioned/unfinished install spaces; garage interior installs need 5/8in Type X gypsum and a self-closing solid-core door; not permitted to emit toxic gases in R-3; ESS emitting hydrogen/flammable gases need mechanical ventilation. 92% · guideline
- Is there a separate ESS permit or inspection? Yes 92% · guideline
- Is a ground mount treated as a structure? Likely yes (treated with added structural scrutiny) 70% · fee schedule
- Is there a local rule on service upgrades or busbar sizing? No unique local busbar/service-upgrade rule beyond the standard NEC 705.12 provisions 62% · conditions of approval (dated 2015)
20 questions answered against City of Woodland’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2023 NEC (adopted as the 2025 California Electrical Code)
Why the confidence is not higherCity FAQ #106 ('What codes are currently adopted in City of Woodland?'): 'The City of Woodland uses the following codes: 2025 California Building Code (CBC)...2025 California Electrical Code (CEC)...' The 2025 CEC statewide is based on NFPA 70 2023 NEC with California amendments (Title 24 Part 3).
department FAQ checked 2026-08-30 https://www.cityofwoodland.gov/Faq.aspx?QID=106
Q30 Which building code edition is in force? Core Code editions in force
2025 California Building Code (CBC) and 2025 California Residential Code (CRC)
Why the confidence is not higherSame FAQ #106, confirmed independently on the live 'Permits & Plan Checking' page's own 'Building Codes' list, which mirrors the FAQ verbatim.
department page checked 2026-08-30 https://www.cityofwoodland.gov/328/Permits-Plan-Checking
Q31 Which fire code edition is in force? Code editions in force
Uncertain — likely still the 2022 California Fire Code as locally amended, not yet confirmed updated to 2025
Why the confidence is not higherFAQ #106's 'codes currently adopted' list (CBC/CPC/CMC/CEC/CRC/CGBC/CEBC) conspicuously omits the Fire Code entirely. The only fire-code-adoption document found, Urgency Ordinance No. 1741 (effective 9/16/2025), amends 'the 2022 Edition of the California Fire Code' — issued shortly before the statewide 2025 Title 24 cycle took effect 1 Jan 2026. No subsequent Woodland ordinance formally adopting the 2025 CFC was located as of this check; this may be a genuine lag or simply an unpublicized adoption-by-reference.
ordinance checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/13389
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes
Why the confidence is not higherFAQ #106 states plainly: 'these model codes are amended by the State of California and the City of Woodland to include various additional requirements.' Urgency Ordinance No. 1741 (eff. 9/16/2025) itemizes ~22 specific local amendments to Fire Code §8.20.040 and one to Building Code §15.04.030(H), including two (M, N) specifically addressing residential ESS disconnect location and fire detection.
ordinance checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/13389
Q33 What is the installation judged against? Core Electrical
The 2025 CBC/CRC/CEC/CMC/CPC as amended locally by Woodland (Title 15 and Title 8.20 of the Municipal Code), plus Woodland Fire Department guideline CRR-002 for any ESS component
Why the confidence is not higherCombination of FAQ #106 code list and CRR-002's own 'References' section (though CRR-002 itself, revised 10/2025, still cites the 2022-cycle codes — a possible internal staleness worth flagging).
ordinance checked 2026-08-30 https://www.cityofwoodland.gov/Faq.aspx?QID=106
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
No unique local busbar/service-upgrade rule beyond the standard NEC 705.12 provisions
Why the confidence is not higherThe city's 2015 'Conditions of Approval for Expedited Permit' PDF reiterates the standard 120%/100% busbar sum rule per NEC 705.12(D)(1)/(D)(7) and requires a Residential Service Load Calculation Worksheet if the main breaker is down-rated — this restates the national code rather than adding an independent local threshold. Document is dated 2015 and references the 2013 CEC, so may not reflect current code section numbers.
conditions of approval (dated 2015) checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/540/Conditions-of-Approval-for-Expedited-Permits---SFD-Solar-System-_10Kw-PDF
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedChecked the Solar Checklist (structural section: only 'A completed Structural Criteria and supporting documentation is attached (if required)') and the Structural Design page for a specific mounting-system or attachment-spacing standard; neither names a specific product, spacing figure, or attachment standard.
https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Clear roof access pathways are required (Solar Checklist item A under Fire Safety Requirements: 'Clear access pathways provided'), consistent with the statewide adopted Fire Code's residential rooftop PV pathway/ridge-setback provisions; Woodland's own checklist does not restate the numeric pathway widths or ridge-setback distances itself.
Why the confidence is not higherSolar Checklist PDF fire-safety section; no Woodland-specific numeric variance from the statewide CFC pathway rule was found.
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes, rapid shutdown is required per NEC 690.12 as adopted in the 2025 CEC
Why the confidence is not higherInferred from the adopted 2025 CEC (FAQ #106); no Woodland-specific exception or modification to NEC 690.12 rapid-shutdown requirements was found in any document reviewed.
adopting ordinance / inference checked 2026-08-30 https://www.cityofwoodland.gov/Faq.aspx?QID=106
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
For ESS: DC conduit/raceway/enclosure/junction-box labels (every 10 ft, at turns, above/below penetrations), an emergency-disconnect label with distance markings, an operations/maintenance-contact label, and NFPA-855/UL-9540/UL-1741 equipment labels. For PV-only systems, only the generic Solar Checklist item 'All required markings and labels are provided' was found — no separate itemized PV-only placard list beyond what NEC 690/705 already requires.
Why the confidence is not higherCRR-002 (Residential ESS Guideline, current, rev. 10/2025) 'Plan Review Information' section; 2015 Solar Checklist for the PV-only item.
guideline / checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
No custom wording found — CRR-002 governs label durability, permanence and legibility ('Labels shall be permanently affixed...and shall not be hand written') and cross-references NEC 2022 Art. 110.21(B), but does not prescribe its own custom placard text.
Why the confidence is not higherCRR-002 label-requirements section.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
For ESS warning labels exposed to sunlight/outdoors: 'Engraved or Etched Plastic Placards with Red Background and White Lettering.' No separate letter-height/colour/material spec was found for PV-only (non-ESS) labels beyond code-default NEC durability language.
Why the confidence is not higherCRR-002, Plan Review Information section, verbatim.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Yes — Woodland requires a 'residential image directory placard' that must show the location of any Energy Storage System installed on or in the residence (per CRR-002). The base document establishing the general (non-ESS) content/format requirements of this placard was not separately located.
Why the confidence is not higherCRR-002 states: 'The residential image directory placard shall include the location of Energy Storage Systems (ESS) installed on or in the residence' — confirming the placard's existence and this added ESS content requirement, but I could not find the underlying document that fully specifies the placard for PV-only installations (checked CRR-001, all TP-series guidelines, and the Fire Department's Guidelines & Technical Policies page — none define it further).
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSearched the full extracted text of PG&E Electric Rule No. 21 (26MB tariff PDF, ~16,600 lines after pdftotext) for utility-specified meter/placard wording (terms: 'dual power', 'warning label', 'marking'); no hits, while a positive control ('interconnection', 1,668 hits) and fabricated control ('zzqqx', 0 hits) confirmed the search itself was valid. The PG&E 'Greenbook' (TD-7001M), which is the more likely source for meter-panel placard specs, is unreachable — its landing page (pge.com/greenbook and the DG-focused interconnections page) both 404/redirect-loop as of this check.
https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
For ESS: emergency disconnect 10-15 ft from the battery, mounted at 5 ft on center above grade, in a clear path of travel not requiring passage through the ESS area; DC labels every 10 ft/at turns/above-below penetrations/at combiner-junction boxes. For general PV, no Woodland-specific placement rule beyond standard NEC 690/705 disconnect and rapid-shutdown label locations was found.
Why the confidence is not higherCRR-002 disconnect-location and labeling sections.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q44 Must equipment be on a specific approved list? Equipment listing
Yes (implied via listing requirements)
Why the confidence is not higherCRR-002 repeatedly requires UL-listed/labeled equipment (UL 9540 for ESS, UL 1741 for inverters, CFC/OSFM-listed heat alarms) and the SolarAPP+ eligibility page requires reviewing the 'SolarAPP+ Eligible Systems' list before submittal — together indicating equipment must be on recognized approved/listing standards rather than the city maintaining its own separate approved-products list.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Yes, extensively regulated. Per CRR-002 (current, rev. 10/2025): individual ESS units capped at 20 kWh; aggregate ratings capped at 40 kWh (utility closets/storage), 80 kWh (attached/detached garages, accessory structures, exterior walls, or outdoors on the ground); must be UL 9540 listed, inverters UL 1741 listed; 3 ft minimum separation between units and from doors/windows (or UL 9540A testing to reduce it); prohibited in sleeping rooms/closets/habitable spaces (CFC 1207.11.3); vehicle impact protection required per CFC Fig. 1207.11.7.1 unless garage clear height ≤7'6" and unit mounted ≥36in above floor; smoke/heat alarm requirements for unconditioned/unfinished install spaces; garage interior installs need 5/8in Type X gypsum and a self-closing solid-core door; not permitted to emit toxic gases in R-3; ESS emitting hydrogen/flammable gases need mechanical ventilation.
Why the confidence is not higherCRR-002, full document, current (rev. 10/6/2025).
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12050
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Yes
Why the confidence is not higherCRR-008 (Residential ESS Plan Review and Inspections, current) establishes ESS as a 'deferred submittal' with its own Fire Permit number issued alongside the building permit number, a distinct 14-business-day Fire plan-review turnaround, and a separate Fire final inspection that must occur before the building final.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q47 Is a ground mount treated as a structure? Core Ground mount
Likely yes (treated with added structural scrutiny)
Why the confidence is not higherThe fee schedule's footnote to the Solar Photovoltaic Ground Mount fee line states: 'Ground Mounted system or other non-rooftop system will require consultant plan review in addition to the fees listed above' — indicating ground-mount systems get separate/added structural (consultant) review beyond the standard rooftop PV review, consistent with being treated as its own structure, though the fee schedule does not use the word 'structure' explicitly.
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Nothing published by this authority.
Where we lookedChecked PG&E Electric Rule No. 21 (full text, positive/fabricated controls passed) for AC-disconnect placement rules relative to the meter — no hits for 'disconnect' placement language beyond generic references. The PG&E 'Greenbook' (TD-7001M), the more likely source, redirect-loops/404s at its published landing pages (pge.com/greenbook and the interconnections/renewables page) as of this check; its DG-specific companion document TD-2306M is stated elsewhere to be gated to PG&E job owners only. No Woodland-specific document addresses AC disconnect placement either.
https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Phone for Building (530-661-5817, 24-hour line); online booking form (Microsoft Bookings-based) for Fire, including a dedicated Solar/SolarApp+ inspection request category. 90% · department page
- How much notice is required? Building: effectively 1 business day (call by 3:30pm the prior business day; requests after 3:30pm Friday or over the weekend go to Tuesday). Fire: 72-hour notice generally stated, though the Fire plan-submittal page also says inspection requests 'shall be received by noon two business days prior to the inspection date.' 85% · department page
- Are same-day or AM/PM windows offered? No AM/PM windows for Building inspections ('due to staffing, we are not able to accommodate am or pm requests'). Fire has fixed, narrow windows specifically for Solar/SolarApp+ inspections: Mondays 8am-12pm and Wednesdays 12pm-4pm (effective 3/20/26), separate from its general construction-inspection windows (Tue 12-4, Thu 8-12, plus Fri 8-12 for residential fire finals). 90% · department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? Typical sequence for a PV+ESS project: (1) plan submittal to Building (and, for ESS, a parallel deferred-submittal Fire plan review, ~14 business days); (2) permit issuance; (3) construction; (4) Fire final inspection (required for any ESS/solar-with-battery component) BEFORE (5) the Building final inspection, which closes out the permit. PV-only (no battery) projects appear to follow just a Building final, per the general SolarAPP+ Step 4.1/4.2 flow which schedules both a Building inspection and a Fire 'Solar/Energy Storage Systems' inspection. 78% · department page
- Is a rough-in or mid-roof inspection required? No separate rough-in/mid-roof inspection stage was found published for PV; the 2015 Conditions-of-Approval doc only describes a single field inspection at which the panel/disconnects/inverter covers must be removed and a ladder secured for inspector access, i.e., appears to be a single (final) inspection model for the expedited PV track. 58% · conditions of approval (dated 2015)
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? Yes — a published Solar Checklist exists (eligibility checklist for the expedited PV track), plus CRR-008 sets out the ESS-specific plan-review/inspection process. The Solar Checklist is dated 2015 and framed around the expedited program rather than being a universal, current inspection checklist. 72% · checklist
- What must be on site at inspection? Approved/stamped plan set on site; City of Woodland Building AND (if ESS involved) Fire permit cards; all required labels in place per approved plans; ladder secured to structure with covers removed at service panel, disconnect(s), and inverter for inspector access. 85% · guideline
- Does the inspector verify labels and listings? Yes 88% · guideline
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- What is issued on pass? Final (permit finaled/closed) rather than a formal Certificate of Occupancy — the Permits & Plan Checking page limits CofO issuance to 'all commercial projects...for new construction or additions'; residential alteration permits such as solar are simply finaled. 70% · department page
- Who notifies the utility for PTO? Installer (submits proof of the AHJ's final inspection clearance to PG&E, which is a precondition for PG&E to issue Permission to Operate) 80% · utility DG manual / tariff
- Is there a re-inspection fee? $137 flat (Building Division standard re-inspection fee); Fire bills re-inspections/failure-to-prepare/cancellations at $220 (minimum, billed in quarter-hour increments thereafter per the fee schedule's general note). 90% · fee schedule
- How are corrections issued and cleared? Fire: CRR Specialist issues a written letter/notice detailing deficiencies and required corrective actions; a follow-up inspection is then scheduled to confirm compliance (CRR-008). Building: standard practice is correction notes given at inspection with re-inspection scheduled by phone through the same 530-661-5817 line; no separate written corrections-process document was found for Building. 75% · guideline
14 questions answered against City of Woodland’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Phone for Building (530-661-5817, 24-hour line); online booking form (Microsoft Bookings-based) for Fire, including a dedicated Solar/SolarApp+ inspection request category.
Why the confidence is not higherScheduling Inspections page (Building) and Plan Submittal, Review & Inspections page (Fire), both current.
department page checked 2026-08-30 https://www.cityofwoodland.gov/345/Scheduling-Inspections
Q50 How much notice is required? Core Booking & scheduling
Building: effectively 1 business day (call by 3:30pm the prior business day; requests after 3:30pm Friday or over the weekend go to Tuesday). Fire: 72-hour notice generally stated, though the Fire plan-submittal page also says inspection requests 'shall be received by noon two business days prior to the inspection date.'
Why the confidence is not higherScheduling Inspections page (Building, current) and Plan Submittal, Review & Inspections page (Fire, current) — both quoted verbatim.
department page checked 2026-08-30 https://www.cityofwoodland.gov/345/Scheduling-Inspections
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
No AM/PM windows for Building inspections ('due to staffing, we are not able to accommodate am or pm requests'). Fire has fixed, narrow windows specifically for Solar/SolarApp+ inspections: Mondays 8am-12pm and Wednesdays 12pm-4pm (effective 3/20/26), separate from its general construction-inspection windows (Tue 12-4, Thu 8-12, plus Fri 8-12 for residential fire finals).
Why the confidence is not higherScheduling Inspections page (Building) and Plan Submittal, Review & Inspections page (Fire) 'INSPECTION AVAILABILITY UPDATE (Eff. 3/20/26)' notice.
department page checked 2026-08-30 https://www.cityofwoodland.gov/227/Plan-Submittal-Review-Inspections
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes
Why the confidence is not higherBoth the Building Division and the Woodland Fire Department (its own, non-contracted department) perform their own final inspections in-house; the Fire final is explicitly required before the Building final for any ESS-involved project (CRR-002/CRR-008).
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q53 If delegated, to whom? Core Who inspects
N/A — not delegated; performed by Woodland Building Division and Woodland Fire Department directly
Why the confidence is not higherSame sourcing as Q52.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q54 Which inspections are required, and in what order? Core Stages & sequence
Typical sequence for a PV+ESS project: (1) plan submittal to Building (and, for ESS, a parallel deferred-submittal Fire plan review, ~14 business days); (2) permit issuance; (3) construction; (4) Fire final inspection (required for any ESS/solar-with-battery component) BEFORE (5) the Building final inspection, which closes out the permit. PV-only (no battery) projects appear to follow just a Building final, per the general SolarAPP+ Step 4.1/4.2 flow which schedules both a Building inspection and a Fire 'Solar/Energy Storage Systems' inspection.
Why the confidence is not higherSynthesized from the SolarAPP+ page (Steps 4.1/4.2), CRR-002 ('A final Fire inspection is required prior to final inspection by the Building Division'), and CRR-008 ('The final Fire Inspection of the ESS should occur before the building's final inspection').
department page checked 2026-08-30 https://www.cityofwoodland.gov/1615/SolarAPP
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
No separate rough-in/mid-roof inspection stage was found published for PV; the 2015 Conditions-of-Approval doc only describes a single field inspection at which the panel/disconnects/inverter covers must be removed and a ladder secured for inspector access, i.e., appears to be a single (final) inspection model for the expedited PV track.
Why the confidence is not higherConditions-of-Approval for Expedited Permit PDF (2015): 'the contractor is required to set up a ladder secured to structure, remove all covers at the service panel, at disconnect(s) and the inverter prior to inspection' — described as a single inspection, not a rough-then-final sequence.
conditions of approval (dated 2015) checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/540/Conditions-of-Approval-for-Expedited-Permits---SFD-Solar-System-_10Kw-PDF
Q56 Does the inspector verify labels and listings? Core What is checked
Yes
Why the confidence is not higherSolar Checklist fire-safety item C: 'All required markings and labels are provided' is an inspected Y/N item; CRR-008 final-inspection prep list explicitly requires 'All required labels to be in place as indicated by the approved plans' to be verified on site.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q57 Is there a published inspection checklist? Core What is checked
Yes — a published Solar Checklist exists (eligibility checklist for the expedited PV track), plus CRR-008 sets out the ESS-specific plan-review/inspection process. The Solar Checklist is dated 2015 and framed around the expedited program rather than being a universal, current inspection checklist.
Why the confidence is not higherSolar Checklist PDF (pdfinfo-confirmed CreationDate 24 Aug 2015).
checklist checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/538/Solar-Checklist-PDF
Q58 What must be on site at inspection? Core Documents on site
Approved/stamped plan set on site; City of Woodland Building AND (if ESS involved) Fire permit cards; all required labels in place per approved plans; ladder secured to structure with covers removed at service panel, disconnect(s), and inverter for inspector access.
Why the confidence is not higherCRR-008 final-inspection prep list + 2015 Conditions-of-Approval PDF.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q59 Is there a re-inspection fee? Corrections & re-inspection
$137 flat (Building Division standard re-inspection fee); Fire bills re-inspections/failure-to-prepare/cancellations at $220 (minimum, billed in quarter-hour increments thereafter per the fee schedule's general note).
Why the confidence is not higherFee Schedule PDF: 'Re-inspection Fee...Flat Fee...$137' (Building, p.9) and 'Failure to Prepare/Cancel/Reinspection...$220' with the note 'All re-inspections will be charged at a minimum of one hour; and in quarter-hour increments thereafter' (Fire section, current, eff. 7/1/2026).
fee schedule checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/426/Fee-Schedule-PDF
Q60 How are corrections issued and cleared? Corrections & re-inspection
Fire: CRR Specialist issues a written letter/notice detailing deficiencies and required corrective actions; a follow-up inspection is then scheduled to confirm compliance (CRR-008). Building: standard practice is correction notes given at inspection with re-inspection scheduled by phone through the same 530-661-5817 line; no separate written corrections-process document was found for Building.
Why the confidence is not higherCRR-008 Corrective Actions section (Fire, explicit); Building process inferred from the general Scheduling Inspections page.
guideline checked 2026-08-30 https://www.cityofwoodland.gov/DocumentCenter/View/12368
Q61 What is issued on pass? Core Final sign-off & PTO
Final (permit finaled/closed) rather than a formal Certificate of Occupancy — the Permits & Plan Checking page limits CofO issuance to 'all commercial projects...for new construction or additions'; residential alteration permits such as solar are simply finaled.
Why the confidence is not higherPermits & Plan Checking page, 'Certificate of Occupancy' section.
department page checked 2026-08-30 https://www.cityofwoodland.gov/328/Permits-Plan-Checking
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Installer (submits proof of the AHJ's final inspection clearance to PG&E, which is a precondition for PG&E to issue Permission to Operate)
Why the confidence is not higherPG&E Electric Rule No. 21, Sheet 45, §D.13.b: PTO requires PG&E's receipt of, among other things, 'evidence of Applicant's final electric inspection clearance from the Governmental Authority having jurisdiction' — 'Applicant' being the installer/customer, not the AHJ itself.
utility DG manual / tariff checked 2026-08-30 https://www.pge.com/tariffs/assets/pdf/tariffbook/ELEC_RULES_21.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Jurisdiction & key facts
The standing 62-question set, answered for City of Woodland against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Woodland is the authority having jurisdiction 90% confidence
- Holds
- Building, electrical, mechanical and plumbing permitting (City of Woodland Community Development Dept, Building Division); fire-code plan review and inspection for ESS/battery components and general fire-safety items on solar installs (Woodland Fire Department, Community Risk Reduction Division — its own department, not contracted out or a JPA for the city proper). Not delegated to Yolo County, which is AHJ only for unincorporated Yolo County per CA-yolo-county.json.
- Overridden by
- PG&E Electric Rule 21 controls interconnection sequencing and Permission-to-Operate timing (requires AHJ final-inspection clearance first). Valley Clean Energy (Yolo County's CCA, covering Woodland/Davis/Winters/unincorporated Yolo) is a generation-billing layer only and does not sit in the interconnection chain — PG&E still delivers, maintains lines, and grants PTO. Statewide, AB 130 (Stats. 2025, Ch. 22) freezes any new more-restrictive local residential code amendments from 1 Oct 2025 to 1 Jun 2031 (subject to narrow exceptions); California's Solar Rights Act (Civil Code §714) preempts HOA/architectural-review denial of solar.
- Why not higher
- Confirmed directly from the city's own Building Division and Fire Department pages, the SolarAPP+ page, and the current fee schedule (which carries separate Building and Fire fee tables, both applying to Woodland addresses specifically, not the county). Woodland runs no municipal electric utility of its own (per its Public Works 'Electrical' page, which covers only streetlights/signals), consistent with PG&E being the interconnecting utility.
Check the code edition before you build
This authority's published code edition does not match what the state has adopted. That usually means the authority's ordinance has not been updated for the current cycle — but a local amendment can also be lawful. Confirm with the building department before you submit.
- Permit required
- Yes95%
- Permit cost
- $280 for residential rooftop OR ground-mount PV up to 15 kW AC, plus $10 per additional kW or fraction thereof (combined plan review & inspection fee, Building Division).80%
- Plan review
- Not solar-specific: general residential plan review is quoted as '2 to 4 weeks' for initial plan-check activities; Fire's ESS-specific plan review has a stated 14-business-day turnaround;70%
- Portal
- SolarAPP+ (gosolarapp.org) for eligible systems; no dedicated online permitting portal for the standard track — applications and approval documents are submitted by email to…82%
- Electrical code
- 2023 NEC (adopted as the 2025 California Electrical Code)90%
- Own placard wording
- No custom wording found — CRR-002 governs label durability, permanence and legibility ('Labels shall be permanently affixed...and shall not be hand written') and cross-references NEC 2022…60%
- Booking an inspection
- Phone for Building (530-661-5817, 24-hour line); online booking form (Microsoft Bookings-based) for Fire, including a dedicated Solar/SolarApp+ inspection request category.90%
Labels & placards for this authority
Wording 60%
No custom wording found — CRR-002 governs label durability, permanence and legibility ('Labels shall be permanently affixed...and shall not be hand written') and cross-references NEC 2022 Art. 110.21(B), but does not prescribe its own custom placard text.
Size, colour & material 80%
For ESS warning labels exposed to sunlight/outdoors: 'Engraved or Etched Plastic Placards with Red Background and White Lettering.' No separate letter-height/colour/material spec was found for PV-only (non-ESS) labels beyond code-default NEC durability language.
Where they go 75%
For ESS: emergency disconnect 10-15 ft from the battery, mounted at 5 ft on center above grade, in a clear path of travel not requiring passage through the ESS area; DC labels every 10 ft/at turns/above-below penetrations/at combiner-junction boxes. For general PV, no Woodland-specific placement rule beyond standard NEC 690/705 disconnect and rapid-shutdown label locations was found.
What the utility wants on top None%
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.