Modoc County

State of California

Verified Aug. 4, 2026

Modoc County is a county authority in the State of California, covering 12 regions, serving 8,700 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Permitting 5 steps · 28 questions

Whether a permit is needed — Yes Q3 Electrical and building permits — Combined Q4 Where you file — iWorQ ("Modoc Building Permit" citizen portal at modocbuildingpermit.portal.iworq.net); Q20

Permit required
Yes95% source
Key document
county policy / checklist (PDF) cited by 5 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes, for the unincorporated area of Modoc County; No for addresses inside the incorporated City of Alturas, which is a separate AHJ 90% · department page
    • What does this authority permit itself, and what does it delegate? Both 88% · department page
    • Is a permit required for a residential rooftop PV system? Yes 95% · county policy (M-007, PDF)
    • Is there a separate electrical permit, or is it combined? Combined 60% · permit application form
    • Is a HOA or architectural approval required first? No 55% · checklist (PDF)
    • Is a wind or windstorm certification required? No separate windstorm-certification program exists (California has no TDI-style wind certification); the county instead requires the 100 mph design wind speed to be addressed within the required structural engineering for elevated/ground-mount PV 72% · county policy (PDF)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Completed permit application; two (2) sets of plans (site plan, electrical single-line diagram, equipment cut sheets); structural details/engineering if ground-mount or roof array exceeding the county's height threshold; module/inverter listing info; voltage-drop and system-voltage calculations 82% · county policy / checklist (PDF)
    • How many copies, and in what format? Two (2) sets, minimum 8.5"x11" up to 24"x36" (M-007 ground mount checklist: 8.5x11 only) 85% · checklist (PDF)
    • Is a site plan required, and what must it show? Yes — must show structure location, north arrow, equipment/disconnect/inverter locations and, for ground mount, setbacks to structures and property lines 88% · checklist (PDF)
    • Is a one-line / three-line diagram required? Yes 92% · checklist (PDF)
    • Are string and conductor calculations required? Yes 88% · checklist (PDF)
    • Is a structural PE stamp required, and at what threshold? A CA-licensed engineer's wet-stamped design is required for ground-mount PV over 7 feet in height per Policy M-007 (Nov 2024; design wind speed 100 mph); an older, still-linked checklist (doc 208) states the same trigger at 6 feet. Roof-mount arrays require an 'engineered or listed system' for mounting regardless of height. 65% · county policy (M-007, PDF)
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? iWorQ ("Modoc Building Permit" citizen portal at modocbuildingpermit.portal.iworq.net); a separate SolarAPP+ instant-permitting page existed on the county's pre-2024 website but no longer appears in the current site's Building & Safety navigation 80% · portal landing page
    • Can the whole application be completed online? Partially — an online portal exists, but the department's own internal Building Permit Workflow Chart describes applicants turning in a completed (paper/PDF) application which STAFF then key into iWorQ, rather than a self-service online submittal-through-issuance flow 60% · internal policy manual (PDF)
    • Is there a separate plan-check fee? Yes (likely) 55% · internal policy manual (PDF)
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • How long is an issued permit valid before it expires? 365 calendar days (1 year) from issuance without a passed inspection; extendable in 365-day increments; may be reinstated within 5 years of expiration 95% · adopting ordinance
    • Which utility handles interconnection here? PacifiCorp (Pacific Power) serves most of the county, including Alturas (~47,000 CA customers across Siskiyou/Del Norte/Modoc/Shasta counties); Surprise Valley Electrification Corp. (SVEC), a member-owned rural electric cooperative, serves the Surprise Valley communities in eastern Modoc County (Cedarville, Eagleville, Fort Bidwell) 70% · utility service-area page
    • Where does the utility sit in the sequence? After permit (for the SVEC service area) — SVEC's own process requires the applicant to obtain county permits/inspections in Phase I, and SVEC will not set the meter until the county Building Inspector has issued final 'green tag' approval in Phase IV 72% · utility DG/service process page

28 questions answered against Modoc County’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes, for the unincorporated area of Modoc County; No for addresses inside the incorporated City of Alturas, which is a separate AHJ

Why the confidence is not higherCounty Building & Safety Dept page states it enforces Title 15 (building regs) and issues building/electrical/plumbing/mechanical permits; Alturas is incorporated with its own building department at a different address (200 W North St vs county's 203 W 4th St).

department page checked 2026-08-30 https://www.countyofmodoc.gov/534/Building-Safety

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both

Why the confidence is not higherDept page states it issues building, electrical, plumbing and mechanical permits directly; no evidence of delegation to a state agency or third party for unincorporated county.

department page checked 2026-08-30 https://www.countyofmodoc.gov/534/Building-Safety

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes

Why the confidence is not higherMultiple county-published checklists (Ground Mount PV Policy M-007, Alternative Energy Submittal Checklist, Residential Solar PV Plan Submittal Requirements) exist specifically to process PV permits, and the Residential Plan Submittal Requirements (rev. 02.19.2025) lists 'Photovoltaic system' as a required deferred submittal for new CRC dwellings.

county policy (M-007, PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined

Why the confidence is not higherNo standalone 'electrical permit' is referenced for PV anywhere in the county's PV checklists (208, 206/207, 212); solar scope is added to one Building Permit Application (electrical is a checked scope on that single form). The county's separate 'Electrical Application' form (210) is for service change-outs/ag pumps, not solar, so I infer solar is filed as a single combined permit rather than a distinct trade permit, but no document states this explicitly.

permit application form checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/197/Building-Permit-Application

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either

Why the confidence is not higherBuilding Permit Application form has parallel declarations: 2a California Licensed Contractor, 2b Owner-Builder — either may be the permit holder of record.

permit application form checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/197/Building-Permit-Application

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

No

Why the confidence is not higherThe Building Permit Application only asks for CSLB license class/number, not a separate local county contractor-registration step. Checked the application form and department page; no local registration requirement found.

permit application form checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/197/Building-Permit-Application

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes

Why the confidence is not higherOwner-Builder Declaration (Section 2b) on the standard Building Permit Application is a valid path to self-permit and self-install per CA Bus. & Prof. Code §7044, cited on the form itself.

permit application form checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/197/Building-Permit-Application

Q8 What documents make up a complete submittal? Core Submittal package

Completed permit application; two (2) sets of plans (site plan, electrical single-line diagram, equipment cut sheets); structural details/engineering if ground-mount or roof array exceeding the county's height threshold; module/inverter listing info; voltage-drop and system-voltage calculations

Why the confidence is not higherCombined from Policy M-007 (Ground Mount PV, Nov 2024), Alternative Energy Submittal Checklist (208), and Residential Solar PV Plan Submittal Requirements (206/207); all are the county's own current, still-linked forms though 206/207 date to 2015/2020.

county policy / checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q9 How many copies, and in what format? Submittal package

Two (2) sets, minimum 8.5"x11" up to 24"x36" (M-007 ground mount checklist: 8.5x11 only)

Why the confidence is not higherStated consistently across doc 206/207 ('Submit two (2) sets of plans, minimum 8.5x11 & maximum 24x36') and doc 212 M-007 ('Completed Site Plan on 8.5 x 11 size paper').

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/206/Residential-Solar-Photovoltaic-PV-System-Plan-Submittal-Requirements-PDF

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes — must show structure location, north arrow, equipment/disconnect/inverter locations and, for ground mount, setbacks to structures and property lines

Why the confidence is not higherExplicit in doc 206/207 item 3 and doc 208/212 site-plan requirements.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/206/Residential-Solar-Photovoltaic-PV-System-Plan-Submittal-Requirements-PDF

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes

Why the confidence is not higherAll three PV checklists (206/207, 208, 212) require an electrical single-line diagram.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q12 Are string and conductor calculations required? Drawings & calculations

Yes

Why the confidence is not higherDoc 208 (Alternative Energy Submittal Checklist) has a full System Summary worksheet requiring calculated system voltage (NEC 690.7) and minimum PV source-circuit ampacity (NEC 690.8); doc 206/207 requires voltage-drop calcs.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/208/Alternative-Energy-Submittal-Checklist-PDF

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

A CA-licensed engineer's wet-stamped design is required for ground-mount PV over 7 feet in height per Policy M-007 (Nov 2024; design wind speed 100 mph); an older, still-linked checklist (doc 208) states the same trigger at 6 feet. Roof-mount arrays require an 'engineered or listed system' for mounting regardless of height.

Why the confidence is not higherTwo of the county's own current documents disagree on the exact height (6 ft vs 7 ft); M-007 is the newer (Nov 2024) and more specific document so I weight it higher, but the conflict itself lowers confidence.

county policy (M-007, PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Nothing published by this authority.

Where we lookedChecked all four county PV submittal checklists (DocumentCenter 206, 207, 208, 212) for a distinct electrical (as opposed to structural) PE-stamp threshold; none is specified beyond general CEC compliance.

https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q15 What does a residential solar permit cost? Core Fees

Nothing published by this authority.

Where we lookedChecked the Policies/Procedures/Forms page (21-item document list), Resolution No. 2024-32 and its Attachment A fee excerpt, and the Building Permit Workflow Chart — no standalone fee schedule ('Schedule A') or PV-specific dollar fee is published on the county site; Resolution 2024-32's Attachment A only excerpts plumbing/mechanical/misc. items plus a $45.80 permit-extension fee, not a PV or valuation-based building-permit fee table.

https://www.countyofmodoc.gov/541/Policies-Procedures-Forms

Q16 How is the fee calculated? Core Fees

Nothing published by this authority.

Where we lookedSame documents as q15 — Resolution 2024-32/Attachment A references 'Schedule A' by name but that base schedule (originally Resolution 2008-09) is not itself published in the DocumentCenter list I retrieved, so the computation method (flat/valuation/per-kW) cannot be confirmed from a primary source.

https://www.countyofmodoc.gov/DocumentCenter/View/226/Resolution-No-2024-32-Approving-Fees-for-Permit-Expiration-Reinstatement-Extension-PDF

Q17 Is there a separate plan-check fee? Fees

Yes (likely)

Why the confidence is not higherInternal Building Permit Workflow Chart lists 'Plan Review Fees' as a fee category tracked separately on the receipt/file, implying a distinct plan-review fee line item, but no published fee schedule confirms the amount or that it is charged separately up front rather than bundled into one total.

internal policy manual (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/232/Building-Permit-Workflow-Chart-PDF

Q18 What is the stated plan-review turnaround? Core Timeline & validity

Nothing published by this authority.

Where we lookedChecked the Building & Safety department page and Instructions/Information page for a stated plan-review turnaround; none is published. (Third-party permit-aggregator sites quote '1-3 weeks' but per this brief's rule against trusting such aggregators as sources, that figure is not used.)

https://www.countyofmodoc.gov/534/Building-Safety

Q19 How long is an issued permit valid before it expires? Timeline & validity

365 calendar days (1 year) from issuance without a passed inspection; extendable in 365-day increments; may be reinstated within 5 years of expiration

Why the confidence is not higherExplicit amendment text in Ordinance No. 221-J (adopted 23 Jul 2024) amending CBC §105.5 and CRC §R105.5.

adopting ordinance checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q20 Which permit portal does this authority use? Core Portal & process

iWorQ ("Modoc Building Permit" citizen portal at modocbuildingpermit.portal.iworq.net); a separate SolarAPP+ instant-permitting page existed on the county's pre-2024 website but no longer appears in the current site's Building & Safety navigation

Why the confidence is not higheriWorQ portal link is live on the current department page, Application Forms page, and EV page. The SolarAPP+ page (co.modoc.ca.us/.../rooftop_solar_permit_processing.php) is still indexed by search engines with live-looking content but 404s on direct fetch and is not archived in the Wayback Machine or linked from the migrated CivicPlus site's Building & Safety menu — I looked in /534, /540, /541, /536 and none link to it, so I cannot confirm it is still active.

portal landing page checked 2026-08-30 https://modocbuildingpermit.portal.iworq.net/portalhome/modocbuildingpermit

Q21 Can the whole application be completed online? Core Portal & process

Partially — an online portal exists, but the department's own internal Building Permit Workflow Chart describes applicants turning in a completed (paper/PDF) application which STAFF then key into iWorQ, rather than a self-service online submittal-through-issuance flow

Why the confidence is not higherDirect contradiction between the portal's public 'apply online' framing and the department's internal SOP document, which is the more authoritative source on actual practice.

internal policy manual (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/232/Building-Permit-Workflow-Chart-PDF

Q22 Which utility handles interconnection here? Core Utility interconnection

PacifiCorp (Pacific Power) serves most of the county, including Alturas (~47,000 CA customers across Siskiyou/Del Norte/Modoc/Shasta counties); Surprise Valley Electrification Corp. (SVEC), a member-owned rural electric cooperative, serves the Surprise Valley communities in eastern Modoc County (Cedarville, Eagleville, Fort Bidwell)

Why the confidence is not higherPacifiCorp's own service-area/CPUC-filed customer-count description and SVEC's own corporate history page (formed 1936 in Eagleville, acquired Fort Bidwell Electric in 1938) — not a ZIP-code lookup tool. Exact boundary depends on the specific address within the county.

utility service-area page checked 2026-08-30 https://www.pacificpower.net/community/service-area.html

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After permit (for the SVEC service area) — SVEC's own process requires the applicant to obtain county permits/inspections in Phase I, and SVEC will not set the meter until the county Building Inspector has issued final 'green tag' approval in Phase IV

Why the confidence is not higherSourced directly from SVEC's own 'New/Modified Service' page. Have not independently confirmed PacifiCorp follows an identical sequence for the rest of the county — this is confirmed only for the SVEC territory.

utility DG/service process page checked 2026-08-30 https://surprisevalleyelectric.org/newmodified-service-1

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No

Why the confidence is not higherNone of the county's PV submittal checklists (206/207, 208, 212) or the general Residential Plan Submittal Requirements ask for HOA/architectural approval as a condition of permit issuance. Absence checked across all four documents; rural county with limited HOA coverage.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/225/Residential-Plan-Submittal-Checklist-PDF

Q25 Is there a historic-district review? Overlays & special cases

Nothing published by this authority.

Where we lookedChecked Title 15 (Building Regulations) via Ordinance 221-J and the county's Building & Safety document list; historic-district review would be a Planning Department zoning matter (Title 17), which I did not have time to review in full, so this is an incomplete rather than a confirmed absence.

https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q26 Is a wind or windstorm certification required? Overlays & special cases

No separate windstorm-certification program exists (California has no TDI-style wind certification); the county instead requires the 100 mph design wind speed to be addressed within the required structural engineering for elevated/ground-mount PV

Why the confidence is not higherDesign wind speed stated directly in Policy M-007; California does not operate a Texas-Department-of-Insurance-style windstorm certification scheme statewide.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Nothing published by this authority.

Where we lookedChecked Building & Safety's Title 15 ordinance and PV checklists; a Specific Use Permit/Council approval trigger (if any) would sit in the Planning Department's zoning ordinance, which was outside the scope I could review in the time available.

https://www.countyofmodoc.gov/584/Planning

Q28 Is there a system-size cap on residential generation? Overlays & special cases

Nothing published by this authority.

Where we lookedChecked Ordinance 221-J (Title 15.01), the LDRD ordinance's Photovoltaic System Requirements section (15.06.410, which states PV is simply 'not mandatory' with no size cap), and all four PV checklists — no residential generation size cap is stated anywhere.

https://www.countyofmodoc.gov/DocumentCenter/View/230/Building-and-Safety-Policy-and-Procedure-Manual-PDF

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? 2017 85% · adopting ordinance
    • Which building code edition is in force? 2022 California Building Code / California Residential Code (Title 24, Parts 2 & 2.5), based on the 2018 IBC/IRC 85% · adopting ordinance
    • Which fire code edition is in force? 2022 California Fire Code (Title 24 Part 9), based on the 2021 International Fire Code 85% · adopting ordinance
    • Are there local amendments to any of the above? Yes 95% · adopting ordinance
    • What is the installation judged against? California Electrical Code Articles 690/705 (per the county's own PV checklists), California Fire Code egress/access requirements, and county Policy M-007's ground-mount inspection criteria 82% · county policy (PDF)
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    • What ridge setback and access pathways are required? Detailed pathway/setback rules published: min. 3 ft clear walkway eave-to-ridge (hip roofs), two 3 ft walkways (single ridge), modules kept 10 ft from hips/valleys when arrays are on both sides, and no modules within 3 ft of the ridge for ventilation; ground-mount arrays require a 10 ft brush-free clearance 68% · checklist (PDF, last modified 17 Apr 2020, cites 2013 code cycle)
  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Yes, under NEC 690.12 as incorporated by the 2022 CEC (2017 NEC base) 68% · adopting ordinance (inference)
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? DC disconnect: 'Photovoltaic Power Source' warning sign; AC point-of-connection sign; alternative/standby power-source switch sign; labels on all DC conduit/raceways/junction and combiner boxes 85% · county policy (PDF)
    • Does the authority specify placard wording of its own? Yes — required wording: "WARNING: PHOTOVOLTAIC POWER SOURCE" 82% · checklist (PDF)
    • Does it specify letter height, colour or material? Labels shall be reflective and water-resistant, minimum 3/8-inch lettering, white lettering on a red background 82% · checklist (PDF)
    • Is a site plan / facility map placard required, and what must it show? No dedicated site-plan/facility-map placard beyond standard NEC 690/705 disconnect labeling was found in any county document 55% · county policy (PDF) — absence across 4 documents
    • Where must the labels be placed? At every service/utility disconnect, and on every DC conduit/raceway/enclosure at 10 ft on-center and within 1 ft of turns, bends, and penetrations 82% · checklist (PDF)
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Must equipment be on a specific approved list? Yes 78% · checklist (PDF)
    • Are batteries permitted, and under what conditions? Yes, if included in the permit's scope of work and shown on the electrical diagram with locations and venting; batteries/ESS in a vehicle path must be protected by bollards per the county's Final Inspection Checklist 82% · checklist (PDF)
    • Is there a separate ESS permit or inspection? No — batteries are added as scope-of-work to the existing PV/building permit rather than requiring a standalone ESS permit 65% · county policy (PDF)
    • Is a ground mount treated as a structure? Yes 85% · county policy (PDF)
    • Is there a local rule on service upgrades or busbar sizing? The NEC 705.12 120% busbar/OCPD rule is explicitly restated as an inspection criterion ("sum of the main OCPD and the inverter OCPD... not more than 120% of the bus bar rating"); no local amendment beyond that NEC rule was found 78% · county policy (PDF)
    • Is a specific mounting system or attachment spacing required? Yes — minimum roof-mount support spacing: 4 ft o.c. at 0-40 lb snow load, 2 ft o.c. at 40-70 lb, and CA-licensed-engineer design required above 70 lb 75% · checklist (PDF, last modified 17 Apr 2020, cites 2013 code cycle)

20 questions answered against Modoc County’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2017

Why the confidence is not higherOrdinance No. 221-J (adopted 23 Jul 2024) adopts the 2022 CCR Title 24 Part 3 California Electrical Code, which is 'based on the 2017 National Electrical Code.' This is the most recent adoption ordinance published by the county; I could not find a newer ordinance adopting the 2025 Title 24 cycle (based on the 2023 NEC), which took automatic statewide effect 1 Jan 2026 absent a superseding local amendment — so as of the current 2025/2026 cycle the applicable edition may already be 2023 NEC by operation of state law even though no local ordinance updating Title 15 was found.

adopting ordinance checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q30 Which building code edition is in force? Core Code editions in force

2022 California Building Code / California Residential Code (Title 24, Parts 2 & 2.5), based on the 2018 IBC/IRC

Why the confidence is not higherDirectly from Ordinance No. 221-J text; same caveat as q29 about a possible superseding 2025 cycle adoption not found on the county's site.

adopting ordinance checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q31 Which fire code edition is in force? Code editions in force

2022 California Fire Code (Title 24 Part 9), based on the 2021 International Fire Code

Why the confidence is not higherDirectly from Ordinance No. 221-J text; building official (not fire chief) holds enforcement responsibility for Group R-3 fire/panic-safety provisions per the same ordinance.

adopting ordinance checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes

Why the confidence is not higherOrdinance No. 221-J itself amends CBC/CRC/CEC/CMC/CPC administrative sections (permit expiration/renewal timelines, fee-refund procedures, deleted CBC 105.1.1/105.1.2, etc.).

adopting ordinance checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q33 What is the installation judged against? Core Electrical

California Electrical Code Articles 690/705 (per the county's own PV checklists), California Fire Code egress/access requirements, and county Policy M-007's ground-mount inspection criteria

Why the confidence is not higherExplicit citations across docs 206/207, 208 and 212.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

The NEC 705.12 120% busbar/OCPD rule is explicitly restated as an inspection criterion ("sum of the main OCPD and the inverter OCPD... not more than 120% of the bus bar rating"); no local amendment beyond that NEC rule was found

Why the confidence is not higherDirectly quoted from Policy M-007's inspection checklist.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Yes — minimum roof-mount support spacing: 4 ft o.c. at 0-40 lb snow load, 2 ft o.c. at 40-70 lb, and CA-licensed-engineer design required above 70 lb

Why the confidence is not higherStated in doc 206/207, still the only published guidance and still linked from the current site, but the PDF's own body text cites the superseded '2013 CA Fire and Residential Codes,' predating the current 2022-code adoption ordinance — a code-year mismatch that reduces confidence in whether it has been updated in substance since 2015/2020.

checklist (PDF, last modified 17 Apr 2020, cites 2013 code cycle) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/206/Residential-Solar-Photovoltaic-PV-System-Plan-Submittal-Requirements-PDF

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Detailed pathway/setback rules published: min. 3 ft clear walkway eave-to-ridge (hip roofs), two 3 ft walkways (single ridge), modules kept 10 ft from hips/valleys when arrays are on both sides, and no modules within 3 ft of the ridge for ventilation; ground-mount arrays require a 10 ft brush-free clearance

Why the confidence is not higherSame source and same code-year caveat as q35 — this document explicitly frames these rules under a 'Solar PV Requirements in the 2013 California Fire, Electrical & Residential Codes' heading, which predates the county's current 2022 code adoption (Ordinance 221-J, Jul 2024). It remains the only published county guidance on this topic, so I'm reporting it, but flagging the mismatch.

checklist (PDF, last modified 17 Apr 2020, cites 2013 code cycle) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/206/Residential-Solar-Photovoltaic-PV-System-Plan-Submittal-Requirements-PDF

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes, under NEC 690.12 as incorporated by the 2022 CEC (2017 NEC base)

Why the confidence is not higherInferred from the adopted NEC edition (Ordinance 221-J); no Modoc document explicitly names 'rapid shutdown,' so this is a code-adoption inference rather than a direct county statement.

adopting ordinance (inference) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/213/Ordinance-No-221-J-Adopting-the-2022-California-Building-Standards-Code-with-Local-Amendments-PDF

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

DC disconnect: 'Photovoltaic Power Source' warning sign; AC point-of-connection sign; alternative/standby power-source switch sign; labels on all DC conduit/raceways/junction and combiner boxes

Why the confidence is not higherConsistent across doc 212 (M-007, Nov 2024) inspection checklist and doc 206/207 labeling section.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

Yes — required wording: "WARNING: PHOTOVOLTAIC POWER SOURCE"

Why the confidence is not higherQuoted verbatim in doc 206/207 (labeling section); note the same code-year caveat as q35/36.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/207/Residential-Solar-PV-Plan-Requirements-PDF

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Labels shall be reflective and water-resistant, minimum 3/8-inch lettering, white lettering on a red background

Why the confidence is not higherQuoted verbatim in doc 206/207 labeling section.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/207/Residential-Solar-PV-Plan-Requirements-PDF

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

No dedicated site-plan/facility-map placard beyond standard NEC 690/705 disconnect labeling was found in any county document

Why the confidence is not higherChecked docs 206/207, 208, 212, 225 — none describe a separate facility/site-plan placard requirement distinct from the individual disconnect/source labels already covered under q38-40.

county policy (PDF) — absence across 4 documents checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedChecked Surprise Valley Electrification Corp.'s 'About SVEC' and 'New/Modified Service' pages for utility-specific placard/label requirements beyond the AHJ's; none published. Did not locate a PacifiCorp California DG interconnection manual with placard specifications.

https://surprisevalleyelectric.org/newmodified-service-1

Q43 Where must the labels be placed? Core Labels Signage & labelling

At every service/utility disconnect, and on every DC conduit/raceway/enclosure at 10 ft on-center and within 1 ft of turns, bends, and penetrations

Why the confidence is not higherQuoted verbatim from doc 206/207.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/207/Residential-Solar-PV-Plan-Requirements-PDF

Q44 Must equipment be on a specific approved list? Equipment listing

Yes

Why the confidence is not higherDoc 206/207 Fire Rating section requires modules to be 'tested, listed and identified' per CBC Table 1505.1; Alt Energy checklist (208) asks whether the inverter is 'Listed for Utility Interconnection'; M-007 inspection checklist checks equipment listing labels against ratings.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/208/Alternative-Energy-Submittal-Checklist-PDF

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes, if included in the permit's scope of work and shown on the electrical diagram with locations and venting; batteries/ESS in a vehicle path must be protected by bollards per the county's Final Inspection Checklist

Why the confidence is not higherDoc 212 (M-007) and doc 208 both require batteries to be disclosed on the permit scope/diagram with venting shown; doc 227 (Final Inspection Checklist, current) independently confirms a bollard-protection rule for 'ESS (batteries)' in vehicle paths.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/227/Single-Family-Dwelling-Final-Inspection-Checklist-PDF

Q46 Is there a separate ESS permit or inspection? Battery / ESS

No — batteries are added as scope-of-work to the existing PV/building permit rather than requiring a standalone ESS permit

Why the confidence is not higherDoc 212 instructs applicants to 'include them on permit application (scope of work)' rather than referencing a separate ESS permit type; no standalone ESS permit application form was found on the county site.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q47 Is a ground mount treated as a structure? Core Ground mount

Yes

Why the confidence is not higherGround-mount PV requires a foundation plan with footings/reinforcement, per Policy M-007's inspection checklist ('Foundation plan with footings and appropriate reinforcement shown') and the Alternative Energy checklist's requirement for wet-stamped engineered plans over 6-7 ft.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Nothing published by this authority.

Where we lookedChecked all four county PV checklists (206, 207, 208, 212) and SVEC's New/Modified Service page for an AC-disconnect-to-meter placement rule; none specifies a distance/location requirement relative to the utility meter.

https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? Foundation → rough/4-way (framing, plumbing, mechanical, electrical) → final. Deferred PV submittals must be reviewed and approved before the 4-way rough inspection. 75% · checklist (PDF, revised 19 Feb 2025)
    • Is a rough-in or mid-roof inspection required? Yes 68% · checklist (PDF)
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? Yes 92% · checklist (PDF)
    • What must be on site at inspection? Approved job-copy plans and calculations, the issued permit with prior correction notices resolved, any special-inspection reports, and operation/maintenance manuals for installed equipment 80% · checklist (PDF)
    • Does the inspector verify labels and listings? Yes 88% · county policy (PDF)
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

14 questions answered against Modoc County’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Phone

Why the confidence is not higherBuilding & Safety Dept page instructs 'Please call to schedule an appointment' (530-233-6413/6406); internal Workflow Chart confirms the Admin Assistant schedules inspections upon request rather than a self-service online booking calendar.

department page checked 2026-08-30 https://www.countyofmodoc.gov/534/Building-Safety

Q50 How much notice is required? Core Booking & scheduling

Nothing published by this authority.

Where we lookedChecked the Building & Safety department page, Instructions/Information page, and internal Workflow Chart; none states a minimum notice period for scheduling an inspection.

https://www.countyofmodoc.gov/536/Instructions-Information

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Nothing published by this authority.

Where we lookedSame documents as q50; no mention of same-day service or AM/PM inspection windows.

https://www.countyofmodoc.gov/534/Building-Safety

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes

Why the confidence is not higherInternal Building Permit Workflow Chart shows the county's own Building Official personally performs and records inspection results in iWorQ; no third-party inspection agency is referenced.

internal policy manual (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/232/Building-Permit-Workflow-Chart-PDF

Q53 If delegated, to whom? Core Who inspects

N/A — not delegated; performed directly by the county Building Official

Why the confidence is not higherSame source as q52; no delegation to another agency is referenced anywhere in the department's own materials.

internal policy manual (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/232/Building-Permit-Workflow-Chart-PDF

Q54 Which inspections are required, and in what order? Core Stages & sequence

Foundation → rough/4-way (framing, plumbing, mechanical, electrical) → final. Deferred PV submittals must be reviewed and approved before the 4-way rough inspection.

Why the confidence is not higherResidential Plan Submittal Requirements (rev. 02.19.2025) states deferred submittals, including 'Photovoltaic system,' must be approved 'prior to a 4-way (Rough framing, plumbing, mechanical and electrical) inspection'; general sequence corroborated by the Final Inspection Checklist and Workflow Chart.

checklist (PDF, revised 19 Feb 2025) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/225/Residential-Plan-Submittal-Checklist-PDF

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Yes

Why the confidence is not higherInferred from the '4-way (Rough framing, plumbing, mechanical, electrical) inspection' referenced as the checkpoint before which PV deferred submittals must be approved — implying a rough-in inspection stage applies to PV wiring as part of that 4-way.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/225/Residential-Plan-Submittal-Checklist-PDF

Q56 Does the inspector verify labels and listings? Core What is checked

Yes

Why the confidence is not higherPolicy M-007's inspection checklist explicitly directs the inspector to verify module/inverter model numbers against plans, verify 'appropriate signs are properly constructed, installed and displayed,' and verify equipment ratings are consistent with installed signage/listings.

county policy (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/212/Modoc-County-Ground-Mount-PV-System-Submittal-and-Inspection-Checklist-PDF

Q57 Is there a published inspection checklist? Core What is checked

Yes

Why the confidence is not higherTwo published inspection checklists exist: the Ground Mount PV Submittal and Inspection Checklist (M-007) and the Single-Family Dwelling Final Inspection Checklist.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/227/Single-Family-Dwelling-Final-Inspection-Checklist-PDF

Q58 What must be on site at inspection? Core Documents on site

Approved job-copy plans and calculations, the issued permit with prior correction notices resolved, any special-inspection reports, and operation/maintenance manuals for installed equipment

Why the confidence is not higherDirectly listed under 'Paperwork Required' in the Single-Family Dwelling Final Inspection Checklist; this is a general SFD checklist rather than PV-specific, but it is the county's only published final-inspection document.

checklist (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/227/Single-Family-Dwelling-Final-Inspection-Checklist-PDF

Q59 Is there a re-inspection fee? Corrections & re-inspection

Nothing published by this authority.

Where we lookedChecked Resolution No. 2024-32 and its Attachment A fee excerpt, and the Building Permit Workflow Chart; no re-inspection fee line item is published (only a $45.80 permit-extension/reinstatement fee is documented).

https://www.countyofmodoc.gov/DocumentCenter/View/226/Resolution-No-2024-32-Approving-Fees-for-Permit-Expiration-Reinstatement-Extension-PDF

Q60 How are corrections issued and cleared? Corrections & re-inspection

Corrections are attached to the field inspection record card and tracked in the county's iWorQ Administration Record; the permit cannot final until 'all previous correction notices are completed,' implying clearance is verified at re-inspection

Why the confidence is not higherInferred by combining the Final Inspection Checklist's 'all previous correction notices are completed' requirement with the internal Workflow Chart's iWorQ note-tracking process; no document independently describes a full corrections-and-clearance procedure end to end.

checklist (PDF) + internal workflow chart checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/227/Single-Family-Dwelling-Final-Inspection-Checklist-PDF

Q61 What is issued on pass? Core Final sign-off & PTO

Final

Why the confidence is not higherThe county's own internal Workflow Chart uses the term 'finaled' for a passed final inspection; the utility SVEC separately refers to this same county approval as a 'green tag' in its own service-connection process, so both terms describe the same underlying county sign-off.

internal policy manual (PDF) checked 2026-08-30 https://www.countyofmodoc.gov/DocumentCenter/View/232/Building-Permit-Workflow-Chart-PDF

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer/applicant

Why the confidence is not higherSVEC's own New/Modified Service process places the burden on the applicant to obtain county Building Inspector 'green tag' approval before SVEC will act (set the meter); nothing in county or SVEC materials describes the county proactively notifying the utility.

utility DG/service process page checked 2026-08-30 https://surprisevalleyelectric.org/newmodified-service-1

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Jurisdiction & key facts

The standing 62-question set, answered for Modoc County against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Modoc County is the authority having jurisdiction 88% confidence
Holds
Both
Overridden by
Applies only to the UNINCORPORATED area of Modoc County. The City of Alturas is incorporated and is a separate AHJ with its own Building Department (200 W. North St., Alturas — a different address/office than the County's Building & Safety Dept at 203 W. 4th St.); the county's own legacy web page for 'City of Alturas' permit forms suggests some historical county involvement in city electrical permitting but this could not be independently confirmed as still current. In the Surprise Valley communities (Cedarville, Eagleville, Fort Bidwell), Surprise Valley Electrification Corp. (SVEC), a member-owned electric cooperative, sets its own interconnection/net-metering terms and requires its own New/Modified Service process independent of, though sequenced after, county building sign-off.
Why not higher
County's own Building & Safety Dept page states it issues building, electrical, plumbing and mechanical permits under Title 15 of the Modoc County Code; confirmed the department (not Planning or a combined agency) actually holds building/electrical, correcting any assumption it might sit under Planning. Alturas's separate building department was confirmed via Municode (Alturas has its own Ch. 5 Building Code) and a business-listing address distinct from the county's.

https://www.countyofmodoc.gov/534/Building-Safety

Check the code edition before you build

This authority's published code edition does not match what the state has adopted. That usually means the authority's ordinance has not been updated for the current cycle — but a local amendment can also be lawful. Confirm with the building department before you submit.

Building code
This authority publishes 2022 2022 California Building Code / California Residential Code (Title 24, Parts 2 & 2.5), based on the 2018 IBC/IRC 85% · source
The state has adopted 2024/2025 2025 California Building Code (Title 24, Part 2, Volumes 1 & 2), based on the 2024 International Building Code, and 2025 California Residential Code (Title 24, Part 2.5), 92% · source
Fire code
This authority publishes 2021/2022 2022 California Fire Code (Title 24 Part 9), based on the 2021 International Fire Code 85% · source
The state has adopted 2024/2025 2025 California Fire Code (Title 24, Part 9), based on the 2024 International Fire Code, adopted by the Office of the State Fire Marshal with BSC approval. 90% · source
Permit required
Yes95%
Portal
iWorQ ("Modoc Building Permit" citizen portal at modocbuildingpermit.portal.iworq.net); a separate SolarAPP+ instant-permitting page existed on the county's pre-2024 website but no longer…80%
Electrical code
201785%
Own placard wording
Yes — required wording: "WARNING: PHOTOVOLTAIC POWER SOURCE"82%
Booking an inspection
Phone82%
Labels & placards for this authority

Modoc County writes its own placard wording. A standard NEC label set will not satisfy it — the exact text, and in most cases the size, colour and font, are specified below.

Wording 82%

Yes — required wording: "WARNING: PHOTOVOLTAIC POWER SOURCE"

Size, colour & material 82%

Labels shall be reflective and water-resistant, minimum 3/8-inch lettering, white lettering on a red background

Where they go 82%

At every service/utility disconnect, and on every DC conduit/raceway/enclosure at 10 ft on-center and within 1 ft of turns, bends, and penetrations

What the utility wants on top None%

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
County
County
Modoc County
Regions served
12
Regions covered
Adin · county
California Pines · county
Canby · county
Cedarville · county
Daphnedale Park · county
Eagleville · county
Fort Bidwell · county
Lake City · county
Lookout · county
Modoc County · county
Newell · county
New Pine Creek · county
Solar Requirements
Required placards
Building & Safety | Modoc County, CA Skip to Main Content Create a Website Account - Manage notification subscriptions, save form progress and more. Website Sign In Home Departments Building & Safety Building & Safety (Authorized under California Building Code, Title 24, and Modoc County Ordinance Code Chapter 15.) Department Overview The County of Modoc Building and Safety Department ensures that
Separate roof inspection
Building & Safety | Modoc County, CA Skip to Main Content Create a Website Account - Manage notification subscriptions, save form progress and more. Website Sign In Home Departments Building & Safety Building & Safety (Authorized under California Building Code, Title 24, and Modoc County Ordinance C
Authority Contact
Address
203 West 4th Street, Alturas, CA 96101
Main Phone
(530) 233-7660
Building Department
Department
Building & Safety Department
Direct Phone
(530) 233-6406
Portal Software
iWorQ
Booking & Scheduling
Preferred channel
phone
Notes
Call (530) 233-6406 to schedule a final solar inspection appointment. Office hours: Monday–Thursday 9:00 AM–5:00 PM, closed noon–1:00 PM for lunch; closed Friday–Sunday. The iworq online portal (modocbuildingpermit.portal.iworq.net) is for permit applications and permit lookup only — inspection scheduling is by phone. County website formerly at co.modoc.ca.us now redirects to countyofmodoc.gov. (collected Jul 2026)