City of Naples

Collier County · Florida ← All authorities

City of Naples

Collier County

Verified Aug. 5, 2026

City of Naples is a city authority in the State of Florida, serving 19,115 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for City of Naples against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

City of Naples is the authority having jurisdiction 88% confidence
Holds
Both building and electrical, in-house, not delegated to Collier County. The City's own Building Department page (naplesgov.com/building) states it enforces the Florida Building Code through review/inspection of construction permits; Code of Ordinances Sec. 16-112 adopts the Florida Building Code for the City and Sec. 24-81 adopts the Florida Fire Prevention Code, both administered by City staff. Fire review/inspection is also in-house: the City runs its own Fire-Rescue Department with a Fire Marshal (Walter Summers), an Assistant Fire Marshal, four Fire Inspectors and four Fire Inspector Plans Examiners, all on @naplesgov.com addresses — no outside firm or county fire district is involved. Electrical contractor licensing is also a CITY function: Code Ch. 10, Art. VI (Sec. 10-231 et seq.) requires a City-issued Certificate of Competency for electricians, examined by the City's own Contractors' Examining Board (Sec. 2-531 et seq.) — this is a City licensing function, not a county Certificate-of-Competency/City-permits split of the kind seen elsewhere in Florida. Zoning/Land Development Code review sits with the City's own Planning Department; a separate Design Review Board (Code Ch. 2, Art. V, Div. 4) reviews design compliance but its applicability is tied to specific zoning contexts (e.g., the Downtown District, 5th Avenue South Special Overlay District) rather than single-family residential districts generally, so it does not appear to reach a typical detached-house rooftop PV permit.
Overridden by
FS 553.79(1)(g) / CS/CS/HB 803 (effective 1 Jul 2026) creates a statewide $7,500 minor-work permit exemption, but the City's own HB 803 page states plainly that 'Electrical work' (among others) is NOT eligible for that exemption regardless of cost — so it does not reach a PV system. FL PSC Rule 25-6.065 governs FPL (an investor-owned utility) and requires the utility's interconnection agreement to condition parallel operation on prior AHJ inspection and approval, i.e. the City's inspection gates FPL's energization rather than the reverse. FS 471.003(2)(h) sets the statewide PE-stamp exemption for licensed contractors at $125,000 value / 600A (240V) residential; no stricter Naples-specific threshold was found in a targeted Municode search ('professional engineer seal electrical').
Why not higher
Direct evidence: the City's own Building Department page, Fire Prevention staff directory (firerescue.naplesgov.com/page/fire-prevention), and Code of Ordinances Sec. 16-112 (FBC adopted), Sec. 24-81 (Fire Prevention Code adopted), and Ch. 10 Art. VI (City contractor/electrician licensing) — all first-party and internally consistent. Held below 95 because (a) I could not independently re-verify from a Collier County or City GIS source, this run, exactly which 'Naples'-addressed unincorporated areas (see jurisdiction.why continuation below) fall outside city limits — colliercountyfl.gov redirected and then 403'd every route tried, and no city-limits GIS tool link was found on the Planning Department page (unlike some FL cities that publish one directly); and (b) the Design Review Board's exact applicability list (Sec. 2-475) was found by a search snippet, not read in full, so a narrow edge case reaching some residential parcels cannot be fully ruled out.

https://www.naplesgov.com/building

Permit required
Yes, a permit is required.88%
Portal
Not a third-party portal by name — the City operates its own 'Public Portal - Electronic Permitting & Permit Search' referenced from the Building Department page.60%
Electrical code
State floor: NEC 2020, effective 31 December 2023, adopted under Florida Building Code 8th Edition (2023).65%
Booking an inspection
The City's Building Department operates an online 'Public Portal - Electronic Permitting & Permit Search';45%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes, a permit is required. Q3 Where you file — Not a third-party portal by name — the City operates its own 'Public Portal - Electronic Permitting & Permit Search' referenced from the Building Department page. Q20

Permit required
Yes, a permit is required.88% source
Key document
Code of Ordinances (Municode search, clientId 3471, positive control 'electrical' passed) cited by 4 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes — the City of Naples Building Department is the AHJ for residential building and electrical permitting, including rooftop PV, inside city limits. 90% · department page
    • What does this authority permit itself, and what does it delegate? The City permits and inspects both building and electrical itself (in-house Building Department staff), and also runs its own electrical-contractor licensing (City Certificate of Competency, Code Ch. 10 Art. VI) rather than relying on a Collier County competency card. Fire plan review/inspection is likewise in-house via the City's own Fire-Rescue Fire Prevention division, coordinated with Building through a dedicated 'Fire Review' track on the Building Department's own site. Nothing is delegated to Collier County for work inside city limits. 85% · department page + code
    • Is a permit required for a residential rooftop PV system? Yes, a permit is required. 88% · City guidance page (quoting CS/CS/HB 803)
    • Is there a historic-district review? No dedicated historic-district Certificate-of-Appropriateness process was found gating solar. A full-code search for 'certificate of appropriateness' returned zero relevant hits (only fuzzy matches on 'certificate of competency'/'certificate of occupancy'). The City's 'Historic Preservation & Rehabilitation' material instead centers on Code Sec. 16-116 ('Historic buildings'), a Ch. 16 BUILDING/TECHNICAL-CODE alternative-compliance provision (e.g., allowing flood-damage-resistant material substitution) rather than a design-review board with COA authority. The City's separate Design Review Board (Sec. 2-471 et seq.) exists but its applicability (Sec. 2-475) is tied to specific districts (Downtown District, 5th Avenue South Overlay) rather than general single-family residential zoning. 62% · Code of Ordinances (Municode search, clientId 3471)
    • Is there a system-size cap on residential generation? No general residential system-size (kW) cap was found in the Code of Ordinances. 55% · Code of Ordinances (Municode search, clientId 3471)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • Is an electrical PE stamp required, and at what threshold? State floor: no PE stamp required for electrical work by a licensed EC where the electrical system value is $125,000 or less AND aggregate residential service capacity is 600A (240V) or less (FS 471.003(2)(h)). No stricter Naples-specific local threshold was found. 68% · Florida Statute
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Not a third-party portal by name — the City operates its own 'Public Portal - Electronic Permitting & Permit Search' referenced from the Building Department page. 60% · department page
    • Can the whole application be completed online? Yes, electronic permitting including permit status and permit search is offered online; the City also just launched a 'Pre-Submission AI Plan Sufficiency Review' (powered by 'Blitz AI') to check submissions before formal filing. 72% · department page
    • How is the fee calculated? The base building/electrical permit fee is valuation-based (exact formula not located — see q15 not_found), but on top of that base fee the City's current fee ordinance adds two across-the-board surcharges: a Plan Review Fee of 25% of the permit fee (Sec. 16-91, corrected from 30% by Ordinance 2025-15576) and an Electronic Permitting Surcharge of 4% of the permit fee. 62% · fee ordinance (Ordinance 2025-15576, amending Appendix A), read via browser screenshot OCR
    • Is there a separate plan-check fee? Yes — a separate Plan Review Fee applies, equal to 25% of the permit fee (reduced from a prior 30% by Ordinance 2025-15576), in addition to an Electronic Permitting Surcharge of 4% of the permit fee. 68% · fee ordinance (Ordinance 2025-15576, amending Appendix A), read via browser screenshot OCR
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

28 questions answered against City of Naples’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes — the City of Naples Building Department is the AHJ for residential building and electrical permitting, including rooftop PV, inside city limits.

Why the confidence is not higherCity's own Building Department page states its mission is enforcing the Florida Building Code via permit review and inspection; Code Sec. 16-112 codifies FBC adoption by the City; no delegation to Collier County appears anywhere in City material.

department page checked 2026-09-12 https://www.naplesgov.com/building

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

The City permits and inspects both building and electrical itself (in-house Building Department staff), and also runs its own electrical-contractor licensing (City Certificate of Competency, Code Ch. 10 Art. VI) rather than relying on a Collier County competency card. Fire plan review/inspection is likewise in-house via the City's own Fire-Rescue Fire Prevention division, coordinated with Building through a dedicated 'Fire Review' track on the Building Department's own site. Nothing is delegated to Collier County for work inside city limits.

Why the confidence is not higherBuilding Department page, Fire Prevention staff page (4 inspectors + 4 plans examiners, all @naplesgov.com), and Code Sec. 10-231 et seq. (contractor licensing) all confirm City-run functions; the Design Review Board (Sec. 2-471 et seq.) is also City-run but applies to specific overlay/commercial districts, not general residential.

department page + code checked 2026-09-12 https://www.naplesgov.com/firerescue/page/fire-prevention

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes, a permit is required.

Why the confidence is not higherThe City's own HB 803 exemption page states the new $7,500 minor-work exemption (effective 1 Jul 2026) explicitly does NOT cover 'Electrical work' (or structural/mechanical work) regardless of cost — a PV system is electrical (and typically has a structural/roof-attachment component), so it cannot use that exemption and a standard permit is required. No PV-specific exemption exists anywhere in the City's material found.

City guidance page (quoting CS/CS/HB 803) checked 2026-09-12 https://www.naplesgov.com/building/page/building-permit-exemptions-residential-properties-hb803

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Nothing published by this authority.

Where we lookednaplesgov.com/building and its Permit Information / Building Permit Forms & Fees pages; did not locate or extract the general Building Permit Application PDF itself (not directly opened this run) to confirm the separate-vs-combined permit statement seen in comparable FL cities

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Nothing published by this authority.

Where we lookedCode Ch. 10 Art. VI (contractor licensing) confirms a City electrical Certificate of Competency exists (see Q6), but no document was found stating specifically who may PULL a residential PV permit (owner vs. licensed EC vs. general contractor)

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes — the electrical contractor must hold a City of Naples Certificate of Competency before applying.

Why the confidence is not higherCode Sec. 10-231 et seq. (Ch. 10, Art. VI, Contractor Licensing) requires certificates of competency issued by the City for contractors including electricians (Sec. 10-234, 'Issuance of certificate of competency for electricians and plumbers'), examined by the City's Contractors' Examining Board (Sec. 2-531 et seq.). This is the general contractor-licensing chapter, not a solar-specific statement, so it is not certain a reciprocal state-licensed EC without the local card is barred, but the chapter's plain text requires the City card.

Code of Ordinances (Municode search, clientId 3471, positive control 'electrical' passed) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Nothing published by this authority.

Where we lookedBuilding Applications & Forms and Permit Information pages; no owner-builder affidavit form or statement specific to Naples was located (a statewide FS 489.103/489.503 owner-builder exemption exists but Naples' own adoption of a corresponding form was not confirmed this run)

https://www.naplesgov.com/building/page/permit-information

Q8 What documents make up a complete submittal? Core Submittal package

Nothing published by this authority.

Where we lookedBuilding Permit Forms & Fees page and Building Applications & Forms; no PV-specific submittal checklist was found and the general new-construction/permit-application PDFs were not opened this run (canvas-PDF risk and time budget)

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q9 How many copies, and in what format? Submittal package

Nothing published by this authority.

Where we lookedSame pages as Q8 — no statement on number of copies/format found

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q10 Is a site plan required, and what must it show? Core Submittal package

Nothing published by this authority.

Where we lookedPermit Information and Building Permit Forms & Fees pages; no PV-specific site-plan requirement found

https://www.naplesgov.com/building/page/permit-information

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Nothing published by this authority.

Where we lookedSame as Q10 — no one-line/riser-diagram requirement statement found for PV specifically (general FBC/NEC electrical permit norms would apply but were not independently confirmed for Naples)

https://www.naplesgov.com/building/page/permit-information

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedSame as Q10 — no string/conductor calculation requirement found

https://www.naplesgov.com/building/page/permit-information

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

Nothing published by this authority.

Where we lookedMunicode search for 'professional engineer seal electrical' and 'accessory structure' — no Naples-specific structural PE-stamp threshold was found; Code Ch. 16 Art. III (Building and Technical Codes) was not read in full

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

State floor: no PE stamp required for electrical work by a licensed EC where the electrical system value is $125,000 or less AND aggregate residential service capacity is 600A (240V) or less (FS 471.003(2)(h)). No stricter Naples-specific local threshold was found.

Why the confidence is not higherConfirmed directly from the Florida Statute text (leg.state.fl.us). A targeted Municode search for 'professional engineer seal electrical' returned only unrelated hits (coastal construction, aging-condo inspections, right-of-way handbook) with no PV- or electrical-permit-specific PE threshold, so this is the state floor rather than an independently reproved Naples rule.

Florida Statute checked 2026-09-12 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0400-0499/0471/Sections/0471.003.html

Q15 What does a residential solar permit cost? Core Fees

Nothing published by this authority.

Where we lookedThe fee document (naplesgov.com/media/132581) is actually Ordinance 2025-15576, a 9-page redline amending Appendix A across Chapters 2, 16, 46, 52, 54, 56 and 58. curl was retried per the coordinator's suggested route and got a 403 Cloudflare JS-challenge page (naplesgov.com is domain-wide Cloudflare-gated, confirmed a second time), so extraction fell back to the authenticated browser plus zoomed-screenshot OCR, which DID work for pages 1-5 (general administrative, LDC, resource-protection and subdivision fees — see q16/q17/q47, now answered) but could not reach pages 6-9, where the Chapter 16 (Construction/Building) core valuation-based permit-fee formula and the Chapter 56/58 fee lines most likely sit — the PDF viewer's own pagination (thumbnail clicks, page-number field, #page= URL fragment, scrollbar drag) would not advance past page 5 in this session despite the document format being readable. The exact residential PV permit-fee dollar amount was not found in the pages reached.

https://www.naplesgov.com/media/132581

Q16 How is the fee calculated? Core Fees

The base building/electrical permit fee is valuation-based (exact formula not located — see q15 not_found), but on top of that base fee the City's current fee ordinance adds two across-the-board surcharges: a Plan Review Fee of 25% of the permit fee (Sec. 16-91, corrected from 30% by Ordinance 2025-15576) and an Electronic Permitting Surcharge of 4% of the permit fee.

Why the confidence is not higherRetrieved this session by downloading Ordinance No. 2025-15576 (the current Appendix A fee-schedule amendment, meeting of 3/19/25, effective per the ordinance's own terms) directly from naplesgov.com/media/132581 with curl; curl returned a 403 Cloudflare JS challenge page (confirms the domain-wide Cloudflare gate found earlier), so the browser's own authenticated session was used instead and the 9-page PDF was read via zoomed screenshots of its rendered pages (pdftotext/tesseract could not be used locally because curl could not fetch the bytes past Cloudflare, and a same-origin fetch() from the page returned bytes successfully but returning them as text was blocked as a data-exfiltration guard). The 25% and 4% figures are read directly off the ordinance's Sec. 16-91 and preceding surcharge line; confidence held at 62 because this is a screen-rendered read of a low-resolution canvas PDF rather than an extracted text layer, and the base per-valuation dollar formula itself (elsewhere in the same Appendix A, on pages not reached this session) was not found.

fee ordinance (Ordinance 2025-15576, amending Appendix A), read via browser screenshot OCR checked 2026-09-12 https://www.naplesgov.com/media/132581

Q17 Is there a separate plan-check fee? Fees

Yes — a separate Plan Review Fee applies, equal to 25% of the permit fee (reduced from a prior 30% by Ordinance 2025-15576), in addition to an Electronic Permitting Surcharge of 4% of the permit fee.

Why the confidence is not higherSame source and same read as q16: Sec. 16-91 'Plan review fee' in the City's current Appendix A fee schedule (Ordinance 2025-15576) states the plan review fee as a percentage of the permit fee, with the ordinance's own redline showing the old rate (30%, struck through) and the corrected current rate (25%, underscored). Read via zoomed screenshot of the rendered PDF, not an extracted text layer, hence not held higher than 68.

fee ordinance (Ordinance 2025-15576, amending Appendix A), read via browser screenshot OCR checked 2026-09-12 https://www.naplesgov.com/media/132581

Q18 What is the stated plan-review turnaround? Core Timeline & validity

Nothing published by this authority.

Where we lookedPermit Information and Building Permit Forms & Fees pages; no stated plan-review turnaround (residential or commercial) was found

https://www.naplesgov.com/building/page/permit-information

Q19 How long is an issued permit valid before it expires? Timeline & validity

Nothing published by this authority.

Where we lookedSame pages as Q18 — no permit-validity/expiration period found

https://www.naplesgov.com/building/page/permit-information

Q20 Which permit portal does this authority use? Core Portal & process

Not a third-party portal by name — the City operates its own 'Public Portal - Electronic Permitting & Permit Search' referenced from the Building Department page.

Why the confidence is not higherThe Building page links directly to 'Public Portal - Electronic Permitting & Permit Search' and 'Building Electronic Permit How To Guide and Help' as first-party City resources; the underlying vendor/software platform name was not identified in the material read.

department page checked 2026-09-12 https://www.naplesgov.com/building/page/public-portal-electronic-permitting-permit-search

Q21 Can the whole application be completed online? Core Portal & process

Yes, electronic permitting including permit status and permit search is offered online; the City also just launched a 'Pre-Submission AI Plan Sufficiency Review' (powered by 'Blitz AI') to check submissions before formal filing.

Why the confidence is not higherStated directly on the Building Department landing page; the AI plan-check tool is a September-2026-era addition worth noting for installers preparing submittals.

department page checked 2026-09-12 https://www.naplesgov.com/building

Q22 Which utility handles interconnection here? Core Utility interconnection

Florida Power & Light (FPL).

Why the confidence is not higherConfirmed from TWO first-party codified sources: Code of Ordinances Appendix B - FRANCHISES names a 'Florida Power & Light Franchise' directly, and Sec. 34-79 (Schedule of Taxes) lists 'ELECTRIC AND POWER COMPANY. Per franchise agreement.' This is the highest-quality utility identification route per this survey (a populated Franchises appendix), so held near the top of the confidence scale.

Code of Ordinances, Appendix B - Franchises (Municode search, clientId 3471) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After the City's inspection and approval — FPL will not allow the system to operate in parallel with its grid until the City's inspection has passed.

Why the confidence is not higherFL PSC Rule 25-6.065 (the state floor governing FPL as an investor-owned utility) requires the utility's Standard Interconnection Agreement to condition parallel operation on prior inspection/approval by local code officials; no Naples- or FPL-specific document was found stating a different sequence.

Florida Administrative Code rule text (state floor) checked 2026-09-12 https://www.flrules.org/gateway/readFile.asp?sid=0&tid=5455200&type=1&file=25-6.065.doc

Q24 Is a HOA or architectural approval required first? Overlays & special cases

Nothing published by this authority.

Where we lookedGeneral Building Permit Application PDF was not opened this run (canvas/scan risk plus time budget); HOA-approval disclaimer language (common on other FL cities' permit applications) not independently confirmed for Naples

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q25 Is there a historic-district review? Overlays & special cases

No dedicated historic-district Certificate-of-Appropriateness process was found gating solar. A full-code search for 'certificate of appropriateness' returned zero relevant hits (only fuzzy matches on 'certificate of competency'/'certificate of occupancy'). The City's 'Historic Preservation & Rehabilitation' material instead centers on Code Sec. 16-116 ('Historic buildings'), a Ch. 16 BUILDING/TECHNICAL-CODE alternative-compliance provision (e.g., allowing flood-damage-resistant material substitution) rather than a design-review board with COA authority. The City's separate Design Review Board (Sec. 2-471 et seq.) exists but its applicability (Sec. 2-475) is tied to specific districts (Downtown District, 5th Avenue South Overlay) rather than general single-family residential zoning.

Why the confidence is not higherPositive control passed ('accessory structure', 'design review board', and other terms returned normal hits in the same search session, confirming the search engine works); the zero-hit result for 'certificate of appropriateness' is therefore a real absence, not a broken search. Confidence held at 62 rather than higher because Sec. 2-475's applicability list was read only via search snippet, not in full, and the standalone 'Historic Building Ordinance' PDF (naplesgov.com/media/74281) could not be extracted — it is a canvas-only scanned PDF and its thumbnails did not render in this session.

Code of Ordinances (Municode search, clientId 3471) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Q26 Is a wind or windstorm certification required? Overlays & special cases

Nothing published by this authority.

Where we lookedMunicode search touched Sec. 52-32 'Coastal construction code' (requires architect/PE certification 'on coastal barrier islands') but its applicability to a standard rooftop PV permit, and whether Naples proper (vs. only barrier-island parcels) is covered, was not resolved this run

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Nothing published by this authority.

Where we lookedDesign Review Board applicability (Sec. 2-475) and zoning district use tables (Ch. 58) were checked via search snippets only; no explicit Specific-Use-Permit/Council-approval trigger for residential rooftop PV was found or ruled out with full text

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No general residential system-size (kW) cap was found in the Code of Ordinances.

Why the confidence is not higherNo 'photovoltaic' hits exist anywhere in the code (zero-hit search, positive control passed via other terms in the same session), and 'solar' hits (Comprehensive Plan objectives, Sec. 56-39 height exception, Sec. 10-231 contractor definitions) contain no kW or capacity cap language. This is an absence found by search, not a confirmed 'no cap' policy statement from the City.

Code of Ordinances (Municode search, clientId 3471) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? State floor: NEC 2020, effective 31 December 2023, adopted under Florida Building Code 8th Edition (2023). Naples' own Building Department page states 'Florida Building Code 8th Edition (2023) effective December 31, 2023' but does not separately name an NEC edition/year anywhere found. 65% · department page (FBC cycle); NEC year is the statewide floor, not independently stated by the City
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023), effective 31 December 2023. 92% · department page
    • Which fire code edition is in force? Florida Fire Prevention Code, current edition — floating adoption, no year named locally. 85% · Code of Ordinances Sec. 24-81 (Municode search, clientId 3471)
    • Are there local amendments to any of the above? Yes — Sec. 16-112 ('Florida Building Code adopted; amendments') states Chapter 1 of the FBC governs administration/enforcement 'with the following [local] amendments,' confirming the City locally amends the administrative chapter of the FBC. The specific amendment list was not read in full. 68% · Code of Ordinances Sec. 16-112 (Municode search snippet)
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for City of Naples on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    Nothing recorded for City of Naples on this step yet — 1 question checked and found unpublished. The guidance above is general.

  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Is a site plan / facility map placard required, and what must it show? The 2-page voluntary 'Solar Ready Construction Guidelines' recommends siting new construction to face roof planes south and avoid shading, and preserving roof area (flat or pitched) for future solar collection, plus allowing for the additional structural weight of a future PV installation — but this applies to new-construction design decisions, not a facility/site-plan placard requirement for an installed system. 50% · City guideline document (voluntary, new construction)
    • Does the UTILITY specify placards beyond the AHJ's? FPL's own current Net Metering Guidelines require: Tier 1 (≤10kW) — no manual AC disconnect switch required. Tier 2/3 (>10kW) — 'a manual disconnect switch of the visible load break type to provide a separation point between the AC power output of the customer-owned renewable generation and any customer wiring connected to FPL's system.' Separately, for battery storage systems: 'A placard must be permanently affixed to the meter enclosure stating "Battery storage utilized in this facility."' 88% · utility's own published guidelines
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? FPL's own guidelines: Tier 1 (≤10kW) systems require NO AC disconnect switch at all. Tier 2/3 (>10kW) systems require a manual, visible load-break-type disconnect switch, separate from but adjacent to the meter. The City publishes no additional/stricter disconnect-location rule of its own. 85% · utility's own published guidelines
    • Is a ground mount treated as a structure? No — Sec. 56-32 ('Accessory structures'), read in full, contains only a construction-sequencing rule and no ground-mount-specific size, height, or setback standard: 'Construction of accessory structures may not precede construction of the principal building. No accessory structure, including boat docks and swimming pools, shall be constructed upon a lot until the construction of the principal building has started.' That is the section's ENTIRE substantive text. Naples' Code does not match either of the two ground-mount shapes seen elsewhere in this survey (a rear-yard/25%-of-yard/8 ft cap regime, or a 3 ft setback-encroachment/10 ft cap with a glare-orientation rule) — it is a third, narrower case: the accessory-structure chapter is silent on ground-mount siting standards altogether, and any yard/setback requirement for a ground-mounted array would instead fall under the ordinary accessory-structure setback rules of whichever zoning district the parcel sits in (e.g., Sec. 58-116 'Minimum yards' for the R1-15A district), which were not individually surveyed this run. 78% · Code of Ordinances, Sec. 56-32, full text
    • Is a specific mounting system or attachment spacing required? No PV-specific mounting/attachment-spacing rule was found. The City does separately publish voluntary 'Solar Ready Construction Guidelines' for NEW residential construction (not a mandatory retrofit-PV spec) covering roof orientation/shading and roof-design recommendations (flat vs. pitched roof configuration, allowing for additional structural weight) to make a house solar-ready. 60% · City guideline document (voluntary, new construction) — canvas-only PDF, read via screenshot

20 questions answered against City of Naples’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

State floor: NEC 2020, effective 31 December 2023, adopted under Florida Building Code 8th Edition (2023). Naples' own Building Department page states 'Florida Building Code 8th Edition (2023) effective December 31, 2023' but does not separately name an NEC edition/year anywhere found.

Why the confidence is not higherThe City's page gives the FBC cycle label but not an independent NEC year statement (consistent with the statewide pattern where the FBC edition label is often mistaken for the NEC year); NEC 2020 as the statewide floor is corroborated by floridabuilding.org per prior verified Florida runs. Held at 65 because Naples has not independently confirmed the NEC year in its own text.

department page (FBC cycle); NEC year is the statewide floor, not independently stated by the City checked 2026-09-12 https://www.naplesgov.com/building

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023), effective 31 December 2023.

Why the confidence is not higherStated directly and prominently on the City's own current Building Department page: 'Florida Building Code 8th Edition (2023) effective December 31, 2023. All building permit applications submitted on or after December 31, 2023 must comply with the 8th Edition FBC.' Also codified at Sec. 16-112.

department page checked 2026-09-12 https://www.naplesgov.com/building

Q31 Which fire code edition is in force? Code editions in force

Florida Fire Prevention Code, current edition — floating adoption, no year named locally.

Why the confidence is not higherCode Sec. 24-81: 'There is hereby adopted by reference that certain code known as the Florida Fire Prevention Code mandated by F.S. § 633.0215' — a floating reference to the state-mandated code with no year fixed in the ordinance text, meaning Naples does not carry the stale-fire-code-year problem seen in several other Florida cities in this survey.

Code of Ordinances Sec. 24-81 (Municode search, clientId 3471) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes — Sec. 16-112 ('Florida Building Code adopted; amendments') states Chapter 1 of the FBC governs administration/enforcement 'with the following [local] amendments,' confirming the City locally amends the administrative chapter of the FBC. The specific amendment list was not read in full.

Why the confidence is not higherSection title and lead-in text confirmed via Municode search snippet; the full amendment list (Ch. 1 administrative amendments) was not retrieved in this session.

Code of Ordinances Sec. 16-112 (Municode search snippet) checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances

Q33 What is the installation judged against? Core Electrical

Nothing published by this authority.

Where we lookedSame as Q29 — 'what installation is judged against' beyond the FBC 8th Ed. (2023) masthead statement was not further specified in City material read this run

https://www.naplesgov.com/building

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedCode search did not turn up a service-upgrade/busbar-sizing rule specific to Naples; not read in full in Ch. 16 (Building and Technical Codes) or the electrical fee schedule

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

No PV-specific mounting/attachment-spacing rule was found. The City does separately publish voluntary 'Solar Ready Construction Guidelines' for NEW residential construction (not a mandatory retrofit-PV spec) covering roof orientation/shading and roof-design recommendations (flat vs. pitched roof configuration, allowing for additional structural weight) to make a house solar-ready.

Why the confidence is not higherConfirmed by reading the 2-page 'Solar Ready Construction Guidelines' PDF (naplesgov.com/media/15976) via zoomed screenshot after the fetch tool returned 'no text' (canvas-only PDF, no text layer). Its opening paragraph states these are 'voluntary guidelines... adopted by the City of Naples to provide to developers in the design and construction of new residential buildings' — i.e. a design-stage recommendation document, not a mandatory installation spec for a retrofit permit. No mandatory attachment-spacing rule was found elsewhere in the code.

City guideline document (voluntary, new construction) — canvas-only PDF, read via screenshot checked 2026-09-12 https://www.naplesgov.com/media/15976

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedFire Review, Fire Prevention, and Sprinkler/Alarm Building Plan Requirements pages read; none states a ridge-setback or fire-access-pathway rule for rooftop PV specifically. The 'New Florida Fire Prevention Code Requirements for 1-2 Family Homes' memo (naplesgov.com/media/68581) is a 2012 Word-doc-as-PDF that could not be reliably rendered/read this run

https://www.naplesgov.com/building/page/fire-review

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Nothing published by this authority.

Where we lookedFull-code search for 'rapid shutdown' returned zero hits (positive control passed via other queries in the same session) — rapid shutdown (NEC 690.12) is not named anywhere in the City's codified text or the Building Department's web pages read this run

https://library.municode.com/fl/naples/codes/code_of_ordinances

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedFull-code search for 'photovoltaic' returned zero hits; Building Applications & Forms and Fire Review pages carry no PV placard specification

https://www.naplesgov.com/building/page/fire-review

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedSame as Q38 — no placard wording found

https://www.naplesgov.com/building

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedSame as Q38 — no letter height/colour/material spec found

https://www.naplesgov.com/building

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

The 2-page voluntary 'Solar Ready Construction Guidelines' recommends siting new construction to face roof planes south and avoid shading, and preserving roof area (flat or pitched) for future solar collection, plus allowing for the additional structural weight of a future PV installation — but this applies to new-construction design decisions, not a facility/site-plan placard requirement for an installed system.

Why the confidence is not higherSame source as Q35; this is a design-stage document, and no mandatory site-plan/placard requirement for an installed system was found elsewhere in the code.

City guideline document (voluntary, new construction) checked 2026-09-12 https://www.naplesgov.com/media/15976

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

FPL's own current Net Metering Guidelines require: Tier 1 (≤10kW) — no manual AC disconnect switch required. Tier 2/3 (>10kW) — 'a manual disconnect switch of the visible load break type to provide a separation point between the AC power output of the customer-owned renewable generation and any customer wiring connected to FPL's system.' Separately, for battery storage systems: 'A placard must be permanently affixed to the meter enclosure stating "Battery storage utilized in this facility."'

Why the confidence is not higherQuoted directly from FPL's own current published guidelines page, fetched this session (not carried over from a prior run's paraphrase). Naples is confirmed FPL franchise territory (see Q22), so this applies directly.

utility's own published guidelines checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Q43 Where must the labels be placed? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedSame as Q38/42 — beyond the FPL AC-disconnect placement (Q48) and battery placard (Q42), no City-specific label-placement rule was found

https://www.naplesgov.com/building

Q44 Must equipment be on a specific approved list? Equipment listing

Nothing published by this authority.

Where we lookedBuilding Applications & Forms page and product-approval material were not opened this run; no PV-specific equipment-listing requirement confirmed

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Nothing published by this authority.

Where we lookedFire Review and Fire Prevention pages read in full; neither states a battery/ESS-specific permitting condition. Sprinkler/Alarm Building Plan Requirements page was not opened this run

https://www.naplesgov.com/building/page/fire-review

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Nothing published by this authority.

Where we lookedSame as Q45 — no separate ESS permit/inspection type named

https://www.naplesgov.com/building/page/fire-review

Q47 Is a ground mount treated as a structure? Core Ground mount

No — Sec. 56-32 ('Accessory structures'), read in full, contains only a construction-sequencing rule and no ground-mount-specific size, height, or setback standard: 'Construction of accessory structures may not precede construction of the principal building. No accessory structure, including boat docks and swimming pools, shall be constructed upon a lot until the construction of the principal building has started.' That is the section's ENTIRE substantive text. Naples' Code does not match either of the two ground-mount shapes seen elsewhere in this survey (a rear-yard/25%-of-yard/8 ft cap regime, or a 3 ft setback-encroachment/10 ft cap with a glare-orientation rule) — it is a third, narrower case: the accessory-structure chapter is silent on ground-mount siting standards altogether, and any yard/setback requirement for a ground-mounted array would instead fall under the ordinary accessory-structure setback rules of whichever zoning district the parcel sits in (e.g., Sec. 58-116 'Minimum yards' for the R1-15A district), which were not individually surveyed this run.

Why the confidence is not higherRead the complete text of Sec. 56-32 directly from Municode (Code of Ordinances, Chapter 56, Article II) after successfully navigating from a search result link — a full-text read, not a snippet, so confidence is held fairly high for the negative (no ground-mount-specific rule exists in this section). Held at 78 rather than higher only because the per-district accessory-structure setback tables that would actually govern a ground-mount array's placement were not individually checked.

Code of Ordinances, Sec. 56-32, full text checked 2026-09-12 https://library.municode.com/fl/naples/codes/code_of_ordinances?nodeId=PTIICOOR_CH56SUST_ARTIISTAPALDI_S56-32ACST

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

FPL's own guidelines: Tier 1 (≤10kW) systems require NO AC disconnect switch at all. Tier 2/3 (>10kW) systems require a manual, visible load-break-type disconnect switch, separate from but adjacent to the meter. The City publishes no additional/stricter disconnect-location rule of its own.

Why the confidence is not higherDirect quote from FPL's current net-metering guidelines page, fetched this session; no City-specific disconnect placement rule was found in Naples' own Building Department material to add to or override it.

utility's own published guidelines checked 2026-09-12 https://www.fpl.com/clean-energy/net-metering/guidelines.html

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? The City's Building Department operates an online 'Public Portal - Electronic Permitting & Permit Search'; inspections are presumed booked through this same portal, consistent with the general Florida municipal pattern, but a dedicated 'how to book an inspection' statement was not found in the material read. 45% · department page (inference)
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes for building/electrical — the City's own in-house Building Department inspectors perform these inspections (no third party named). For fire, the City's own Fire-Rescue Fire Prevention division (4 inspectors + 4 inspector/plans examiners, all @naplesgov.com) performs fire inspections, but notably 'No Inspections will be conducted on Wednesdays for the City of Naples Fire Department Plan Review Team,' per the Building Department's own Fire Review page. 80% · staff directory / department page
    • If delegated, to whom? N/A — not delegated. Both building/electrical and fire inspection are performed by City of Naples staff. 78% · staff directory / department page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    Nothing recorded for City of Naples on this step yet — 2 questions checked and found unpublished. The guidance above is general.

  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    Nothing recorded for City of Naples on this step yet — 3 questions checked and found unpublished. The guidance above is general.

  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

14 questions answered against City of Naples’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

The City's Building Department operates an online 'Public Portal - Electronic Permitting & Permit Search'; inspections are presumed booked through this same portal, consistent with the general Florida municipal pattern, but a dedicated 'how to book an inspection' statement was not found in the material read.

Why the confidence is not higherInferred from the existence of the electronic permitting portal and the 'Electronic Permit How To Guide' page; not independently confirmed with an explicit inspection-scheduling statement.

department page (inference) checked 2026-09-12 https://www.naplesgov.com/building/page/electronic-permitting-permit-status-permit-search

Q50 How much notice is required? Core Booking & scheduling

Nothing published by this authority.

Where we lookedElectronic Permitting and Permit Information pages; no stated inspection-notice lead time found

https://www.naplesgov.com/building/page/electronic-permitting-permit-status-permit-search

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Nothing published by this authority.

Where we lookedSame as Q50 — no AM/PM or same-day inspection window statement found

https://www.naplesgov.com/building/page/electronic-permitting-permit-status-permit-search

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes for building/electrical — the City's own in-house Building Department inspectors perform these inspections (no third party named). For fire, the City's own Fire-Rescue Fire Prevention division (4 inspectors + 4 inspector/plans examiners, all @naplesgov.com) performs fire inspections, but notably 'No Inspections will be conducted on Wednesdays for the City of Naples Fire Department Plan Review Team,' per the Building Department's own Fire Review page.

Why the confidence is not higherStaff roster and department pages are first-party City material naming individual in-house inspectors by name and City email domain; no outsourcing firm (SAFEbuilt, PDCS, CAP Government, etc.) or county fire department is named anywhere in the material read.

staff directory / department page checked 2026-09-12 https://www.naplesgov.com/firerescue/page/fire-prevention

Q53 If delegated, to whom? Core Who inspects

N/A — not delegated. Both building/electrical and fire inspection are performed by City of Naples staff.

Why the confidence is not higherFollows from Q52; no delegation language found anywhere in the City's building or fire material.

staff directory / department page checked 2026-09-12 https://www.naplesgov.com/firerescue/page/fire-prevention

Q54 Which inspections are required, and in what order? Core Stages & sequence

Nothing published by this authority.

Where we lookedNo published inspection-sequence list (rough-in, mid-roof, final, etc.) was found on the Building Department's pages read this run

https://www.naplesgov.com/building

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedSame as Q54 — no rough-in/mid-roof inspection statement found for PV or roofing generally

https://www.naplesgov.com/building

Q56 Does the inspector verify labels and listings? Core What is checked

Nothing published by this authority.

Where we lookedSame as Q54 — no statement that the inspector verifies labels/listings as a discrete item

https://www.naplesgov.com/building

Q57 Is there a published inspection checklist? Core What is checked

Nothing published by this authority.

Where we lookedNo published PV-specific (or general) inspection checklist was located on naplesgov.com in the pages read this run

https://www.naplesgov.com/building

Q58 What must be on site at inspection? Core Documents on site

Nothing published by this authority.

Where we lookedNo PV-specific on-site document requirement found; the general Building Permit Application (which might state this for all trades) was not opened this run

https://www.naplesgov.com/building/page/building-permit-forms-fees

Q59 Is there a re-inspection fee? Corrections & re-inspection

Nothing published by this authority.

Where we lookedFound the section this time: Ordinance 2025-15576's Appendix A amendment includes Sec. 16-95 'Inspection fees', which does contain a re-inspection fee line among several inspection-fee items (after-hours inspection, re-inspection, time-certain inspection, partial inspection) on an escalating first/second/third-occurrence basis. The exact dollar figures could not be read with confidence from the zoomed-screenshot render of this canvas-only page (two attempts produced inconsistent digits), so the amount is left unconfirmed rather than guessed — pages 6-9 (unreached, see q15) may also carry a cleaner restatement.

https://www.naplesgov.com/media/132581

Q60 How are corrections issued and cleared? Corrections & re-inspection

Nothing published by this authority.

Where we lookedNo corrections/re-inspection workflow statement found in the Building Department pages read this run

https://www.naplesgov.com/building

Q61 What is issued on pass? Core Final sign-off & PTO

Nothing published by this authority.

Where we lookedNo statement of what document (CO, Final, Green Tag) is issued specifically on passing a PV/electrical-alteration final inspection was found

https://www.naplesgov.com/building

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

The customer/installer, per the state-floor interconnection rule — not the City.

Why the confidence is not higherInferred from FL PSC Rule 25-6.065, which places the Standard Interconnection Agreement execution and utility-notification duties on the customer; no Naples-specific statement was found saying the City itself notifies FPL for PTO.

Florida Administrative Code rule text (state floor) checked 2026-09-12 https://www.flrules.org/gateway/readFile.asp?sid=0&tid=5455200&type=1&file=25-6.065.doc

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording None%

Size, colour & material None%

Where they go None%

What the utility wants on top 88%

FPL's own current Net Metering Guidelines require: Tier 1 (≤10kW) — no manual AC disconnect switch required. Tier 2/3 (>10kW) — 'a manual disconnect switch of the visible load break type to provide a separation point between the AC power output of the customer-owned renewable generation and any customer wiring connected to FPL's system.' Separately, for battery storage systems: 'A placard must be permanently affixed to the meter enclosure stating "Battery storage utilized in this facility."'

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Notes
Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.naplesgov.com/building
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
City
County
Collier County
Regions covered
Authority Contact
Building Department
Direct Phone
(239) 213-5020
Booking & Scheduling