Town of Davie is a town authority in the State of Florida, serving 105,691 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Town of Davie against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Town of Davie is the authority having jurisdiction 88% confidence
Holds
Building and Electrical (plus Plumbing where applicable, and Planning & Zoning review specifically when panels are ground-mounted). Davie's own Building Division reviews and inspects solar permits itself; it is not delegated to Broward County.
Overridden by
Three separate overrides apply on top of Davie's own review: (1) Broward County's Board of Rules and Appeals (BORA) sets countywide MINIMUM HVHZ submittal standards that bind every building official in Broward, including Davie -- Policy #09-02's Uniform Permit Submittal Matrix for Solar Thermal/Electric, plus Formal Interpretations FI-31 (rooftop-clearance exemption for PV, FBC 1522.3) and FI-35 (confirms NFPA 70, 2020 as the electrical code edition). BORA issues no permits itself. (2) Florida Statute overrides Davie's own stated permit-validity practice: CS/CS/HB 803 (enrolled, 2026 Legislature, effective 1 Jul 2026) amends F.S. 553.79(1)(c) to set a 1-year floor on local-government-issued single-family-dwelling permits, and F.S. 553.792(1)(a) sets a 30-business-day plan-review floor for most residential work (5 business days only for electrical work under $15,000 on an existing home). Davie's own General Information page still states a 180-day permit-validity figure that is now below the statutory floor. (3) Florida Power & Light (FPL), not the Town, controls interconnection sequencing, the AC-disconnect-switch requirement (waived entirely for UL-1741 Tier-1 systems), and Permission to Operate, per FPL's own PSC-filed tariff.
Why not higher
Davie's own Building Division hosts a full set of solar-specific documents (Solar Panel Checklist, Permit Matrix, Solar Panel Information Required, Solar Permits/ESS handout) naming itself as the reviewing and inspecting authority, and Broward County's own building-department page confirms Davie is NOT one of the seven small unincorporated communities the County itself permits -- i.e., this was checked from the county side, not just taken on Davie's word. The three overrides above are each sourced to a primary document (BORA's own Formal Interpretations index via a dated Wayback capture since broward.org/CodeAppeals is now a bare, link-less Next.js landing page; the enrolled 2026 HB 803 text from flsenate.gov; and FPL's own PSC-filed tariff sections 7 and 9).

https://www.davie-fl.gov/206/Building

Permit required
Yes — a building permit is required for residential rooftop PV95%
Permit cost
No flat fee — valuation-based: Permit fee is 0.95% of construction value (minimum $55), PLUS a separate Plan Review fee of 0.75% of construction value (minimum $25),90%
Plan review
Approximately 30 business/working days85%
Portal
Three linked systems: OAS (Online Application Submittal, required for all new submissions as of 12 Jan 2026) feeds into ProjectDox for electronic plan review;88%
Electrical code
202085%
Own placard wording
No — Davie does not specify its own placard wording; it requires that required signage be shown on the electrical plans but leaves the wording to NEC 690/705/70665%
Booking an inspection
Portal (eSuite, for registered contractors) or Phone (automated call-in system) — plus an OAS-based inspection-request form85%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes — a building permit is required for residential rooftop PV Q3 Electrical and building permits — Combined under a master permit with separate trade reviews — Broward County BORA Policy #09-02 requires 'Building Departments shall establish an individual master… Q4 Plan review — Approximately 30 business/working days Q18 Where you file — Three linked systems: OAS (Online Application Submittal, required for all new submissions as of 12 Jan 2026) feeds into ProjectDox for electronic plan review; Q20

Permit required
Yes — a building permit is required for residential rooftop PV95% source
What it costs
No flat fee — valuation-based: Permit fee is 0.95% of construction value (minimum $55), PLUS a separate Plan Review fee of 0.75% of construction value (minimum $25),90% source
Plan review turnaround
Approximately 30 business/working days85% source
Key document
Town of Davie Solar Panel Checklist + Broward BORA Permit Matrix cited by 9 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes — the Town of Davie Building Division is the AHJ for residential rooftop solar within town limits 92% · department page + county-side confirmation
    • What does this authority permit itself, and what does it delegate? Both — Davie's Building Division issues and reviews Structural, Electrical and (if applicable) Plumbing permits itself for solar. A Planning & Zoning review is also triggered if panels are ground-mounted. No delegation to Broward County; Broward County's Board of Rules and Appeals (BORA) sets countywide minimum HVHZ submittal standards that Davie's review must meet, but BORA issues no permits itself. 90% · Town of Davie Solar Panel Checklist
    • Is a permit required for a residential rooftop PV system? Yes — a building permit is required for residential rooftop PV 95% · Town of Davie Solar Panel Checklist
    • Is there a separate electrical permit, or is it combined? Combined under a master permit with separate trade reviews — Broward County BORA Policy #09-02 requires 'Building Departments shall establish an individual master permit for both Solar Thermal and Solar Electric installations to which applicable subsidiary categories are to be tied,' and Davie's own checklist lists Structural, Electrical and Plumbing as separate 'Required Permit Applications' tied to the same job, each with its own review stop. 80% · Broward County BORA Policy #09-02, as hosted by Davie
    • Is a HOA or architectural approval required first? No — no HOA/architectural-board approval appears in Davie's own list of required reviews for solar 70% · Town of Davie Solar Panel Checklist
    • Is there a historic-district review? No — historic-district review does not appear among Davie's solar review stops 60% · Town of Davie Solar Panel Checklist
    • Is a wind or windstorm certification required? Effectively yes, via the required structural PE stamp rather than a separate 'wind certification' document — the same PE/RA-sealed structural submittal required for every roof-mounted PV job must document compliance with FBC wind-uplift and lateral-force provisions (FBCB 1616.1.2, 1620.1-3, 1621) as part of Broward's HVHZ overlay. 75% · Broward County BORA Permit Submittal Matrix, as hosted by Davie
    • Is there a system-size cap on residential generation? No AHJ-imposed system-size cap was found in Davie's own materials; the effective ceiling on residential systems comes from FPL's net-metering tariff, not the Town: FPL's Tier 1 program requires the Gross Power Rating to (a) not exceed 90% of the customer's utility distribution service rating, (b) be 10 kW AC or less, and (c) have AC generating capacity under 115% of the customer's trailing 12-month kWh usage. 70% · FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement 2.1
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Either, with a restriction — a licensed Electrical Contractor may perform both the PV and electrical scope; a Certified/Registered Solar Contractor may not perform the electrical portion. Davie's checklist states plainly: 'Solar contractors cannot install electrical portion. Electrical contractors can install solar panels and electrical portion.' BORA Policy #09-02 additionally allows Certified/Registered Plumbing Contractors to hold the Solar Thermal master permit. 90% · Town of Davie Solar Panel Checklist
    • Must the contractor be registered with this authority before applying? Yes — contractors must register with the Town before pulling permits 85% · Town of Davie General Information page
    • Is a homeowner permitted to self-install and self-permit? Yes — owner-builder self-permit is explicitly available for solar 92% · Town of Davie Solar Panel Checklist
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Per Davie's Solar Panel Checklist: Building Permit Application; signed/notarized Addendum Form (contractor + owner); Notice of Commencement if job >$5,000; Owner-Builder Disclosure Statement if owner-builder; signed contract recommended as proof of job value >$5,000; Workers' Comp Exemption Letter if applicable; copy of Broward County Property Appraiser ownership search. Minimum plan submittal: Planning & Zoning review triggered if ground-mounted; signed/sealed survey (or Survey Affidavit if >2 yrs old and unchanged); site plan/elevations showing all proposed work with dimensions/setbacks; Hold Harmless utility-easement form if work is in an easement; Tree Affidavit if applicable; drainage-district approvals if applicable; a dedicated set of electrical and structural plans; a completed Special Inspector form for any PV job of more than 1 panel; the county Permit Submittal Matrix for Solar Thermal/Electric; an electrical schematic showing all components labeled, wire sizes, grounding, circuit sizing, overcurrent protection, disconnect location and signage location; plus the separate 'Solar Panel Information Required' handout (manufacturer specs/listings for modules, inverters, combiners, ESS, racking, and wire-size calcs). 93% · Town of Davie Solar Panel Checklist
    • How many copies, and in what format? Electronic only, via the Town's OAS/ProjectDox portal — no paper-copy count is specified because submittal is now a required electronic upload 70% · Town of Davie Online Self Service page
    • Is a site plan required, and what must it show? Yes. Provide a signed/sealed survey (or executed Survey Affidavit if the survey is >2 years old and the property is unchanged), plus a site plan (and building elevations if applicable) clearly showing the location of the proposed work with dimensions and setbacks; all existing site features (fencing, driveways, generators, etc.) must be highlighted, and Planning & Zoning review is triggered if the panels will be ground-mounted. 90% · Town of Davie Solar Panel Checklist
    • Is a one-line / three-line diagram required? Yes — an electrical schematic/one-line diagram is required 90% · Town of Davie Solar Panel Checklist + Broward BORA Permit Matrix
    • Are string and conductor calculations required? Yes — wire size calculations are required 88% · Town of Davie Solar Panel Information Required handout
    • Is a structural PE stamp required, and at what threshold? Yes, for essentially every job — signed/sealed structural design by a Florida-licensed PE or Registered Architect is required for roof-mounted PV/solar-thermal equipment (documenting wind-uplift/lateral force compliance and connection design), and Davie separately requires a completed Special Inspector form for any PV job proposing more than 1 panel — i.e. there is effectively no de-minimis exemption for a typical residential array. 85% · Broward County BORA Permit Submittal Matrix, as hosted by Davie
    • Is an electrical PE stamp required, and at what threshold? Yes, in the alternative — PV system plans must be signed and sealed by a Florida-licensed Professional Engineer, OR certified by the Florida Solar Energy Center (FSEC), which issues a System Certification Approval Form; there is no minimum-size threshold stated — this applies to the PV system generally. 85% · Broward County BORA Permit Submittal Matrix, as hosted by Davie
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Three linked systems: OAS (Online Application Submittal, required for all new submissions as of 12 Jan 2026) feeds into ProjectDox for electronic plan review; eSuite (esuite.davie-fl.gov) is used for permit status lookup, balance-due, and inspection scheduling/results. 88% · Town of Davie Online Self Service page
    • Can the whole application be completed online? Yes, as of 12 Jan 2026 — OAS is the required electronic route for submitting the application and all required documents 82% · Town of Davie Online Self Service page
    • What does a residential solar permit cost? No flat fee — valuation-based: Permit fee is 0.95% of construction value (minimum $55), PLUS a separate Plan Review fee of 0.75% of construction value (minimum $25), plus statutory surcharges (BORA 0.25/$1,000, Training/Tech 6% of permit fee, DBPR 1% min $2, BCAIB 1.5% min $2). There is no dedicated 'solar' or 'photovoltaic' line item anywhere in the fee schedule. 90% · Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025
    • How is the fee calculated? Valuation — percentage of declared/assessed construction value, not a flat, per-kW, or per-panel fee 90% · Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025
    • Is there a separate plan-check fee? Yes — plan review is a separate, non-refundable fee from the permit fee 90% · Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? Approximately 30 business/working days 85% · Town of Davie Building Division FAQ
    • How long is an issued permit valid before it expires? Davie's own General Information page currently states 180 days: once a permit is printed it 'remains valid as long as work begins within 180 days from the date issued' (FBC 105.3.2.1), and expires if inactive 90 days; renewal is for another 180 days. This is now BELOW the Florida statutory floor: CS/CS/HB 803 (enrolled, 2026 Legislature, effective 1 Jul 2026) amends F.S. 553.79(1)(c): 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later.' Davie's public-facing page does not appear to have been updated to reflect the new 1-year statutory floor for single-family-dwelling permits (most residential PV falls in that category). 75% · Town of Davie General Information page vs. enrolled CS/CS/HB 803 (2026), F.S. 553.79(1)(c)
    • Which utility handles interconnection here? Florida Power & Light Company (FPL) 95% · Town of Davie FY2026 Adopted Budget + FPL PSC-filed tariff Section 7
    • Where does the utility sit in the sequence? Parallel application, but After permit for the substantive step — FPL's own Tier 1 Interconnection Agreement (the form covering virtually all residential PV, ≤10kW AC) requires the customer to 'provide Local Building Code Official inspection and certification of installation... that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications' before FPL will complete interconnection/grant Permission to Operate. The interconnection application itself can be filed in parallel with permitting, but PTO is gated on the completed local permit and final inspection. 85% · FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement

28 questions answered against Town of Davie’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes — the Town of Davie Building Division is the AHJ for residential rooftop solar within town limits

Why the confidence is not higherDavie's own Building Division page states it enforces the Florida Building Code and is organized by discipline (structural, electrical, plumbing, mechanical); Davie hosts its own Solar Panel Checklist, Permit Matrix, and Solar Panel Information Required documents naming Davie's Building Division as the reviewing/permitting body. Confirmed from the county side: Broward County's own Building Code Services page lists only seven small unincorporated communities (Boulevard Gardens, Broadview Park, Franklin Park, Hillsboro Pines, Hillsboro Ranches, Rosevelt Gardens, Washington Park) plus Fort Lauderdale airport as served by the County; Davie is not on that list, so Davie self-permits.

department page + county-side confirmation checked 2026-09-12 https://www.davie-fl.gov/206/Building

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both — Davie's Building Division issues and reviews Structural, Electrical and (if applicable) Plumbing permits itself for solar. A Planning & Zoning review is also triggered if panels are ground-mounted. No delegation to Broward County; Broward County's Board of Rules and Appeals (BORA) sets countywide minimum HVHZ submittal standards that Davie's review must meet, but BORA issues no permits itself.

Why the confidence is not higherDavie's own Solar Panel Checklist lists 'Required Permit Applications: Structural, Electrical, Plumbing (if applicable)' and 'Permit Review Stops: Structural, Electrical, Fire, Planning & Zoning, Plumbing (if applicable)'.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes — a building permit is required for residential rooftop PV

Why the confidence is not higherDavie's Solar Panel Checklist and General Information page (FBC 104.1: 'It shall be unlawful to construct... or install... any equipment... without first having filed application and obtained a permit') both assume/require a permit; no solar/PV exemption appears on Davie's permit-exemption materials.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined under a master permit with separate trade reviews — Broward County BORA Policy #09-02 requires 'Building Departments shall establish an individual master permit for both Solar Thermal and Solar Electric installations to which applicable subsidiary categories are to be tied,' and Davie's own checklist lists Structural, Electrical and Plumbing as separate 'Required Permit Applications' tied to the same job, each with its own review stop.

Why the confidence is not higherBORA Policy #09-02 (countywide, binds Davie) explicitly directs a single master permit per solar job with subsidiary trade permits/reviews tied to it, rather than fully independent permits. Some ambiguity remains because Davie's own checklist lists the trade permits as separate 'applications.'

Broward County BORA Policy #09-02, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either, with a restriction — a licensed Electrical Contractor may perform both the PV and electrical scope; a Certified/Registered Solar Contractor may not perform the electrical portion. Davie's checklist states plainly: 'Solar contractors cannot install electrical portion. Electrical contractors can install solar panels and electrical portion.' BORA Policy #09-02 additionally allows Certified/Registered Plumbing Contractors to hold the Solar Thermal master permit.

Why the confidence is not higherVerbatim from Davie's own Solar Panel Checklist 'Other Requirements' section, corroborated by BORA Policy #09-02 Section C on contractor qualification by category.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes — contractors must register with the Town before pulling permits

Why the confidence is not higherDavie's General Information page: 'Contractor Registration — You may register/update contractor information through OAS... New Contractor Registration Form' requiring State License OR County Certificate of Competency, Liability Insurance, Workers' Comp Exemption Letter/Certificate, and Business Tax Receipt. This is a general Building Division requirement, not solar-specific, but nothing on the solar pages exempts solar contractors from it.

Town of Davie General Information page checked 2026-09-12 https://www.davie-fl.gov/1224/General-Information

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes — owner-builder self-permit is explicitly available for solar

Why the confidence is not higherDavie's own Solar Panel Checklist, Required Forms list, item 4: 'If permit submitted as an Owner Builder provide Owner Builder Disclosure Statement' — naming the owner-builder route directly on the solar checklist. The Owner-Builder Disclosure Statement itself (Davie form, per F.S. 489.103) lets an owner act as their own contractor on a one- or two-family residence for their own use.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q8 What documents make up a complete submittal? Core Submittal package

Per Davie's Solar Panel Checklist: Building Permit Application; signed/notarized Addendum Form (contractor + owner); Notice of Commencement if job >$5,000; Owner-Builder Disclosure Statement if owner-builder; signed contract recommended as proof of job value >$5,000; Workers' Comp Exemption Letter if applicable; copy of Broward County Property Appraiser ownership search. Minimum plan submittal: Planning & Zoning review triggered if ground-mounted; signed/sealed survey (or Survey Affidavit if >2 yrs old and unchanged); site plan/elevations showing all proposed work with dimensions/setbacks; Hold Harmless utility-easement form if work is in an easement; Tree Affidavit if applicable; drainage-district approvals if applicable; a dedicated set of electrical and structural plans; a completed Special Inspector form for any PV job of more than 1 panel; the county Permit Submittal Matrix for Solar Thermal/Electric; an electrical schematic showing all components labeled, wire sizes, grounding, circuit sizing, overcurrent protection, disconnect location and signage location; plus the separate 'Solar Panel Information Required' handout (manufacturer specs/listings for modules, inverters, combiners, ESS, racking, and wire-size calcs).

Why the confidence is not higherDirectly and comprehensively enumerated on Davie's own two-page Solar Panel Checklist plus its companion Solar Panel Information Required handout, both current as of the Building Division's Electrical page.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q9 How many copies, and in what format? Submittal package

Electronic only, via the Town's OAS/ProjectDox portal — no paper-copy count is specified because submittal is now a required electronic upload

Why the confidence is not higherDavie's Online Self Service page: 'Starting January 12th 2026' OAS 'will be the required method for submitting permits and all other Building Department service requests,' feeding into ProjectDox for plan upload. Davie's own checklist and handouts do not state a document format/page-count requirement (e.g., single merged PDF) the way some other jurisdictions' checklists do, so the specific file-packaging convention is inferred rather than quoted.

Town of Davie Online Self Service page checked 2026-09-12 https://www.davie-fl.gov/213/Online-Self-Service

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes. Provide a signed/sealed survey (or executed Survey Affidavit if the survey is >2 years old and the property is unchanged), plus a site plan (and building elevations if applicable) clearly showing the location of the proposed work with dimensions and setbacks; all existing site features (fencing, driveways, generators, etc.) must be highlighted, and Planning & Zoning review is triggered if the panels will be ground-mounted.

Why the confidence is not higherVerbatim from the 'Minimum Plan Submittal' section of Davie's Solar Panel Checklist.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes — an electrical schematic/one-line diagram is required

Why the confidence is not higherDavie's Solar Panel Checklist: 'Electrical plans shall have a schematic showing all system components labeled, wire sizes, grounding, circuit sizing, overcurrent protection, and disconnect location complete with signage and location of signage.' The countywide BORA Permit Matrix separately requires an 'Electrical Diagram' under NEC Article 690/705 showing components, interconnects, conductor types/sizes, conduit types/sizes, disconnects, and point of interconnection.

Town of Davie Solar Panel Checklist + Broward BORA Permit Matrix checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q12 Are string and conductor calculations required? Drawings & calculations

Yes — wire size calculations are required

Why the confidence is not higherDavie's 'Solar Panel Information Required' handout states plainly: 'Provide Manufacturer's specifications of PV modules, converters, inverters, combiner, ESS (Batteries), charge controllers (smart switches), racking system AND installation instructions of all equipment. Wire Size Calculations.'

Town of Davie Solar Panel Information Required handout checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/19057/Solar-Panel-Information-Required

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

Yes, for essentially every job — signed/sealed structural design by a Florida-licensed PE or Registered Architect is required for roof-mounted PV/solar-thermal equipment (documenting wind-uplift/lateral force compliance and connection design), and Davie separately requires a completed Special Inspector form for any PV job proposing more than 1 panel — i.e. there is effectively no de-minimis exemption for a typical residential array.

Why the confidence is not higherBroward County BORA Uniform Permit Submittal Matrix (HVHZ), Section 3 'Structural Design,' hosted on Davie's own Electrical page, requires PE/RA-signed drawings citing FBCB 1522.2, 1616.1.2, 1605, 1620.1-3, 1621; Davie's Solar Panel Checklist separately requires the Special Inspector form above 1 panel.

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Yes, in the alternative — PV system plans must be signed and sealed by a Florida-licensed Professional Engineer, OR certified by the Florida Solar Energy Center (FSEC), which issues a System Certification Approval Form; there is no minimum-size threshold stated — this applies to the PV system generally.

Why the confidence is not higherBORA Permit Matrix, 'System Components' table: 'Photovoltaic System — Plans must be signed and sealed by a Florida Professional Engineer or Certified by FSEC' (citing F.S. 471.025 and 377.705(4)(d)), and 'Statutory Requirement — FSEC will generate a System Certification Approval Form or signed and sealed by a Florida Professional Engineer.'

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q15 What does a residential solar permit cost? Core Fees

No flat fee — valuation-based: Permit fee is 0.95% of construction value (minimum $55), PLUS a separate Plan Review fee of 0.75% of construction value (minimum $25), plus statutory surcharges (BORA 0.25/$1,000, Training/Tech 6% of permit fee, DBPR 1% min $2, BCAIB 1.5% min $2). There is no dedicated 'solar' or 'photovoltaic' line item anywhere in the fee schedule.

Why the confidence is not higherDavie's Building Permit Fee Schedule (Exhibit A, modified fees effective 1 Oct 2025) sections (4) Plan Review Fees and (5) Permit Fees, read in full. Controls run in the extracted text: 'electrical' present (word-broken by PDF kerning as 'Electrica l' but confirmed present with spaces stripped), 'solar'/'photovoltaic'/'pv' absent, fabricated control 'zzqqx' absent — confirming the search worked and the absence of a PV-specific line is real, not a retrieval failure.

Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/21688/Building-Fee-Schedule-2023

Q16 How is the fee calculated? Core Fees

Valuation — percentage of declared/assessed construction value, not a flat, per-kW, or per-panel fee

Why the confidence is not higherSame fee schedule: Permit Fees section (5)(b) '0.95% of construction value' and Plan Review Fees section (4)(b)/(c) '0.75% of construction value,' with no per-kW or per-panel alternative shown anywhere in the document.

Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/21688/Building-Fee-Schedule-2023

Q17 Is there a separate plan-check fee? Fees

Yes — plan review is a separate, non-refundable fee from the permit fee

Why the confidence is not higherFee schedule sections (4) 'PLAN REVIEW FEES' (0.75% of construction value, non-refundable once review has commenced) and (5) 'PERMIT FEES' (0.95% of construction value) are listed as distinct line items with distinct minimums ($25 vs $55).

Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/21688/Building-Fee-Schedule-2023

Q18 What is the stated plan-review turnaround? Core Timeline & validity

Approximately 30 business/working days

Why the confidence is not higherDavie's published FAQ: 'How long does it take to get a permit? ... we generally attempt to review permit applications within 30 working days (per FBC 105.3.1).' This also matches the Florida statutory floor: FS 553.792(1)(a) (as amended by 2026 CS/CS/HB 803, enrolled, eff. 1 Jul 2026) sets 30 business days for most residential building-permit categories (5 business days only applies to electrical work under $15,000 on an existing single-family dwelling, a threshold most PV jobs exceed).

Town of Davie Building Division FAQ checked 2026-09-12 https://www.davie-fl.gov/FAQ.aspx

Q19 How long is an issued permit valid before it expires? Timeline & validity

Davie's own General Information page currently states 180 days: once a permit is printed it 'remains valid as long as work begins within 180 days from the date issued' (FBC 105.3.2.1), and expires if inactive 90 days; renewal is for another 180 days. This is now BELOW the Florida statutory floor: CS/CS/HB 803 (enrolled, 2026 Legislature, effective 1 Jul 2026) amends F.S. 553.79(1)(c): 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later.' Davie's public-facing page does not appear to have been updated to reflect the new 1-year statutory floor for single-family-dwelling permits (most residential PV falls in that category).

Why the confidence is not higherDavie's own General Information/FAQ text is dated by content (still cites the pre-HB-803 180-day figure) versus the enrolled 2026 act's plain text, read directly from flsenate.gov. Confidence is not higher because it is unclear whether Davie's *practice* already follows the new 1-year floor even though its website text has not been updated — the webpage and the statute conflict, and I have not found a Davie document reconciling them.

Town of Davie General Information page vs. enrolled CS/CS/HB 803 (2026), F.S. 553.79(1)(c) checked 2026-09-12 https://www.davie-fl.gov/1224/General-Information

Q20 Which permit portal does this authority use? Core Portal & process

Three linked systems: OAS (Online Application Submittal, required for all new submissions as of 12 Jan 2026) feeds into ProjectDox for electronic plan review; eSuite (esuite.davie-fl.gov) is used for permit status lookup, balance-due, and inspection scheduling/results.

Why the confidence is not higherDavie's Online Self Service page describes all three by name and states OAS became 'the required method for submitting permits and all other Building Department service requests' from 12 Jan 2026; the Building Division landing page links directly to eSuite (esuite.davie-fl.gov/eSuite.Permits/WelcomePage.aspx).

Town of Davie Online Self Service page checked 2026-09-12 https://www.davie-fl.gov/213/Online-Self-Service

Q21 Can the whole application be completed online? Core Portal & process

Yes, as of 12 Jan 2026 — OAS is the required electronic route for submitting the application and all required documents

Why the confidence is not higher'A new permitting submission system will be available named Online Application Submittal (OAS) starting January 12th 2026. This new process will be the required method for submitting permits and all other Building Department service requests.' Some steps (e.g. final permit card pickup or in-person walk-through Wednesdays 8-10:30am) remain available/required in specific cases, so 'entirely online' is not unconditionally true for every applicant.

Town of Davie Online Self Service page checked 2026-09-12 https://www.davie-fl.gov/213/Online-Self-Service

Q22 Which utility handles interconnection here? Core Utility interconnection

Florida Power & Light Company (FPL)

Why the confidence is not higherConfirmed from two independent primary sources: (1) Davie's own FY2026 Adopted Budget lists revenue line items '3141703 - FPL Utility Service Tax' ($11.1-11.7M/yr) and '3231603 - FPL Franchise Fee' ($6.9-8.8M/yr); (2) FPL's own PSC-filed Electric Tariff, Section 7 'General Description of the Areas Served,' lists 'Davie' by name among the communities in FPL's territory.

Town of Davie FY2026 Adopted Budget + FPL PSC-filed tariff Section 7 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/23270/FY-2026-Final-Budget-for-Public-Hearings

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Parallel application, but After permit for the substantive step — FPL's own Tier 1 Interconnection Agreement (the form covering virtually all residential PV, ≤10kW AC) requires the customer to 'provide Local Building Code Official inspection and certification of installation... that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications' before FPL will complete interconnection/grant Permission to Operate. The interconnection application itself can be filed in parallel with permitting, but PTO is gated on the completed local permit and final inspection.

Why the confidence is not higherFPL Electric Tariff, Section 9 (Standard Forms), Sheet No. 9.050-9.051, Tier 1 Interconnection Agreement Section 3.4, read directly from FPL's own PSC-filed tariff.

FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No — no HOA/architectural-board approval appears in Davie's own list of required reviews for solar

Why the confidence is not higherDavie's Solar Panel Checklist's own 'Permit Review Stops' list (Structural, Electrical, Fire, Planning & Zoning, Plumbing) does not include an HOA or architectural-review stop; Florida's Solar Rights Act (F.S. 163.04) also statewide-preempts HOA architectural-committee denial of solar installations, reinforcing the absence at the AHJ level. Positive control: the same checklist positively lists five other named review stops, confirming the list is a real enumerated field and not blank by omission-of-search.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q25 Is there a historic-district review? Overlays & special cases

No — historic-district review does not appear among Davie's solar review stops

Why the confidence is not higherSame reasoning as Q24: the Solar Panel Checklist's enumerated 'Permit Review Stops' (Structural, Electrical, Fire, Planning & Zoning, Plumbing) does not list Historic Preservation, even though Davie does maintain a separate Historic Preservation Board for other purposes. Confidence is capped in the 60s because I did not find a document stating affirmatively that solar is exempt from historic review on a historic-designated property specifically — only that it is absent from the general checklist.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q26 Is a wind or windstorm certification required? Overlays & special cases

Effectively yes, via the required structural PE stamp rather than a separate 'wind certification' document — the same PE/RA-sealed structural submittal required for every roof-mounted PV job must document compliance with FBC wind-uplift and lateral-force provisions (FBCB 1616.1.2, 1620.1-3, 1621) as part of Broward's HVHZ overlay.

Why the confidence is not higherBroward BORA Permit Submittal Matrix, Section 3 'Structural Design,' as hosted on Davie's Electrical page: required documentation includes 'Documentation/verification exposed solar panel equipment meet wind loads' and 'Design of connections for the wind loads' citing the FBC wind-load sections.

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Nothing published by this authority.

Where we lookedDavie's Solar Panel Checklist, Solar Panel Information Required handout, and the BORA Permit Submittal Matrix — none mention a Specific Use Permit or Town Council approval step for residential rooftop or ground-mount PV of any size

https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No AHJ-imposed system-size cap was found in Davie's own materials; the effective ceiling on residential systems comes from FPL's net-metering tariff, not the Town: FPL's Tier 1 program requires the Gross Power Rating to (a) not exceed 90% of the customer's utility distribution service rating, (b) be 10 kW AC or less, and (c) have AC generating capacity under 115% of the customer's trailing 12-month kWh usage.

Why the confidence is not higherAbsence checked directly against Davie's Solar Panel Checklist and Solar Panel Information Required handout (no size-cap language found; positive control terms like 'kW', 'disconnect' present elsewhere confirming the documents were actually read). The FPL figures come from FPL's own PSC-filed Tier 1 Interconnection Agreement, Section 2.1.

FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement 2.1 checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for Town of Davie on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Does the authority specify placard wording of its own? No — Davie does not specify its own placard wording; it requires that required signage be shown on the electrical plans but leaves the wording to NEC 690/705/706 65% · Town of Davie Solar Panel Checklist
    • Does the UTILITY specify placards beyond the AHJ's? Yes, in one specific case — FPL requires a permanent weather-proof plaque adjacent to the FPL meter socket indicating the location of the manual disconnect switch, but only where the disconnect cannot be mounted adjacent to the meter for safety/design reasons; where a UL 1741-listed inverter-based Tier 1 system (virtually all residential PV) can be sited normally, FPL requires no customer disconnect switch or plaque at all. 85% · FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement
    • Where must the labels be placed? At the disconnect location shown on the approved electrical plans — Davie requires the plans to show 'disconnect location complete with signage and location of signage'; FPL separately requires that where a manual disconnect switch is not adjacent to the meter, a weatherproof plaque go 'adjacent to FPL's meter socket' pointing to the switch's actual location. 75% · Town of Davie Solar Panel Checklist + FPL PSC-filed tariff
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? For the ~10kW-and-under UL 1741-listed inverter systems that cover almost all residential PV (FPL Tier 1), no AC disconnect switch is required by the utility at all. Where a disconnect IS required (non-UL-1741 Tier 1, or Tier 2/3), it must be a visible load-break-type switch mounted separate from, but immediately adjacent to, the FPL meter socket, lockable by a single FPL padlock; only if that location is impractical may it be relocated elsewhere on the premises, in which case a permanent weatherproof plaque must be posted at the meter socket pointing to its actual location. 85% · FPL PSC-filed Electric Tariff, Section 9
    • Must equipment be on a specific approved list? Yes — PV system components must carry recognized product/listing approval 85% · Broward County BORA Permit Submittal Matrix, as hosted by Davie
    • Are batteries permitted, and under what conditions? Yes, under the 2021 IRC Section R328 as adopted: ESS must be UL 9540-listed/labeled (or, for repurposed EV batteries, meet specific outdoor/detached-shed siting rules); units must be installed per manufacturer instructions with ≥3 ft spacing; restricted to detached garages/accessory structures, separated attached garages, exterior walls ≥3 ft from doors/windows, or enclosed/fire-rated utility spaces — never in sleeping rooms or their closets; individual units capped at 20 kWh with aggregate caps of 40-80 kWh depending on location; inverters must be UL 1741-listed; smoke/heat detection and, where applicable, mechanical ventilation and vehicle-impact protection are required; and documentation/labeling (O&M/decommissioning instructions plus a maintenance-contact label) must be provided. 90% · Town of Davie Solar Permits/Energy Storage Systems (2021 IRC) handout
    • Is there a separate ESS permit or inspection? No — ESS is bundled into the same solar electrical permit rather than requiring its own separate permit/inspection 60% · Town of Davie Solar Panel Information Required handout
    • Is a ground mount treated as a structure? Yes — a ground-mounted array triggers Planning & Zoning review the way a structure would 88% · Town of Davie Solar Panel Checklist
    • Is a specific mounting system or attachment spacing required? No fixed spacing table — Davie/Broward require an engineered, project-specific attachment design rather than a prescriptive spacing rule: the structural submittal must be a PE/RA-signed design demonstrating the racking and support framing meet HVHZ wind-uplift and lateral-force requirements, with connection design and dead-load compliance shown for that specific installation. 75% · Broward County BORA Permit Submittal Matrix, as hosted by Davie

20 questions answered against Town of Davie’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

2020

Why the confidence is not higherBroward County BORA's Formal Interpretations index (FBC 8th Edition, 2023, currently in force) lists FI-35: 'Modification of NFPA 70, 2020, Section 555.5 and 555.9, Marina Voltages' — a live formal interpretation of the electrical code explicitly naming NFPA 70 2020 as the edition adopted under the current (8th) FBC cycle. broward.org/CodeAppeals itself now redirects to a bare Next.js landing page with no document links (confirmed by direct fetch), so this is read from a stable Wayback Machine capture of the prior SharePoint-era index (13 Jun 2025 snapshot, digest OAIZLY3RMNPWRCFGOXCJBFYYUVWP4V6G) rather than the live site.

Broward County BORA Formal Interpretations index (Wayback capture, 13 Jun 2025) checked 2026-09-12 https://web.archive.org/web/20250613171651/https://www.broward.org/CodeAppeals/Pages/FormalInterpretations.aspx

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023) — in force since 31 December 2023

Why the confidence is not higherThe same BORA Formal Interpretations index shows every current FI dated 'FBC 8th Edition, 2023' with an effective date of 31 December 2023 (and later dates for individually-issued FIs), and Davie's own hosted Permit Submittal Matrix cites current FBC section numbers throughout. Caveat: Davie's own hosted copy of the BORA solar Permit Matrix is itself an older working document still titled 'FBC 7th Edition (2020)' with a 2022 amendment date, even though the code cycle now in force is the 8th Edition — Davie has not replaced that file with an 8th-edition-labeled version, though its cited section numbers (1512, 1522, 1616, 1620, 1621) remain live in the 8th edition.

Broward County BORA Formal Interpretations index (Wayback capture, 13 Jun 2025) checked 2026-09-12 https://web.archive.org/web/20250613171651/https://www.broward.org/CodeAppeals/Pages/FormalInterpretations.aspx

Q31 Which fire code edition is in force? Code editions in force

Florida Fire Prevention Code, 8th Edition, with Broward County Amendments

Why the confidence is not higherBroward County BORA's own homepage 'Important Links' list (live fetch) names: 'Municode – Florida Fire Prevention Code, Broward County Amendments (8th Edition)' alongside the parallel Building Code (8th Edition) link, i.e. the two run on the same code cycle.

Broward County BORA homepage checked 2026-09-12 https://www.broward.org/CodeAppeals/Pages/Default.aspx

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes — Broward County (BORA) local amendments and Formal Interpretations apply on top of the base Florida Building/Fire codes, countywide including Davie

Why the confidence is not higherBORA Policy #09-02 (the Uniform Permit Submittal Matrix for Solar Thermal and Solar Electric Installations in the HVHZ) is itself a countywide amendment/administrative-guideline layer on top of the base FBC, binding every Broward building official including Davie's; FI-31 (rooftop-clearance exemption for PV) and FI-35 (NFPA 70 2020 marina-voltage modification) are further formal amendments to the base code text.

Broward County BORA Policy #09-02, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q33 What is the installation judged against? Core Electrical

The Florida Building Code (Building, Residential and Existing Building volumes, 8th Edition/2023) plus NFPA 70 (NEC), 2020 edition, as amended by Broward County's countywide Administrative Provisions (BCAP) and BORA policies/Formal Interpretations for the High-Velocity Hurricane Zone (HVHZ), which Broward is one of only two Florida counties inside.

Why the confidence is not higherSynthesis of the BORA Permit Submittal Matrix (citing FBCB, FBCEB, BCAP and NEC Articles 690/705 throughout) and the BORA Formal Interpretations index (8th Edition/2023, NFPA 70 2020).

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedDavie's Residential Overhead/Underground Service Change form and Electrical Service Change Checklist (both reviewed) are generic worksheets citing standard NEC Article 220/230/250 sizing tables; neither states a Davie-specific local rule on service upgrades or busbar sizing (e.g. a local 120%-rule amendment) beyond referencing the stock NEC sections

https://www.davie-fl.gov/DocumentCenter/View/11617/Electrical-Service-Change

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

No fixed spacing table — Davie/Broward require an engineered, project-specific attachment design rather than a prescriptive spacing rule: the structural submittal must be a PE/RA-signed design demonstrating the racking and support framing meet HVHZ wind-uplift and lateral-force requirements, with connection design and dead-load compliance shown for that specific installation.

Why the confidence is not higherBORA Permit Submittal Matrix, Section 3 'Structural Design' (FBCB 1616.1.2, 1620.1-3, 1621) requires case-by-case PE/RA verification rather than naming a fixed attachment-spacing figure.

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedChecked Davie's Solar Panel Checklist, Solar Panel Information Required handout, the 2021-IRC-based Solar Permits/ESS handout, and the BORA HVHZ Permit Submittal Matrix — none of the four publishes a ridge-setback dimension or a fire-department access-pathway diagram for rooftop PV (unlike some AHJs that publish a dedicated fire-pathway placard/diagram)

https://www.davie-fl.gov/1226/Electrical

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes, by inference from the mandatory NEC Article 690 compliance requirement — but not independently cited by section number in any Davie document

Why the confidence is not higherDavie's Solar Panel Information Required handout requires equipment location/labeling 'In compliance with... PV Systems Article 690 N.E.C.' Since NEC 2020 is the edition in force (Q29) and NEC 690.12 (rapid shutdown) has been mandatory since the 2017 NEC, rapid shutdown is required — but no Davie document explicitly names '690.12' or 'rapid shutdown' by that term, so this is an inference from the governing code edition rather than a direct local citation.

Town of Davie Solar Panel Information Required handout checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/19057/Solar-Panel-Information-Required

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedChecked Davie's Solar Panel Checklist, Solar Panel Information Required handout, and Solar Permits/ESS (2021 IRC) handout for a named placard list (e.g. AC disconnect placard, rapid-shutdown placard, main service placard, PV placard, battery placard) — Davie requires that plans show 'disconnect location complete with signage and location of signage' but does not itself enumerate which specific placards must be posted; that specification is left to NEC 690/705/706 rather than restated locally

https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No — Davie does not specify its own placard wording; it requires that required signage be shown on the electrical plans but leaves the wording to NEC 690/705/706

Why the confidence is not higherPositive control: the checklist does use the word 'signage' twice ('disconnect location complete with signage and location of signage'), so the document was actually read and signage is addressed; fabricated control 'zzqqx' returns nothing. No specific wording text is quoted anywhere in Davie's solar documents.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedChecked the same three Davie solar documents (checklist, info-required handout, ESS/2021-IRC handout) for letter-height, color, or material specification for placards — none is given; Davie requires only that signage location be shown on plans

https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedChecked Davie's Solar Panel Checklist and Information Required handout for a dedicated site-plan/facility-map placard requirement beyond the general site plan already required for the permit (Q10) — no separate facility-map placard (of the kind some AHJs require under NEC 690.56/705.10) is named

https://www.davie-fl.gov/DocumentCenter/View/19057/Solar-Panel-Information-Required

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes, in one specific case — FPL requires a permanent weather-proof plaque adjacent to the FPL meter socket indicating the location of the manual disconnect switch, but only where the disconnect cannot be mounted adjacent to the meter for safety/design reasons; where a UL 1741-listed inverter-based Tier 1 system (virtually all residential PV) can be sited normally, FPL requires no customer disconnect switch or plaque at all.

Why the confidence is not higherFPL Electric Tariff Section 9, Sheet Nos. 9.050-9.051, Tier 1 Interconnection Agreement, Sections 5.1-5.3, read directly from FPL's own PSC-filed tariff.

FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the disconnect location shown on the approved electrical plans — Davie requires the plans to show 'disconnect location complete with signage and location of signage'; FPL separately requires that where a manual disconnect switch is not adjacent to the meter, a weatherproof plaque go 'adjacent to FPL's meter socket' pointing to the switch's actual location.

Why the confidence is not higherCombination of Davie's Solar Panel Checklist and FPL's Tier 1 Interconnection Agreement Section 5.3 (both read directly).

Town of Davie Solar Panel Checklist + FPL PSC-filed tariff checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q44 Must equipment be on a specific approved list? Equipment listing

Yes — PV system components must carry recognized product/listing approval

Why the confidence is not higherBORA Permit Submittal Matrix, 'System Components': PV modules require FSEC Approval/Listing or PE-sealed drawings; the PV system overall must be 'signed and sealed by a Florida Professional Engineer or Certified by FSEC' (F.S. 471.025, 377.705(4)(d)); Davie's Solar Panel Information Required handout separately requires manufacturer listing documentation for modules, inverters, combiners, ESS, charge controllers and racking per NEC 690.4(B)/110.3(B). Because Broward is HVHZ, racking/mounting hardware also needs a Florida Product Approval evaluated for HVHZ or a Miami-Dade NOA to satisfy the structural product-approval citation (FBCB 1512.2.1) in the same matrix, though no Davie document names 'Miami-Dade NOA' by that exact term.

Broward County BORA Permit Submittal Matrix, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes, under the 2021 IRC Section R328 as adopted: ESS must be UL 9540-listed/labeled (or, for repurposed EV batteries, meet specific outdoor/detached-shed siting rules); units must be installed per manufacturer instructions with ≥3 ft spacing; restricted to detached garages/accessory structures, separated attached garages, exterior walls ≥3 ft from doors/windows, or enclosed/fire-rated utility spaces — never in sleeping rooms or their closets; individual units capped at 20 kWh with aggregate caps of 40-80 kWh depending on location; inverters must be UL 1741-listed; smoke/heat detection and, where applicable, mechanical ventilation and vehicle-impact protection are required; and documentation/labeling (O&M/decommissioning instructions plus a maintenance-contact label) must be provided.

Why the confidence is not higherVerbatim from Davie's own hosted 'Solar Permits/Energy Storage Systems' handout, which reproduces 2021 IRC Section R328 in full.

Town of Davie Solar Permits/Energy Storage Systems (2021 IRC) handout checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/19331/Solar-PermitsEnergy-Storage-Systems-IRCODE-2021

Q46 Is there a separate ESS permit or inspection? Battery / ESS

No — ESS is bundled into the same solar electrical permit rather than requiring its own separate permit/inspection

Why the confidence is not higherDavie's Solar Panel Information Required handout lists ESS/batteries as one of the items to be shown and labeled on the same electrical site plan alongside modules and inverters, and BORA Policy #09-02 defines only 'Solar Thermal,' 'Solar Electric,' and 'Hybrid' permit categories (no separate ESS/battery category). No Davie document describes a standalone battery permit process, but I also did not find an explicit statement that ESS is never separately permitted, so confidence is moderate.

Town of Davie Solar Panel Information Required handout checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/19057/Solar-Panel-Information-Required

Q47 Is a ground mount treated as a structure? Core Ground mount

Yes — a ground-mounted array triggers Planning & Zoning review the way a structure would

Why the confidence is not higherDavie's Solar Panel Checklist, 'Minimum Plan Submittal': 'Planning and Zoning review required if proposed location of panels will be on the ground' — a requirement not triggered for roof-mounted panels on the same checklist.

Town of Davie Solar Panel Checklist checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/11550/Solar-Panels-Checklist

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

For the ~10kW-and-under UL 1741-listed inverter systems that cover almost all residential PV (FPL Tier 1), no AC disconnect switch is required by the utility at all. Where a disconnect IS required (non-UL-1741 Tier 1, or Tier 2/3), it must be a visible load-break-type switch mounted separate from, but immediately adjacent to, the FPL meter socket, lockable by a single FPL padlock; only if that location is impractical may it be relocated elsewhere on the premises, in which case a permanent weatherproof plaque must be posted at the meter socket pointing to its actual location.

Why the confidence is not higherFPL Electric Tariff Section 9, Sheet Nos. 9.050-9.051 (Tier 1) and continuing sheets for Tier 2, read directly from FPL's own PSC-filed tariff, not from a secondary summary.

FPL PSC-filed Electric Tariff, Section 9 checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal (eSuite, for registered contractors) or Phone (automated call-in system) — plus an OAS-based inspection-request form 85% · Town of Davie Inspections page
    • How much notice is required? Effectively 1 business day — requests received by 4:30pm are scheduled for the next business day 85% · Town of Davie Inspections page
    • Are same-day or AM/PM windows offered? No fixed AM/PM window is offered at booking; an approximate time frame becomes visible online only on the morning of the inspection 75% · Town of Davie Inspections page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes, by default — Davie's own in-house Electrical, Structural, Mechanical and Plumbing inspectors perform final inspections; a state-licensed Private Provider under F.S. 553.791 may be used instead, at the applicant's election 85% · Town of Davie Inspections page + Private Providers page
    • If delegated, to whom? A Florida-licensed private provider (engineer, architect, or state-certified building code inspector) engaged under Florida Statute 553.791, at the applicant's option and subject to prior Building Official approval 75% · Town of Davie Private Providers page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? Per Broward County BORA Policy #09-02 (binding on Davie): for Solar Electric — Building/Structure/Roofing at Time of Installation and Final, plus Electrical Rough and Final; for Solar Thermal — Building/Structure/Roofing at Time of Installation and Final, plus Plumbing Final; for Hybrid (combined PV + integral solar-thermal) systems — Building/Structure/Roofing Time-of-Installation and Final, Electrical Rough and Final, and Plumbing Final. 88% · Broward County BORA Policy #09-02, as hosted by Davie
    • Is a rough-in or mid-roof inspection required? Yes — a 'Time of Installation'/roofing inspection and an Electrical Rough inspection are both required ahead of the finals 85% · Broward County BORA Policy #09-02, as hosted by Davie
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • What must be on site at inspection? A certified copy of the recorded Notice of Commencement, posted at the job site, is required for the first inspection (which cannot occur less than 7 days after permit issuance) if job value exceeds $5,000 — 'In the absence of such posted notice, the inspection will not be approved and a re-inspection fee will be charged.' The physical inspection record card/sheet (Town of Davie seal, 8.5x11) issued with the permit package must also be available on site for the inspector. 80% · Town of Davie General Information page
    • Does the inspector verify labels and listings? Likely yes, but not stated as an explicit inspector checklist item in any Davie document I could read 60% · Town of Davie Solar Panel Information Required handout (inferred inspector practice)
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? Final — the electrical/building permit is closed out on passing its final inspection(s); a Certificate of Occupancy/Completion is not generally reissued for an existing single-family home undergoing a PV retrofit (Davie's CO/TCO fee schedule addresses new construction and use changes, not routine PV additions). 60% · Broward County BORA Policy #09-02 inspection sequence, as hosted by Davie
    • Who notifies the utility for PTO? Installer/Customer — FPL does not pull the local permit result itself; the customer/installer submits proof of the Building Official's completed inspection and certification to FPL as part of completing the Interconnection Agreement, which is a precondition to Permission to Operate 75% · FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement
    • Is there a re-inspection fee? $75 for the first re-inspection, $100 for the second, $150 for the third and each subsequent re-inspection 90% · Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025
    • How are corrections issued and cleared? Corrections are issued through the electronic review system (ProjectDox/OAS) as reviewer comments tied to the plan set; resubmittals are free the first two times but a Correction Resubmission fee ('$50.00 per Discipline or $15.00 a sheet, whichever is greater') applies starting at the third submittal and every submittal after that where prior comments were not addressed. This is Davie's general plan-review correction process; no solar-specific correction procedure is separately published. 65% · Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025

14 questions answered against Town of Davie’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal (eSuite, for registered contractors) or Phone (automated call-in system) — plus an OAS-based inspection-request form

Why the confidence is not higherDavie's Inspections page: 'Automated Phone Line: ...at 954-797-1128/1129' using a phone access code and inspection code from the permit package; 'Via OAS: You may request an inspection through OAS...'; 'Via eSuite: You may use your online eSuite account to schedule inspections and view permit status.'

Town of Davie Inspections page checked 2026-09-12 https://www.davie-fl.gov/1229/Inspections

Q50 How much notice is required? Core Booking & scheduling

Effectively 1 business day — requests received by 4:30pm are scheduled for the next business day

Why the confidence is not higherDavie's Inspections page: 'Inspection requests received before 4:30 p.m. will be added to the inspection schedule for the next business day.' Requests received Friday/Saturday/Sunday/holiday roll to the following business day, with the inspection then occurring the business day after that.

Town of Davie Inspections page checked 2026-09-12 https://www.davie-fl.gov/1229/Inspections

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

No fixed AM/PM window is offered at booking; an approximate time frame becomes visible online only on the morning of the inspection

Why the confidence is not higherDavie's Inspections page: 'Please check online at our E-Suites website after 8:00a.m. the morning of your inspection to view the approximate inspection time frame. If you would like to speak to the inspector, you must call 954-797-1111 between 7:30a.m.-8:15a.m. the morning of your inspection.' No AM/PM slot selection is offered when the inspection is booked.

Town of Davie Inspections page checked 2026-09-12 https://www.davie-fl.gov/1229/Inspections

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes, by default — Davie's own in-house Electrical, Structural, Mechanical and Plumbing inspectors perform final inspections; a state-licensed Private Provider under F.S. 553.791 may be used instead, at the applicant's election

Why the confidence is not higherDavie's Inspections page names its own staff inspectors by discipline including two dedicated Electrical Inspectors; Davie's separate Private Providers page confirms an opt-in private-provider route exists for plan review and/or inspections, requiring prior Building Official approval, meaning the Town's own inspectors are the default and delegation is optional, not automatic.

Town of Davie Inspections page + Private Providers page checked 2026-09-12 https://www.davie-fl.gov/1229/Inspections

Q53 If delegated, to whom? Core Who inspects

A Florida-licensed private provider (engineer, architect, or state-certified building code inspector) engaged under Florida Statute 553.791, at the applicant's option and subject to prior Building Official approval

Why the confidence is not higherDavie's Private Providers page: 'If applying to have a Private Provider, you must first be approved by the Building Official. You may begin the process in OAS by filling out the Private Provider request.' The statutory basis (F.S. 553.791) is referenced on Davie's own Uniform Building Permit Application (which asks 'Private Provider? YES/NO... attach Form #61G20-2.005-2002-01').

Town of Davie Private Providers page checked 2026-09-12 https://www.davie-fl.gov/1460/Private-Providers

Q54 Which inspections are required, and in what order? Core Stages & sequence

Per Broward County BORA Policy #09-02 (binding on Davie): for Solar Electric — Building/Structure/Roofing at Time of Installation and Final, plus Electrical Rough and Final; for Solar Thermal — Building/Structure/Roofing at Time of Installation and Final, plus Plumbing Final; for Hybrid (combined PV + integral solar-thermal) systems — Building/Structure/Roofing Time-of-Installation and Final, Electrical Rough and Final, and Plumbing Final.

Why the confidence is not higherVerbatim from BORA Policy #09-02, Section D, as hosted on Davie's own Electrical page.

Broward County BORA Policy #09-02, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Yes — a 'Time of Installation'/roofing inspection and an Electrical Rough inspection are both required ahead of the finals

Why the confidence is not higherBORA Policy #09-02, Section D lists 'Building/Structure/Roofing – Time of Installation and Final' and 'Electrical – Rough and Final' as the required inspection set for Solar Electric systems, i.e. more than a single final-only inspection.

Broward County BORA Policy #09-02, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q56 Does the inspector verify labels and listings? Core What is checked

Likely yes, but not stated as an explicit inspector checklist item in any Davie document I could read

Why the confidence is not higherDavie's own submittal handout requires NEC 690.4(B)/110.3(B) listing compliance and labeling to be documented on the plans, and inspectors verify the installed work against the approved plans as a matter of course, but no Davie inspections document states in so many words that the field inspector specifically checks equipment labels/listings at time of inspection, so this is an inference rather than a direct citation.

Town of Davie Solar Panel Information Required handout (inferred inspector practice) checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/19057/Solar-Panel-Information-Required

Q57 Is there a published inspection checklist? Core What is checked

Nothing published by this authority.

Where we lookedReviewed Davie's full Building Forms document list (30 documents, incl. TCC/TCO/CO checklists for residential and commercial, revision/change forms, and the Solar Panel Checklist itself) and the Inspections page — the 'Solar Panel Checklist' that exists is a pre-submittal document checklist, not a field inspection checklist; no separate PV-specific inspection-day checklist is published

https://www.davie-fl.gov/1301/Building-Forms

Q58 What must be on site at inspection? Core Documents on site

A certified copy of the recorded Notice of Commencement, posted at the job site, is required for the first inspection (which cannot occur less than 7 days after permit issuance) if job value exceeds $5,000 — 'In the absence of such posted notice, the inspection will not be approved and a re-inspection fee will be charged.' The physical inspection record card/sheet (Town of Davie seal, 8.5x11) issued with the permit package must also be available on site for the inspector.

Why the confidence is not higherDavie's General Information page (Notice of Commencement section) and Inspections page (description of the physical inspection sheet with the Town seal) both read directly.

Town of Davie General Information page checked 2026-09-12 https://www.davie-fl.gov/1224/General-Information

Q59 Is there a re-inspection fee? Corrections & re-inspection

$75 for the first re-inspection, $100 for the second, $150 for the third and each subsequent re-inspection

Why the confidence is not higherFee schedule section (6) 'INSPECTION FEES': 'Re-inspection fee - First occurrence $75.00,' 'Second occurrence $100.00,' 'Third occurrence and each consecutive re-inspection... $150.00.'

Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/21688/Building-Fee-Schedule-2023

Q60 How are corrections issued and cleared? Corrections & re-inspection

Corrections are issued through the electronic review system (ProjectDox/OAS) as reviewer comments tied to the plan set; resubmittals are free the first two times but a Correction Resubmission fee ('$50.00 per Discipline or $15.00 a sheet, whichever is greater') applies starting at the third submittal and every submittal after that where prior comments were not addressed. This is Davie's general plan-review correction process; no solar-specific correction procedure is separately published.

Why the confidence is not higherFee schedule section (4)(f) 'Correction Resubmission' and the general ProjectDox/OAS description on Davie's Online Self Service page; neither is written specifically for solar jobs.

Town of Davie Building Permit Fee Schedule, eff. 1 Oct 2025 checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/21688/Building-Fee-Schedule-2023

Q61 What is issued on pass? Core Final sign-off & PTO

Final — the electrical/building permit is closed out on passing its final inspection(s); a Certificate of Occupancy/Completion is not generally reissued for an existing single-family home undergoing a PV retrofit (Davie's CO/TCO fee schedule addresses new construction and use changes, not routine PV additions).

Why the confidence is not higherInference from BORA Policy #09-02's inspection sequence (which ends in Building/Structure/Roofing 'Final' and Electrical 'Final' rather than a CO step) plus Davie's fee schedule section (7), which frames Certificates of Occupancy/Completion around new construction rather than trade permits on existing homes. No Davie document states in terms 'a PV permit closes with a Final and not a CO.'

Broward County BORA Policy #09-02 inspection sequence, as hosted by Davie checked 2026-09-12 https://www.davie-fl.gov/DocumentCenter/View/18925/Permit-Matrix-Solar-Installations

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer/Customer — FPL does not pull the local permit result itself; the customer/installer submits proof of the Building Official's completed inspection and certification to FPL as part of completing the Interconnection Agreement, which is a precondition to Permission to Operate

Why the confidence is not higherFPL Electric Tariff Section 9, Tier 1 Interconnection Agreement Section 3.4: 'The Customer agrees to provide Local Building Code Official inspection and certification of installation' — placing the burden of notifying/proving to FPL on the customer/installer, not on the AHJ or on FPL itself pulling the record.

FPL PSC-filed Electric Tariff, Section 9, Tier 1 Interconnection Agreement checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 65%

No — Davie does not specify its own placard wording; it requires that required signage be shown on the electrical plans but leaves the wording to NEC 690/705/706

Size, colour & material None%

Where they go 75%

At the disconnect location shown on the approved electrical plans — Davie requires the plans to show 'disconnect location complete with signage and location of signage'; FPL separately requires that where a manual disconnect switch is not adjacent to the meter, a weatherproof plaque go 'adjacent to FPL's meter socket' pointing to the switch's actual location.

What the utility wants on top 85%

Yes, in one specific case — FPL requires a permanent weather-proof plaque adjacent to the FPL meter socket indicating the location of the manual disconnect switch, but only where the disconnect cannot be mounted adjacent to the meter for safety/design reasons; where a UL 1741-listed inverter-based Tier 1 system (virtually all residential PV) can be sited normally, FPL requires no customer disconnect switch or plaque at all.

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Required placards
Building Division | Davie, FL Skip to Main Content National Night Out Davie Police Department Invites You to National Night Out Event on Tuesday, August 4, 2026 Read On... Create a Website Account - Manage notification subscriptions, save form progress and more. Website Sign In Building Division ANNOUNCEMENTS *PLEASE BE AWARE* - Starting January 12th, the Building Department will be using an Onlin
Separate roof inspection
For inspection requests received on Friday, Saturday, Sunday, or Town Observed Holiday, the requested date will be changed to the next business day, and the inspection will be completed the business day after the inspection request date. For example: The request received on Friday, October 4, will b
Reinspection fee
As of 03/09/2026 this new form will be required with the Town of Davie. *Please be advised*  starting November 1, 2025. Due to changes in our system, we will not be able to cancel any inspection after
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
Town
County
Broward County
Regions covered
Authority Contact
Building Department
Direct Phone
954-797-1111