City of Perry
City of Perry
Taylor County
City of Perry is a city authority in the State of Florida, serving 6,898 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Jurisdiction & key facts
The standing 62-question set, answered for City of Perry against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
City of Perry is the authority having jurisdiction 88% confidence
- Holds
- building, electrical, mechanical, plumbing and gas permitting and inspection; zoning; floodplain administration; contractor competency licensing; fire (own fire department)
- Delegated to
- No government. The permitting/inspection LABOUR is bought in under budget line 001-524-342 CONTRACT SERV BLD PERMITS at roughly 90-100% of building permit revenue; the provider is not named in any published document. Taylor County's Building & Planning Department is a separate AHJ for the unincorporated county, not a delegate for the city.
- Overridden by
- Florida Building Code 8th Ed. (2023) and NEC 2020 apply by floating adoption (city code Sec. 8-41) with only flood-elevation local amendments (Sec. 8-42). The electric utility -- Duke Energy Florida or Tri-County Electric Cooperative, address-dependent -- is a separate gatekeeper for interconnection, disconnect hardware and safety labelling; FPSC Rule 25-6.065 binds Duke but NOT the cooperative, which runs its own policy under FS 366.91.
- Why not higher
- Three first-party instruments put building permitting in the City: code Sec. 2-265(3) (Community Development functions include 'Building permits, inspection and building code implementation'); the Planning & Zoning department page ('handles the development and enforcement of state and local building codes... oversees land use changes and building permit applications'); and the FY2025-26 adopted budget's own PROTECTIVE INSPECTIONS department, which collects building permit revenue and remits the state radon and DBPR surcharges. The brief's implied 'Building Department' is WRONG as a department name -- there is no Building Department on the City's site or in its 11-entry staff directory, and the only named person on the permitting side is Dianne Cruce, Planning/Zoning & Code Compliance Clerk. Held at 88 because the City publishes no permit page, no application and no fee handout, and the contracted provider who actually reviews and inspects is unnamed.
- Permit required
- Yes. Code Sec. 8-41 adopts the Florida Building Code by floating reference ('as the same may be amended from time to time'), so FBC 105.1 governs and a permit is required for PV.88%
- Permit cost
- No solar line exists. The City's only published permit fee schedule is codified at Appendix A, Ch. 8 (adopted by Ord.70%
- Portal
- None. The City of Perry has NO permitting portal. Its website (Drupal / Municode Web 'starter8' profile, behind Cloudflare) has a 17-item main menu -- Meetings, City Council,88%
- Electrical code
- NEC 2020, effective 31 December 2023, as adopted statewide through the Florida Building Code. Perry adopts the FBC by floating reference (Sec.90%
- Own placard wording
- No. Perry specifies no placard wording of its own anywhere. The only city-specified wording of any kind that touches a solar job is the re-roof condition in the fee schedule,85%
- Booking an inspection
- By phone or in person -- there is no portal (Q20) and no email address published for permits. The city code's Appendix B records that an 'Electrical inspection' request form and a…70%
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes. Code Sec. 8-41 adopts the Florida Building Code by floating reference ('as the same may be amended from time to time'), Q3 Electrical and building permits — Either/combined in practice, and the fee schedule says so: Appendix A, Ch. 8 has ONE line, 'All trades $80.00', for the trade permits, Q4 Where you file — None. The City of Perry has NO permitting portal. Its website (Drupal / Municode Web 'starter8' profile, behind Cloudflare) has a 17-item main menu -- Meetings, Q20
- Permit required
- Yes. Code Sec. 8-41 adopts the Florida Building Code by floating reference ('as the same may be amended from time to time'), so FBC 105.1 governs and a permit is required for PV.88% source
- What it costs
- No solar line exists. The City's only published permit fee schedule is codified at Appendix A, Ch. 8 (adopted by Ord.70% source
- Key document
- city code Sec. 8-41 (floating FBC adoption, no administrative amendments) cited by 5 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes. The City of Perry is the AHJ for residential solar building and electrical permitting inside the city limits. There is NO separate 'Building Department' on the City's website or staff directory; the function sits in the COMMUNITY DEVELOPMENT DEPARTMENT (Code Sec. 2-265(3): department functions include 'Building permits, inspection and building code implementation') and is fronted day-to-day by PLANNING & ZONING, whose page states it 'handles the development and enforcement of state and local building codes and zoning ordinances within the City of Perry' and 'oversees land use changes and building permit applications'. Single named contact: Dianne Cruce, Planning/Zoning & Code Compliance Clerk, 850-584-7161 ext 4, City Hall, 224 S. Jefferson St, Perry FL 32347. The City Manager (John Hart II) is responsible for Community Development. Confirmed independently on the money side: the FY2025-26 adopted budget carries expenditure department 001-524-000 PROTECTIVE INSPECTIONS and revenue accounts 001-322-110 BUILDING PERMITS and 001-322-551 (surcharge), plus 001-524-491 RADON SURCHARGE -- only a local enforcement agency collects and remits the FS 553.721 / FS 404.056 surcharges. Taylor County runs its own separate Building & Planning Department (Terry McKeever, Building Director; John Perkins, inspections; LeeAnn Shreve, permitting; 201 E. Green St, Perry) for the UNINCORPORATED county; nothing on either site says the County permits inside the city limits. 92% · city code Sec. 2-265 + department pages + FY2025-26 adopted budget
- What does this authority permit itself, and what does it delegate? Both, plus zoning and floodplain, all in one department. Code Sec. 2-265 gives Community Development: (1) zoning administration and liaison to the zoning board and board of adjustment; (2) comprehensive planning and growth management; (3) building permits, inspection and building code implementation. Appendix A, Ch. 8 sets city building permit fees including a single 'All trades $80.00' line that covers the electrical/plumbing/mechanical trade permits, so electrical is NOT delegated away. NOT held by the City: (a) fire code enforcement is under the Fire Chief (Code Sec. 26-55) but the City adopts no fire code of its own -- Sec. 26-84 simply states the Florida Fire Prevention Code adopted under FS 633.202 'is in effect'; (b) the plan review / inspection labour itself is bought in under budget line 001-524-342 CONTRACT SERV BLD PERMITS (see Q53). Contractor competency is held by the CITY, not the county: Code Sec. 10-80 makes it unlawful to do business as a building trades contractor in the city without a City licence, and Sec. 10-81 requires a city certificate of competency which 'shall precede receipt of building permits'. 88% · city code Ch. 2 Art. VIII + Ch. 10 Art. IV + Appendix A Ch. 8
- Is a permit required for a residential rooftop PV system? Yes. Code Sec. 8-41 adopts the Florida Building Code by floating reference ('as the same may be amended from time to time'), so FBC 105.1 governs and a permit is required for PV. The City's own codified fee schedule (Appendix A, Ch. 8) prices building permits and 'All trades' permits, which only makes sense against a permit requirement, and Code Sec. 10-81 says a certificate of competency 'shall precede receipt of building permits'. There is NO solar-specific permit type published anywhere and NO permit exemption list in the city code. 88% · city code Sec. 8-41 (adopting ordinance)
- Is there a separate electrical permit, or is it combined? Either/combined in practice, and the fee schedule says so: Appendix A, Ch. 8 has ONE line, 'All trades $80.00', for the trade permits, sitting beside the square-foot building permit lines. There is no separate priced electrical permit and no solar line. So a residential PV job is priced as a trade permit at $80.00 unless the City treats it as a 'Remodel' at $0.20/sq ft. No published process document distinguishes the two. 62% · city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005)
- Is a HOA or architectural approval required first? No -- not for a single-family house. Perry does operate an architectural design review gate, but it is confined to the Downtown Central Business District and it EXCLUDES single-family residences. Code Sec. 30-21(a) requires Planning & Zoning Board approval of an architectural design review application 'prior to the issuance of a building permit in the downtown central business district' for new non-single-family construction, additions/alterations to non-single-family buildings, exterior renovation of non-single-family buildings, and new single-family construction on a site whose last building was non-single-family. Sec. 30-21(b) then exempts: '(1) Single-family residences, except as in subsection (a)(4)'; '(2) Routine exterior repair or maintenance of structures used for nonresidential purposes'; and '(5) Modifications to the exterior of any existing structure that is solely for the purpose of providing safe means of egress or access'. A rooftop PV retrofit on an existing house in Perry therefore trips no architectural gate anywhere in the city. HOAs: the LDR mentions homeowners associations only twice, in the Planned Residential Development article, where covenants 'must be approved by the City Attorney before final approval of the plan' -- there is no city-wide HOA approval requirement. 90% · city code Ch. 30 Art. II (Ord. 898, 10 Jan 2012)
- Is there a historic-district review? No true historic-district review exists. Perry's Chapter 30 is titled HISTORIC PRESERVATION but contains only Article II, Downtown Central Business District architectural design review -- there is no historic district, no historic landmark designation, no certificate of appropriateness and no historic preservation board. Sec. 30-22(a) says so in terms: the criteria are 'not intended to dictate specific building styles, or to mandate historical preservation, restoration or replication'. Administration is vested in the Planning & Zoning Board (Sec. 30-20(a)), which may engage a consulting architect and charge the applicant for it (Sec. 30-20(b),(c)). Single-family residences are exempt (Sec. 30-21(b)(1)). 90% · city code Ch. 30 Art. II
- Is a wind or windstorm certification required? No local windstorm certification and NO local wind-speed minimum. Perry sits in the Big Bend, which is in the ASCE 7 Wind-Borne Debris Region, NOT the HVHZ (HVHZ is Miami-Dade and Broward only). Searched for a local wind provision in both instruments that could carry one and found none: the codified code returns no 'mph', 'wind speed', 'wind load', 'wind-borne' or 'windborne' hits (its only 'miles per hour' is a bicycle-speed provision), and the 329-page Land Development Regulations return ZERO hits on all six of those terms. Perry's ONLY local amendment to the Florida Building Code (Sec. 8-42) is flood-elevation, not wind. So Florida Product Approval under the statewide FBC is the whole of it. 85% · city code Sec. 8-42 + Land Development Regulations (both searched)
- Is a Specific Use Permit or Council approval ever required? Not for residential rooftop PV. Perry's LDR carries the usual special exception / variance machinery administered by the Planning & Zoning Board and Board of Adjustment, and LDR Sec. 1.7.1 lets the City charge fees for 'zoning permits, sign permits, special exceptions applications, subdivision plat approval, zoning amendments, variances and other administrative relief'. But the LDR names no solar use, no accessory energy use and no generation use at all -- 'solar' and 'photovoltaic' each return ZERO hits in 329 pages -- so there is no listed use to trigger a special exception. Council approval is required only for an ordinance, e.g. rezoning. 70% · City of Perry Land Development Regulations (2023 ed.), Secs. 1.7, definitions
- Is there a system-size cap on residential generation? No local cap. The City imposes none: 'solar' and 'photovoltaic' return zero hits in the LDR and the codified code's single 'solar' hit is the thermal trap (Sec. 10-80 plumbing-contractor scope: a master plumber may install 'solar water heating systems'), which is a trade-scope definition and not a PV provision. The operative cap is the utility's. Duke Energy Florida: three tiers, Tier 1 <=10 kW, Tier 2 >10 to <=100 kW, Tier 3 >100 kW to 2 MW, with total generating capacity separately capped at 90% of the customer's existing service rating, and the system may not be sized to consistently produce more than the customer consumes. Tri-County Electric Cooperative's published rate sheet (2018) carries no DG rate class and no size table. 78% · Land Development Regulations + city code (searched) + Duke Energy Florida tier agreements
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? A contractor licensed BY THE CITY. Code Sec. 10-80(a): 'It shall be unlawful for any person, partnership or corporation to do business within the city as a building trades contractor unless licensed as a contractor under this article'. Sec. 10-81: state-exempt persons 'shall be required to obtain a certificate of competency through the building department. Receipt of a certificate of competency shall precede receipt of building permits'. The code's electrical contractor classification covers work 'for electrical wiring for lights, heat or power and all appurtenances thereto'. Licensure requires proof of an active state licence, liability and workers' compensation insurance, financial stability, experience and three client references. 90% · city code Secs. 10-80, 10-81
- Must the contractor be registered with this authority before applying? Yes -- and this is a real, codified gate, not a courtesy registration. Perry licenses building trades contractors itself (Code Sec. 10-80) rather than relying on a county competency card. Sec. 10-81 makes the certificate of competency a precondition of the permit in terms: it 'shall precede receipt of building permits'. Sec. 10-80(e) adds a trap for out-of-town installers: 'Application for or receipt of three or more building/construction permits within any 12-month period shall be considered prima facie evidence of maintaining a permanent business location in the city' -- i.e. a solar company doing a third job in Perry inside a year is presumed to be locally established. Licences run to 30 September with renewal to 31 January. Taylor County separately operates a Licensing Board (LB Application on the county building page); that is a second, distinct licensing body for the unincorporated county. 90% · city code Secs. 10-80, 10-81
- Is a homeowner permitted to self-install and self-permit? Not published by the City. The city code contains no owner-builder provision and no self-permit exemption; FS 489.103(7) (the state owner-builder exemption) applies statewide and Sec. 10-81's route for state-exempt persons requires a city certificate of competency instead. I searched the whole codified code (Ch. 8 Buildings, Ch. 10 Businesses incl. contractor licensing, Appendix A fees, Appendix B forms) and the 329-page Land Development Regulations; neither uses the words 'owner-builder' or 'homeowner'. 45% · city code Ch. 10 Art. IV (searched, no owner-builder clause)
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? Not published. The City of Perry publishes NO submittal checklist, NO building permit application and NO permit page. Proved by exhaustive enumeration, not by a failed search: I swept the site's media store by id (/media/1 .. /media/1300, HEAD, filename read from Content-Disposition) and recovered 227 published documents by real filename. Not one contains 'permit', 'build' (except bid invitations for city-owned buildings), 'fee', 'inspect', 'solar', 'photovolt', 'flood', '553', 'utiliz', 'impact', 'franchis' or 'schedule' (except garbage collection schedules). The site's own Forms library (/forms) holds exactly 8 documents, all of them employment applications, Dream Grant papers and the Regulatory License Application. Appendix B of the code confirms why: the building permit form, the electrical inspection request and the reinspection request exist but are 'on file in the office of the city clerk'. For a comparable published package, Taylor County's forms library (a separate authority) has a NEW RESIDENTIAL BUILDING PERMIT PACKAGE, an Electrical Permit Application rev. April 2025, a Roof Permit and a Private Provider Application. 90% · city Forms library + city code Appendix B + media-id sweep of 227 published documents
- Is a site plan required, and what must it show? Not published by the City for building permits. The only site-plan requirement Perry publishes is in the Land Development Regulations: LDR Sec. 14.11 'site and development plan' review, which the historic/architectural article (Code Sec. 30-21) cross-references and which applies to non-single-family development. For single-family residential work the LDR imposes no site plan. Taylor County, by contrast, publishes a 'Sample Site Plan Template' for its own permits. 55% · City of Perry Land Development Regulations (2023 edition), Sec. 14.11
- Is a structural PE stamp required, and at what threshold? Not set locally. Perry's code adopts the Florida Building Code by floating reference (Sec. 8-41) with only ONE set of local technical amendments (Sec. 8-42), and those are entirely flood-elevation amendments to FBC-R R322 -- no structural, no wind, no attachment and no PE-stamp threshold. So the threshold is the state one (FS 471.003 / FBC 107), not a local one. Note the LDR contains no wind or structural provision either: 'wind speed', 'miles per hour', 'mph', 'wind load', 'wind-borne' and 'windborne' all return ZERO hits across its 329 pages, and the same terms return zero in the codified code. 75% · city code Secs. 8-41, 8-42 (local FBC amendments, Ord. 958, 14 Jun 2016)
- Is an electrical PE stamp required, and at what threshold? Not set locally -- same reasoning as Q13. Perry adopts no electrical amendments at all and its only FBC amendments are flood-elevation. The statewide FS 471.003(2)(h) exemption ($125,000 / 600A) therefore governs. Perry's code prints no dollar trigger of any kind for engineering stamps. 70% · city code Sec. 8-42 (searched; no electrical or PE-stamp amendment)
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? None. The City of Perry has NO permitting portal. Its website (Drupal / Municode Web 'starter8' profile, behind Cloudflare) has a 17-item main menu -- Meetings, City Council, Administration, Utilities & Business Licenses, Finance, Public Works, Public Safety, Planning & Zoning, City Attorney, Fire, Police, About Perry, City Parks, Community Development, Incentives, Job Opportunities, Calendar -- and no Permits, Building or Portal entry. The only online transaction offered is utility bill pay (/finance-department/page/bill-pay), which is water/sewer/gas/garbage billing. The media-id sweep found no portal link, no iWorQ, no Citizenserve, no EnerGov, no MyGov. Taylor County likewise publishes only downloadable PDF forms with no portal. 88% · rendered site navigation + media-id sweep
- Can the whole application be completed online? No. With no portal and no downloadable application (see Q8, Q20), the application cannot be started online at all. The city code's Appendix B states that the building permit form, the electrical inspection request and the reinspection request are 'on file in the office of the city clerk' -- i.e. counter intake at 224 S. Jefferson Street. 85% · city code Appendix B + city website
- What does a residential solar permit cost? No solar line exists. The City's only published permit fee schedule is codified at Appendix A, Ch. 8 (adopted by Ord. 811, 22 Nov 2005): Single-family residence (heated) $0.24/sq ft; (unheated) $0.18/sq ft; Mobile home single-wide $300 / double-wide $400; Modular homes $300; Recertification (mobile and modular) $40; ALL TRADES $80.00; Remodel $0.20/sq ft; Move/raise house $200; Pool $100; Re-roof $100; Demolition $100; Re-inspection $25.00. A residential PV permit has no line of its own and most plausibly lands on ALL TRADES $80.00. State surcharges are collected on top (the budget carries 001-322-551 surcharge revenue and 001-524-491 RADON SURCHARGE). There is NO newer fee schedule anywhere on the city website -- the 227-document media sweep found no fee document at all. 70% · city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005)
- How is the fee calculated? Mixed, by work type: VALUATION-free. Perry prices by SQUARE FOOT for new construction and remodels ($0.24 / $0.18 / $0.20 per sq ft) and FLAT for everything else (trades $80, pool $100, re-roof $100, demolition $100, mobile homes $300/$400). There is no per-kW, no per-panel and no valuation-percentage method anywhere in the schedule. If PV is treated as a trade permit it is a FLAT $80.00. 72% · city code Appendix A, Ch. 8
- Is there a separate plan-check fee? No. The codified fee schedule contains no plan-check, plan-review or plans-examination fee line of any kind. The only add-on fees in it are Re-inspection $25.00 and, for the downtown architectural review, a consulting-architect fee the Planning & Zoning Board 'may impose... to cover its expenses' (Code Sec. 30-20(b),(c)) -- which does not reach single-family residential (Sec. 30-21(b)(1)). 72% · city code Appendix A, Ch. 8 + Sec. 30-20
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- How long is an issued permit valid before it expires? Not published locally. Perry adopts the FBC by floating reference with no Chapter 1 administrative amendments, so FBC 105.4.1 (permit void after 180 days without commencement / 180 days of abandonment) governs by default. The City publishes no permit-validity statement of its own. 50% · city code Sec. 8-41 (floating FBC adoption, no administrative amendments)
- Which utility handles interconnection here? NOT the City. The City of Perry does NOT own or operate an electric utility -- this is settled from first-party instruments and corrects a hypothesis carried into this survey. Evidence, four ways: (1) the City's own Utilities page states 'The City of Perry provides utility services consisting of natural gas, water, sewer and garbage'; (2) city code Chapter 50 UTILITIES has articles for Billing, Cross-Connection Control, Sewers, WATER SERVICE and GAS SERVICE and the word 'electric' appears ZERO times in the whole chapter; (3) the FY2025-26 adopted budget carries revenue account 001-313-103 ELECTRICAL FRANCHISE at $650,000 budgeted (actuals $449,929 / $629,006 / $710,362 / $623,833 / $572,420) and 103-314-101 ELECTRICITY (public service tax) at $750,000 -- a city that owns its electric system collects neither; (4) code Sec. 52-68(3) requires limbs near high-voltage conductors to be cleared 'by the electric utility company in compliance with any applicable franchise agreements', and Sec. 52-68(4) requires 'the utility company' to file a tree-trimming policy with the city tree board. WHO the franchisee is: the 2025 Taylor County Local Mitigation Strategy (approved March 2026, a multi-jurisdictional plan covering the City of Perry) states 'Tri-County Electric Cooperative and Duke Energy serve the electricity needs in Taylor County. The natural gas, water, sewer, and garbage services are provided by the City of Perry.' So TWO retail electric utilities operate in the county and the answer is ADDRESS-LEVEL. Indicator (not proof) that Duke serves the city limits: the City's own ACFR principal-taxpayer schedule ranks Duke Energy #2 with $18,424,366 of taxable assessed value, 22.20% of the entire city tax base, while Tri-County Electric does not appear in the top ten. Tri-County Electric Cooperative's Seminole Electric member page lists 'Counties Served: Jefferson, Madison, Taylor, N.W. 1/4 of Dixie' -- county granularity only, and a co-op county listing has been shown elsewhere in this survey not to settle city limits. 72% · city Utilities page + city code Ch. 50 and Sec. 52-68 + FY2025-26 adopted budget + Taylor County LMS 2025
- Where does the utility sit in the sequence? Before the utility's final sign-off, and after the local permit -- both candidate utilities sequence the AHJ first. Tri-County Electric Cooperative's published Interconnection Process is an 11-step sequence in which step 7 is construction with 'a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative', step 8 is 'Inspection by County Inspector -- The installation of the system must be inspected and approved by the county', step 9 is notifying TCEC of completion, step 10 is TCEC's on-site verification of the disconnect and safety features, and step 11 is TCEC counter-signing the Interconnection Agreement. Duke Energy Florida's Tier 1 Standard Interconnection Agreement likewise makes it a customer General Responsibility to obtain LOCAL BUILDING CODE OFFICIAL certification that the installation was permitted and approved before Duke's sign-off. Note TCEC's own wording says 'the county' -- written for its rural membership; inside Perry city limits the inspecting authority is the City, not Taylor County. 85% · TCEC Interconnection Process (PDF, created 1 Aug 2017) + Duke Energy Florida Tier 1 Standard Interconnection Agreement
28 questions answered against City of Perry’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes. The City of Perry is the AHJ for residential solar building and electrical permitting inside the city limits. There is NO separate 'Building Department' on the City's website or staff directory; the function sits in the COMMUNITY DEVELOPMENT DEPARTMENT (Code Sec. 2-265(3): department functions include 'Building permits, inspection and building code implementation') and is fronted day-to-day by PLANNING & ZONING, whose page states it 'handles the development and enforcement of state and local building codes and zoning ordinances within the City of Perry' and 'oversees land use changes and building permit applications'. Single named contact: Dianne Cruce, Planning/Zoning & Code Compliance Clerk, 850-584-7161 ext 4, City Hall, 224 S. Jefferson St, Perry FL 32347. The City Manager (John Hart II) is responsible for Community Development. Confirmed independently on the money side: the FY2025-26 adopted budget carries expenditure department 001-524-000 PROTECTIVE INSPECTIONS and revenue accounts 001-322-110 BUILDING PERMITS and 001-322-551 (surcharge), plus 001-524-491 RADON SURCHARGE -- only a local enforcement agency collects and remits the FS 553.721 / FS 404.056 surcharges. Taylor County runs its own separate Building & Planning Department (Terry McKeever, Building Director; John Perkins, inspections; LeeAnn Shreve, permitting; 201 E. Green St, Perry) for the UNINCORPORATED county; nothing on either site says the County permits inside the city limits.
Why the confidence is not higherThree independent first-party instruments agree (codified ordinance, department web page, adopted budget with its own inspection department and state surcharge remittance line). Held below 95 because the City publishes no permit page, no permit application and no fee handout of its own, so the practical intake route is not documented anywhere public -- and because the City's building work is bought by contract (see Q53), which leaves open who actually signs the permit.
city code Sec. 2-265 + department pages + FY2025-26 adopted budget checked 2026-09-13 https://www.cityofperry.net/community-development
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
Both, plus zoning and floodplain, all in one department. Code Sec. 2-265 gives Community Development: (1) zoning administration and liaison to the zoning board and board of adjustment; (2) comprehensive planning and growth management; (3) building permits, inspection and building code implementation. Appendix A, Ch. 8 sets city building permit fees including a single 'All trades $80.00' line that covers the electrical/plumbing/mechanical trade permits, so electrical is NOT delegated away. NOT held by the City: (a) fire code enforcement is under the Fire Chief (Code Sec. 26-55) but the City adopts no fire code of its own -- Sec. 26-84 simply states the Florida Fire Prevention Code adopted under FS 633.202 'is in effect'; (b) the plan review / inspection labour itself is bought in under budget line 001-524-342 CONTRACT SERV BLD PERMITS (see Q53). Contractor competency is held by the CITY, not the county: Code Sec. 10-80 makes it unlawful to do business as a building trades contractor in the city without a City licence, and Sec. 10-81 requires a city certificate of competency which 'shall precede receipt of building permits'.
Why the confidence is not higherCode sections are explicit and current-as-codified (through Ord. 1033, 26 Sep 2023). Held at 88 because the split between the salaried city clerk and the contracted inspector is inferred from budget account names, not from a published agreement.
city code Ch. 2 Art. VIII + Ch. 10 Art. IV + Appendix A Ch. 8 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH2AD
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes. Code Sec. 8-41 adopts the Florida Building Code by floating reference ('as the same may be amended from time to time'), so FBC 105.1 governs and a permit is required for PV. The City's own codified fee schedule (Appendix A, Ch. 8) prices building permits and 'All trades' permits, which only makes sense against a permit requirement, and Code Sec. 10-81 says a certificate of competency 'shall precede receipt of building permits'. There is NO solar-specific permit type published anywhere and NO permit exemption list in the city code.
Why the confidence is not higherInferred from the floating FBC adoption plus the city's own fee schedule rather than from a city permit page -- the City publishes no permits page, no application form and no exemption list. Positive control ('electrical' = 33 hits) and fabricated control ('zzqqx' = 0) both passed on the full code corpus.
city code Sec. 8-41 (adopting ordinance) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
Either/combined in practice, and the fee schedule says so: Appendix A, Ch. 8 has ONE line, 'All trades $80.00', for the trade permits, sitting beside the square-foot building permit lines. There is no separate priced electrical permit and no solar line. So a residential PV job is priced as a trade permit at $80.00 unless the City treats it as a 'Remodel' at $0.20/sq ft. No published process document distinguishes the two.
Why the confidence is not higherRead directly off the codified fee schedule, but that schedule is from Ord. 811 (22 Nov 2005) and has no PV line at all, so the mapping of PV onto 'All trades' is my inference from the structure of the schedule, not a city statement.
city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q5 Who is allowed to pull the electrical permit? Core Who may apply
A contractor licensed BY THE CITY. Code Sec. 10-80(a): 'It shall be unlawful for any person, partnership or corporation to do business within the city as a building trades contractor unless licensed as a contractor under this article'. Sec. 10-81: state-exempt persons 'shall be required to obtain a certificate of competency through the building department. Receipt of a certificate of competency shall precede receipt of building permits'. The code's electrical contractor classification covers work 'for electrical wiring for lights, heat or power and all appurtenances thereto'. Licensure requires proof of an active state licence, liability and workers' compensation insurance, financial stability, experience and three client references.
Why the confidence is not higherCodified and unambiguous. Held at 90 because the code does not separately say who may pull a PV permit, and because the City licence file is not published.
city code Secs. 10-80, 10-81 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH10BUBURE
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Yes -- and this is a real, codified gate, not a courtesy registration. Perry licenses building trades contractors itself (Code Sec. 10-80) rather than relying on a county competency card. Sec. 10-81 makes the certificate of competency a precondition of the permit in terms: it 'shall precede receipt of building permits'. Sec. 10-80(e) adds a trap for out-of-town installers: 'Application for or receipt of three or more building/construction permits within any 12-month period shall be considered prima facie evidence of maintaining a permanent business location in the city' -- i.e. a solar company doing a third job in Perry inside a year is presumed to be locally established. Licences run to 30 September with renewal to 31 January. Taylor County separately operates a Licensing Board (LB Application on the county building page); that is a second, distinct licensing body for the unincorporated county.
Why the confidence is not higherCodified text, current as of Supp. 2. Held at 90 because the fee for the city contractor licence and the application form itself are not published online (Appendix B says the forms are 'on file in the office of the city clerk').
city code Secs. 10-80, 10-81 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH10BUBURE
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Not published by the City. The city code contains no owner-builder provision and no self-permit exemption; FS 489.103(7) (the state owner-builder exemption) applies statewide and Sec. 10-81's route for state-exempt persons requires a city certificate of competency instead. I searched the whole codified code (Ch. 8 Buildings, Ch. 10 Businesses incl. contractor licensing, Appendix A fees, Appendix B forms) and the 329-page Land Development Regulations; neither uses the words 'owner-builder' or 'homeowner'.
Why the confidence is not higherThis is a reasoned reading of an absence, not a city statement -- recorded low deliberately. The state exemption is real but the City's certificate-of-competency clause makes the local position genuinely unclear.
city code Ch. 10 Art. IV (searched, no owner-builder clause) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH10BUBURE
Q8 What documents make up a complete submittal? Core Submittal package
Not published. The City of Perry publishes NO submittal checklist, NO building permit application and NO permit page. Proved by exhaustive enumeration, not by a failed search: I swept the site's media store by id (/media/1 .. /media/1300, HEAD, filename read from Content-Disposition) and recovered 227 published documents by real filename. Not one contains 'permit', 'build' (except bid invitations for city-owned buildings), 'fee', 'inspect', 'solar', 'photovolt', 'flood', '553', 'utiliz', 'impact', 'franchis' or 'schedule' (except garbage collection schedules). The site's own Forms library (/forms) holds exactly 8 documents, all of them employment applications, Dream Grant papers and the Regulatory License Application. Appendix B of the code confirms why: the building permit form, the electrical inspection request and the reinspection request exist but are 'on file in the office of the city clerk'. For a comparable published package, Taylor County's forms library (a separate authority) has a NEW RESIDENTIAL BUILDING PERMIT PACKAGE, an Electrical Permit Application rev. April 2025, a Roof Permit and a Private Provider Application.
Why the confidence is not higherHigh confidence in the ABSENCE because it rests on a full id sweep of the media store plus the code's own statement that the forms are held at the clerk's office, not on a site search box.
city Forms library + city code Appendix B + media-id sweep of 227 published documents checked 2026-09-13 https://www.cityofperry.net/forms
Q9 How many copies, and in what format? Submittal package
Nothing published by this authority.
Where we lookedCity Forms library (/forms, 8 documents), full media-id sweep of the city's document store (/media/1 .. /media/1300 by HEAD, 227 documents recovered by real filename), city code Appendix B (which says the building permit form is 'on file in the office of the city clerk'), and the rendered site navigation. No submittal, copy-count or format requirement is published anywhere.
Q10 Is a site plan required, and what must it show? Core Submittal package
Not published by the City for building permits. The only site-plan requirement Perry publishes is in the Land Development Regulations: LDR Sec. 14.11 'site and development plan' review, which the historic/architectural article (Code Sec. 30-21) cross-references and which applies to non-single-family development. For single-family residential work the LDR imposes no site plan. Taylor County, by contrast, publishes a 'Sample Site Plan Template' for its own permits.
Why the confidence is not higherInferred from the LDR's structure and the Ch. 30 cross-reference; the City publishes no residential submittal requirements at all, so this is an absence-shaped answer rather than a positive rule.
City of Perry Land Development Regulations (2023 edition), Sec. 14.11 checked 2026-09-13 https://www.cityofperry.net/media/626
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Nothing published by this authority.
Where we lookedSame as Q9 -- no checklist or plan-content requirement exists. Also searched the codified code (Ch. 8 Buildings, Appendix A, Appendix B) and the 329-page Land Development Regulations for 'one-line', 'single line', 'riser' and 'diagram': nothing applicable.
Q12 Are string and conductor calculations required? Drawings & calculations
Nothing published by this authority.
Where we lookedSame instruments as Q11. No string/conductor calculation requirement exists in the city code, the LDR, or any published document; the City publishes no electrical submittal requirements at all.
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Not set locally. Perry's code adopts the Florida Building Code by floating reference (Sec. 8-41) with only ONE set of local technical amendments (Sec. 8-42), and those are entirely flood-elevation amendments to FBC-R R322 -- no structural, no wind, no attachment and no PE-stamp threshold. So the threshold is the state one (FS 471.003 / FBC 107), not a local one. Note the LDR contains no wind or structural provision either: 'wind speed', 'miles per hour', 'mph', 'wind load', 'wind-borne' and 'windborne' all return ZERO hits across its 329 pages, and the same terms return zero in the codified code.
Why the confidence is not higherSolid on the absence of a local threshold (both instruments searched with passing controls); the statewide threshold is carried from state law rather than from a Perry document.
city code Secs. 8-41, 8-42 (local FBC amendments, Ord. 958, 14 Jun 2016) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Not set locally -- same reasoning as Q13. Perry adopts no electrical amendments at all and its only FBC amendments are flood-elevation. The statewide FS 471.003(2)(h) exemption ($125,000 / 600A) therefore governs. Perry's code prints no dollar trigger of any kind for engineering stamps.
Why the confidence is not higherAbsence proved against the two instruments that could carry it (Ch. 8 amendments, LDR); the operative number is state law, not a Perry document.
city code Sec. 8-42 (searched; no electrical or PE-stamp amendment) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q15 What does a residential solar permit cost? Core Fees
No solar line exists. The City's only published permit fee schedule is codified at Appendix A, Ch. 8 (adopted by Ord. 811, 22 Nov 2005): Single-family residence (heated) $0.24/sq ft; (unheated) $0.18/sq ft; Mobile home single-wide $300 / double-wide $400; Modular homes $300; Recertification (mobile and modular) $40; ALL TRADES $80.00; Remodel $0.20/sq ft; Move/raise house $200; Pool $100; Re-roof $100; Demolition $100; Re-inspection $25.00. A residential PV permit has no line of its own and most plausibly lands on ALL TRADES $80.00. State surcharges are collected on top (the budget carries 001-322-551 surcharge revenue and 001-524-491 RADON SURCHARGE). There is NO newer fee schedule anywhere on the city website -- the 227-document media sweep found no fee document at all.
Why the confidence is not higherThe schedule itself is first-party and current-as-codified, but it is twenty-one years old, has no PV or ESS line, and the mapping of PV onto 'All trades $80.00' is my inference. Whether the City instead prices PV as 'Remodel' at $0.20/sq ft is genuinely unresolved.
city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q16 How is the fee calculated? Core Fees
Mixed, by work type: VALUATION-free. Perry prices by SQUARE FOOT for new construction and remodels ($0.24 / $0.18 / $0.20 per sq ft) and FLAT for everything else (trades $80, pool $100, re-roof $100, demolition $100, mobile homes $300/$400). There is no per-kW, no per-panel and no valuation-percentage method anywhere in the schedule. If PV is treated as a trade permit it is a FLAT $80.00.
Why the confidence is not higherRead straight off the codified schedule. Held at 72 because the schedule never names PV, so which of the two methods catches it is not stated.
city code Appendix A, Ch. 8 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q17 Is there a separate plan-check fee? Fees
No. The codified fee schedule contains no plan-check, plan-review or plans-examination fee line of any kind. The only add-on fees in it are Re-inspection $25.00 and, for the downtown architectural review, a consulting-architect fee the Planning & Zoning Board 'may impose... to cover its expenses' (Code Sec. 30-20(b),(c)) -- which does not reach single-family residential (Sec. 30-21(b)(1)).
Why the confidence is not higherA clean read of the whole schedule; held at 72 only because the schedule is from 2005 and the City may charge something administratively that it never codified.
city code Appendix A, Ch. 8 + Sec. 30-20 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Nothing published by this authority.
Where we lookedRendered site navigation (17 menu items, no permits page), the Planning & Zoning and Community Development department pages, the Forms library, and the 227-document media sweep. No plan-review turnaround, service standard or processing time is stated anywhere. FS 553.79(3)'s 30-day statutory clock applies by default but is not restated by the City.
Q19 How long is an issued permit valid before it expires? Timeline & validity
Not published locally. Perry adopts the FBC by floating reference with no Chapter 1 administrative amendments, so FBC 105.4.1 (permit void after 180 days without commencement / 180 days of abandonment) governs by default. The City publishes no permit-validity statement of its own.
Why the confidence is not higherPure inheritance from the state code because the local instrument is silent; recorded low. No Perry document states a duration.
city code Sec. 8-41 (floating FBC adoption, no administrative amendments) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q20 Which permit portal does this authority use? Core Portal & process
None. The City of Perry has NO permitting portal. Its website (Drupal / Municode Web 'starter8' profile, behind Cloudflare) has a 17-item main menu -- Meetings, City Council, Administration, Utilities & Business Licenses, Finance, Public Works, Public Safety, Planning & Zoning, City Attorney, Fire, Police, About Perry, City Parks, Community Development, Incentives, Job Opportunities, Calendar -- and no Permits, Building or Portal entry. The only online transaction offered is utility bill pay (/finance-department/page/bill-pay), which is water/sewer/gas/garbage billing. The media-id sweep found no portal link, no iWorQ, no Citizenserve, no EnerGov, no MyGov. Taylor County likewise publishes only downloadable PDF forms with no portal.
Why the confidence is not higherProved by reading the rendered navigation out of the live DOM plus a full sweep of published documents, not by a site search. Held at 88 because a non-linked portal on a third-party host cannot be excluded absolutely.
rendered site navigation + media-id sweep checked 2026-09-13 https://www.cityofperry.net/
Q21 Can the whole application be completed online? Core Portal & process
No. With no portal and no downloadable application (see Q8, Q20), the application cannot be started online at all. The city code's Appendix B states that the building permit form, the electrical inspection request and the reinspection request are 'on file in the office of the city clerk' -- i.e. counter intake at 224 S. Jefferson Street.
Why the confidence is not higherFollows directly from the two proved absences plus the code's own statement about where the forms live.
city code Appendix B + city website checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXBFOAPORFO
Q22 Which utility handles interconnection here? Core Utility interconnection
NOT the City. The City of Perry does NOT own or operate an electric utility -- this is settled from first-party instruments and corrects a hypothesis carried into this survey. Evidence, four ways: (1) the City's own Utilities page states 'The City of Perry provides utility services consisting of natural gas, water, sewer and garbage'; (2) city code Chapter 50 UTILITIES has articles for Billing, Cross-Connection Control, Sewers, WATER SERVICE and GAS SERVICE and the word 'electric' appears ZERO times in the whole chapter; (3) the FY2025-26 adopted budget carries revenue account 001-313-103 ELECTRICAL FRANCHISE at $650,000 budgeted (actuals $449,929 / $629,006 / $710,362 / $623,833 / $572,420) and 103-314-101 ELECTRICITY (public service tax) at $750,000 -- a city that owns its electric system collects neither; (4) code Sec. 52-68(3) requires limbs near high-voltage conductors to be cleared 'by the electric utility company in compliance with any applicable franchise agreements', and Sec. 52-68(4) requires 'the utility company' to file a tree-trimming policy with the city tree board. WHO the franchisee is: the 2025 Taylor County Local Mitigation Strategy (approved March 2026, a multi-jurisdictional plan covering the City of Perry) states 'Tri-County Electric Cooperative and Duke Energy serve the electricity needs in Taylor County. The natural gas, water, sewer, and garbage services are provided by the City of Perry.' So TWO retail electric utilities operate in the county and the answer is ADDRESS-LEVEL. Indicator (not proof) that Duke serves the city limits: the City's own ACFR principal-taxpayer schedule ranks Duke Energy #2 with $18,424,366 of taxable assessed value, 22.20% of the entire city tax base, while Tri-County Electric does not appear in the top ten. Tri-County Electric Cooperative's Seminole Electric member page lists 'Counties Served: Jefferson, Madison, Taylor, N.W. 1/4 of Dixie' -- county granularity only, and a co-op county listing has been shown elsewhere in this survey not to settle city limits.
Why the confidence is not higherThe negative (not municipal) is 95-grade and rests on four independent first-party instruments. The positive (which of Duke / TCEC serves a given Perry address) is NOT settled: the LMS names both for the county, the city budget shows a single undifferentiated ELECTRICAL FRANCHISE line with no vendor, there is no street-lighting expenditure account and no free-text note beside it, the City publishes no accounts-payable report, and the ACFR taxpayer schedule is explicitly not a service-territory instrument. Overall confidence set by the weaker half.
city Utilities page + city code Ch. 50 and Sec. 52-68 + FY2025-26 adopted budget + Taylor County LMS 2025 checked 2026-09-13 https://www.cityofperry.net/utilities-and-business-licenses
Q23 Where does the utility sit in the sequence? Core Utility interconnection
Before the utility's final sign-off, and after the local permit -- both candidate utilities sequence the AHJ first. Tri-County Electric Cooperative's published Interconnection Process is an 11-step sequence in which step 7 is construction with 'a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative', step 8 is 'Inspection by County Inspector -- The installation of the system must be inspected and approved by the county', step 9 is notifying TCEC of completion, step 10 is TCEC's on-site verification of the disconnect and safety features, and step 11 is TCEC counter-signing the Interconnection Agreement. Duke Energy Florida's Tier 1 Standard Interconnection Agreement likewise makes it a customer General Responsibility to obtain LOCAL BUILDING CODE OFFICIAL certification that the installation was permitted and approved before Duke's sign-off. Note TCEC's own wording says 'the county' -- written for its rural membership; inside Perry city limits the inspecting authority is the City, not Taylor County.
Why the confidence is not higherBoth utilities' own published documents, read directly. Held at 85 because the applicable one depends on the unresolved address-level utility question, and because TCEC's 'county' wording does not contemplate an incorporated city.
TCEC Interconnection Process (PDF, created 1 Aug 2017) + Duke Energy Florida Tier 1 Standard Interconnection Agreement checked 2026-09-13 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf
Q24 Is a HOA or architectural approval required first? Overlays & special cases
No -- not for a single-family house. Perry does operate an architectural design review gate, but it is confined to the Downtown Central Business District and it EXCLUDES single-family residences. Code Sec. 30-21(a) requires Planning & Zoning Board approval of an architectural design review application 'prior to the issuance of a building permit in the downtown central business district' for new non-single-family construction, additions/alterations to non-single-family buildings, exterior renovation of non-single-family buildings, and new single-family construction on a site whose last building was non-single-family. Sec. 30-21(b) then exempts: '(1) Single-family residences, except as in subsection (a)(4)'; '(2) Routine exterior repair or maintenance of structures used for nonresidential purposes'; and '(5) Modifications to the exterior of any existing structure that is solely for the purpose of providing safe means of egress or access'. A rooftop PV retrofit on an existing house in Perry therefore trips no architectural gate anywhere in the city. HOAs: the LDR mentions homeowners associations only twice, in the Planned Residential Development article, where covenants 'must be approved by the City Attorney before final approval of the plan' -- there is no city-wide HOA approval requirement.
Why the confidence is not higherCodified, current (Ord. 898, 10 Jan 2012), and the exemption is explicit in terms. Held at 90 because private HOA covenants on individual subdivisions are not city documents and cannot be enumerated.
city code Ch. 30 Art. II (Ord. 898, 10 Jan 2012) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH30HIPR
Q25 Is there a historic-district review? Overlays & special cases
No true historic-district review exists. Perry's Chapter 30 is titled HISTORIC PRESERVATION but contains only Article II, Downtown Central Business District architectural design review -- there is no historic district, no historic landmark designation, no certificate of appropriateness and no historic preservation board. Sec. 30-22(a) says so in terms: the criteria are 'not intended to dictate specific building styles, or to mandate historical preservation, restoration or replication'. Administration is vested in the Planning & Zoning Board (Sec. 30-20(a)), which may engage a consulting architect and charge the applicant for it (Sec. 30-20(b),(c)). Single-family residences are exempt (Sec. 30-21(b)(1)).
Why the confidence is not higherRead the whole chapter; it is short and unambiguous. Held at 90 because the Planning & Zoning Board is authorised by Sec. 30-20(d) to 'develop application materials, check lists and other documents' which are not published anywhere -- an unpublished checklist could exist.
city code Ch. 30 Art. II checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH30HIPR
Q26 Is a wind or windstorm certification required? Overlays & special cases
No local windstorm certification and NO local wind-speed minimum. Perry sits in the Big Bend, which is in the ASCE 7 Wind-Borne Debris Region, NOT the HVHZ (HVHZ is Miami-Dade and Broward only). Searched for a local wind provision in both instruments that could carry one and found none: the codified code returns no 'mph', 'wind speed', 'wind load', 'wind-borne' or 'windborne' hits (its only 'miles per hour' is a bicycle-speed provision), and the 329-page Land Development Regulations return ZERO hits on all six of those terms. Perry's ONLY local amendment to the Florida Building Code (Sec. 8-42) is flood-elevation, not wind. So Florida Product Approval under the statewide FBC is the whole of it.
Why the confidence is not higherTwo complete instruments searched with passing positive and fabricated controls. Held at 85 rather than higher because 28 ordinances adopted since codification (Ord. 1037-1064) are not published anywhere -- see could_not_reach.
city code Sec. 8-42 + Land Development Regulations (both searched) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Not for residential rooftop PV. Perry's LDR carries the usual special exception / variance machinery administered by the Planning & Zoning Board and Board of Adjustment, and LDR Sec. 1.7.1 lets the City charge fees for 'zoning permits, sign permits, special exceptions applications, subdivision plat approval, zoning amendments, variances and other administrative relief'. But the LDR names no solar use, no accessory energy use and no generation use at all -- 'solar' and 'photovoltaic' each return ZERO hits in 329 pages -- so there is no listed use to trigger a special exception. Council approval is required only for an ordinance, e.g. rezoning.
Why the confidence is not higherThe absence of a solar use in the LDR is proved (controls passed). Held at 70 because with no listed use the classification of a ground-mounted array falls to the administrator's discretion and could in principle be routed to a special exception.
City of Perry Land Development Regulations (2023 ed.), Secs. 1.7, definitions checked 2026-09-13 https://www.cityofperry.net/media/626
Q28 Is there a system-size cap on residential generation? Overlays & special cases
No local cap. The City imposes none: 'solar' and 'photovoltaic' return zero hits in the LDR and the codified code's single 'solar' hit is the thermal trap (Sec. 10-80 plumbing-contractor scope: a master plumber may install 'solar water heating systems'), which is a trade-scope definition and not a PV provision. The operative cap is the utility's. Duke Energy Florida: three tiers, Tier 1 <=10 kW, Tier 2 >10 to <=100 kW, Tier 3 >100 kW to 2 MW, with total generating capacity separately capped at 90% of the customer's existing service rating, and the system may not be sized to consistently produce more than the customer consumes. Tri-County Electric Cooperative's published rate sheet (2018) carries no DG rate class and no size table.
Why the confidence is not higherCity absence is well proved. Utility side is first-party for Duke; for TCEC the tariff PDF simply has no DG provision, which is itself a finding but leaves the co-op's cap unknown.
Land Development Regulations + city code (searched) + Duke Energy Florida tier agreements checked 2026-09-13 https://www.cityofperry.net/media/626
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? NEC 2020, effective 31 December 2023, as adopted statewide through the Florida Building Code. Perry adopts the FBC by floating reference (Sec. 8-41: 'as the same may be amended from time to time, adopted by the state building commission pursuant to F.S. 553.73') and makes NO electrical amendment, so the state edition applies unchanged. Do not read the '2023' on the FBC 8th Edition as an NEC year. 90% · city code Sec. 8-41 (floating FBC adoption)
- Which building code edition is in force? Florida Building Code, 8th Edition (2023), current statewide edition -- inherited automatically. Sec. 8-41 adopts 'the Florida Building Code, as the same may be amended from time to time' with no edition number, so the base never goes stale. The LOCAL AMENDMENTS do lag: Sec. 8-42's amendments are written against FBC-Residential R322.2.1 / R322.2.2 and were adopted by Ord. 958 on 14 June 2016, applying to applications submitted on or after 26 April 2016. Base current, amendments ten years old. 90% · city code Secs. 8-41, 8-42 (Ord. 958, 14 Jun 2016)
- Which fire code edition is in force? Florida Fire Prevention Code (8th Edition, 2023), by pure statutory reference. Perry adopts nothing of its own: Code Sec. 26-84 says only that 'The Florida Fire Prevention Code adopted pursuant to F.S. 633.202 is in effect'. There is no NFPA edition number, no local fire amendment and no adopting ordinance date in Chapter 26. The Fire Chief's inspection power (Sec. 26-55) expressly excludes 'the interiors of private dwellings'. Code Sec. 8-43 defines a downtown 'fire district' by metes and bounds for FBC 301.4 purposes -- a construction-type district, not a permitting overlay. 85% · city code Sec. 26-84
- Are there local amendments to any of the above? Yes -- but only ONE set, and it is entirely flood. Code Sec. 8-42 'Amendments adopted' contains exactly four substantive items plus an applicability clause: (1) R322.2.1 elevation -- lowest floors in flood hazard areas not designated Coastal A to BFE + 1 FOOT or the design flood elevation, whichever is higher; Coastal A zones likewise BFE + 1 foot (305 mm); AO zones the FIRM depth number + 1 foot, or at least 3 feet if no depth number; basements below grade on all sides to BFE + 1 foot; (2) R322.2.2 enclosed areas below design flood elevation -- parking/access/storage only, at least two flood openings on different sides, 1 sq in per sq ft, bottom within 1 foot of grade, openings at least 3 inches in any direction; (3) a substantial-damage definition; (4) a fiscal impact statement; (5) applicability to all development applications submitted on or after 26 April 2016. There is NO electrical, structural, wind, mounting, fire-pathway, signage or solar amendment anywhere in the city code. 92% · city code Sec. 8-42 (Ord. 958, 14 Jun 2016)
- What is the installation judged against? NEC 2020 as incorporated in the Florida Building Code (8th Ed., 2023), unamended locally, plus the electric utility's own interconnection requirements. Perry adds nothing: no local electrical amendment exists anywhere in its code, and its Land Development Regulations contain no electrical provision. 88% · city code Secs. 8-41, 8-42
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? No local rule -- the statewide Florida Fire Prevention Code applies as adopted by FS 633.202, with no Perry amendment. Perry adopts no fire code text of its own (Sec. 26-84 is a bare reference) and adds no access-pathway or ridge-setback provision. The City does maintain its own Fire Department under a Fire Chief appointed by the City Manager (Secs. 26-19, 26-21, 26-54), so the AHJ for fire is the City, but it has published no PV roof-access policy, checklist or bulletin -- confirmed against the 227-document media sweep, which found no fire, solar or access document. 78% · city code Sec. 26-84 + media-id sweep
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Yes -- NEC 2020 Article 690.12 rapid shutdown, including the 690.12(B)(2) inside-the-array requirement, via the statewide adoption. Perry adds nothing and takes nothing away: no electrical amendment exists in its code, and it publishes no inspection checklist that would soften or vary it. 85% · city code Sec. 8-41 + NEC 2020 as adopted statewide
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
- Which placards does this authority require at the service equipment? None of its own -- the placards come from NEC 2020 (690.13(B), 690.54, 690.56(C), 705.10, 705.12(B)(3)) as adopted statewide, plus whatever the serving utility requires. Perry's codified code contains no placard, label, marking, sign-at-service or warning requirement for electrical work of any kind, and its Land Development Regulations contain none either. The media sweep of 227 published city documents found no signage or labelling document. 85% · city code (searched) + Land Development Regulations (searched) + media-id sweep
- Does the authority specify placard wording of its own? No. Perry specifies no placard wording of its own anywhere. The only city-specified wording of any kind that touches a solar job is the re-roof condition in the fee schedule, which requires 'a notarized statement for planned disposal of old shingles' -- a disposal affidavit, not a placard. 85% · city code Appendix A Ch. 8 + full code search
- Does it specify letter height, colour or material? No. No letter height, no colour, no material, no reflectivity and no durability requirement appears anywhere in Perry's code or Land Development Regulations. NEC 110.21(B) and the utility's own standards govern. 85% · city code + Land Development Regulations (both searched)
- Is a site plan / facility map placard required, and what must it show? Nothing local. NEC 2020 705.10 (directory of all electric power sources at each service equipment location) applies through the statewide adoption; Perry imposes no site-plan placard, facility map or emergency-responder diagram of its own. Note the City also imposes no site plan at submittal for single-family work (Q10), so there is no local document from which such a placard could be derived. 80% · city code (searched) + NEC 2020 705.10 as adopted
- Does the UTILITY specify placards beyond the AHJ's? Yes, and this is where the real signage requirement lives -- but which utility's applies is address-level (see Q22). Tri-County Electric Cooperative: its published Interconnection Process, step 7, requires the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative to protect its personnel, facilities and operations', and step 10 has a TCEC representative attend to 'review the system's disconnect and safety features' before approval. TCEC prescribes no wording, letter height or material in that document. Duke Energy Florida: its filed Tier 1 Standard Interconnection Agreement deals with the disconnect switch (discretionary at Duke's expense for Tier 1) and does not itself carry a placard wording specification. 72% · TCEC Interconnection Process (PDF) + Duke Energy Florida Tier 1 agreement
- Where must the labels be placed? Not specified by the City. Placement follows NEC 2020 (at each service equipment location / at the disconnecting means / on the PV system disconnect) and the utility's requirement that the disconnect remain readily accessible. Duke Energy Florida's tier agreements require any disconnect to be 'mounted separate from, but adjacent to, the Company's meter socket', 'readily accessible to the Company' and 'capable of being locked in the open position with a single Company utility lock' -- with no distance figure given. Perry itself says nothing about label location anywhere. 75% · Duke Energy Florida Tier 1/2/3 Standard Interconnection Agreements + city code (searched)
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Where must the AC disconnect be, relative to the meter? Utility-set, and it differs sharply between the two candidates. Duke Energy Florida, Tier 1 (<=10 kW): NO customer disconnect is required; Duke MAY elect to install one at ITS OWN expense, in which case it must be visible load-break type, 'mounted separate from, but adjacent to, the Company's meter socket', readily accessible to Duke and lockable open with a single Duke lock. Tier 2 (>10 to <=100 kW) and Tier 3: a manual AC load-break disconnect IS required at the CUSTOMER's expense, same location and lock language, with NO distance figure stated. Tri-County Electric Cooperative: a disconnect switch is required with NO size exemption -- its Interconnection Process step 7 directs the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative', and step 10 has TCEC verify it on site before approval; TCEC publishes no location or distance specification. Note the baseline rule: FPSC Rule 25-6.065 binds investor-owned utilities (Duke) but NOT cooperatives, which run their own policies under FS 366.91 -- so TCEC's no-exemption stance is lawful and a PSC citation would not override it. The City of Perry specifies nothing. 80% · Duke Energy Florida Tier 1/2/3 Standard Interconnection Agreements + TCEC Interconnection Process
- Must equipment be on a specific approved list? Not by the City. Perry adopts no approved-products list, no local product approval and no evaluation-report requirement; statewide Florida Product Approval under the FBC applies, and equipment must be listed under the NEC as adopted. Because Taylor County is in the Wind-Borne Debris Region and NOT the HVHZ, Miami-Dade NOA is not required. 78% · city code Sec. 8-42 (searched) + FBC product approval
- Are batteries permitted, and under what conditions? Permitted, under the statewide Florida Building Code and Florida Fire Prevention Code only. Perry has no local ESS, battery or energy-storage provision: the words do not appear in the codified code or in the 329-page Land Development Regulations, and no ESS document exists in the 227-document media store. A flood consideration does apply: Perry sits in a FEMA flood hazard area (Chapter 28 FLOODS plus the LDR's Article 8 floodplain article), and Sec. 8-42's BFE + 1 foot elevation requirement reaches buildings and structures -- but see Q46 for the literal reach of the equipment clause. 72% · city code Ch. 28 + Ch. 8 + Land Development Regulations (all searched)
- Is there a separate ESS permit or inspection? No separate ESS permit or inspection type exists -- there is no published permit type list at all (no portal, no application form). And a trap worth recording literally: the ONLY 'utility equipment' elevation clause in Perry's floodplain instrument reaches manufactured homes ONLY. LDR Sec. 8.13.8 reads: 'Utility equipment. Utility equipment that serves MANUFACTURED HOMES, including electric, heating, ventilation, plumbing, and air conditioning equipment and other service facilities, shall comply with...'. It is inside the manufactured-home article. PV inverters, rapid-shutdown gear, combiners and batteries at a SITE-BUILT house are not caught by that clause; for a site-built dwelling the elevation duty comes from FBC-R R322 as amended by city code Sec. 8-42, which speaks of lowest floors and enclosed areas, not equipment. This is the third Florida authority in this survey where the equipment clause reads only to manufactured homes. 88% · City of Perry Land Development Regulations (2023 ed.), Sec. 8.13.8
- Is a ground mount treated as a structure? Not addressed. Perry's Land Development Regulations define 'Accessory Use or Structure' generically ('a use or structure of a nature customarily incidental and subordinate to the principal use or structure and... on the same premises') and 'Addition' as 'an extension or increase in floor area or height of a building or structure', but they name no solar use, no ground-mounted array and no energy equipment -- 'solar' and 'photovoltaic' return ZERO hits across 329 pages. So a ground mount would be classified by the Land Development Regulation Administrator under the generic accessory-structure definition, subject to the accessory setbacks of the zoning district, with no published solar-specific rule, height allowance or screening requirement. 70% · City of Perry Land Development Regulations (2023 ed.), Art. 2 definitions
- Is there a local rule on service upgrades or busbar sizing? No local rule. Perry has no electrical amendments at all (Sec. 8-42 is flood-only), so NEC 705.12 as adopted governs service upgrades and busbar sizing. Note the utility-side constraint instead: Duke Energy Florida caps total generating capacity at 90% of the customer's existing service rating in all three of its tier agreements, which is the practical service-size gate here if Duke serves the address. 75% · city code Sec. 8-42 (searched)
- Is a specific mounting system or attachment spacing required? No. Perry specifies no mounting system, attachment spacing, standoff or fastener schedule. Its only FBC amendments are flood-elevation (Sec. 8-42) and its LDR contains nothing on roof attachment. Florida Product Approval under the statewide FBC and the manufacturer's listed installation instructions are the whole of the requirement. 80% · city code Sec. 8-42 + Land Development Regulations (searched)
20 questions answered against City of Perry’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
NEC 2020, effective 31 December 2023, as adopted statewide through the Florida Building Code. Perry adopts the FBC by floating reference (Sec. 8-41: 'as the same may be amended from time to time, adopted by the state building commission pursuant to F.S. 553.73') and makes NO electrical amendment, so the state edition applies unchanged. Do not read the '2023' on the FBC 8th Edition as an NEC year.
Why the confidence is not higherThe floating adoption is first-party and unambiguous; the NEC edition itself is the statewide answer corroborated across this survey against floridabuilding.org. Perry publishes no permit form at all, so there is no local document printing a wrong code year here (unlike several other Florida authorities).
city code Sec. 8-41 (floating FBC adoption) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q30 Which building code edition is in force? Core Code editions in force
Florida Building Code, 8th Edition (2023), current statewide edition -- inherited automatically. Sec. 8-41 adopts 'the Florida Building Code, as the same may be amended from time to time' with no edition number, so the base never goes stale. The LOCAL AMENDMENTS do lag: Sec. 8-42's amendments are written against FBC-Residential R322.2.1 / R322.2.2 and were adopted by Ord. 958 on 14 June 2016, applying to applications submitted on or after 26 April 2016. Base current, amendments ten years old.
Why the confidence is not higherFirst-party floating adoption plus a dated amendment ordinance. This is the 'floating base with lagging amendments' shape the baseline warns to record as two separate facts.
city code Secs. 8-41, 8-42 (Ord. 958, 14 Jun 2016) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q31 Which fire code edition is in force? Code editions in force
Florida Fire Prevention Code (8th Edition, 2023), by pure statutory reference. Perry adopts nothing of its own: Code Sec. 26-84 says only that 'The Florida Fire Prevention Code adopted pursuant to F.S. 633.202 is in effect'. There is no NFPA edition number, no local fire amendment and no adopting ordinance date in Chapter 26. The Fire Chief's inspection power (Sec. 26-55) expressly excludes 'the interiors of private dwellings'. Code Sec. 8-43 defines a downtown 'fire district' by metes and bounds for FBC 301.4 purposes -- a construction-type district, not a permitting overlay.
Why the confidence is not higherSec. 26-84 is first-party and explicit; the 8th Edition year is the statewide current edition rather than a Perry statement.
city code Sec. 26-84 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH26FIPRPR
Q32 Are there local amendments to any of the above? Core Code editions in force
Yes -- but only ONE set, and it is entirely flood. Code Sec. 8-42 'Amendments adopted' contains exactly four substantive items plus an applicability clause: (1) R322.2.1 elevation -- lowest floors in flood hazard areas not designated Coastal A to BFE + 1 FOOT or the design flood elevation, whichever is higher; Coastal A zones likewise BFE + 1 foot (305 mm); AO zones the FIRM depth number + 1 foot, or at least 3 feet if no depth number; basements below grade on all sides to BFE + 1 foot; (2) R322.2.2 enclosed areas below design flood elevation -- parking/access/storage only, at least two flood openings on different sides, 1 sq in per sq ft, bottom within 1 foot of grade, openings at least 3 inches in any direction; (3) a substantial-damage definition; (4) a fiscal impact statement; (5) applicability to all development applications submitted on or after 26 April 2016. There is NO electrical, structural, wind, mounting, fire-pathway, signage or solar amendment anywhere in the city code.
Why the confidence is not higherRead the amendment section in full from the codified text. Held at 92 because 28 post-codification ordinances (1037-1064) are unpublished and one of them could in principle amend Ch. 8.
city code Sec. 8-42 (Ord. 958, 14 Jun 2016) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q33 What is the installation judged against? Core Electrical
NEC 2020 as incorporated in the Florida Building Code (8th Ed., 2023), unamended locally, plus the electric utility's own interconnection requirements. Perry adds nothing: no local electrical amendment exists anywhere in its code, and its Land Development Regulations contain no electrical provision.
Why the confidence is not higherFollows from the floating FBC adoption and the proved absence of any electrical amendment in either instrument.
city code Secs. 8-41, 8-42 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
No local rule. Perry has no electrical amendments at all (Sec. 8-42 is flood-only), so NEC 705.12 as adopted governs service upgrades and busbar sizing. Note the utility-side constraint instead: Duke Energy Florida caps total generating capacity at 90% of the customer's existing service rating in all three of its tier agreements, which is the practical service-size gate here if Duke serves the address.
Why the confidence is not higherCity absence proved against both instruments; the substantive constraint quoted is the utility's, carried from Duke's own tier agreements.
city code Sec. 8-42 (searched) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
No. Perry specifies no mounting system, attachment spacing, standoff or fastener schedule. Its only FBC amendments are flood-elevation (Sec. 8-42) and its LDR contains nothing on roof attachment. Florida Product Approval under the statewide FBC and the manufacturer's listed installation instructions are the whole of the requirement.
Why the confidence is not higherAbsence proved against both city instruments with controls passing; the fallback is statewide law rather than a Perry document.
city code Sec. 8-42 + Land Development Regulations (searched) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
No local rule -- the statewide Florida Fire Prevention Code applies as adopted by FS 633.202, with no Perry amendment. Perry adopts no fire code text of its own (Sec. 26-84 is a bare reference) and adds no access-pathway or ridge-setback provision. The City does maintain its own Fire Department under a Fire Chief appointed by the City Manager (Secs. 26-19, 26-21, 26-54), so the AHJ for fire is the City, but it has published no PV roof-access policy, checklist or bulletin -- confirmed against the 227-document media sweep, which found no fire, solar or access document.
Why the confidence is not higherAbsence proved for the local layer. The operative pathway numbers come from the statewide FFPC/NFPA 1, not from any Perry document, which is why this is not higher.
city code Sec. 26-84 + media-id sweep checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH26FIPRPR
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Yes -- NEC 2020 Article 690.12 rapid shutdown, including the 690.12(B)(2) inside-the-array requirement, via the statewide adoption. Perry adds nothing and takes nothing away: no electrical amendment exists in its code, and it publishes no inspection checklist that would soften or vary it.
Why the confidence is not higherFollows from the floating FBC adoption plus the proved absence of local electrical amendment. Not higher because no Perry document mentions rapid shutdown at all.
city code Sec. 8-41 + NEC 2020 as adopted statewide checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
None of its own -- the placards come from NEC 2020 (690.13(B), 690.54, 690.56(C), 705.10, 705.12(B)(3)) as adopted statewide, plus whatever the serving utility requires. Perry's codified code contains no placard, label, marking, sign-at-service or warning requirement for electrical work of any kind, and its Land Development Regulations contain none either. The media sweep of 227 published city documents found no signage or labelling document.
Why the confidence is not higherA well-proved absence across both city instruments and the full document store. The applicable requirements are state and utility, not city.
city code (searched) + Land Development Regulations (searched) + media-id sweep checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
No. Perry specifies no placard wording of its own anywhere. The only city-specified wording of any kind that touches a solar job is the re-roof condition in the fee schedule, which requires 'a notarized statement for planned disposal of old shingles' -- a disposal affidavit, not a placard.
Why the confidence is not higherSame proved absence as Q38, with the one genuine city-specified document requirement recorded so the answer is not merely negative.
city code Appendix A Ch. 8 + full code search checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
No. No letter height, no colour, no material, no reflectivity and no durability requirement appears anywhere in Perry's code or Land Development Regulations. NEC 110.21(B) and the utility's own standards govern.
Why the confidence is not higherProved absence across both instruments with controls passing.
city code + Land Development Regulations (both searched) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Nothing local. NEC 2020 705.10 (directory of all electric power sources at each service equipment location) applies through the statewide adoption; Perry imposes no site-plan placard, facility map or emergency-responder diagram of its own. Note the City also imposes no site plan at submittal for single-family work (Q10), so there is no local document from which such a placard could be derived.
Why the confidence is not higherAbsence proved locally; the operative rule is the adopted NEC.
city code (searched) + NEC 2020 705.10 as adopted checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Yes, and this is where the real signage requirement lives -- but which utility's applies is address-level (see Q22). Tri-County Electric Cooperative: its published Interconnection Process, step 7, requires the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative to protect its personnel, facilities and operations', and step 10 has a TCEC representative attend to 'review the system's disconnect and safety features' before approval. TCEC prescribes no wording, letter height or material in that document. Duke Energy Florida: its filed Tier 1 Standard Interconnection Agreement deals with the disconnect switch (discretionary at Duke's expense for Tier 1) and does not itself carry a placard wording specification.
Why the confidence is not higherTCEC's requirement is quoted verbatim from its own current published process document. Held at 72 because it is open-ended ('as may be required by the Cooperative') with no published specification, and because the applicable utility at a given Perry address is unresolved.
TCEC Interconnection Process (PDF) + Duke Energy Florida Tier 1 agreement checked 2026-09-13 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
Not specified by the City. Placement follows NEC 2020 (at each service equipment location / at the disconnecting means / on the PV system disconnect) and the utility's requirement that the disconnect remain readily accessible. Duke Energy Florida's tier agreements require any disconnect to be 'mounted separate from, but adjacent to, the Company's meter socket', 'readily accessible to the Company' and 'capable of being locked in the open position with a single Company utility lock' -- with no distance figure given. Perry itself says nothing about label location anywhere.
Why the confidence is not higherThe city absence is proved; the placement language is quoted from Duke's own filed tier agreements and applies only if Duke serves the address.
Duke Energy Florida Tier 1/2/3 Standard Interconnection Agreements + city code (searched) checked 2026-09-13 https://www.duke-energy.com/-/media/pdfs/for-your-business/generate-your-own-renewable/florida/tier-1-contract.pdf
Q44 Must equipment be on a specific approved list? Equipment listing
Not by the City. Perry adopts no approved-products list, no local product approval and no evaluation-report requirement; statewide Florida Product Approval under the FBC applies, and equipment must be listed under the NEC as adopted. Because Taylor County is in the Wind-Borne Debris Region and NOT the HVHZ, Miami-Dade NOA is not required.
Why the confidence is not higherAbsence proved against the city instruments; the fallback is the statewide regime.
city code Sec. 8-42 (searched) + FBC product approval checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Permitted, under the statewide Florida Building Code and Florida Fire Prevention Code only. Perry has no local ESS, battery or energy-storage provision: the words do not appear in the codified code or in the 329-page Land Development Regulations, and no ESS document exists in the 227-document media store. A flood consideration does apply: Perry sits in a FEMA flood hazard area (Chapter 28 FLOODS plus the LDR's Article 8 floodplain article), and Sec. 8-42's BFE + 1 foot elevation requirement reaches buildings and structures -- but see Q46 for the literal reach of the equipment clause.
Why the confidence is not higherThe local absence is proved; the statewide permission is inherited. Held at 72 because the practical ESS review at a flood-zone address is not documented anywhere by the City.
city code Ch. 28 + Ch. 8 + Land Development Regulations (all searched) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH28FL
Q46 Is there a separate ESS permit or inspection? Battery / ESS
No separate ESS permit or inspection type exists -- there is no published permit type list at all (no portal, no application form). And a trap worth recording literally: the ONLY 'utility equipment' elevation clause in Perry's floodplain instrument reaches manufactured homes ONLY. LDR Sec. 8.13.8 reads: 'Utility equipment. Utility equipment that serves MANUFACTURED HOMES, including electric, heating, ventilation, plumbing, and air conditioning equipment and other service facilities, shall comply with...'. It is inside the manufactured-home article. PV inverters, rapid-shutdown gear, combiners and batteries at a SITE-BUILT house are not caught by that clause; for a site-built dwelling the elevation duty comes from FBC-R R322 as amended by city code Sec. 8-42, which speaks of lowest floors and enclosed areas, not equipment. This is the third Florida authority in this survey where the equipment clause reads only to manufactured homes.
Why the confidence is not higherThe clause is quoted verbatim from the City's own current Land Development Regulations and its placement inside the manufactured-home article is unambiguous. Held at 88 because the practical consequence -- that an inspector may nonetheless apply FBC R322 equipment provisions -- is not something the document settles.
City of Perry Land Development Regulations (2023 ed.), Sec. 8.13.8 checked 2026-09-13 https://www.cityofperry.net/media/626
Q47 Is a ground mount treated as a structure? Core Ground mount
Not addressed. Perry's Land Development Regulations define 'Accessory Use or Structure' generically ('a use or structure of a nature customarily incidental and subordinate to the principal use or structure and... on the same premises') and 'Addition' as 'an extension or increase in floor area or height of a building or structure', but they name no solar use, no ground-mounted array and no energy equipment -- 'solar' and 'photovoltaic' return ZERO hits across 329 pages. So a ground mount would be classified by the Land Development Regulation Administrator under the generic accessory-structure definition, subject to the accessory setbacks of the zoning district, with no published solar-specific rule, height allowance or screening requirement.
Why the confidence is not higherThe absence is proved with passing controls; the classification is a reasoned reading of the generic definitions, not a city determination. No published administrator interpretation exists.
City of Perry Land Development Regulations (2023 ed.), Art. 2 definitions checked 2026-09-13 https://www.cityofperry.net/media/626
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Utility-set, and it differs sharply between the two candidates. Duke Energy Florida, Tier 1 (<=10 kW): NO customer disconnect is required; Duke MAY elect to install one at ITS OWN expense, in which case it must be visible load-break type, 'mounted separate from, but adjacent to, the Company's meter socket', readily accessible to Duke and lockable open with a single Duke lock. Tier 2 (>10 to <=100 kW) and Tier 3: a manual AC load-break disconnect IS required at the CUSTOMER's expense, same location and lock language, with NO distance figure stated. Tri-County Electric Cooperative: a disconnect switch is required with NO size exemption -- its Interconnection Process step 7 directs the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative', and step 10 has TCEC verify it on site before approval; TCEC publishes no location or distance specification. Note the baseline rule: FPSC Rule 25-6.065 binds investor-owned utilities (Duke) but NOT cooperatives, which run their own policies under FS 366.91 -- so TCEC's no-exemption stance is lawful and a PSC citation would not override it. The City of Perry specifies nothing.
Why the confidence is not higherDuke's language is verbatim from its filed tier agreements; TCEC's is verbatim from its own published process. Held at 80 because which regime applies at a given Perry address is unresolved and because TCEC publishes no location specification at all.
Duke Energy Florida Tier 1/2/3 Standard Interconnection Agreements + TCEC Interconnection Process checked 2026-09-13 https://www.duke-energy.com/-/media/pdfs/for-your-business/generate-your-own-renewable/florida/tier-1-contract.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? By phone or in person -- there is no portal (Q20) and no email address published for permits. The city code's Appendix B records that an 'Electrical inspection' request form and a 'Reinspection request' form exist and are 'on file in the office of the city clerk'. The published contact route is Planning & Zoning, 850-584-7161 ext 4 (Dianne Cruce, Planning/Zoning & Code Compliance Clerk), City Hall, 224 S. Jefferson Street. 70% · city code Appendix B + Planning & Zoning department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes, the City does its own inspections -- but it buys the inspector. The City remains the legal AHJ (Code Sec. 2-265(3): 'Building permits, inspection and building code implementation'; Sec. 8-44 penalties; Sec. 46-58(b) 'The building official will be required to make an inspection of all work performed'; Secs. 2-193 to 2-197 establish a five-member City Construction Board of Adjustments and Appeals -- one engineer or architect, one general/building contractor, one ELECTRICAL contractor, one plumbing contractor, one citizen at large, plus mechanical and roofing alternates -- expressly to hear appeals from orders of 'the building official'). The inspection labour is contracted (Q53). Reinspection is priced in the city's own fee schedule at $25.00, which only makes sense against city-run inspections. 82% · city code Secs. 2-193 to 2-197, 2-265, 46-58 + Appendix A Ch. 8
- If delegated, to whom? Contracted out, to an unnamed provider -- and the budget shape is new for this survey. The FY2025-26 adopted budget, expenditure department 001-524-000 PROTECTIVE INSPECTIONS, carries BOTH: a salaried line 001-524-120 REGULAR SALARIES at $37,483.43 (FY26 budget; FY25 $36,387; actuals $28,464 / $30,024 / $30,352 / $33,481 / $32,434) with FICA $2,867, retirement $5,259, life & health $88.80 and workers comp $1,923 -- roughly one clerical post, consistent with the single named staffer Dianne Cruce; AND a contract line 001-524-342 CONTRACT SERV BLD PERMITS at $40,000 (FY26 budget; FY25 $40,000; actuals $40,087.48 / $80,502.66 / $81,168.52 / $41,755.38 / $28,505.52). Set that against revenue account 001-322-110 BUILDING PERMITS: $40,000 budget, actuals $44,427.48 / $82,422.66 / $80,968.52 / $36,023.64 / $34,180.66. The contract expenditure tracks the permit revenue essentially one-for-one, year after year -- roughly 90-100% pass-through, a materially harder shape than the 'Building Official on 50-60% of permit revenue' and 'operator on ~75%' patterns recorded elsewhere in this survey. Other department lines: 001-524-340 OTHER CONTRACTUAL SERV $4,500; 001-524-344 DEMOLITIONS $36,000; 001-524-491 RADON SURCHARGE $2,000; TRAINING & PER DIEM $0 for FY26; vehicle maintenance $500; gas/oil/tires $600. The provider is NOT named: the budget names no firm, the staff directory lists no Building Official or Inspector among its 11 entries, and no contract, RFP or agreement appears among the 227 published city documents. 80% · City of Perry FY2025-26 Adopted Budget, dept 001-524 PROTECTIVE INSPECTIONS + revenue 001-322-110
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? Not published as a sequence. What is evidenced: the city code's Appendix B records a standing 'Electrical inspection' request form (old Code 1983 Sec. 8-43) and a 'Reinspection request' form (Sec. 8-45), plus a 'Plumbing inspection request' (Sec. 21-2) -- i.e. trade inspections are requested individually, per trade. The fee schedule prices one re-inspection at $25.00. Taylor County, a separate authority, publishes a 'Pre-Inspection' fee of $50.00 in its own schedule, which Perry does not have. 55% · city code Appendix B (forms on file with the city clerk)
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- Is there a published inspection checklist? No. There is no published inspection checklist of any kind. Proved by the media-id sweep: 227 published city documents enumerated by real filename, none containing 'inspect', 'checklist', 'permit', 'solar' or 'fee'. The only checklist-adjacent authority in the code is Sec. 30-20(d), which lets the Planning & Zoning Board 'develop application materials, check lists and other documents' for downtown architectural review -- and nothing developed under it is published. 88% · media-id sweep of 227 published documents + city Forms library
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- Who notifies the utility for PTO? The installer/customer notifies the utility -- the AHJ does not. Tri-County Electric Cooperative's Interconnection Process step 9: 'Notify the Cooperative in advance of energizing your small power generating installation and allow TCEC staff to verify and test protective equipment. Upon completion of installation, please notify TCEC by sending an email to engineering@tcec.com.' TCEC then schedules a site visit (step 10) and a TCEC representative counter-signs the Interconnection Agreement (step 11). Duke Energy Florida likewise puts the burden on the customer, who must supply the local building code official's certification and then execute the tier agreement; since 9 February 2026 Duke Energy Florida's application channel is PowerClerk, replacing the legacy Interconnection Portal. Nothing in Perry's code or on its website says the City notifies any utility. 82% · TCEC Interconnection Process (PDF) + Duke Energy Florida interconnection materials
- Is there a re-inspection fee? $25.00. Codified at Appendix A, Ch. 8: 'Re-inspection $25.00'. It sits in the same schedule as Re-roof $100.00, which carries the condition '(In addition to a notarized statement for planned disposal of old shingles.)'. 82% · city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005)
- How are corrections issued and cleared? Not published as a corrections procedure. What the code does provide is the appeal route: the City Construction Board of Adjustments and Appeals (Secs. 2-193 to 2-197) hears appeals from interpretations of the adopted building, plumbing, mechanical and gas codes and from orders of the building official. The board must meet within 30 days after a notice of appeal is received; a simple majority of members serving on a specific appeal is a quorum; and varying a provision or modifying an order of the building official needs affirmative votes of the majority present but not less than a majority of the board serving in the appeal. Sec. 2-198 sets the appeal fee. Day-to-day correction notices are not documented anywhere. 62% · city code Secs. 2-193 to 2-198
14 questions answered against City of Perry’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
By phone or in person -- there is no portal (Q20) and no email address published for permits. The city code's Appendix B records that an 'Electrical inspection' request form and a 'Reinspection request' form exist and are 'on file in the office of the city clerk'. The published contact route is Planning & Zoning, 850-584-7161 ext 4 (Dianne Cruce, Planning/Zoning & Code Compliance Clerk), City Hall, 224 S. Jefferson Street.
Why the confidence is not higherThe form names and their location are first-party from the code's own Appendix B, and the phone number is from the live department page; but no Perry document states the booking procedure itself, so the mechanism is inferred from the absence of any online route.
city code Appendix B + Planning & Zoning department page checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXBFOAPORFO
Q50 How much notice is required? Core Booking & scheduling
Nothing published by this authority.
Where we lookedCity code Appendix B (inspection request forms on file with the clerk), the Planning & Zoning and Community Development department pages, and the 227-document media sweep. No inspection notice period is published.
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedSame as Q50. No AM/PM window, same-day option or scheduling window is published.
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes, the City does its own inspections -- but it buys the inspector. The City remains the legal AHJ (Code Sec. 2-265(3): 'Building permits, inspection and building code implementation'; Sec. 8-44 penalties; Sec. 46-58(b) 'The building official will be required to make an inspection of all work performed'; Secs. 2-193 to 2-197 establish a five-member City Construction Board of Adjustments and Appeals -- one engineer or architect, one general/building contractor, one ELECTRICAL contractor, one plumbing contractor, one citizen at large, plus mechanical and roofing alternates -- expressly to hear appeals from orders of 'the building official'). The inspection labour is contracted (Q53). Reinspection is priced in the city's own fee schedule at $25.00, which only makes sense against city-run inspections.
Why the confidence is not higherFour codified provisions point the same way and the budget carries the department. Held at 82 because no Perry document describes the inspection process itself and the contracted arrangement is unnamed.
city code Secs. 2-193 to 2-197, 2-265, 46-58 + Appendix A Ch. 8 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH2AD
Q53 If delegated, to whom? Core Who inspects
Contracted out, to an unnamed provider -- and the budget shape is new for this survey. The FY2025-26 adopted budget, expenditure department 001-524-000 PROTECTIVE INSPECTIONS, carries BOTH: a salaried line 001-524-120 REGULAR SALARIES at $37,483.43 (FY26 budget; FY25 $36,387; actuals $28,464 / $30,024 / $30,352 / $33,481 / $32,434) with FICA $2,867, retirement $5,259, life & health $88.80 and workers comp $1,923 -- roughly one clerical post, consistent with the single named staffer Dianne Cruce; AND a contract line 001-524-342 CONTRACT SERV BLD PERMITS at $40,000 (FY26 budget; FY25 $40,000; actuals $40,087.48 / $80,502.66 / $81,168.52 / $41,755.38 / $28,505.52). Set that against revenue account 001-322-110 BUILDING PERMITS: $40,000 budget, actuals $44,427.48 / $82,422.66 / $80,968.52 / $36,023.64 / $34,180.66. The contract expenditure tracks the permit revenue essentially one-for-one, year after year -- roughly 90-100% pass-through, a materially harder shape than the 'Building Official on 50-60% of permit revenue' and 'operator on ~75%' patterns recorded elsewhere in this survey. Other department lines: 001-524-340 OTHER CONTRACTUAL SERV $4,500; 001-524-344 DEMOLITIONS $36,000; 001-524-491 RADON SURCHARGE $2,000; TRAINING & PER DIEM $0 for FY26; vehicle maintenance $500; gas/oil/tires $600. The provider is NOT named: the budget names no firm, the staff directory lists no Building Official or Inspector among its 11 entries, and no contract, RFP or agreement appears among the 227 published city documents.
Why the confidence is not higherThe numbers are verbatim from the City's own adopted budget and the revenue/expenditure correspondence is checked across five actual years. Held at 80 for the part that matters most operationally -- the provider's identity -- which is genuinely not published. It could be a private firm, an individual on contract, or Taylor County under an interlocal; I found no evidence for any of the three.
City of Perry FY2025-26 Adopted Budget, dept 001-524 PROTECTIVE INSPECTIONS + revenue 001-322-110 checked 2026-09-13 https://www.cityofperry.net/media/906
Q54 Which inspections are required, and in what order? Core Stages & sequence
Not published as a sequence. What is evidenced: the city code's Appendix B records a standing 'Electrical inspection' request form (old Code 1983 Sec. 8-43) and a 'Reinspection request' form (Sec. 8-45), plus a 'Plumbing inspection request' (Sec. 21-2) -- i.e. trade inspections are requested individually, per trade. The fee schedule prices one re-inspection at $25.00. Taylor County, a separate authority, publishes a 'Pre-Inspection' fee of $50.00 in its own schedule, which Perry does not have.
Why the confidence is not higherInferred from the surviving form names in the code's own appendix; no Perry document lists inspection stages or order. Recorded low deliberately.
city code Appendix B (forms on file with the city clerk) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXBFOAPORFO
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
Nothing published by this authority.
Where we lookedCity code Ch. 8, Appendix A (which prices only a single 'Re-inspection $25.00'), Appendix B form list, and the 227-document media sweep. No rough-in, mid-roof or in-progress inspection is named in any published Perry document.
https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q56 Does the inspector verify labels and listings? Core What is checked
Nothing published by this authority.
Where we lookedCity code Ch. 8 and Ch. 2 Art. VII (construction board), the Land Development Regulations, and the 227-document media sweep. No inspection scope, checklist or label-verification statement is published. NEC 2020 as adopted requires the labels; whether Perry's contracted inspector verifies them is undocumented.
https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q57 Is there a published inspection checklist? Core What is checked
No. There is no published inspection checklist of any kind. Proved by the media-id sweep: 227 published city documents enumerated by real filename, none containing 'inspect', 'checklist', 'permit', 'solar' or 'fee'. The only checklist-adjacent authority in the code is Sec. 30-20(d), which lets the Planning & Zoning Board 'develop application materials, check lists and other documents' for downtown architectural review -- and nothing developed under it is published.
Why the confidence is not higherAbsence rests on a full enumeration of the document store plus the site navigation, not on a search box.
media-id sweep of 227 published documents + city Forms library checked 2026-09-13 https://www.cityofperry.net/forms
Q58 What must be on site at inspection? Core Documents on site
Nothing published by this authority.
Where we lookedCity code Appendix B, Appendix A, Ch. 8, and the 227-document media sweep. Nothing states what must be on site at inspection. The one on-site document Perry does demand anywhere is the notarised shingle-disposal statement attached to the re-roof fee line.
https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q59 Is there a re-inspection fee? Corrections & re-inspection
$25.00. Codified at Appendix A, Ch. 8: 'Re-inspection $25.00'. It sits in the same schedule as Re-roof $100.00, which carries the condition '(In addition to a notarized statement for planned disposal of old shingles.)'.
Why the confidence is not higherQuoted directly from the City's own codified fee schedule. Held at 82 only because that schedule dates from Ord. 811 (22 Nov 2005) and there is no newer published schedule to check it against -- the media sweep found no fee document at all.
city code Appendix A, Ch. 8 (Ord. 811, 22 Nov 2005) checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_APXASCFERACH
Q60 How are corrections issued and cleared? Corrections & re-inspection
Not published as a corrections procedure. What the code does provide is the appeal route: the City Construction Board of Adjustments and Appeals (Secs. 2-193 to 2-197) hears appeals from interpretations of the adopted building, plumbing, mechanical and gas codes and from orders of the building official. The board must meet within 30 days after a notice of appeal is received; a simple majority of members serving on a specific appeal is a quorum; and varying a provision or modifying an order of the building official needs affirmative votes of the majority present but not less than a majority of the board serving in the appeal. Sec. 2-198 sets the appeal fee. Day-to-day correction notices are not documented anywhere.
Why the confidence is not higherThe appeal machinery is codified and quoted; the ordinary correction-and-reinspection cycle is not published at all, so this answers a neighbouring question.
city code Secs. 2-193 to 2-198 checked 2026-09-13 https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH2AD
Q61 What is issued on pass? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedCity code Ch. 8 (no certificate-of-occupancy or final-approval provision beyond the FBC by reference), Appendix B form list, the department pages, and the 227-document media sweep. Perry publishes nothing about what is issued on a passed final. Taylor County's page states that IT 'issues occupancy permits upon compliance', but that is the county's own process, not Perry's.
https://api.municode.com/CodesContent?jobId=434039&productId=11420&nodeId=PTIICOOR_CH8BUBURE
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
The installer/customer notifies the utility -- the AHJ does not. Tri-County Electric Cooperative's Interconnection Process step 9: 'Notify the Cooperative in advance of energizing your small power generating installation and allow TCEC staff to verify and test protective equipment. Upon completion of installation, please notify TCEC by sending an email to engineering@tcec.com.' TCEC then schedules a site visit (step 10) and a TCEC representative counter-signs the Interconnection Agreement (step 11). Duke Energy Florida likewise puts the burden on the customer, who must supply the local building code official's certification and then execute the tier agreement; since 9 February 2026 Duke Energy Florida's application channel is PowerClerk, replacing the legacy Interconnection Portal. Nothing in Perry's code or on its website says the City notifies any utility.
Why the confidence is not higherVerbatim from TCEC's own published process; Duke's side carried from its first-party tier agreements and customer pages. Held at 82 because the applicable utility at a given Perry address is unresolved.
TCEC Interconnection Process (PDF) + Duke Energy Florida interconnection materials checked 2026-09-13 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
No change record for this authority yet. Values arrive here as they are researched, and each one is dated.
Labels & placards for this authority
Wording 85%
No. Perry specifies no placard wording of its own anywhere. The only city-specified wording of any kind that touches a solar job is the re-roof condition in the fee schedule, which requires 'a notarized statement for planned disposal of old shingles' -- a disposal affidavit, not a placard.
Size, colour & material 85%
No. No letter height, no colour, no material, no reflectivity and no durability requirement appears anywhere in Perry's code or Land Development Regulations. NEC 110.21(B) and the utility's own standards govern.
Where they go 75%
Not specified by the City. Placement follows NEC 2020 (at each service equipment location / at the disconnecting means / on the PV system disconnect) and the utility's requirement that the disconnect remain readily accessible. Duke Energy Florida's tier agreements require any disconnect to be 'mounted separate from, but adjacent to, the Company's meter socket', 'readily accessible to the Company' and 'capable of being locked in the open position with a single Company utility lock' -- with no distance figure given. Perry itself says nothing about label location anywhere.
What the utility wants on top 72%
Yes, and this is where the real signage requirement lives -- but which utility's applies is address-level (see Q22). Tri-County Electric Cooperative: its published Interconnection Process, step 7, requires the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative to protect its personnel, facilities and operations', and step 10 has a TCEC representative attend to 'review the system's disconnect and safety features' before approval. TCEC prescribes no wording, letter height or material in that document. Duke Energy Florida: its filed Tier 1 Standard Interconnection Agreement deals with the disconnect switch (discretionary at Duke's expense for Tier 1) and does not itself carry a placard wording specification.
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Solar Requirements
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.