Hendry County is a county authority in the State of Florida, serving 39,619 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Jurisdiction & key facts
The standing 62-question set, answered for Hendry County against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
Hendry County is the authority having jurisdiction 90% confidence
- Holds
- Building and Electrical permitting/plans review/inspection for UNINCORPORATED Hendry County only, including named unincorporated communities Harlem, Sky Valley, Montura/Montura Ranch, Flaghole, Pioneer, Hookers Point, and Tropical. The County is NOT the AHJ inside the City of LaBelle or the City of Clewiston — both are incorporated municipalities that run their own Community Development/Building Divisions and issue their own permits under their own portals. This is stated affirmatively from the OUTSIDE: the City of Clewiston's own Permitting page reads 'Note: The Community Development Department only issues permits within the city limits. For any questions regarding the Harlem, Sky Valley, Montura/Montura Ranch, Flaghole, Pioneer, Hookers Point, or Tropical areas, contact the Hendry County offices' — i.e. Clewiston itself names the county as AHJ for those specific unincorporated pockets and excludes itself. LaBelle's own site (citylabelle.com) independently confirms a full Community Development building-permit apparatus (Building Forms & Permit Applications, Fee Schedules, Planning & Zoning) separate from the county's. Both cities are physically inside Hendry County but are carved out of the county's building-permit jurisdiction. Note the County's Building & Licensing Department maintains a 'Clewiston Office' (1100 Olympia St) in addition to its LaBelle office — this is a satellite office location for county unincorporated-area business (per the same Clewiston page, callers about Clewiston's own city permits are directed to Clewiston's own Community Development Dept, not this county office), not evidence the county permits inside city limits.
- Overridden by
- FS 553.791 (Private Provider) lets a fee owner elect a private plans-reviewer/inspector instead of the County for any permit including electrical/PV — an owner election, not a delegation by the County. FS 553.79(1)(g) (HB 803, statewide, effective 1 Jul 2026 per the County's own FAQ) exempts <$7,500 single-family work from a permit, but the County's own FAQ states the exemption explicitly EXCLUDES 'any electrical, plumbing, structural, mechanical, or gas work' on a single-family dwelling — so it cannot reach a PV system, which is filed as an Electrical permit type here. FS 471.003(2)(h) statewide exempts a licensed electrical contractor from a PE-stamp requirement up to $125,000/600A on a residential job, regardless of county rule.
- Why not higher
- Direct, current, first-party evidence on both sides of the line: the County's own Building & Licensing homepage (hendryfla.net) plus its permit application, fee schedule, and permit-category documents describe unincorporated-area permitting; the City of Clewiston's own Permitting page affirmatively excludes itself and names the specific unincorporated places that remain the County's; the City of LaBelle's own site independently shows a full, separate building-permit operation. Held at 90 rather than higher only because I could not fully verify from primary text whether Hendry County's Land Development Code (Municode-hosted, disallowed to ClaudeBot per robots.txt, checked 12 Sep 2026) contains any interlocal-agreement language that might complicate this at the margins (e.g. a specific annexed parcel still under county permitting), and because Hendry County's own briefed URL required no re-derivation (it was live), but subpages were reached by URL construction rather than a site-wide crawl.
https://www.hendryfla.net/government/county_departments/building___licensing/index.php
- Permit required
- Yes95%
- Permit cost
- $65.00 flat fee for the Solar/Wind/Water Energy Generating Device permit line item (plus the $65 non-refundable application fee credited to it at issuance — these are not necessarily…85%
- Portal
- BS&A Online (bsaonline.com) — the County's Building Department permitting/inspection-scheduling/contractor-registration/record-search portal90%
- Electrical code
- 2020 NEC, effective 31 December 2023 — NOT the 2023 edition (see why)96%
- Booking an inspection
- By phone (863-675-5245 LaBelle office / 863-983-1463 Clewiston office) or email (inspection@hendryfla.net), providing the permit number;82%
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes Q3 Electrical and building permits — PV is filed under the ELECTRICAL trade ('Energy Generating Device' category) on the County's single, multi-trade Building Permit Application; Q4 Where you file — BS&A Online (bsaonline.com) — the County's Building Department permitting/inspection-scheduling/contractor-registration/record-search portal Q20
- Permit required
- Yes95% source
- What it costs
- $65.00 flat fee for the Solar/Wind/Water Energy Generating Device permit line item (plus the $65 non-refundable application fee credited to it at issuance — these are not necessarily additive,85% source
- Key document
- department page + County fee schedule cited by 3 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes, for unincorporated Hendry County only — not inside LaBelle or Clewiston city limits 90% · department page
- What does this authority permit itself, and what does it delegate? The County permits and inspects Building, Electrical, Plumbing, Mechanical and Mobile Home trades itself for unincorporated county; it does not permit inside LaBelle or Clewiston, and it allows an owner to 'delegate' plan review/inspection to a state-licensed Private Provider under FS 553.791 (an owner election, not a County delegation) 82% · department page + building permit application
- Is a permit required for a residential rooftop PV system? Yes 95% · County permit-category reference (PDF, extracted with pdftotext)
- Is there a separate electrical permit, or is it combined? PV is filed under the ELECTRICAL trade ('Energy Generating Device' category) on the County's single, multi-trade Building Permit Application; the same application form has a 'Trades' checkbox list (Electrical/Mechanical/Plumbing) alongside the general Building checkbox, and a Sub-Contractor List assigns each trade its own contractor/license/signature line — so it is closer to one application producing per-trade permit lines than two wholly separate applications 62% · County building permit application (PDF, extracted with pdftotext)
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? A state-licensed Electrical Contractor pulls/signs the Electrical trade line, unless the property owner qualifies and elects Owner-Builder 75% · County building permit application (PDF, extracted with pdftotext)
- Must the contractor be registered with this authority before applying? Yes — the County requires contractors to submit registration/state license/BTL/workers' comp/liability insurance documentation to the Building Department, and separately charges its own local contractor-licensing fees (state-registered contractor initial registration $150, renewal $120) 72% · department page + County fee schedule
- Is a homeowner permitted to self-install and self-permit? Yes — Owner-Builder self-permitting is explicitly allowed even for the Electrical trade specifically 80% · County permit application checklist (PDF, extracted with pdftotext)
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? For the Electrical/Energy Generating Device permit type: the $65 non-refundable application fee, Contractor+Subs licensing info (or Owner-Builder Affidavit + proof of ownership), a detailed description of work and purpose including amps and phase(s), a site plan showing all existing structures and distance from all property lines to the proposed equipment location, and signed energy calculations 'if applicable' 78% · County permit application checklist (PDF, extracted with pdftotext)
- How many copies, and in what format? Electronic submission is accepted (online, by email, or in person); where a hard copy is submitted, 1 hard copy plus 1 digital PDF copy is required for any document larger than 11x17 68% · County permitting flow chart (PDF, extracted with pdftotext)
- Is a site plan required, and what must it show? Yes — a site plan showing all existing structures and the distance from all property lines to the proposed equipment location is required on the Electrical permit checklist 80% · County permit application checklist (PDF, extracted with pdftotext)
- Is an electrical PE stamp required, and at what threshold? Statewide floor: no PE stamp is required for a licensed electrical contractor's work valued at $125,000 or less with aggregate residential service capacity of 600 amperes (240V) or less (FS 471.003(2)(h)) 62% · Florida Statute
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? BS&A Online (bsaonline.com) — the County's Building Department permitting/inspection-scheduling/contractor-registration/record-search portal 90% · department page (live portal links)
- Can the whole application be completed online? Largely yes for the application itself via BS&A Online, but the paper Building Permit Application form requires the applicant's signature to be notarized (in person or via online notarization), so a from-scratch retrofit-PV application may still involve an offline/notarization step depending on which submission path is used 60% · County permitting flow chart + building permit application form
- What does a residential solar permit cost? $65.00 flat fee for the Solar/Wind/Water Energy Generating Device permit line item (plus the $65 non-refundable application fee credited to it at issuance — these are not necessarily additive, see why) 85% · County adopted fee schedule (PDF, extracted with pdftotext)
- How is the fee calculated? Flat fee for the Energy Generating Device line item itself ($65); valuation- or amperage-based for any accompanying electrical service work 78% · County adopted fee schedule (PDF, extracted with pdftotext)
- Is there a separate plan-check fee? Yes, generally — Plan Review fee is 30% of the base building permit fee — but it is unconfirmed whether this line applies on top of the flat $65 solar fee specifically or only to valuation-based permits 55% · County adopted fee schedule (PDF, extracted with pdftotext)
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- How long is an issued permit valid before it expires? A permit that becomes idle (no activity/inspection) for six (6) months or more expires and must be renewed (at 50% of the original permit fee) before further inspections 80% · department FAQ page
- Which utility handles interconnection here? Depends on location within the county. For the County's own AHJ area (unincorporated Hendry, including Harlem, Sky Valley, Montura, Flaghole, Pioneer, Hookers Point, Tropical): Glades Electric Cooperative, a not-for-profit rural electric cooperative, confirmed to serve 'portions of Glades, Hendry, Highlands, and Okeechobee counties.' Inside LaBelle city limits: Florida Power & Light (FPL) — stated directly by the City of LaBelle's own Utilities Department page. Inside Clewiston city limits: the City of Clewiston's own municipal electric utility (Clewiston Utilities) — the city is self-described as one of Florida's most reliable MUNICIPAL utilities and runs its own Net Metering Program page. 78% · utility 'About Us' page + city utility pages
- Where does the utility sit in the sequence? For the co-op-served county area: not established from a published interconnection standard. GEC's own guidance says to contact its Engineering Department BEFORE signing with a solar contractor for a load analysis and to complete a Net Metering Agreement — this places utility engagement early/concurrent with installation rather than describing a formal post-inspection energization gate the way the PSC's IOU rule does. 45% · utility program page (interconnection sequence not confirmed)
28 questions answered against Hendry County’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes, for unincorporated Hendry County only — not inside LaBelle or Clewiston city limits
Why the confidence is not higherSee jurisdiction block. County's own Building & Licensing page describes itself as issuing 'permits for all new construction...service equipment changes' with LaBelle and Clewiston office locations serving the unincorporated county; Clewiston's own Permitting page names the county as AHJ only for specific unincorporated communities outside Clewiston's city limits.
department page checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
The County permits and inspects Building, Electrical, Plumbing, Mechanical and Mobile Home trades itself for unincorporated county; it does not permit inside LaBelle or Clewiston, and it allows an owner to 'delegate' plan review/inspection to a state-licensed Private Provider under FS 553.791 (an owner election, not a County delegation)
Why the confidence is not higherBuilding Permit Application requires a signed Sub-Contractor List covering Building/Mobile Home/Electrical/Plumbing/Mechanical/Aluminum/Gas/Roofing/Drywall/Carpentry/Masonry/Concrete trades, all administered by the same County Building & Licensing office; the Private Provider program is documented on the County's own Private Provider page citing FS 553.791.
department page + building permit application checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/private_provider.php
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes
Why the confidence is not higherThe County's own online Permit Category list has a dedicated entry: 'For Solar Panels Use ENERGY GENERATING DEVICE' under the ELECTRICAL permit type, and the County's Adopted Fee Schedule has a specific line item: 'Solar, Wind and Water Energy Generating Devices (Ground, Wall, or Roof Mounted) $65.00' — both are unambiguous, current, first-party evidence a permit is required and categorized.
County permit-category reference (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/PERMIT-CATEGORY%20-%20ONLINE.pdf?t=202604011439260
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
PV is filed under the ELECTRICAL trade ('Energy Generating Device' category) on the County's single, multi-trade Building Permit Application; the same application form has a 'Trades' checkbox list (Electrical/Mechanical/Plumbing) alongside the general Building checkbox, and a Sub-Contractor List assigns each trade its own contractor/license/signature line — so it is closer to one application producing per-trade permit lines than two wholly separate applications
Why the confidence is not higherRead directly from the County's current Building Permit Application (Rev. 3/2026) form structure: one application, a checkbox for 'Energy Generated Device (solar)' under new-work types, and a separate 'Trades: Electrical/Mechanical/Plumbing' checkbox plus a per-trade Sub-Contractor signature table. Confidence held at 62 because the form does not state in words whether Building and Electrical for a PV job are legally two permit numbers or one; that is an inference from the form's layout.
County building permit application (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/Building%20Permit%20Application_March2026_Fillable%20App.pdf?t=202603060806010
Q5 Who is allowed to pull the electrical permit? Core Who may apply
A state-licensed Electrical Contractor pulls/signs the Electrical trade line, unless the property owner qualifies and elects Owner-Builder
Why the confidence is not higherThe Building Permit Application's Sub-Contractor List has a dedicated 'Electrical' row requiring a contractor's printed name, license number and signature before that trade's permit issues; the Permit Application Check List's Electrical section independently requires either 'Contractor + Subs Licensing Information' with contract price OR an Owner-Builder Affidavit.
County building permit application (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/Building%20Permit%20Application_March2026_Fillable%20App.pdf?t=202603060806010
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
Yes — the County requires contractors to submit registration/state license/BTL/workers' comp/liability insurance documentation to the Building Department, and separately charges its own local contractor-licensing fees (state-registered contractor initial registration $150, renewal $120)
Why the confidence is not higherThe Building & Licensing homepage states verbatim: 'Starting immediately, please send all contractors' information, Registration, State License, BTL, Workers' Comp., and Liability Insurance to: contractors@hendryfla.net'; the County's Adopted Fee Schedule Section III ('Contractor Licensing Fees') separately charges County-specific registration/renewal fees layered on top of state licensure. Held below 80 because the notice is not phrased as an explicit precondition-to-permit statement the way Ocoee's was.
department page + County fee schedule checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes — Owner-Builder self-permitting is explicitly allowed even for the Electrical trade specifically
Why the confidence is not higherThe County's Permit Application Check List's own 'Electrical' section lists as an acceptable alternative: 'OR State Form - O.B. Affidavit signed by Prop Owner at the time of permit issuance' — this is stated per-trade, including Electrical by name, which is stronger evidence than a generic owner-builder statute reference; it implements FS 489.103.
County permit application checklist (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/PERMIT%20APP%20CHECKLIST%20w%20PRODUCT%20APPROVALS%20-REV%207.1.26.pdf?t=202606261619530
Q8 What documents make up a complete submittal? Core Submittal package
For the Electrical/Energy Generating Device permit type: the $65 non-refundable application fee, Contractor+Subs licensing info (or Owner-Builder Affidavit + proof of ownership), a detailed description of work and purpose including amps and phase(s), a site plan showing all existing structures and distance from all property lines to the proposed equipment location, and signed energy calculations 'if applicable'
Why the confidence is not higherQuoted directly from the 'Electrical' section of the County's own Permit Application Check List (Rev. 2/2026), which is the general electrical-permit checklist used for all electrical work including the ENERGY GENERATING DEVICE (solar) category; not a PV-specific checklist by name, so a few line items (e.g. energy calcs) are hedged 'if applicable' rather than mandatory.
County permit application checklist (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/PERMIT%20APP%20CHECKLIST%20w%20PRODUCT%20APPROVALS%20-REV%207.1.26.pdf?t=202606261619530
Q9 How many copies, and in what format? Submittal package
Electronic submission is accepted (online, by email, or in person); where a hard copy is submitted, 1 hard copy plus 1 digital PDF copy is required for any document larger than 11x17
Why the confidence is not higherThe County's own Permitting Flow Chart for Single Family/Mobile Home states 'Applicant can apply online, by email, or in person'; the general Building Permit Application checklist elsewhere specifies '(1) hard copy - if larger than 11x17 include (1) Digital PDF format thru email, CD or thumb drive.' Neither is solar-specific.
County permitting flow chart (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/building_code_enforcement/docs/Permitting%20Flow%20Chart%20for%20SFD%20or%20Mobile%20Home%206.2026%20EN.ES.pdf?t=202606301438340
Q10 Is a site plan required, and what must it show? Core Submittal package
Yes — a site plan showing all existing structures and the distance from all property lines to the proposed equipment location is required on the Electrical permit checklist
Why the confidence is not higherQuoted directly from the Electrical section of the County's Permit Application Check List: 'Site Plan showing ALL existing structures + distance from ALL property lines to proposed location.'
County permit application checklist (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/PERMIT%20APP%20CHECKLIST%20w%20PRODUCT%20APPROVALS%20-REV%207.1.26.pdf?t=202606261619530
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Nothing published by this authority.
Where we lookedBuilding Permit Application (full text), Permit Application Check List Electrical section (full text) — neither uses the term 'one-line diagram,' 'three-line diagram,' or 'riser diagram'; only 'Detailed Description of Work and Purpose *Amps* *Phase(s)*' is required for the Electrical trade
Q12 Are string and conductor calculations required? Drawings & calculations
Nothing published by this authority.
Where we lookedSame Electrical-section checklist as Q11 — no mention of string sizing, conductor sizing, or ampacity calculations beyond the amps/phase(s) fields
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Nothing published by this authority.
Where we lookedBuilding Permit Application, Permit Application Check List, Adopted Fee Schedule — none states a numeric structural PE-stamp threshold; Hendry County's Land Development Code and Code of Ordinances (where such a threshold might be codified) are hosted only on library.municode.com, which disallows ClaudeBot per robots.txt (checked 12 Sep 2026)
https://library.municode.com/fl/hendry_county/codes/code_of_ordinances
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Statewide floor: no PE stamp is required for a licensed electrical contractor's work valued at $125,000 or less with aggregate residential service capacity of 600 amperes (240V) or less (FS 471.003(2)(h))
Why the confidence is not higherSourced directly to the Florida Statute; I found no Hendry-County-specific document stating a different or additional threshold in the Building Permit Application, Fee Schedule, or Permit Checklist, so this is the state floor, not a confirmed County-specific rule.
Florida Statute checked 2026-09-12 http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&URL=0400-0499/0471/Sections/0471.003.html
Q15 What does a residential solar permit cost? Core Fees
$65.00 flat fee for the Solar/Wind/Water Energy Generating Device permit line item (plus the $65 non-refundable application fee credited to it at issuance — these are not necessarily additive, see why)
Why the confidence is not higherQuoted verbatim from the County's own August 2026 Adopted Fee Schedule, Section IV.10: 'Solar, Wind and Water Energy Generating Devices (Ground, Wall, or Roof Mounted) $65.00.' Ran controls in the same document: 'electrical' = multiple hits (Electric Fees section, positive control passed); 'zzqqx' = 0 hits (fabricated control passed) — confirms the search and extraction were working and this is genuinely the only solar-specific fee line, not a missed one. If the job also requires a new/upgraded electrical service, the separate per-amp New Electrical Service fee (Section IV.20) would also apply — held at 85 rather than higher because I could not confirm from this document alone whether the $65 line item is inclusive of or additional to a same-project electrical-service fee.
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q16 How is the fee calculated? Core Fees
Flat fee for the Energy Generating Device line item itself ($65); valuation- or amperage-based for any accompanying electrical service work
Why the confidence is not higherFee Schedule Section IV.10 sets a flat $65 for the solar/wind/water generating-device line, distinct from the valuation-based general building fee formula (Section I) and the per-amp new-electrical-service formula (Section IV.20: $0.90/amp for the first 100 amps, $0.60/amp above that).
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q17 Is there a separate plan-check fee? Fees
Yes, generally — Plan Review fee is 30% of the base building permit fee — but it is unconfirmed whether this line applies on top of the flat $65 solar fee specifically or only to valuation-based permits
Why the confidence is not higherFee Schedule Section IV.13: 'Plan review fee 30% of the base building permit fee.' This is stated as a general rule for 'the base building permit fee,' and the solar line item is a flat miscellaneous fee rather than a 'base building permit fee' in the valuation sense used elsewhere in the schedule, so applicability to a PV-only Electrical permit is an inference, not a confirmed statement.
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q18 What is the stated plan-review turnaround? Core Timeline & validity
Nothing published by this authority.
Where we lookedBuilding & Licensing homepage, FAQ page (full text), Permitting Flow Chart, Post-Storm Permitting page — none states a stated plan-review turnaround time (business days) for a standard, non-emergency permit
https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q19 How long is an issued permit valid before it expires? Timeline & validity
A permit that becomes idle (no activity/inspection) for six (6) months or more expires and must be renewed (at 50% of the original permit fee) before further inspections
Why the confidence is not higherCounty's own Building & Licensing FAQ (Impact Fees section) states: 'If a permit submitted prior to February 10, 2025 becomes idle for a period of six (6) months or more, the permit will expire, and the Impact Fee (along with the renewal or new permit fee) must be paid prior to any further inspections.' This 6-month idle-permit expiration rule matches the FBC default and reads as the County's general permit-validity rule, not one limited to pre-2025 permits, though it is phrased in the context of the 2025 Impact Fee rollout. Fee Schedule separately lists 'Renewal of Expired Permit — 50% of original fee.'
department FAQ page checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/building_and_permiting_faqs.php
Q20 Which permit portal does this authority use? Core Portal & process
BS&A Online (bsaonline.com) — the County's Building Department permitting/inspection-scheduling/contractor-registration/record-search portal
Why the confidence is not higherConfirmed directly from live links on the County's own Building & Licensing page: 'Apply for Permit' and 'Schedule Inspection' (both homeowner and contractor variants) route to bsaonline.com/DirectUrl/Cd_PermitApplication(Contractor)/3193 and Cd_InspectionRequest(Contractor)/3193; contractor account creation routes to bsaonline.com/Contractors/?uid=3193; and the County's own SFD/Mobile-Home permitting flow chart footer literally reads 'Apply for Permit | Hendry County / Port LaBelle Utilities | BS&A Online.'
department page (live portal links) checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q21 Can the whole application be completed online? Core Portal & process
Largely yes for the application itself via BS&A Online, but the paper Building Permit Application form requires the applicant's signature to be notarized (in person or via online notarization), so a from-scratch retrofit-PV application may still involve an offline/notarization step depending on which submission path is used
Why the confidence is not higherThe County's Permitting Flow Chart states applicants 'can apply online, by email, or in person'; separately, the current Building Permit Application form itself is designed around a notarized wet/online-notary signature block ('SIGN IN PRESENCE OF NOTARY PUBLIC... OR ONLINE NOTARIZATION'), which is in tension with a purely self-serve online flow depending on how BS&A Online implements it. I did not access the BS&A portal's actual submission UI to confirm which path an Electrical-only PV permit uses.
County permitting flow chart + building permit application form checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/building_code_enforcement/docs/Permitting%20Flow%20Chart%20for%20SFD%20or%20Mobile%20Home%206.2026%20EN.ES.pdf?t=202606301438340
Q22 Which utility handles interconnection here? Core Utility interconnection
Depends on location within the county. For the County's own AHJ area (unincorporated Hendry, including Harlem, Sky Valley, Montura, Flaghole, Pioneer, Hookers Point, Tropical): Glades Electric Cooperative, a not-for-profit rural electric cooperative, confirmed to serve 'portions of Glades, Hendry, Highlands, and Okeechobee counties.' Inside LaBelle city limits: Florida Power & Light (FPL) — stated directly by the City of LaBelle's own Utilities Department page. Inside Clewiston city limits: the City of Clewiston's own municipal electric utility (Clewiston Utilities) — the city is self-described as one of Florida's most reliable MUNICIPAL utilities and runs its own Net Metering Program page.
Why the confidence is not higherThree separate first-party sources for the three separate utility regimes: Glades Electric Cooperative's own 'Our Story' page states its service area; City of LaBelle's own 'Open Utility Account' how-do-I page states verbatim 'For electric services, please contact Florida Power and Light'; City of Clewiston's own site has a dedicated Utilities department (/178/Utilities) with a 'Net-Metering-Program-and-Agreements' page (/317) and a news item on municipal-utility reliability rankings. Held below 90 because I could not confirm from a territory map exactly which unincorporated parcels are Glades Electric Cooperative vs. potentially Lee County Electric Cooperative (LCEC), which also operates in this part of Southwest Florida — I found no direct evidence LCEC serves any part of Hendry County in this run, so I am not asserting it.
utility 'About Us' page + city utility pages checked 2026-09-12 https://www.gladeselectric.com/about-us/our-story/
Q23 Where does the utility sit in the sequence? Core Utility interconnection
For the co-op-served county area: not established from a published interconnection standard. GEC's own guidance says to contact its Engineering Department BEFORE signing with a solar contractor for a load analysis and to complete a Net Metering Agreement — this places utility engagement early/concurrent with installation rather than describing a formal post-inspection energization gate the way the PSC's IOU rule does.
Why the confidence is not higherGlades Electric Cooperative's 'Considering Solar?' page describes contacting GEC before contracting and completing a Net Metering Agreement, and states inverters must have automatic anti-islanding shutoff, but does not state in writing that the County must inspect and approve the system before GEC allows parallel operation (the explicit sequence that FL PSC Rule 25-6.065 imposes on investor-owned utilities like FPL). Fla. Stat. 366.91 leaves cooperatives to set their own net-metering/interconnection rules, so the PSC sequence cannot be assumed to carry over; I could not find GEC's actual written interconnection agreement/policy document (no PDF found on GEC's Member Forms page) to confirm the sequence directly.
utility program page (interconnection sequence not confirmed) checked 2026-09-12 https://www.gladeselectric.com/member-services/considering-solar/
Q24 Is a HOA or architectural approval required first? Overlays & special cases
Nothing published by this authority.
Where we lookedBuilding Permit Application, FAQ page — neither mentions HOA or architectural-review approval as a submittal precondition; not checked against the Land Development Code (Municode-hosted, disallowed)
Q25 Is there a historic-district review? Overlays & special cases
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page (full document list, 40+ items), FAQ page, general county FAQ page — no historic-district review process or document found for unincorporated county (LaBelle has its own separate 'Historical Downtown Plan,' but that is LaBelle's, outside county jurisdiction)
Q26 Is a wind or windstorm certification required? Overlays & special cases
Nothing published by this authority.
Where we lookedBuilding Permit Application, Permit Application Check List, Product Approval process description — no separate 'wind certification' distinct from the standard Florida Product Approval process was found
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page document list, FAQ page — no Specific Use Permit or Council-approval process for residential solar found; Land Development Code (where zoning approvals of this kind would be defined) is Municode-hosted and disallowed
Q28 Is there a system-size cap on residential generation? Overlays & special cases
Nothing published by this authority.
Where we lookedBuilding Permit Application, Fee Schedule, Permit Category list, and the County's 2014 (voluntary, new-construction-only) Solar Ready Construction Guidelines — the Guidelines mention a 10kW system as 'the largest that can easily be installed by a Florida homeowner under current policies and regulations' but this is 2014 background color in a voluntary document, not a stated regulatory cap, so it is not recorded as an answer
https://cms2.revize.com/revize/hendrycountyflnw/Solar_Ready_FL_Guidelines.pdf?t=202511041438090
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2020 NEC, effective 31 December 2023 — NOT the 2023 edition (see why) 96% · department page
- Which building code edition is in force? Florida Building Code, 8th Edition (2023) 92% · building permit application masthead
- What is the installation judged against? Florida Building Code 8th Edition (2023) and the 2020 NEC (effective 31 Dec 2023) 90% · department page + building permit application masthead
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
Nothing recorded for Hendry County on this step yet — 1 question checked and found unpublished. The guidance above is general.
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Not stated by the County in writing; the state floor is NEC 2020 §690.12 rapid shutdown, which the County has adopted as its electrical code effective 31 Dec 2023 55% · department page (NEC adoption notice; rapid-shutdown citation is inference)
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
Nothing recorded for Hendry County on this step yet — 6 questions checked and found unpublished. The guidance above is general.
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Must equipment be on a specific approved list? Not confirmed as PV-specific; the County's Product Approval List / Product Approval process (FL Product Approval or Miami-Dade NOA numbers) governs exterior building products (doors, windows, roofing) generally, per the County's own Permit Application Check List, but I found no statement that PV modules, inverters, or racking must appear on the Product Approval List specifically 45% · County permit application checklist (PDF, extracted with pdftotext)
- Is there a local rule on service upgrades or busbar sizing? No County-specific busbar-sizing rule found; a 'Change of Service or Reactivation of inactive service' is its own $65 minimum-fee electrical permit line, and new electrical service is fee-tiered by amperage ($0.90/amp first 100A, $0.60/amp above), which implies a permit is required for a service upgrade but does not itself state a technical busbar/sizing rule beyond NEC 50% · County adopted fee schedule (PDF, extracted with pdftotext)
20 questions answered against Hendry County’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2020 NEC, effective 31 December 2023 — NOT the 2023 edition (see why)
Why the confidence is not higherThis is the NEC-year trap named in this run's baseline. The County's own Building & Licensing homepage states verbatim, immediately below the 8th-Edition FBC notice: 'Also, the 2020 National Electrical Code will become effective on December 31, 2023.' The '(2023)' that appears elsewhere on County documents (e.g. the Building Permit Application's 'Current: 2023 8th Edition Florida Building Code') refers to the Florida Building Code cycle, not the NEC edition — exactly the conflation this brief warns against. Both the FBC-cycle-label and the NEC-edition statements come from the County's own current, first-party pages.
department page checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q30 Which building code edition is in force? Core Code editions in force
Florida Building Code, 8th Edition (2023)
Why the confidence is not higherStated on the masthead of the County's own current Building Permit Application: 'Current: 2023 8th Edition Florida Building Code,' and repeated on the Building & Licensing homepage notice ('the 8th Edition (2023) Florida Building Codes became effective on December 31, 2023').
building permit application masthead checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/Building%20Permit%20Application_March2026_Fillable%20App.pdf?t=202603060806010
Q31 Which fire code edition is in force? Code editions in force
Nothing published by this authority.
Where we lookedBuilding & Licensing homepage, Building Permit Application, FAQ page — none names a Fire Prevention Code edition; Hendry County's Public Safety (EMS) department page does not present itself as a separate Fire Marshal/fire-plans-review function the way some counties do, and no fire-code-edition notice equivalent to the FBC/NEC ones was found
https://www.hendryfla.net/government/county_departments/public_safety/index.php
Q32 Are there local amendments to any of the above? Core Code editions in force
Nothing published by this authority.
Where we lookedBuilding & Licensing homepage, FAQ page, Building Permit Application, Fee Schedule — no local technical amendment to the FBC or NEC (beyond the County's own fee-schedule/impact-fee ordinances, which are administrative, not technical, amendments) was found; Hendry County's Code of Ordinances is Municode-hosted and disallowed to ClaudeBot
https://library.municode.com/fl/hendry_county/codes/code_of_ordinances
Q33 What is the installation judged against? Core Electrical
Florida Building Code 8th Edition (2023) and the 2020 NEC (effective 31 Dec 2023)
Why the confidence is not higherCombines the County's own Building Permit Application masthead (FBC 8th Ed. 2023) with the Building & Licensing homepage's explicit NEC statement (2020 NEC, effective 12/31/2023) — same sources as Q29/Q30.
department page + building permit application masthead checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
No County-specific busbar-sizing rule found; a 'Change of Service or Reactivation of inactive service' is its own $65 minimum-fee electrical permit line, and new electrical service is fee-tiered by amperage ($0.90/amp first 100A, $0.60/amp above), which implies a permit is required for a service upgrade but does not itself state a technical busbar/sizing rule beyond NEC
Why the confidence is not higherFee Schedule Section IV.20 quoted directly; no separate technical busbar-sizing standard was found in the Building Permit Application, Permit Checklist, or FAQ pages reviewed.
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
Nothing published by this authority.
Where we lookedSolar Ready Construction Guidelines (2014, voluntary, new-construction-only — recommends 200A service and roof reinforcement for future PV, not a mandatory retrofit attachment-spacing rule), Permit Application Check List — no mandatory mounting-system or attachment-spacing rule for an as-built retrofit PV installation was found
https://cms2.revize.com/revize/hendrycountyflnw/Solar_Ready_FL_Guidelines.pdf?t=202511041438090
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page, FAQ page, Permit Application Check List — no ridge-setback or fire-access-pathway rule for rooftop PV is stated; the Florida Fire Prevention Code text that would set this (via NFPA 1) is not hosted by the County and was not independently located within this run's budget
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Not stated by the County in writing; the state floor is NEC 2020 §690.12 rapid shutdown, which the County has adopted as its electrical code effective 31 Dec 2023
Why the confidence is not higherInference from the County's own confirmed adoption of the 2020 NEC (Q29) — 2020 NEC §690.12 mandates rapid shutdown for PV systems on or in buildings — but no County document I found names 'rapid shutdown' or NEC 690.12 specifically.
department page (NEC adoption notice; rapid-shutdown citation is inference) checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page (40+ document titles read directly), Permit Application Check List, FAQ page — no placard requirement of any kind for PV/ESS is published by the County
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as Q38 — no placard wording is published anywhere on the County's Building & Licensing pages or documents
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as Q38 — no letter-height/colour/material spec published
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as Q38 — no facility/site-plan placard spec published by the County (the general Electrical-permit site plan under Q10 is a submittal document, not a posted field placard)
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedGlades Electric Cooperative's public site: 'Considering Solar?' page, Net Metering Guide PDF, and Member Forms & Information page (checked for a dedicated interconnection-standards document; none found publicly) — no placard specification beyond a generic reference to inverter automatic anti-islanding shutoff
https://www.gladeselectric.com/member-services/member-forms-information/
Q43 Where must the labels be placed? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame sources as Q42 — no label-placement specification found from either the County or Glades Electric Cooperative
https://www.gladeselectric.com/member-services/considering-solar/
Q44 Must equipment be on a specific approved list? Equipment listing
Not confirmed as PV-specific; the County's Product Approval List / Product Approval process (FL Product Approval or Miami-Dade NOA numbers) governs exterior building products (doors, windows, roofing) generally, per the County's own Permit Application Check List, but I found no statement that PV modules, inverters, or racking must appear on the Product Approval List specifically
Why the confidence is not higherThe Permit Application Check List requires a 'Product Approval List' with FLPA/NOA numbers for 'Exterior Doors, Exterior Windows, Roof Material, Exterior Fixtures' on new construction and roofing jobs; it does not name PV racking/modules/inverters among the covered categories, so applicability to solar equipment specifically is unconfirmed rather than a stated requirement.
County permit application checklist (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/PERMIT%20APP%20CHECKLIST%20w%20PRODUCT%20APPROVALS%20-REV%207.1.26.pdf?t=202606261619530
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page, Permit Application Check List, Permit Category list — no battery/ESS-specific permitting language exists in any of these; the Permit Category list's ELECTRICAL 'Energy Generating Device' entry does not distinguish PV-only from PV+storage
https://cms2.revize.com/revize/hendrycountyflnw/PERMIT-CATEGORY%20-%20ONLINE.pdf?t=202604011439260
Q46 Is there a separate ESS permit or inspection? Battery / ESS
Nothing published by this authority.
Where we lookedSame as Q45 — no separate ESS permit or inspection type is named
https://cms2.revize.com/revize/hendrycountyflnw/PERMIT-CATEGORY%20-%20ONLINE.pdf?t=202604011439260
Q47 Is a ground mount treated as a structure? Core Ground mount
Nothing published by this authority.
Where we lookedFee Schedule (Section IV.10 groups Ground/Wall/Roof-mounted devices under one fee line, which does not settle a structure-classification question), Permit Application Check List — whether the Land Development Code defines a ground-mount array as a 'structure' triggering separate setback/height rules is not stated in any County document reached; the LDC itself is Municode-hosted and disallowed
https://library.municode.com/fl/hendry_county/codes/code_of_ordinances
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
Nothing published by this authority.
Where we lookedGlades Electric Cooperative's public site (Considering Solar page, Net Metering Guide PDF, Member Forms page) — no published interconnection/technical standards document stating AC-disconnect placement was found; unlike an IOU bound by FL PSC Rule 25-6.065(6)(a), GEC as a cooperative sets its own standard under Fla. Stat. 366.91 and does not appear to publish it online
https://www.gladeselectric.com/member-services/member-forms-information/
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? By phone (863-675-5245 LaBelle office / 863-983-1463 Clewiston office) or email (inspection@hendryfla.net), providing the permit number; contractors can additionally schedule through BS&A Online 82% · County inspection-order document (PDF, extracted with pdftotext)
- How much notice is required? Inspections must be requested before 3:30 PM to be scheduled for the next business day 88% · County inspection-order document (PDF, extracted with pdftotext)
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Yes, ordinarily the County's own Building Inspectors perform the final inspection, unless the fee owner has elected a registered Private Provider under FS 553.791 for that permit 78% · department page
- If delegated, to whom? Not delegated by the County by default; if the fee owner elects a Private Provider under FS 553.791, that firm performs plan review and/or inspection instead of the County 75% · department page
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? For new single-family construction the County publishes a fixed 21-stage inspection order that includes, among others, Rough Electric and Final Electric; for a PV-only retrofit on an existing home, this new-construction sequence would not apply in full — only the relevant electrical stage(s) (most likely Final Electric, and Rough Electric if a new service/panel is involved) would be required, but the County does not publish a PV-specific reduced sequence 68% · County inspection-order document (PDF, extracted with pdftotext)
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- What must be on site at inspection? The issued permit must be posted/available on the property at the time of inspection 65% · County permitting flow chart (PDF, extracted with pdftotext)
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- What is issued on pass? For new construction, a Certificate of Occupancy/Certificate of Completion ($30 fee line item) is issued; for a PV-only retrofit permit on an existing dwelling, the County's material does not state a specific issued document beyond a passed Final Electrical inspection closing the permit 52% · County adopted fee schedule (PDF, extracted with pdftotext)
- Who notifies the utility for PTO? Not established for Hendry-County-served areas from a County document; for the cooperative-served unincorporated area, GEC's own material implies the customer/installer completes GEC's Net Metering Agreement and load-analysis process directly with GEC rather than through the County 45% · utility program page (inference)
- Is there a re-inspection fee? $60.00 92% · County adopted fee schedule (PDF, extracted with pdftotext)
- How are corrections issued and cleared? Via a Revision Request submitted to the Building Department (there is a $45 Plans Revision fee on the County's fee schedule); the County's flow chart shows the Department contacting the applicant if 'additional information is required,' with missing documentation submitted by email to permit@hendryfla.net 60% · County fee schedule + permitting flow chart
14 questions answered against Hendry County’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
By phone (863-675-5245 LaBelle office / 863-983-1463 Clewiston office) or email (inspection@hendryfla.net), providing the permit number; contractors can additionally schedule through BS&A Online
Why the confidence is not higherQuoted directly from the County's own 'New House Inspection Order' document footer and the BS&A Online contractor inspection-request link on the Building & Licensing page.
County inspection-order document (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/NEW%20HOUSE%20INSPECTION%20ORDER%20FOR%20PUBLIC.pdf?t=202602181119300
Q50 How much notice is required? Core Booking & scheduling
Inspections must be requested before 3:30 PM to be scheduled for the next business day
Why the confidence is not higherQuoted verbatim from the County's own 'New House Inspection Order' document: 'Inspections need to be requested in advance before 3:30 PM for the next business day.'
County inspection-order document (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/NEW%20HOUSE%20INSPECTION%20ORDER%20FOR%20PUBLIC.pdf?t=202602181119300
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedNew House Inspection Order document (full text), Building & Licensing homepage — neither states whether same-day or AM/PM inspection windows are offered; only the next-business-day/3:30pm cutoff rule (Q50) is stated
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Yes, ordinarily the County's own Building Inspectors perform the final inspection, unless the fee owner has elected a registered Private Provider under FS 553.791 for that permit
Why the confidence is not higherBuilding & Licensing page names Building_Inspectors@hendryfla.net as the County's own inspection contact with no third-party default; the County's separate Private Provider page confirms an OWNER may opt out to a private inspector, which is an election, not the County's default delegation.
department page checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/index.php
Q53 If delegated, to whom? Core Who inspects
Not delegated by the County by default; if the fee owner elects a Private Provider under FS 553.791, that firm performs plan review and/or inspection instead of the County
Why the confidence is not higherFollows from the County's own Private Provider Registration page, which frames private-provider use as a fee-owner election under state statute, not a County referral or default arrangement.
department page checked 2026-09-12 https://www.hendryfla.net/government/county_departments/building___licensing/private_provider.php
Q54 Which inspections are required, and in what order? Core Stages & sequence
For new single-family construction the County publishes a fixed 21-stage inspection order that includes, among others, Rough Electric and Final Electric; for a PV-only retrofit on an existing home, this new-construction sequence would not apply in full — only the relevant electrical stage(s) (most likely Final Electric, and Rough Electric if a new service/panel is involved) would be required, but the County does not publish a PV-specific reduced sequence
Why the confidence is not higherThe County's own 'New House Inspection Order' document lists the full 21-step sequence for new house construction (Footer, Underground Plumbing, Setbacks/Soil/Compaction/Foundation, Tie/Bond Beam, Truss, Roof Sheathing, Wall Sheathing, Roof Dry-In, Final Roof, 2nd Rough Plumbing, Rough Electric, Rough HVAC, Framing, Lathe/Stucco, Insulation, Final HVAC, Final Plumbing, Final Electric, Final Building, Water Service, Sewer Connection). Its title and content ('NEW HOUSE') make clear it governs new construction, not a PV retrofit onto an existing dwelling; the retrofit-specific subset is my inference, not a stated County reduction.
County inspection-order document (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/NEW%20HOUSE%20INSPECTION%20ORDER%20FOR%20PUBLIC.pdf?t=202602181119300
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
Nothing published by this authority.
Where we lookedNew House Inspection Order document — the published sequence includes 'Roof Dry-In' and 'Final Roof' stages for new construction, but no statement addresses whether a PV-only retrofit (no re-roofing) on an existing home ever triggers a rough-in or mid-roof-type inspection
Q56 Does the inspector verify labels and listings? Core What is checked
Nothing published by this authority.
Where we lookedNew House Inspection Order document, Building & Licensing homepage, FAQ page — none states that the inspector verifies equipment labels/listings as a discrete checked item at Final Electric
Q57 Is there a published inspection checklist? Core What is checked
Nothing published by this authority.
Where we lookedBuilding & Licensing Documents page (full 40+ item list) — the County publishes an inspection ORDER (sequence of stages, see Q54) but no itemized inspection CHECKLIST (i.e., a list of pass/fail criteria at each stage) was found
Q58 What must be on site at inspection? Core Documents on site
The issued permit must be posted/available on the property at the time of inspection
Why the confidence is not higherThe County's own Permitting Flow Chart, Step Six, states: '...Post the permit on property.' This is stated in the context of new-construction permitting, not solar-specifically, but is the only on-site-document requirement found.
County permitting flow chart (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/building_code_enforcement/docs/Permitting%20Flow%20Chart%20for%20SFD%20or%20Mobile%20Home%206.2026%20EN.ES.pdf?t=202606301438340
Q59 Is there a re-inspection fee? Corrections & re-inspection
$60.00
Why the confidence is not higherQuoted verbatim from the County's own August 2026 Adopted Fee Schedule: 'Reinspection Fee $60.00.' This is the County-wide reinspection fee, not solar-specific, but it is the only reinspection fee the County publishes.
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q60 How are corrections issued and cleared? Corrections & re-inspection
Via a Revision Request submitted to the Building Department (there is a $45 Plans Revision fee on the County's fee schedule); the County's flow chart shows the Department contacting the applicant if 'additional information is required,' with missing documentation submitted by email to permit@hendryfla.net
Why the confidence is not higherCombines the County's own 'Revision Request' form (listed among New Application Forms), the $45 'Plans Revision fee' line item in the Adopted Fee Schedule, and Step Four of the County's Permitting Flow Chart ('Building Dept. will contact applicant if the permit is ready or additional information is required'). None of these three sources is solar-specific.
County fee schedule + permitting flow chart checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q61 What is issued on pass? Core Final sign-off & PTO
For new construction, a Certificate of Occupancy/Certificate of Completion ($30 fee line item) is issued; for a PV-only retrofit permit on an existing dwelling, the County's material does not state a specific issued document beyond a passed Final Electrical inspection closing the permit
Why the confidence is not higherThe Fee Schedule lists 'Certificate of Occupancy/Certificate of Completion $30.00' as a line item, but this is a general new-construction/change-of-occupancy item; nothing in the Building Permit Application, Fee Schedule, or Inspection Order documents I read states what closes out an Electrical-only PV retrofit permit specifically (e.g. whether a distinct 'PTO letter' or approval document is issued by the Building Department itself, as opposed to the utility's own PTO process under Q62).
County adopted fee schedule (PDF, extracted with pdftotext) checked 2026-09-12 https://cms2.revize.com/revize/hendrycountyflnw/August%202026_Adopted%20Fee%20Schedule.pdf?t=202608251355470
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Not established for Hendry-County-served areas from a County document; for the cooperative-served unincorporated area, GEC's own material implies the customer/installer completes GEC's Net Metering Agreement and load-analysis process directly with GEC rather than through the County
Why the confidence is not higherNo Hendry County Building Department document addresses utility PTO notification at all (this sits at the utility, not the AHJ, per the brief's own guidance). Glades Electric Cooperative's 'Considering Solar?' page describes the customer/installer engaging GEC's Engineering Department directly and completing GEC's own Net Metering Agreement, which places the notification obligation on the customer/installer rather than the County — consistent with, but not a direct statement of, standard practice.
utility program page (inference) checked 2026-09-12 https://www.gladeselectric.com/member-services/considering-solar/
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
No change record for this authority yet. Values arrive here as they are researched, and each one is dated.
Labels & placards for this authority
Wording None%
Size, colour & material None%
Where they go None%
What the utility wants on top None%
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Solar Requirements
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.