City of Bonita Springs is a city authority in the State of Florida, serving 53,644 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for City of Bonita Springs against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

City of Bonita Springs is the authority having jurisdiction 88% confidence
Holds
Building and electrical, via the City's Community Development Department. PV is filed under a combined 'Trade Permit Application' (section D. SOLAR) that also carries Electric, Mechanical, Plumbing and LP Gas trade sections; a PV job additionally triggers 'building plan review.' Note: the Community Development Department (Building, Planning & Zoning) has been operated under contract since a 21 May 2008 City Council agreement, most recently by Jacobs Engineering (career-opportunities page on the City's own cityofbonitaspringscd.org domain: 'Jacobs is an Equal Opportunity/Affirmative Action Employer') — successor to CH2M HILL, named in Fee Resolution 25-129's recitals ('on May 21, 2008, Bonita Springs City Council entered into an agreement with CH2M HILL to provide Community Development, Building Permitting and Inspections and Administrative Support Services'). Fire-code review and fire permits are NOT held by the City or by a 'Bonita Springs Fire Control & Rescue District' as briefed — the City's own current Community Development forms page hosts the 'Estero Fire Permit Application' as its fire-permit form, instructing plan submittal to Bonita Springs CD (239-444-6150) with inspections scheduled directly with Estero Fire Rescue District (239-390-8000). I could not locate any competing 'Bonita Springs Fire Control and Rescue District' document to contradict this — it is the only fire-permit routing the City publishes.
Delegated to
Community Development (building/electrical/PV) contracted to Jacobs Engineering Group (successor to CH2M HILL, 2008 agreement). Fire review/permitting delegated to Estero Fire Rescue District, an independent special district, per the City's own current fire-permit application form.
Overridden by
Utility interconnection/PTO is gated by Florida Power & Light (FPL) — see jurisdiction confidence note; FPL's tariff and net-metering guidelines control disconnect, placard and energization sequencing independent of the City. Florida HB 803/SB 1202 (2025-2026 sessions) affect permit validity and third-party inspection options statewide.
Why not higher
City of Bonita Springs incorporated 1999; its own Community Development Department (cityofbonitaspringscd.org) publishes the Trade Permit application, Residential Building Permit application, fee schedule (Resolution 25-129) and contractor-registration requirements used city-wide. The department's operation is contracted (Jacobs/ex-CH2M HILL) — this is a genuine correction to any assumption of a purely in-house city department, though the City remains the AHJ of record (permits issued in the City's name, fees set by City Council resolution). Fire review sits with the independent Estero Fire Rescue District, not a Bonita-named district. I could not verify whether Lee County retains any residual jurisdiction (e.g., over unincorporated enclaves) because Lee County's own DCD page was not fetched in this run; within incorporated Bonita Springs city limits the City (via its contracted CD department) is the AHJ.

https://www.cityofbonitaspringscd.org/about/career_opportunities.html

Permit required
Yes — a permit is required for residential rooftop PV92%
Permit cost
$200.00 flat ('Trade Permit - Roof, Solar')90%
Plan review
5 to 7 working days for 'a complete and accurate' application (stated generally for residential permitting; not published as a PV-specific figure)55%
Portal
City of Bonita Springs EnerGov Self-Service Permit Portal (Tyler Technologies EnerGov), at https://egweb1.cityofbonitasprings.org/energov/selfservice#/search88%
Electrical code
2020 — NEC 2020 is the edition in force96%
Own placard wording
No — the City specifies no placard wording of its own; FPL (the confirmed utility) sets the applicable wording and explicitly requires the installer to 'contact FPL for approval of...the…70%
Booking an inspection
Portal or Phone — inspections can be requested online via the EnerGov Permit Portal (Permit Details page > 'Request' button),78%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes — a permit is required for residential rooftop PV Q3 Electrical and building permits — Combined — a plain residential PV job is filed and billed under a single 'Trade Permit - Roof, Solar' ($200 flat) fee line, Q4 Plan review — 5 to 7 working days for 'a complete and accurate' application (stated generally for residential permitting; not published as a PV-specific figure) Q18 Where you file — City of Bonita Springs EnerGov Self-Service Permit Portal (Tyler Technologies EnerGov), at https://egweb1.cityofbonitasprings.org/energov/selfservice#/search Q20

Permit required
Yes — a permit is required for residential rooftop PV92% source
What it costs
$200.00 flat ('Trade Permit - Roof, Solar')90% source
Plan review turnaround
5 to 7 working days for 'a complete and accurate' application (stated generally for residential permitting; not published as a PV-specific figure)55% source
Key document
permit application, Solar Truss Affidavit (2026 bundle) cited by 6 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes — the City of Bonita Springs Community Development Department is the AHJ for residential solar within city limits 92% · adopted permit application (2026)
    • What does this authority permit itself, and what does it delegate? Both — the City's Community Development Dept. permits and inspects building and electrical itself for PV, via a single 'Trade Permit Application' with a dedicated D. SOLAR section (Photovoltaic System checkbox) alongside F. ELECTRIC; the form itself notes 'building plan review required for PV systems' 85% · permit application (2026)
    • Is a permit required for a residential rooftop PV system? Yes — a permit is required for residential rooftop PV 92% · department procedures handout (2024)
    • Is there a separate electrical permit, or is it combined? Combined — a plain residential PV job is filed and billed under a single 'Trade Permit - Roof, Solar' ($200 flat) fee line, distinct from the separate 'Trade Permit - Electrical, Gas' ($150) line used for standalone electrical work; the electrical connection inherent to PV does not require pulling a second, separate Electrical trade permit 75% · fee schedule (Resolution 25-129, adopted 15 Oct 2025, eff. 1 Jan 2026)
    • Is a HOA or architectural approval required first? Not addressed by the City for solar specifically; the City's Land Development Code contains a 'Deed Restrictions' provision, but it sits on Municode (library.municode.com), which disallows automated access (robots.txt: 'User-agent: ClaudeBot / Disallow: /'), so I could not read its text to confirm whether it bears on HOA/architectural approval for PV 45% · department LDC-snippets index page
    • Is a wind or windstorm certification required? No dedicated wind/windstorm 'certification' document exists for PV specifically; the closest analogues in the City's own Trade Permit package are (a) the Re-Roof wind-speed design values printed on the same form ('Nominal wind speed 124, Ultimate wind speed 160') that apply to any roofing scope including panel-bearing roofs, and (b) the Solar Truss Affidavit's reference to manufacturer standard FSEC-IN-24-06 for truss attachment 55% · permit application (2026)
    • Is a Specific Use Permit or Council approval ever required? No — residential PV is handled administratively through the Trade Permit process; no Specific Use Permit or Council approval is mentioned in any reviewed City document 55% · department FAQ page
    • Is there a system-size cap on residential generation? No City-stated cap on residential PV system size was found. The interconnecting utility (FPL, see q22) defines its own tiers (Tier 1 <=10kW AC, Tier 2 >10-100kW, Tier 3 >100kW-2MW) and limits an approved system's estimated output to under 115% of the customer's annual kWh consumption, and to 90% of existing service capacity absent an upgrade — these are utility interconnection limits, not a City zoning cap 60% · utility net-metering guidelines page
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Any contractor registered with the City (state-licensed under Ch. 489 F.S., or a Lee County Grandfathered Local License per Lee County Ordinance 23-09); the City's own forms do not name a specific trade-license class (e.g., Solar/Electrical Contractor) for the SOLAR section of the Trade Permit 55% · contractor registration form (2025)
    • Must the contractor be registered with this authority before applying? Yes — contractors must register with the City of Bonita Springs Community Development Dept. before applying for any permit, including Trade Permits 90% · department FAQ page
    • Is a homeowner permitted to self-install and self-permit? Yes — a homeowner may self-permit as an owner-builder 85% · department FAQ page
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Trade Permit Application (SOLAR section: Photovoltaic System, KW of PV) + Solar Truss Affidavit (if truss/panel weight ≤5 lbs/sq ft, per FSEC-IN-24-06) or sealed structural calculations if that threshold is exceeded (triggers 'building plan review required for PV systems') + current Contractor Registration on file (or Owner-Builder Statement/Affidavit if self-permitted) + recorded Notice of Commencement if job value ≥$5,000 80% · permit application package (2026)
    • How many copies, and in what format? Electronic — submitted through the City's EnerGov 'Permit Portal' (self-service), with file uploads by document type; no paper-copy count is specified for the Trade Permit itself (contrast: new residential construction explicitly requires 3 paper sets + 1 digital set). Approved plans/permit documents must still be picked up in person 60% · department FAQ / portal guide
    • Is a site plan required, and what must it show? Not specifically flagged for the SOLAR line on the Trade Permit — the form marks '**site plan & zoning review required' next to back-up generators and new AC systems under the ELECTRIC/MECHANICAL sections, but the SOLAR section (Roof Truss Affidavit / Pool Heater / Water Heater / Photovoltaic System) carries no such annotation. A 'building plan review' is separately triggered for PV, which may include a roof/site drawing, but no dedicated PV site-plan content list is published 60% · permit application (2026)
    • Is a structural PE stamp required, and at what threshold? A Solar Truss Affidavit (no PE stamp) suffices where the completed PV installation 'does not exceed five (5) pounds per square foot' per manufacturer standard FSEC-IN-24-06/FSEC-FP-7-80, signed by the owner/authorized agent (or by an owner-builder, licensed contractor, engineer/architect, or FS 468 building inspector per the parallel 504 Roof Inspection Affidavit). Installations exceeding that threshold, or any PV job routed to 'building plan review,' require sealed structural documentation 75% · permit application, Solar Truss Affidavit (2026 bundle)
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? City of Bonita Springs EnerGov Self-Service Permit Portal (Tyler Technologies EnerGov), at https://egweb1.cityofbonitasprings.org/energov/selfservice#/search 88% · portal landing link / department page
    • Can the whole application be completed online? Mostly, not entirely — application submittal, fee payment, license renewal and inspection requests are done through the Portal, but approved plans and permit documents must still be picked up in person 80% · Portal Inspection Request Guide (rev. 6/24/2024)
    • What does a residential solar permit cost? $200.00 flat ('Trade Permit - Roof, Solar') 90% · fee schedule (Resolution 25-129, eff. 1 Jan 2026)
    • How is the fee calculated? Flat 90% · fee schedule (Resolution 25-129)
    • Is there a separate plan-check fee? No separate PV plan-check fee is itemized — the $200 flat Trade Permit fee is the only Solar-specific charge published; a generic 'Permit - Additional Electric, Mechanical, Plumbing $75.00' line exists for extra trade lines on the same permit but is not tied specifically to PV plan review 60% · fee schedule (Resolution 25-129)
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

28 questions answered against City of Bonita Springs’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes — the City of Bonita Springs Community Development Department is the AHJ for residential solar within city limits

Why the confidence is not higherCD department's own forms (Trade Permit, Residential Building Permit) are issued in the City's name and required for solar; the department itself is contracted to Jacobs (ex-CH2M HILL) but the City remains the permitting authority of record

adopted permit application (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both — the City's Community Development Dept. permits and inspects building and electrical itself for PV, via a single 'Trade Permit Application' with a dedicated D. SOLAR section (Photovoltaic System checkbox) alongside F. ELECTRIC; the form itself notes 'building plan review required for PV systems'

Why the confidence is not higherVerbatim from the current (1/27/2026) Trade Permit Application, section D: '**solar truss affidavit required; building plan review required for PV systems'. Deduction: the same universal form also covers Electric/Mechanical/Plumbing/Gas as separate trade sections, so the split between the 'solar' function and general 'electrical' function is by form section, not by separate department

permit application (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes — a permit is required for residential rooftop PV

Why the confidence is not higherThe 2024 Residential Permitting Procedures lists 'Solar' among 'ADDITIONAL PERMITS (if required): Plumbing, Electrical, Air Conditioning, Roofing, Lawn Sprinkler system, Pools..., Solar, Fire Sprinklers or Alarm Systems'; the Trade Permit Application carries a dedicated SOLAR section; and Fee Resolution 25-129 lists a specific 'Trade Permit - Roof, Solar $200.00' fee line

department procedures handout (2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Permitting_Procedures_20240105_final.pdf

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined — a plain residential PV job is filed and billed under a single 'Trade Permit - Roof, Solar' ($200 flat) fee line, distinct from the separate 'Trade Permit - Electrical, Gas' ($150) line used for standalone electrical work; the electrical connection inherent to PV does not require pulling a second, separate Electrical trade permit

Why the confidence is not higherFee Resolution 25-129 (eff. 1 Jan 2026) lists 'Trade Permit - Roof, Solar $200.00' and 'Trade Permit - Electrical, Gas $150.00' as distinct line items; the Trade Permit Application's SOLAR section (D) is self-contained (Roof Truss Affidavit / Pool Heater / Water Heater / Photovoltaic System) and does not cross-reference the ELECTRIC section (F). Deduction: I could not confirm with a City staff statement whether an inspector would ever require a second Electrical trade permit for a large PV job with a service upgrade

fee schedule (Resolution 25-129, adopted 15 Oct 2025, eff. 1 Jan 2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Any contractor registered with the City (state-licensed under Ch. 489 F.S., or a Lee County Grandfathered Local License per Lee County Ordinance 23-09); the City's own forms do not name a specific trade-license class (e.g., Solar/Electrical Contractor) for the SOLAR section of the Trade Permit

Why the confidence is not higherContractor Registration form requires 'Active State License (if required by state law) or Lee County Grandfathered Local License (if required by Lee County Ordinance 23-09)' generically for all trades; the Trade Permit's SOLAR section asks only for 'Contractor License Number' with no class restriction stated

contractor registration form (2025) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Contractor_Registration_20250912_final.pdf

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes — contractors must register with the City of Bonita Springs Community Development Dept. before applying for any permit, including Trade Permits

Why the confidence is not higherFAQ: 'All contractors licensed by the state of Florida or who hold a Lee County Competency License, doing work in the City of Bonita Springs, must register with the City of Bonita Springs Community Development office'; corroborated by the standalone Contractor Registration form and by the Authorized Agent Affidavit process

department FAQ page checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Building_Questions.html

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes — a homeowner may self-permit as an owner-builder

Why the confidence is not higherFAQ: 'Can a home owner apply for a permit? Yes, a home owner may apply for a building permit without the need for a contractor. However, the home owner will be expected to fully comply with all zoning regulations and the Florida Building Code as amended.' Corroborated by the standalone 'Owner Builder Statement/Affidavit (HB425)' form required for owner-builder permits

department FAQ page checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Building_Questions.html

Q8 What documents make up a complete submittal? Core Submittal package

Trade Permit Application (SOLAR section: Photovoltaic System, KW of PV) + Solar Truss Affidavit (if truss/panel weight ≤5 lbs/sq ft, per FSEC-IN-24-06) or sealed structural calculations if that threshold is exceeded (triggers 'building plan review required for PV systems') + current Contractor Registration on file (or Owner-Builder Statement/Affidavit if self-permitted) + recorded Notice of Commencement if job value ≥$5,000

Why the confidence is not higherAssembled from the current (1/27/2026) Trade Permit Application package (application, Roof Truss/Solar Truss affidavits, NOC threshold note) and the Contractor Registration / Owner-Builder Statement forms bundled in the same 'building_general' forms page

permit application package (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q9 How many copies, and in what format? Submittal package

Electronic — submitted through the City's EnerGov 'Permit Portal' (self-service), with file uploads by document type; no paper-copy count is specified for the Trade Permit itself (contrast: new residential construction explicitly requires 3 paper sets + 1 digital set). Approved plans/permit documents must still be picked up in person

Why the confidence is not higherPermit Portal FAQ page directs registration and application questions to the 'Permit Portal Guide'; the 6/24/2024 Inspection Request Guide states 'approved plans and documents must still be picked up in-person'; no Trade-Permit-specific copy count is stated anywhere in the reviewed document set

department FAQ / portal guide checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Permit_Portal.html

Q10 Is a site plan required, and what must it show? Core Submittal package

Not specifically flagged for the SOLAR line on the Trade Permit — the form marks '**site plan & zoning review required' next to back-up generators and new AC systems under the ELECTRIC/MECHANICAL sections, but the SOLAR section (Roof Truss Affidavit / Pool Heater / Water Heater / Photovoltaic System) carries no such annotation. A 'building plan review' is separately triggered for PV, which may include a roof/site drawing, but no dedicated PV site-plan content list is published

Why the confidence is not higherRead the full current (1/27/2026) Trade Permit Application line by line: the '**site plan & zoning review required' marker appears on E.1/E.2/E.5/E.6 (Mechanical) and F.1 (Electric back-up generator) but is absent from D. SOLAR. Positive control confirmed: the marker itself is present and legible elsewhere in the same document

permit application (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Nothing published by this authority.

Where we lookedTrade Permit Application (2026), Residential Permitting Procedures (2024), Residential Building Permit Application (2026) — none require a one-line/three-line diagram as a City submittal item for the SOLAR trade line. (LCEC's own Net Metering process separately requires 'an electric one-line diagram and spec sheet of the inverter' as a condition of ITS interconnection application — a utility, not AHJ, requirement, and LCEC is not the utility confirmed for this address; see q22)

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedSame Trade Permit / Residential Permitting Procedures document set — no string/conductor calculation requirement stated for the SOLAR trade line

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

A Solar Truss Affidavit (no PE stamp) suffices where the completed PV installation 'does not exceed five (5) pounds per square foot' per manufacturer standard FSEC-IN-24-06/FSEC-FP-7-80, signed by the owner/authorized agent (or by an owner-builder, licensed contractor, engineer/architect, or FS 468 building inspector per the parallel 504 Roof Inspection Affidavit). Installations exceeding that threshold, or any PV job routed to 'building plan review,' require sealed structural documentation

Why the confidence is not higherVerbatim from the Solar Truss Affidavit and 504 Roof Inspection Affidavit bundled in the current Trade Permit Application package; the 5 lb/sq ft threshold and FSEC-IN-24-06 citation are explicit. Deduction: the City does not separately publish the threshold that triggers full sealed structural calculations beyond 5 psf — it is inferred from 'building plan review required for PV systems' on the same form

permit application, Solar Truss Affidavit (2026 bundle) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Nothing published by this authority.

Where we lookedTrade Permit Application and Solar Truss Affidavit address structural (roof-weight) thresholds only; no electrical PE-stamp threshold is stated anywhere in the reviewed City document set

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q15 What does a residential solar permit cost? Core Fees

$200.00 flat ('Trade Permit - Roof, Solar')

Why the confidence is not higherFee Resolution No. 25-129, Exhibit A, 'PERMIT TYPE - WORK CLASS' table: 'Trade Permit - Roof, Solar $200.00'. Adopted 15 Oct 2025, new fees effective 1 Jan 2026. Controls run on this document: positive control 'electrical' = 1 hit (the adjacent 'Trade Permit - Electrical, Gas' line), fabricated control 'zzqqx' = 0 hits — search reliable

fee schedule (Resolution 25-129, eff. 1 Jan 2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q16 How is the fee calculated? Core Fees

Flat

Why the confidence is not higherSame fee-schedule line item is a single flat dollar figure ($200.00) with no valuation, per-kW or per-panel variable, unlike the Building Permit fee (which is 'Based on Job Value and the Building Permit Fee Valuation table')

fee schedule (Resolution 25-129) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q17 Is there a separate plan-check fee? Fees

No separate PV plan-check fee is itemized — the $200 flat Trade Permit fee is the only Solar-specific charge published; a generic 'Permit - Additional Electric, Mechanical, Plumbing $75.00' line exists for extra trade lines on the same permit but is not tied specifically to PV plan review

Why the confidence is not higherReviewed the complete Exhibit A fee table in Resolution 25-129: no 'PV plan review' or 'Solar plan review' line exists alongside the $200 Trade Permit fee

fee schedule (Resolution 25-129) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q18 What is the stated plan-review turnaround? Core Timeline & validity

5 to 7 working days for 'a complete and accurate' application (stated generally for residential permitting; not published as a PV-specific figure)

Why the confidence is not higher2024 Residential Permitting Procedures: 'REVIEW PROCESS TIME: The review process for a complete and accurate application is anticipated to be between 5 to 7 working days.' This is the general residential review-time statement; no PV-specific turnaround is published separately

department procedures handout (2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Permitting_Procedures_20240105_final.pdf

Q19 How long is an issued permit valid before it expires? Timeline & validity

Nothing published by this authority.

Where we lookedFee Resolution 25-129 shows extension fees ('$50.00/3 months 1st extension; $100.00/3 months 2nd extension') implying an underlying base validity period, but no City document in the reviewed set (Trade Permit App, Residential Building Permit App, Residential Permitting Procedures, Portal guides) states the base number of days/months a permit is valid before expiration. Florida HB 803 (2026) sets a 1-year floor under FS 553.79(1)(c) for local-government-issued permits effective 1 Jul 2026 — the City's own published figure could not be located to compare against it

https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q20 Which permit portal does this authority use? Core Portal & process

City of Bonita Springs EnerGov Self-Service Permit Portal (Tyler Technologies EnerGov), at https://egweb1.cityofbonitasprings.org/energov/selfservice#/search

Why the confidence is not higherLinked site-wide from the CD site as 'Permit Portal (opens in a new tab)'; URL path 'energov/selfservice' identifies the Tyler Technologies EnerGov product

portal landing link / department page checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Permit_Portal.html

Q21 Can the whole application be completed online? Core Portal & process

Mostly, not entirely — application submittal, fee payment, license renewal and inspection requests are done through the Portal, but approved plans and permit documents must still be picked up in person

Why the confidence is not higherVerbatim from the 6/24/2024 Inspection Request Guide: 'Please note, approved plans and documents must still be picked up in-person.' Portal FAQ confirms online registration, payment, inspection requests and file uploads

Portal Inspection Request Guide (rev. 6/24/2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Permit_Portal_Inspection_Request_Guide_20240624.pdf

Q22 Which utility handles interconnection here? Core Utility interconnection

Florida Power & Light Company (FPL) — NOT Lee County Electric Cooperative (LCEC)

Why the confidence is not higherFPL's own PSC-filed retail tariff, Section 7 'Communities Served' (Eighth Revised Sheet No. 7.010, effective 1 Jan 2026), lists 'Bonita Springs' explicitly under the 'LEE' county heading, alongside Fort Myers, Estero, Fort Myers Beach and Unincorporated-Lee. Corroborated two ways: (a) the City of Bonita Springs' own main website (cityofbonitasprings.org) links 'Florida Power and Light' as an assisting utility agency and names no other electric utility anywhere in its site content; (b) LCEC's own service-territory description (lcec.net) names only Cape Coral/Matlacha, Sanibel/Captiva/Pine Island, parts of Lehigh Acres & Estero, and North Fort Myers within Lee County — Bonita Springs does not appear in any of LCEC's six named districts. This corrects the brief's assumption that LCEC serves Bonita Springs

FPL PSC-filed retail tariff, Section 7 Communities Served (Eighth Revised Sheet No. 7.010, eff. 1 Jan 2026) checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section7.pdf

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After permit — FPL will not energize/grant Permission-to-Operate until the customer submits proof that the local permit has been approved, including sign-off from the local inspector

Why the confidence is not higherFPL Net Metering Guidelines: 'a customer should provide a copy of the approved permit or a screen print from the local authority's website indicating the permit has been approved and that includes: Electrical and mechanical inspection signed off / approved by the local inspector... Operation of the renewable generation system, except for testing and inspection, prior to the installation of a new bi-directional meter is strictly prohibited.' Application + interconnect agreement + building permit are obtained first; the passed-inspection proof and bidirectional meter install follow

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q24 Is a HOA or architectural approval required first? Overlays & special cases

Not addressed by the City for solar specifically; the City's Land Development Code contains a 'Deed Restrictions' provision, but it sits on Municode (library.municode.com), which disallows automated access (robots.txt: 'User-agent: ClaudeBot / Disallow: /'), so I could not read its text to confirm whether it bears on HOA/architectural approval for PV

Why the confidence is not higherThe City's own curated 'Land Development Code Snippets' page links 'Deed Restrictions (MuniCode)' as one of its named topics, confirming the provision exists, but Municode's robots.txt blocks ClaudeBot from the underlying page

department LDC-snippets index page checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Land_Development_Code_Snippets.html

Q25 Is there a historic-district review? Overlays & special cases

Nothing published by this authority.

Where we lookedChecked the CD Department's 'Architectural Design' FAQ (covers only building-color regulation, LDC 3-487/3-489(n)) and the full 'Land Development Code Snippets' curated topic list (32 named topics) — neither names a historic district or historic-preservation review. The full LDC is hosted on Municode, which disallows ClaudeBot (robots.txt), so a historic-preservation ordinance elsewhere in the code could not be ruled out

https://www.cityofbonitaspringscd.org/resources/Architectural_Design.html

Q26 Is a wind or windstorm certification required? Overlays & special cases

No dedicated wind/windstorm 'certification' document exists for PV specifically; the closest analogues in the City's own Trade Permit package are (a) the Re-Roof wind-speed design values printed on the same form ('Nominal wind speed 124, Ultimate wind speed 160') that apply to any roofing scope including panel-bearing roofs, and (b) the Solar Truss Affidavit's reference to manufacturer standard FSEC-IN-24-06 for truss attachment

Why the confidence is not higherVerbatim wind-speed figures and FSEC citation from the current (1/27/2026) Trade Permit Application and its bundled Solar Truss Affidavit. Neither document uses the word 'certification' for wind specifically — this is an inference from the closest available City text

permit application (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

No — residential PV is handled administratively through the Trade Permit process; no Specific Use Permit or Council approval is mentioned in any reviewed City document

Why the confidence is not higherAbsence checked across the Trade Permit Application, Residential Building Permit Application, Residential Permitting Procedures, and Building Questions FAQ — none references SUP or Council review for solar or any residential trade permit

department FAQ page checked 2026-09-12 https://www.cityofbonitaspringscd.org/resources/Building_Questions.html

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No City-stated cap on residential PV system size was found. The interconnecting utility (FPL, see q22) defines its own tiers (Tier 1 <=10kW AC, Tier 2 >10-100kW, Tier 3 >100kW-2MW) and limits an approved system's estimated output to under 115% of the customer's annual kWh consumption, and to 90% of existing service capacity absent an upgrade — these are utility interconnection limits, not a City zoning cap

Why the confidence is not higherFPL Net Metering Guidelines page states the tier thresholds and the 115%/90% limits verbatim; no City fee schedule, Trade Permit application, or FAQ imposes an independent generation-size cap

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? 2020 — NEC 2020 is the edition in force 96% · permit application masthead (2026, corroborated 2024-2026)
    • Which building code edition is in force? 8th Edition (2023) Florida Building Code — Building, Existing, Mechanical, Plumbing (and Energy) 95% · permit application masthead (2026)
    • Which fire code edition is in force? 8th Edition (2023) Florida Fire Prevention Code 93% · permit application masthead (2026)
    • Are there local amendments to any of the above? Yes — local amendments to the Land Development Code exist and interact with construction (e.g., mechanical-equipment-encroachment Sec. 4-1892, fence regulations Sec. 4-1742/4-1467, metal-building restriction Sec. 4-2225), though I could not access the full LDC or a dedicated local building-code-amendment ordinance directly because it is hosted on Municode, which disallows ClaudeBot 55% · permit application (2026) + department FAQ
    • What is the installation judged against? The installation is judged against the codes named on the permit itself: 8th ed. 2023 FBC, 8th ed. 2023 FFC, and NEC 2020, per the standard clause 'Permit reviewed and approved based on information provided by applicant. Omitted and/or falsified information may void permit in accordance with 4-162(d)' 85% · permit application (2026)
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for City of Bonita Springs on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? The City requires no placard of its own beyond code compliance. The confirmed interconnecting utility, FPL, requires: a sign at the meter noting the disconnect-switch location, a warning sign stating 'both sides of the switch may be energized' (mandatory disconnect only for Tier 2/3, >10kW), and — for battery storage — a placard permanently affixed to the meter enclosure reading 'Battery storage utilized in this facility' 78% · utility net-metering guidelines page
    • Does the authority specify placard wording of its own? No — the City specifies no placard wording of its own; FPL (the confirmed utility) sets the applicable wording and explicitly requires the installer to 'contact FPL for approval of...the verbiage...of the sign' before finalizing the design 70% · utility net-metering guidelines page
    • Does it specify letter height, colour or material? Not specified by the City. FPL's guideline does not give an exact letter height, colour or material for the disconnect-location sign or warning sign beyond requiring FPL's prior approval of the verbiage; for battery storage, only 'a placard must be permanently affixed' is specified with no dimensions 52% · utility net-metering guidelines page
    • Is a site plan / facility map placard required, and what must it show? Not addressed by the City. FPL's guideline implies only a location-indicator sign at the meter pointing to the disconnect switch, not a full facility/site-plan placard; NEC 705.10 (directory of disconnecting means) would apply generically via the adopted NEC 2020 but is not separately called out by the City or by FPL's guideline text 55% · utility net-metering guidelines page
    • Does the UTILITY specify placards beyond the AHJ's? Yes — FPL (the confirmed utility) specifies requirements beyond anything the City asks for: a visible-load-break manual disconnect switch mandatory for Tier 2/3 systems (>10kW), mounted separate from but adjacent to the FPL meter socket, lockable with a single FPL padlock, plus a location sign and an energization warning sign, with FPL's prior approval required for sign verbiage/placement; and a permanent 'Battery storage utilized in this facility' placard for any battery installation 85% · utility net-metering guidelines page
    • Where must the labels be placed? At the meter/disconnect location: FPL's disconnect-location sign and energization-warning sign are posted at the meter, with the Tier 2/3 manual disconnect itself mounted separate from but adjacent to the meter socket; the battery-storage placard is permanently affixed to the meter enclosure 78% · utility net-metering guidelines page
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? Utility-specified, not a City rule: FPL requires a manual disconnect of the visible load-break type for Tier 2/3 systems (>10 kW AC), mounted separate from but adjacent to the FPL meter socket, lockable with a single FPL padlock, and readily accessible to FPL at all times. Tier 1 (<=10 kW AC — the great majority of residential installs) is NOT stated by FPL as requiring this dedicated disconnect at all 82% · utility net-metering guidelines page
    • Are batteries permitted, and under what conditions? Batteries are not restricted by the City (no ESS checkbox or exclusion appears anywhere in the SOLAR section of the Trade Permit or in the fee schedule); at the utility level, FPL requires UL 1741-certified battery equipment, a permanent 'Battery storage utilized in this facility' placard, and — for a battery installed with backup-only intent and no export — no interconnection agreement at all, versus a full Small Generator Interconnection Agreement if paired with RGS or grid-interactive 55% · utility net-metering guidelines page (utility-level; City itself is silent)
    • Is there a separate ESS permit or inspection? No — no separate ESS permit type or fee line exists in the City's own Trade Permit Application or Fee Resolution 25-129 68% · fee schedule (Resolution 25-129)
    • Is a specific mounting system or attachment spacing required? No specific mounting-system or attachment-spacing rule is published; the only dimensional constraint found is the Solar Truss Affidavit's weight limit — the installation 'does not exceed five (5) pounds per square foot' per FSEC-IN-24-06 truss-manufacturer standard — above which full structural review applies 60% · permit application, Solar Truss Affidavit (2026 bundle)

20 questions answered against City of Bonita Springs’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2020 — NEC 2020 is the edition in force

Why the confidence is not higherStated identically on four current City documents: Trade Permit Application (1/27/2026): 'NEC 2020; National Electric Code'; Residential Building Permit Application (1/26/2026): same; Residential Permitting Procedures (1/5/2024): same; Authorized Agent Affidavit (9/12/2025): same. Note: the CD Department's own 'Building Questions' FAQ page is stale and still states '2008 edition National Electrical Code' alongside '2010 FBC' — that page is superseded by the current permit-application masthead text and should not be relied on

permit application masthead (2026, corroborated 2024-2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q30 Which building code edition is in force? Core Code editions in force

8th Edition (2023) Florida Building Code — Building, Existing, Mechanical, Plumbing (and Energy)

Why the confidence is not higherSame four current documents as q29 state '8th ed. 2023 FBC; Florida Building Code: Building, Existing, Mechanical, Plumbing' (Residential Permitting Procedures adds ', Energy'). The FAQ page's '2010 FBC' text is stale and superseded

permit application masthead (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q31 Which fire code edition is in force? Code editions in force

8th Edition (2023) Florida Fire Prevention Code

Why the confidence is not higherSame four current documents state '8th ed. 2023 FFC; Florida Fire Prevention Code'. Note: the separate Estero Fire Rescue District permit-procedures handout (the City's own fire-permit routing document) is dated 2014 and still cites the '2010 Florida Fire Prevention Code' — a live document that has not been updated to match the City's current building-permit masthead

permit application masthead (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes — local amendments to the Land Development Code exist and interact with construction (e.g., mechanical-equipment-encroachment Sec. 4-1892, fence regulations Sec. 4-1742/4-1467, metal-building restriction Sec. 4-2225), though I could not access the full LDC or a dedicated local building-code-amendment ordinance directly because it is hosted on Municode, which disallows ClaudeBot

Why the confidence is not higherLDC section numbers and quoted text are drawn from the City's own Trade Permit Application (mechanical encroachment) and Building Questions FAQ (fences, metal buildings) — both self-hosted, not Municode. The broader building/electrical-code amendment ordinance itself sits on library.municode.com/fl/bonita_springs, blocked by robots.txt for ClaudeBot

permit application (2026) + department FAQ checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q33 What is the installation judged against? Core Electrical

The installation is judged against the codes named on the permit itself: 8th ed. 2023 FBC, 8th ed. 2023 FFC, and NEC 2020, per the standard clause 'Permit reviewed and approved based on information provided by applicant. Omitted and/or falsified information may void permit in accordance with 4-162(d)'

Why the confidence is not higherVerbatim from the current Trade Permit Application and Residential Building Permit Application

permit application (2026) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedNo City-specific service-upgrade or busbar-sizing rule was found in the Trade Permit Application, Residential Building Permit Application, or Residential Permitting Procedures. (FPL's own Net Metering Guidelines address service-capacity and transformer-upgrade cost allocation, but that is a utility rule, not an AHJ rule, and is answered separately at q48 where it is on-topic)

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

No specific mounting-system or attachment-spacing rule is published; the only dimensional constraint found is the Solar Truss Affidavit's weight limit — the installation 'does not exceed five (5) pounds per square foot' per FSEC-IN-24-06 truss-manufacturer standard — above which full structural review applies

Why the confidence is not higherVerbatim from the Solar Truss Affidavit bundled in the current Trade Permit Application package; no separate racking/attachment-spacing standard is published by the City

permit application, Solar Truss Affidavit (2026 bundle) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedNo ridge-setback or fire-access-pathway language was found in the Trade Permit Application, Residential Permitting Procedures, or the Estero Fire Rescue District permit-procedures handout (which addresses only permit types and submittal counts, not roof-access pathways). The Florida Fire Prevention Code's own PV chapter would carry this, but the adopting/amending ordinance is on Municode (blocked)

https://www.cityofbonitaspringscd.org/forms/Estero_Fire_Permit_Application.pdf

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes, via the adopted NEC 2020 (Art. 690.12); the City adds no rapid-shutdown rule of its own in any reviewed document

Why the confidence is not higherThe 'no local rule' half is proved by absence across the Trade Permit Application, Residential Permitting Procedures and Solar Truss Affidavit — none mentions rapid shutdown. The 'yes' half is inference from the adopted NEC 2020 edition (q29), not a City statement

permit application (2026) — rapid shutdown by NEC 2020 inference checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

The City requires no placard of its own beyond code compliance. The confirmed interconnecting utility, FPL, requires: a sign at the meter noting the disconnect-switch location, a warning sign stating 'both sides of the switch may be energized' (mandatory disconnect only for Tier 2/3, >10kW), and — for battery storage — a placard permanently affixed to the meter enclosure reading 'Battery storage utilized in this facility'

Why the confidence is not higherFPL Net Metering Guidelines, verbatim: 'A sign noting the location of the disconnect switch should be installed at the meter... The disconnect switch should also have a warning sign indicating that both sides of the switch may be energized... Please contact FPL for approval of a remote switch location and the verbiage or the location of the sign prior to the final design'; and 'A placard must be permanently affixed to the meter enclosure stating "Battery storage utilized in this facility."' No City document (Trade Permit, Residential Permitting Procedures) adds its own placard list

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No — the City specifies no placard wording of its own; FPL (the confirmed utility) sets the applicable wording and explicitly requires the installer to 'contact FPL for approval of...the verbiage...of the sign' before finalizing the design

Why the confidence is not higherSame FPL guideline quote as q38; no City document sets placard text

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Not specified by the City. FPL's guideline does not give an exact letter height, colour or material for the disconnect-location sign or warning sign beyond requiring FPL's prior approval of the verbiage; for battery storage, only 'a placard must be permanently affixed' is specified with no dimensions

Why the confidence is not higherRead the full FPL Net Metering Guidelines page — no numeric letter-height, colour or material specification is present for the residential disconnect/warning signs (contrast: PG&E's equivalent document in other jurisdictions is far more prescriptive, e.g. minimum letter height and ANSI Z535.4 material — no such detail is published by FPL on this page)

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Not addressed by the City. FPL's guideline implies only a location-indicator sign at the meter pointing to the disconnect switch, not a full facility/site-plan placard; NEC 705.10 (directory of disconnecting means) would apply generically via the adopted NEC 2020 but is not separately called out by the City or by FPL's guideline text

Why the confidence is not higherFPL Net Metering Guidelines: 'A sign noting the location of the disconnect switch should be installed at the meter to enable FPL personnel to easily locate the disconnect switch' — a location pointer, not a facility map. No City document adds a facility-map requirement

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes — FPL (the confirmed utility) specifies requirements beyond anything the City asks for: a visible-load-break manual disconnect switch mandatory for Tier 2/3 systems (>10kW), mounted separate from but adjacent to the FPL meter socket, lockable with a single FPL padlock, plus a location sign and an energization warning sign, with FPL's prior approval required for sign verbiage/placement; and a permanent 'Battery storage utilized in this facility' placard for any battery installation

Why the confidence is not higherAll verbatim from FPL's Net Metering Guidelines page, current as fetched 12 Sep 2026

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the meter/disconnect location: FPL's disconnect-location sign and energization-warning sign are posted at the meter, with the Tier 2/3 manual disconnect itself mounted separate from but adjacent to the meter socket; the battery-storage placard is permanently affixed to the meter enclosure

Why the confidence is not higherSame FPL Net Metering Guidelines page, verbatim placement language for both the disconnect switch and the battery placard

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q44 Must equipment be on a specific approved list? Equipment listing

Nothing published by this authority.

Where we lookedNo City-published approved-equipment list was found across the Trade Permit Application, Residential Permitting Procedures, or Building Questions FAQ; UL/NEC listing requirements would apply generically via the adopted NEC 2020 but no City or FPL document names a specific approved-products list

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Batteries are not restricted by the City (no ESS checkbox or exclusion appears anywhere in the SOLAR section of the Trade Permit or in the fee schedule); at the utility level, FPL requires UL 1741-certified battery equipment, a permanent 'Battery storage utilized in this facility' placard, and — for a battery installed with backup-only intent and no export — no interconnection agreement at all, versus a full Small Generator Interconnection Agreement if paired with RGS or grid-interactive

Why the confidence is not higherCity-side absence checked across the current Trade Permit Application (SOLAR section lists only Roof Truss Affidavit / Pool Heater / Water Heater / Photovoltaic System — no battery item) and the fee schedule (no ESS line). Utility-side requirement is verbatim from FPL's Net Metering Guidelines 'Battery systems for personal use' section

utility net-metering guidelines page (utility-level; City itself is silent) checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q46 Is there a separate ESS permit or inspection? Battery / ESS

No — no separate ESS permit type or fee line exists in the City's own Trade Permit Application or Fee Resolution 25-129

Why the confidence is not higherFee Resolution 25-129's full Exhibit A table was read line by line: no 'battery,' 'ESS' or 'energy storage' permit type or fee appears anywhere. Controls run on the same document: positive control 'electrical' = 1 hit, fabricated control 'zzqqx' = 0 hits, confirming the search was working

fee schedule (Resolution 25-129) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q47 Is a ground mount treated as a structure? Core Ground mount

Nothing published by this authority.

Where we lookedNo ground-mount-specific text was found. The Residential Building Permit Application's 'ACCESSORY' job-type checklist (Awning/Canopy, Carport, Gazebo, Greenhouse, Glass/Utility Room, Deck/Slab, Pool Enclosure, Pergola, Screen Room, Shed, Sun Rooms) does not include a ground-mount-PV category, and the Trade Permit's SOLAR section is silent on mounting type

https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Building_Permit_20260126_final.pdf

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Utility-specified, not a City rule: FPL requires a manual disconnect of the visible load-break type for Tier 2/3 systems (>10 kW AC), mounted separate from but adjacent to the FPL meter socket, lockable with a single FPL padlock, and readily accessible to FPL at all times. Tier 1 (<=10 kW AC — the great majority of residential installs) is NOT stated by FPL as requiring this dedicated disconnect at all

Why the confidence is not higherFPL Net Metering Guidelines, verbatim: 'Tier 2 and tier 3 renewable generation systems require a manual disconnect switch of the visible load break type... The manual disconnect switch shall be mounted separate from, but adjacent to, the FPL meter socket... capable of being locked in the open position with a single FPL utility padlock.' No equivalent mandatory clause is stated for Tier 1 on this page

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal or Phone — inspections can be requested online via the EnerGov Permit Portal (Permit Details page > 'Request' button), or by phone to the Inspection Line (239) 444-6170 / field inspectors' cell numbers listed on the CD staff directory 78% · Portal Inspection Request Guide (2024) + department procedures handout
    • How much notice is required? By 6:00 PM the business day before the requested inspection date (stated for the phone-booking route); the current Portal Inspection Request Guide does not itself state a cutoff time for online-submitted requests 65% · department procedures handout (2024)
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes — the City's own (contracted) Building Inspectors perform final solar/electrical inspections 80% · department staff directory
    • If delegated, to whom? Not delegated for building/electrical (City's own Building Inspectors perform these, see q52). Fire-related permits/inspections ARE delegated to the Estero Fire Rescue District, an independent special district — its own current permit-procedures document instructs 'Scheduling Inspection(s): Call 239-390-8000' (the District's own number, not the City's) 75% · Estero Fire Rescue District permit-procedures handout (hosted by City CD dept.)
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    Nothing recorded for City of Bonita Springs on this step yet — 2 questions checked and found unpublished. The guidance above is general.

  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? No — no published inspection checklist specific to solar/PV was found 70% · Residential Plan Review Checklist (7 Jul 2016) — no PV content
    • What must be on site at inspection? A recorded Notice of Commencement (jobs ≥$5,000), the permit itself posted at eye level and visible from the road, and a set of the approved plans on site at time of inspection; a completed Solar Truss Affidavit if applicable 78% · department procedures handout (2024)
    • Does the inspector verify labels and listings? Not stated as a written policy in any reviewed document; inferred as standard NEC-compliance inspection practice but not confirmed by a City statement 45% · absence across full reviewed document set
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? Final (passed final inspection) — for a Trade Permit retrofit (not new construction), no separate Certificate of Occupancy is issued; the customer's proof of the passed/approved permit (a portal screenshot or permit printout) is what is furnished to the utility for PTO 68% · utility net-metering guidelines page + department procedures handout
    • Who notifies the utility for PTO? Installer/customer — the property owner or their installer submits proof of the approved, passed-inspection permit directly to FPL as part of the interconnection application; the City does not proactively notify FPL for solar PTO the way it notifies for new-construction permanent power at Certificate of Occupancy 72% · utility net-metering guidelines page
    • Is there a re-inspection fee? $50.00 per re-inspection 90% · fee schedule (Resolution 25-129)
    • How are corrections issued and cleared? Rejected plans trigger written/phone/email notification; corrections are re-submitted in person at the Permit Intake Counter for normal-track reprocessing. Failed field inspections incur the $50 re-inspection fee and require a new inspection request via the Portal or phone 70% · department procedures handout (2024)

14 questions answered against City of Bonita Springs’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal or Phone — inspections can be requested online via the EnerGov Permit Portal (Permit Details page > 'Request' button), or by phone to the Inspection Line (239) 444-6170 / field inspectors' cell numbers listed on the CD staff directory

Why the confidence is not higherPortal route verbatim from the 6/24/2024 Inspection Request Guide ('From the Permit Details page, click the Request button to request a single inspection'); phone route verbatim from the 2024 Residential Permitting Procedures ('You must call for inspections. Please call 239.444.6170...') and the CD Staff Directory listing 'Call for Inspections (239) 444-6170'

Portal Inspection Request Guide (2024) + department procedures handout checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Permit_Portal_Inspection_Request_Guide_20240624.pdf

Q50 How much notice is required? Core Booking & scheduling

By 6:00 PM the business day before the requested inspection date (stated for the phone-booking route); the current Portal Inspection Request Guide does not itself state a cutoff time for online-submitted requests

Why the confidence is not higherVerbatim from the 2024 Residential Permitting Procedures: 'Please call 239.444.6170 to schedule an inspection by 6pm the day prior.' Deduction: this figure is from the phone-booking procedures document; the newer Portal guide (6/24/2024) gives no cutoff time of its own, so it is not certain the same cutoff applies to portal-submitted requests

department procedures handout (2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Permitting_Procedures_20240105_final.pdf

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Nothing published by this authority.

Where we lookedNo AM/PM window or same-day-inspection language was found in the 2024 Residential Permitting Procedures or the 6/24/2024 Portal Inspection Request Guide

https://www.cityofbonitaspringscd.org/forms/Permit_Portal_Inspection_Request_Guide_20240624.pdf

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes — the City's own (contracted) Building Inspectors perform final solar/electrical inspections

Why the confidence is not higherCD Staff Directory lists a Chief Building Official and eight named 'Building Inspector' positions under 'Building and Inspections', each with a direct phone extension; inspections are not delegated to an outside agency for building/electrical trades (fire is delegated separately — see q53)

department staff directory checked 2026-09-12 https://www.cityofbonitaspringscd.org/about/staff.html

Q53 If delegated, to whom? Core Who inspects

Not delegated for building/electrical (City's own Building Inspectors perform these, see q52). Fire-related permits/inspections ARE delegated to the Estero Fire Rescue District, an independent special district — its own current permit-procedures document instructs 'Scheduling Inspection(s): Call 239-390-8000' (the District's own number, not the City's)

Why the confidence is not higherVerbatim from the Estero Fire Rescue District 'New Construction / Required Fire Permits' handout, hosted on the City's own current Community Development forms page

Estero Fire Rescue District permit-procedures handout (hosted by City CD dept.) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Estero_Fire_Permit_Application.pdf

Q54 Which inspections are required, and in what order? Core Stages & sequence

Nothing published by this authority.

Where we lookedNo PV-specific ordered inspection sequence (e.g., rough-in, mid-roof, final) is published in the Trade Permit Application, Residential Permitting Procedures, or Portal Inspection Request Guide — all three were read in full and none lists inspection stages by name for solar

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedNo mid-roof or rough-in PV inspection is named in any reviewed document; the only roof-related affidavits found (504 Roof Inspection Affidavit, Solar Truss Affidavit) are self-certifications submitted by the applicant, not a scheduled City inspection stage

https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q56 Does the inspector verify labels and listings? Core What is checked

Not stated as a written policy in any reviewed document; inferred as standard NEC-compliance inspection practice but not confirmed by a City statement

Why the confidence is not higherNo City document (Trade Permit App, Residential Permitting Procedures, FAQ, Portal guides) states that inspectors specifically verify labels/listings as a checklist item

absence across full reviewed document set checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Trade_Permit_20260127_final.pdf

Q57 Is there a published inspection checklist? Core What is checked

No — no published inspection checklist specific to solar/PV was found

Why the confidence is not higherChecked the CD Forms page (Forms.html) and all three category pages (building_residential.html, building_general.html, building_commercial.html) plus the standalone 'Residential Plan Review Checklist' (7/7/2016) — that checklist contains zero occurrences of 'solar' or 'photovoltaic' despite containing detailed electrical-fixture items ('Are all electrical fixtures shown?'), confirming the search mechanism works (positive control 'electrical' = hit; fabricated control 'zzqqx' = 0 hits) and the absence is real for that document

Residential Plan Review Checklist (7 Jul 2016) — no PV content checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Residential_Plan_Review_Checklist_20160707.pdf

Q58 What must be on site at inspection? Core Documents on site

A recorded Notice of Commencement (jobs ≥$5,000), the permit itself posted at eye level and visible from the road, and a set of the approved plans on site at time of inspection; a completed Solar Truss Affidavit if applicable

Why the confidence is not higher2024 Residential Permitting Procedures: 'POSTING THE PERMIT: Permits must be posted at eye-level, visible from the road and protected from the weather. There must also be a set of the approved plans on the job at the time of inspection(s)'; NOC requirement stated on the Trade Permit Application itself ('All Jobs Over $5,000...Require an NOC before the First Inspection')

department procedures handout (2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Permitting_Procedures_20240105_final.pdf

Q59 Is there a re-inspection fee? Corrections & re-inspection

$50.00 per re-inspection

Why the confidence is not higherStated identically in two City sources: Fee Resolution 25-129 Exhibit A ('Permit - Reinspection $50.00') and the 2024 Residential Permitting Procedures ('When an inspection has failed, a fee will be charged for all recalls and turn-downs. Fees are $50.00 per re-inspection')

fee schedule (Resolution 25-129) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Resolution-No._25-129_Community_Development_Building_Permit_Fee_Schedule.pdf

Q60 How are corrections issued and cleared? Corrections & re-inspection

Rejected plans trigger written/phone/email notification; corrections are re-submitted in person at the Permit Intake Counter for normal-track reprocessing. Failed field inspections incur the $50 re-inspection fee and require a new inspection request via the Portal or phone

Why the confidence is not higher2024 Residential Permitting Procedures: 'REJECTED PLANS: ...Customer will be notified in writing, by phone or email... RE-SUBMITTING REJECTED PLANS: ...re-submittal of rejected plans must be made at the Permit Intake Counter and will be processed through the normal procedure time'

department procedures handout (2024) checked 2026-09-12 https://www.cityofbonitaspringscd.org/forms/Bld_Residential_Permitting_Procedures_20240105_final.pdf

Q61 What is issued on pass? Core Final sign-off & PTO

Final (passed final inspection) — for a Trade Permit retrofit (not new construction), no separate Certificate of Occupancy is issued; the customer's proof of the passed/approved permit (a portal screenshot or permit printout) is what is furnished to the utility for PTO

Why the confidence is not higherInferred from two sources: the 2024 Residential Permitting Procedures ties Certificate of Occupancy specifically to new-construction occupancy ('The building may not be occupied until the final inspection has been completed and a Certificate of Occupancy is issued'), which does not apply to an existing occupied home getting a Trade Permit; and FPL's Net Metering Guidelines describe the deliverable as 'a copy of the approved permit or a screen print from the local authority's website indicating the permit has been approved,' not a CO

utility net-metering guidelines page + department procedures handout checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer/customer — the property owner or their installer submits proof of the approved, passed-inspection permit directly to FPL as part of the interconnection application; the City does not proactively notify FPL for solar PTO the way it notifies for new-construction permanent power at Certificate of Occupancy

Why the confidence is not higherFPL Net Metering Guidelines: 'a customer should provide a copy of the approved permit or a screen print...' places the burden on the customer/installer. Contrast the City's own new-construction language, 'at which time the power company will be notified to connect permanent power,' which describes a different (non-solar, CO-triggered) process

utility net-metering guidelines page checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 70%

No — the City specifies no placard wording of its own; FPL (the confirmed utility) sets the applicable wording and explicitly requires the installer to 'contact FPL for approval of...the verbiage...of the sign' before finalizing the design

Size, colour & material 52%

Not specified by the City. FPL's guideline does not give an exact letter height, colour or material for the disconnect-location sign or warning sign beyond requiring FPL's prior approval of the verbiage; for battery storage, only 'a placard must be permanently affixed' is specified with no dimensions

Where they go 78%

At the meter/disconnect location: FPL's disconnect-location sign and energization-warning sign are posted at the meter, with the Tier 2/3 manual disconnect itself mounted separate from but adjacent to the meter socket; the battery-storage placard is permanently affixed to the meter enclosure

What the utility wants on top 85%

Yes — FPL (the confirmed utility) specifies requirements beyond anything the City asks for: a visible-load-break manual disconnect switch mandatory for Tier 2/3 systems (>10kW), mounted separate from but adjacent to the FPL meter socket, lockable with a single FPL padlock, plus a location sign and an energization warning sign, with FPL's prior approval required for sign verbiage/placement; and a permanent 'Battery storage utilized in this facility' placard for any battery installation

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Required placards
Apply for a Building Permit - City of Bonita Springs Skip to Content {1} ##LOC[OK]## MENU Apply for a Building Permit Side Navigation Skip Sidebar Navigation Apply for a Building Permit How Do I? Contact Procurement Do Business in the City Find out what District I'm in? Citizen Request Fair Housing See Employment Opportunities Submit a Records Request View the Budget Watch a Meeting Live Watch a V
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
City
County
Lee County
Regions covered
Authority Contact
Building Department
Direct Phone
(239) 444-6150