Town of Greenville is a town authority in the State of Florida, serving 746 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Town of Greenville against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Town of Greenville is not the permitting authority for residential solar here 85% confidence
Holds
Nothing of its own that this run could find. The Town of Greenville has no website (eight candidate domains fail DNS or resolve to unrelated sites - see q1), no Municode presence (library.municode.com/fl/greenville returns a clean 404, not the soft-200 JS-shell this project has learned to distrust elsewhere), and no entry of its own on the state's floridabuilding.org local-enforcement-agency registry. Building and electrical permitting, plan review and inspection for Greenville addresses are performed by the Madison County Building Department under the county's own stated rule that 'All other residents in Madison County' besides the City of Madison use the county's Annex Building office. Whether Greenville has retained any zoning/land-use authority of its own is genuinely unresolved - Madison County's Land Development Code textually excludes incorporated areas (Section 1.5) and names no interlocal agreement with Greenville the way some neighbouring Florida counties' LDCs name their towns by name.
Delegated to
Madison County Building Department, 229 SW Pinckney Street, Suite 219, Madison, FL 32340 (upstairs in the County Annex Building), 850-973-6785, Building Official Dennis Pitts, Single Family Dwelling Inspector Pat O'Brian. Permitting is processed through the Cloudpermit portal (us.cloudpermit.com/gov/dashboard), and inspections are booked by phone. Madison County's Planning & Zoning Department (Land Development Administrator Shelley Hoschar, same address and main phone) administers the county's Land Development Code, but that Code applies only in unincorporated Madison County by its own Section 1.5 - it is NOT established that Planning & Zoning has any role inside Greenville's town limits.
Overridden by
The Florida Building Code, 8th Edition (2023), adopted statewide by FAC 61G20-1.001(1), in force over any local rule; a 9th Edition (2026) exists in draft only. NFPA 70, the National Electrical Code, 2020 edition (FAC 69A-60.005(2)(qq)) - which Madison County's own Building Codes page confirms in its own words is the code 'effective on work permitted after January 1, 2021'. The Florida Fire Prevention Code - NFPA 1 and NFPA 101, Florida 2021 Editions (FAC 69A-60.003 and .004), effective 31 December 2023 - which binds Greenville by operation of state rule whether or not the Town has ever passed anything of its own. F.S. 163.04, prohibiting any ordinance or deed restriction/covenant that prohibits or has the effect of prohibiting solar collectors, subject only to a narrow south-facing siting carve-out. F.S. 553.792, setting binding plan-review deadlines (5 business days for an electrical/structural permit on an existing single-family dwelling under $15,000; 30 business days otherwise for a structure under 7,500 sq ft), and deeming an application complete if the County misses its own 5-day notice-of-deficiency deadline. F.S. 553.79, requiring electronic submission be accepted and setting the 1-year-or-next-FBC-edition permit validity floor. F.S. 553.791, the private-provider plan-review/inspection route. F.S. 471.003(2)(h), exempting a ch. 489-licensed electrical contractor from engineering licensure at $125,000/600A residential or less. F.S. 489.503(6), the electrical owner-builder exemption Madison County's own Electrical Disclosure Statement is built on. At the utility level, if the address is served by Tri-County Electric Cooperative (unconfirmed but the historically and geographically likelier of the two utilities named on the county's own permit forms - see q22), F.S. 366.91 places TCEC outside the FPSC's investor-owned net-metering rule, so TCEC's own Interconnection Agreement and its 90%-of-service-rating generation cap govern instead.
Why not higher
Proved in this run from first-party sources, deliberately NOT inherited from the Madison County or City of Madison runs elsewhere in this project, even though this run's conclusion (Greenville is not the AHJ; Madison County Building Department is) may resemble theirs. County side, read in full in this run: (1) the Building Department's own page, whose 'Obtaining a Permit' section is the single clearest sentence found anywhere in this run - it names the ONE municipality carved out (City of Madison) and states everyone else in the county, which necessarily includes Greenville, uses the county's own office; (2) the Building Department's Contact Information page, naming the Building Official and inspector; (3) the Land Development Code Chapter 1, Section 1.5, whose 'unincorporated areas... and to any other area authorized by law or interlocal agreement' language was checked specifically for a Greenville carve-in and found to have none - contrast the Washington County, FL LDC surveyed elsewhere in this project, which names Ebro, Caryville, Vernon and Wausau by name as co-adopters; Madison's LDC names no town anywhere in Chapters 1, 3, 4 or 6, all read in full; (4) the state's own floridabuilding.org local-enforcement-agency registry (392 entries; 65 counties, one of them 'County of Madison', one 'City of Madison' - no 'Town of Greenville' entry, and no 'zzqqx' fabricated-control hit either), which is meaningful rather than a size artefact because very small Florida towns DO appear on that registry when they run their own department. Town side: eight candidate domains for a Greenville town website were checked and every one either fails DNS resolution outright or resolves to something else (greenvillefl.com is parked for sale on HugeDomains; townofgreenville.com is Greenville, WISCONSIN); library.municode.com/fl/greenville returns a genuine 404, not the soft-200 JS-shell behaviour this project has learned to distrust for other Municode non-clients. Independent third-party corroboration: Tri-County Electric Cooperative's own published Interconnection Process, read in full in this run, names 'the county' - not Greenville - as the authority whose inspection and approval the member must obtain before the utility will proceed toward interconnection (step 8), which is strong evidence this is how the arrangement actually operates in practice, from a party with no institutional stake in how it is described. Held at 85, not higher, for two honest gaps. First, no single document says in words 'Madison County issues building permits inside the Town of Greenville' by name - the case rests on the county naming only the City of Madison as its one exception, combined with Greenville's total absence from every other channel checked. Second, and more consequentially than in most other authorities surveyed in this project, the LAND-USE half of this jurisdiction question is unresolved rather than merely under-documented: Madison County's LDC affirmatively excludes incorporated areas by its own text, so - unlike Washington County's arrangement for Ebro, where the same LDC that covers building also covers zoning and names the town - there is a real, sourced possibility that Greenville retains its own zoning authority that this run could not find any trace of (no website, no Municode, no search-engine-independent registry listing it). That gap is reported here rather than resolved either way.

https://madisoncountyfl.com/departments-services/building-department/

Permit required
Yes, by inference rather than by an explicit PV line. Madison County's general Building Permit Application covers any residential construction/installation work ('Type of Work: Residential…70%
Plan review
No plan-review turnaround is published by the county. The statutory floor applies: F.S. 553.792(1)(a) sets 5 business days after a complete and sufficient application for an electrical or…65%
Portal
Cloudpermit. The county's 'Before submitting information for a permit' guide directs applicants to 'us.cloudpermit.com/gov/dashboard or go to: Permit Applications on madisoncountyfl.com and…85%
Electrical code
NEC 2020 (NFPA 70, 2020 edition). Madison County's own Building Codes page states this in its own words: 'Florida's current electrical code was adopted statewide and effective on work…90%
Own placard wording
No. Neither Greenville nor Madison County specifies placard wording of its own anywhere this run could find.68%
Booking an inspection
Phone. The Building Department's own Inspections page states: 'Request an Inspection - To request an inspection, call (850) 973-6785 and provide the following information: Permit Number,85%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes, by inference rather than by an explicit PV line. Madison County's general Building Permit Application covers any residential construction/installation work… Q3 Electrical and building permits — Separate. The county publishes a distinct 'Electrical Permit Packet' (its own cover page collecting service voltage, amperage and use, e.g. Q4 Plan review — No plan-review turnaround is published by the county. The statutory floor applies: F.S. Q18 Where you file — Cloudpermit. The county's 'Before submitting information for a permit' guide directs applicants to 'us.cloudpermit.com/gov/dashboard or go to: Permit Applications… Q20

Permit required
Yes, by inference rather than by an explicit PV line. Madison County's general Building Permit Application covers any residential construction/installation work ('Type of Work: Residential /…70% source
Plan review turnaround
No plan-review turnaround is published by the county. The statutory floor applies: F.S. 553.792(1)(a) sets 5 business days after a complete and sufficient application for an electrical or structural…65% source
Key document
permit application form cited by 5 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? No. The Town of Greenville is not the AHJ for residential solar. Building permits, electrical (trade) permits, plan review and inspections inside the Greenville town limits are issued and performed by the MADISON COUNTY Building Department, 229 SW Pinckney Street, Suite 219, Madison, FL 32340 (upstairs in the County Annex Building), 850-973-6785, Building Official Dennis Pitts. The county's own Building Department page states in words: 'Residents of the City of Madison must obtain permits and inspections at City Hall, located at 321 SW Rutledge Street, Madison, FL 32340. All other residents in Madison County can visit the second floor of the Madison County Annex Building at 229 SW Pinckney Street, Suite 219, Madison, FL 32340, for permits and inspections.' Greenville is not the City of Madison, so it falls in that second sentence. Town Hall for Greenville itself was searched for and could not be found: eight candidate domains (townofgreenvillefl.com/.org, greenvillefl.com/.org, cityofgreenvillefl.com, townofgreenvillefl.org, townofgreenville-fl.com, townofgreenville.com) either fail DNS resolution or resolve to something else entirely - greenvillefl.com is a parked-for-sale HugeDomains page, and townofgreenville.com is the Town of Greenville, WISCONSIN, not Florida. 92% · county department page
    • What does this authority permit itself, and what does it delegate? Delegated. Greenville permits nothing itself - no building permit, no electrical permit, no plan review, no inspection, no published fee schedule, and no adopted construction code of its own that could be found anywhere online. Building AND electrical both sit with the Madison County Building Department (see q1). Land development/zoning is a separate and more uncertain question: Madison County's own Land Development Code Section 1.5 states 'The provisions of this Code shall apply to all land, buildings, structures and uses in the unincorporated areas of Madison County and to any other area authorized by law or interlocal agreement' - so the County's LDC does NOT reach incorporated Greenville unless an interlocal agreement extends it there, and no such agreement could be found (contrast Washington County, where the LDC is co-adopted by name by the Town Councils of Caryville, Ebro, Vernon and Wausau - Madison's LDC contains no comparable clause naming Greenville or Lee, the county's other town). Whether Greenville has any zoning ordinance of its own is unresolved: it has no website and no presence on Municode. 85% · land development code
    • Is a permit required for a residential rooftop PV system? Yes, by inference rather than by an explicit PV line. Madison County's general Building Permit Application covers any residential construction/installation work ('Type of Work: Residential / Commercial', 'Class of Work: New / Repair / Alteration / Addition / Demolition', 'Value of Work: $'), and nothing on the form or anywhere else in the Building Department's published material exempts photovoltaic installations from that general requirement. F.S. 553.79 requires a permit for construction work statewide subject to narrow statutory exemptions, none of which reach rooftop PV. No county document contains a PV-specific checkbox or line item of any kind (see the controls note at q11) - Madison, unlike some Florida counties surveyed elsewhere in this project, has not built a dedicated solar line into its form. 70% · permit application form
    • Is there a separate electrical permit, or is it combined? Separate. The county publishes a distinct 'Electrical Permit Packet' (its own cover page collecting service voltage, amperage and use, e.g. 'Residential-100 amps (min)', '200amps', RV/well service) that is bundled with, but precedes, a copy of the general Building Permit Application - functioning as an electrical-specific front sheet rather than a single combined form. The general Building Permit Application itself lists 'Electrical Subcontractor' as one line among several trade subcontractors (electrical, plumbing, mechanical, roofing), consistent with one building permit carrying multiple trade sub-permits/inspections rather than one single undifferentiated permit. 62% · permit application form
    • Is a HOA or architectural approval required first? Not by the authority. Neither Greenville nor Madison County requires HOA or architectural approval for rooftop PV, and F.S. 163.04(2) voids any deed restriction or covenant that prohibits or has the effect of prohibiting solar collectors - such a body may only 'determine the specific location where solar collectors may be installed on the roof within an orientation to the south or within 45 degrees east or west of due south if such determination does not impair the effective operation of the solar collectors.' 65% · state statute
    • Is there a historic-district review? No historic-district review reaches Greenville from the county, and no Greenville historic ordinance of any kind could be found. Madison County's Land Development Code does have a historic/archaeological sites provision (LDC Section 6.3-5, 'Historic and/or Archaeological Sites', keyed to the county's own Natural Resource maps and National Register of Historic Places eligibility), but it sits inside the LDC, which by its own Section 1.5 applies only in unincorporated Madison County (see q2) - so this provision does not reach incorporated Greenville on its own terms. 60% · land development code chapter
    • Is a wind or windstorm certification required? No county- or town-specific windstorm certificate or wind-speed-line ordinance could be found for Madison County (contrast some other Florida counties surveyed in this project, which have their own locally adopted wind-speed-line ordinance). What applies is the statewide Florida Building Code, 8th Edition (2023), which incorporates the ASCE 7-22 ultimate design wind speed maps. Neither the Building Permit Application nor the Electrical Permit Packet contains a 'Florida Product Approval' field of the kind other Florida counties print on their trade-permit forms. 58% · county department page
    • Is a Specific Use Permit or Council approval ever required? No Special Use Permit or Council approval requirement for rooftop PV could be found at either the county or town level. Because Madison County's LDC (the instrument that would define Special Exception/SUP uses) applies only in unincorporated Madison County (q2), any such approval process for a Greenville address would have to be Greenville's own - and Greenville publishes no ordinances, zoning code, or council-approval process of any kind that could be found online. 55% · land development code chapter
    • Is there a system-size cap on residential generation? No cap from the county or town. The binding cap is functional rather than a fixed kW number, and comes from the utility: Tri-County Electric Cooperative's Interconnection Agreement states 'The RGS must have a GPR [Gross Power Rating] that does not exceed ninety percent (90%) of the Customer's utility distribution service rating at the Customer's location. If the GPR does exceed that ninety percent (90%) limit, the Customer shall be responsible to pay the cost of upgrades for that distribution service.' The agreement's own recital line leaves the specific kW figure blank ('rated at no more than ___ kilowatts (kW)'), to be filled in per application rather than fixed cooperative-wide. 75% · utility interconnection agreement
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Either. A Florida-licensed electrical contractor (DBPR license number is a required field on both the Building Permit Application and the Electrical Permit Packet) may pull it, or a property owner may act as his/her own electrical contractor under the F.S. 489.503(6) exemption, for which the county publishes its own Electrical Disclosure Statement: 'State law requires electrical contracting to be done by licensed electrical contractors. You have applied for a permit under an exemption to that law. The exemption allows you, as the owner of your property, to act as your own electrical contractor even though you do not have a license... single-family or duplex residence... for your own use and occupancy.' 88% · owner disclosure form
    • Must the contractor be registered with this authority before applying? Probably yes in some form, but no registration packet or process is published online. The Building Department's own page states it 'is also responsible for the licensing of contractors registered through the Department of Business and Professional Regulation within Madison County; this is done through the Competency Licensing Board' - naming a county-level Competency Licensing Board distinct from state DBPR licensure. But the Building Department's Forms page (20 items enumerated) contains no contractor-registration form, no competency-card application, and no fee schedule for one, unlike neighbouring Florida counties surveyed elsewhere in this project that publish a full registration packet. 55% · county department page
    • Is a homeowner permitted to self-install and self-permit? Yes. Madison County's Electrical Disclosure Statement is built on the F.S. 489.503(6) owner-as-own-electrical-contractor exemption for a single-family or duplex residence for the owner's own use and occupancy, not offered for sale or lease; a sale or lease of more than one such owner-built structure within 1 year is prima facie evidence the work was done for sale or lease, voiding the exemption. The general Building Permit Application also has separate signature blocks for 'Signature of Owner/Agent' and 'Signature of Contractor', consistent with an owner pulling and signing a permit without a contractor. 85% · owner disclosure form
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? No solar-specific submittal checklist is published. What the general Building Permit Application requires for 'Addition and New Construction Projects': plans and specifications sealed by an architect and/or engineer; Two Sets of Plans (2); Site Plan (2); Wind Load Analysis (2); Florida Energy Form (2); Truss Layout (2); Septic/Sewer Permit; Zoning Compliance; Notice of Commencement; Driveway Permit; Warranty Deed; plus, for commercial projects only, a Lease Agreement and Utility Agreement and four (4) sets of plans instead of two. Whether a rooftop PV retrofit on an EXISTING house is read by this department as 'Addition' (checklist applies) or ordinary 'Repair/Alteration' (checklist may not fully apply) is not stated. 68% · permit application form
    • How many copies, and in what format? Format is digital-first: the county's own 'Before submitting information for a permit' guide instructs applicants to complete the entire application at us.cloudpermit.com/gov/dashboard and 'upload your completed forms when you reach the attachment section.' The paper Building Permit Application itself still calls for 'Two Sets of Plans (2)... If indicated provide two (2) copies, one will be returned with building permit noting any required corrections' for in-person or mailed submittals. No page count, sheet size or file-format specification (e.g. PDF, DWG) is published for the digital upload route. 70% · county guidance document
    • Is a site plan required, and what must it show? Yes for new construction/additions - 'Site Plan (2)' is one of the checklist items on the Building Permit Application - but what it must show is not specified anywhere in the Building Department's published material. A separate 'Zoning Compliance' line also appears on the same checklist, which is in tension with Madison County's own Land Development Code Section 1.5 stating the LDC applies only in unincorporated areas (see q2) - it is not established whether the county's generic Building Permit Application checklist, including this Zoning Compliance line, is applied literally inside Greenville's limits or is understood to be inapplicable there. 55% · permit application form
    • Is a one-line / three-line diagram required? Not required by the county's own building/electrical forms - no line diagram field or requirement appears on either the Building Permit Application or the Electrical Permit Packet. It IS required by the utility: Tri-County Electric Cooperative's own Interconnection Process states at step 3, 'Provide Supporting Documents - Submit a one-line diagram showing the electrical design of the generating installation, including equipment for interconnection with the Cooperative's system. TCEC's Engineering Department may require additional documents.' Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents. 72% · utility interconnection process
    • Is a structural PE stamp required, and at what threshold? No local structural PE-stamp threshold is published. What the Building Permit Application does say is that 'For Addition and New Construction Projects all plans and specifications are required to be sealed by an architect and/or engineer showing seal and signature with license number' - a trigger tied to project CLASSIFICATION (Addition/New Construction) rather than to a size, load or kW threshold. Whether a rooftop PV retrofit on an existing house counts as an 'Addition' for this purpose is not stated (see q8). 58% · permit application form
    • Is an electrical PE stamp required, and at what threshold? No local electrical PE-stamp requirement is published by Madison County. At state level, F.S. 471.003(2)(h) exempts a ch. 489-licensed electrical contractor from engineering licensure where the project 'Requires an electrical or plumbing or air-conditioning and refrigeration system with a value of $125,000 or less' and 'Requires an aggregate service capacity of 600 amperes (240 volts) or less on a residential electrical system' - which covers essentially every residential rooftop PV job. 68% · state statute
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Cloudpermit. The county's 'Before submitting information for a permit' guide directs applicants to 'us.cloudpermit.com/gov/dashboard or go to: Permit Applications on madisoncountyfl.com and click Online Permit', and the Permit Applications page itself is titled 'e permit application at US.CLOUDPERMIT.COM Online Permit Application' alongside a 'Print a Permit Application' route for paper forms. 85% · permit portal landing page
    • Can the whole application be completed online? Yes, by the county's own instructions. The 'Before submitting information for a permit' guide walks the applicant through completing the ENTIRE application inside Cloudpermit: select forms, complete and sign them, then 'Complete the New Application on us.cloudpermit.com/gov/dashboard and upload your completed forms when you reach the attachment section... Complete and submit your application.' This is a materially different process from counties that require an in-person or emailed submittal - Madison's own guidance describes a start-to-finish online flow, apart from any documents (like a notarized Notice of Commencement) that must still be recorded with the County Clerk separately. 78% · county guidance document
    • How is the fee calculated? Likely valuation-based, by inference. The general Building Permit Application asks for 'Value of Work: $' as a required field, which is the standard input for a valuation-table fee calculation, but no published fee schedule confirms this or gives the multiplier/table (see q15). 55% · permit application form
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? No plan-review turnaround is published by the county. The statutory floor applies: F.S. 553.792(1)(a) sets 5 business days after a complete and sufficient application for an electrical or structural permit on an EXISTING single-family residential dwelling where the value of the work is under $15,000, and 30 business days for a residential unit or electrical permit where the structure is under 7,500 square feet. The county must give written notice within 5 business days of anything missing, or the application is automatically deemed complete under 553.792(1)(c). 65% · state statute
    • How long is an issued permit valid before it expires? No Madison County document (searched: Building Permit Application, Electrical Permit Packet, Notice of Commencement, Before-Submitting guide) states a local permit-validity period. The statutory floor is F.S. 553.79(1)(c): a building permit issued by a local government for a single-family dwelling expires 1 year after issuance, or on the effective date of the next Florida Building Code edition, whichever is later. 55% · state statute
    • Which utility handles interconnection here? Uncertain between two named utilities. Madison County's own Building Permit Application and Electrical Permit Packet both carry the field 'Utility Company: [ ] DUKE [ ] TCEC' with no geographic guidance, confirming both Duke Energy Florida and Tri-County Electric Cooperative (TCEC) operate somewhere in the county. TCEC is headquartered in Madison, FL and was chartered in 1940 'to proceed with a program of rural electrification for Madison, Taylor, and Jefferson counties' - and its own published history names two of its nine founding trustees as being 'from Greenville' (James R. Laney, Sr. and J.E. Hagan), which is first-party (if historical) evidence tying the cooperative to the Greenville area specifically. No Greenville-specific service-territory statement from either utility could be found. 52% · utility own page
    • Where does the utility sit in the sequence? Parallel, with a hard AHJ-inspection gate before the utility will energize. TCEC's own published Interconnection Process lists 11 steps: sign the interconnection agreement and submit a one-line diagram (steps 2-3) can happen before or during construction; step 7 is 'Complete Construction' (install disconnect switch, warning/safety labels); step 8 is 'Inspection by County Inspector - The installation of the system must be inspected and approved by the county'; only after that does step 9 (notify TCEC of completion), step 10 (utility verification visit) and step 11 (TCEC signs and approves) follow. The member 'may not interconnect or initiate parallel operation until such conditions are corrected and written notification has been provided to TCEC at least 10 days in advance.' 75% · utility interconnection process

28 questions answered against Town of Greenville’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

No. The Town of Greenville is not the AHJ for residential solar. Building permits, electrical (trade) permits, plan review and inspections inside the Greenville town limits are issued and performed by the MADISON COUNTY Building Department, 229 SW Pinckney Street, Suite 219, Madison, FL 32340 (upstairs in the County Annex Building), 850-973-6785, Building Official Dennis Pitts. The county's own Building Department page states in words: 'Residents of the City of Madison must obtain permits and inspections at City Hall, located at 321 SW Rutledge Street, Madison, FL 32340. All other residents in Madison County can visit the second floor of the Madison County Annex Building at 229 SW Pinckney Street, Suite 219, Madison, FL 32340, for permits and inspections.' Greenville is not the City of Madison, so it falls in that second sentence. Town Hall for Greenville itself was searched for and could not be found: eight candidate domains (townofgreenvillefl.com/.org, greenvillefl.com/.org, cityofgreenvillefl.com, townofgreenvillefl.org, townofgreenville-fl.com, townofgreenville.com) either fail DNS resolution or resolve to something else entirely - greenvillefl.com is a parked-for-sale HugeDomains page, and townofgreenville.com is the Town of Greenville, WISCONSIN, not Florida.

Why the confidence is not higherProved in this run from first-party sources, deliberately NOT inherited from the Madison County or City of Madison runs. The Building Department's own 'Obtaining a Permit' text was read in full and is unambiguous about which residents go where, and it is a rare case where the county names the ONE municipality that is carved out (City of Madison) rather than leaving the reader to infer who is covered. Corroborated independently by the state's own local-enforcement-agency registry (see q2) and by Tri-County Electric Cooperative's own published Interconnection Process, step 8 of which reads 'Inspection by County Inspector - The installation of the system must be inspected and approved by the county', naming the county rather than any town, in a document TCEC hands to every member in its territory including Greenville. Held at 92 rather than higher only because no single sentence anywhere says 'Madison County issues permits inside the Town of Greenville' by name - the case rests on the county excluding only the City of Madison by name, plus the absence of any Greenville building function anywhere (no website, no Municode entry, no floridabuilding.org registry entry - see q2).

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Delegated. Greenville permits nothing itself - no building permit, no electrical permit, no plan review, no inspection, no published fee schedule, and no adopted construction code of its own that could be found anywhere online. Building AND electrical both sit with the Madison County Building Department (see q1). Land development/zoning is a separate and more uncertain question: Madison County's own Land Development Code Section 1.5 states 'The provisions of this Code shall apply to all land, buildings, structures and uses in the unincorporated areas of Madison County and to any other area authorized by law or interlocal agreement' - so the County's LDC does NOT reach incorporated Greenville unless an interlocal agreement extends it there, and no such agreement could be found (contrast Washington County, where the LDC is co-adopted by name by the Town Councils of Caryville, Ebro, Vernon and Wausau - Madison's LDC contains no comparable clause naming Greenville or Lee, the county's other town). Whether Greenville has any zoning ordinance of its own is unresolved: it has no website and no presence on Municode.

Why the confidence is not higherThe Building Department half is the same first-party 'Obtaining a Permit' text as q1. The LDC territorial limit is Section 1.5 of Chapter 1 of Madison County's own Land Development Code, read in full from the PDF in this run, and its silence on Greenville was checked directly: the word 'Greenville' does not appear anywhere in LDC Chapters 1, 3, 4 or 6, all four of which were pulled and read as text in this run (Chapter 4, the largest, is 4,597 lines). Held at 85 rather than higher because Section 1.5's own 'or to any other area authorized by law or interlocal agreement' clause means an interlocal extension into Greenville cannot be ruled out from absence in the LDC text alone - it would live in a separate interlocal agreement document, which was searched for on the county site and not found.

land development code checked 2026-09-14 https://madisoncountyfl.com/departments-services/planning-zoning/land-development-codes/

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes, by inference rather than by an explicit PV line. Madison County's general Building Permit Application covers any residential construction/installation work ('Type of Work: Residential / Commercial', 'Class of Work: New / Repair / Alteration / Addition / Demolition', 'Value of Work: $'), and nothing on the form or anywhere else in the Building Department's published material exempts photovoltaic installations from that general requirement. F.S. 553.79 requires a permit for construction work statewide subject to narrow statutory exemptions, none of which reach rooftop PV. No county document contains a PV-specific checkbox or line item of any kind (see the controls note at q11) - Madison, unlike some Florida counties surveyed elsewhere in this project, has not built a dedicated solar line into its form.

Why the confidence is not higherThe Building Permit Application was extracted from PDF and read in full in this run. Held at 70 rather than higher because the inference rests on the GENERAL permit requirement plus the absence of any solar carve-out, not on an explicit statement that photovoltaic systems need a permit - no Madison County document was found that names solar, PV, or renewable energy at all.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Separate. The county publishes a distinct 'Electrical Permit Packet' (its own cover page collecting service voltage, amperage and use, e.g. 'Residential-100 amps (min)', '200amps', RV/well service) that is bundled with, but precedes, a copy of the general Building Permit Application - functioning as an electrical-specific front sheet rather than a single combined form. The general Building Permit Application itself lists 'Electrical Subcontractor' as one line among several trade subcontractors (electrical, plumbing, mechanical, roofing), consistent with one building permit carrying multiple trade sub-permits/inspections rather than one single undifferentiated permit.

Why the confidence is not higherBoth PDFs (Building Permit Application and Electrical Permit Packet) were extracted and read in full in this run. Held at 62 because no county document states in words whether a stand-alone electrical job (as opposed to an electrical subcontractor under a building permit) gets its own permit NUMBER and fee, or whether it is always issued as a sub-permit under a parent building permit - the Electrical Permit Packet's own second page is a verbatim copy of the general Building Permit Application, which blurs rather than settles the question.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27130434/Electrical-Permit-Package-1.pdf

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either. A Florida-licensed electrical contractor (DBPR license number is a required field on both the Building Permit Application and the Electrical Permit Packet) may pull it, or a property owner may act as his/her own electrical contractor under the F.S. 489.503(6) exemption, for which the county publishes its own Electrical Disclosure Statement: 'State law requires electrical contracting to be done by licensed electrical contractors. You have applied for a permit under an exemption to that law. The exemption allows you, as the owner of your property, to act as your own electrical contractor even though you do not have a license... single-family or duplex residence... for your own use and occupancy.'

Why the confidence is not higherThe Electrical Disclosure Statement was extracted from PDF and read in full, and its citation '(489.503-6)' was independently verified against the actual statute text at the Florida Legislature's own site in this run, which confirms F.S. 489.503(6)(a) exempts 'An owner of property... acting as his or her own electrical contractor... when building or improving a farm outbuilding or a single-family or duplex residence... for the occupancy or use of such owner and not offered for sale or lease.' Held at 88 rather than higher only because neither document addresses solar specifically, and TCEC's interconnection agreement (see q23) does not say whether it will accept a self-installed system without a licensed contractor's signature.

owner disclosure form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27130435/Electrical-Disclosure-1.pdf

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Probably yes in some form, but no registration packet or process is published online. The Building Department's own page states it 'is also responsible for the licensing of contractors registered through the Department of Business and Professional Regulation within Madison County; this is done through the Competency Licensing Board' - naming a county-level Competency Licensing Board distinct from state DBPR licensure. But the Building Department's Forms page (20 items enumerated) contains no contractor-registration form, no competency-card application, and no fee schedule for one, unlike neighbouring Florida counties surveyed elsewhere in this project that publish a full registration packet.

Why the confidence is not higherThe 'Competency Licensing Board' sentence is quoted from the Building Department's own page, read in full in this run. The Forms page was enumerated in full (20 items) and contains no matching document. Held at 55 - genuinely uncertain rather than a confident absence, because a county-level Competency Licensing Board almost certainly implies SOME registration step happens at the counter even though nothing about it is published.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes. Madison County's Electrical Disclosure Statement is built on the F.S. 489.503(6) owner-as-own-electrical-contractor exemption for a single-family or duplex residence for the owner's own use and occupancy, not offered for sale or lease; a sale or lease of more than one such owner-built structure within 1 year is prima facie evidence the work was done for sale or lease, voiding the exemption. The general Building Permit Application also has separate signature blocks for 'Signature of Owner/Agent' and 'Signature of Contractor', consistent with an owner pulling and signing a permit without a contractor.

Why the confidence is not higherBoth documents read in full from PDF, and the statute cross-checked at the Legislature's own site in this run. Held at 85 rather than higher because no document addresses solar specifically, and because F.S. 489.103 (the broader owner-builder exemption covering all trades, not just electrical) was not found published anywhere on the county's site - only the narrower electrical-specific 489.503(6) disclosure is published, so it is unclear whether Madison County requires a SEPARATE owner-builder affidavit for the building-permit half of a solar job the way it clearly does for the electrical half.

owner disclosure form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27130435/Electrical-Disclosure-1.pdf

Q8 What documents make up a complete submittal? Core Submittal package

No solar-specific submittal checklist is published. What the general Building Permit Application requires for 'Addition and New Construction Projects': plans and specifications sealed by an architect and/or engineer; Two Sets of Plans (2); Site Plan (2); Wind Load Analysis (2); Florida Energy Form (2); Truss Layout (2); Septic/Sewer Permit; Zoning Compliance; Notice of Commencement; Driveway Permit; Warranty Deed; plus, for commercial projects only, a Lease Agreement and Utility Agreement and four (4) sets of plans instead of two. Whether a rooftop PV retrofit on an EXISTING house is read by this department as 'Addition' (checklist applies) or ordinary 'Repair/Alteration' (checklist may not fully apply) is not stated.

Why the confidence is not higherThe checklist is quoted verbatim from the Building Permit Application, extracted from PDF and read in full in this run. The Building Department's Forms page (20 items) was enumerated in full and contains no PV or renewable-energy-specific checklist of any kind - see the controls note at q11. Held at 68 because this is a reconstruction from a checklist written for new construction/additions generally, not a document the county publishes as a solar submittal list.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q9 How many copies, and in what format? Submittal package

Format is digital-first: the county's own 'Before submitting information for a permit' guide instructs applicants to complete the entire application at us.cloudpermit.com/gov/dashboard and 'upload your completed forms when you reach the attachment section.' The paper Building Permit Application itself still calls for 'Two Sets of Plans (2)... If indicated provide two (2) copies, one will be returned with building permit noting any required corrections' for in-person or mailed submittals. No page count, sheet size or file-format specification (e.g. PDF, DWG) is published for the digital upload route.

Why the confidence is not higherBoth the 'Before submitting' PDF and the Building Permit Application PDF were extracted and read in full in this run. Held at 70 because the two instructions (2 paper copies vs. digital upload) are not reconciled anywhere - it is not stated whether a Cloudpermit applicant must also bring paper copies, or whether the '2 copies' language is now legacy text left over from a pre-portal process.

county guidance document checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2026/08/03163053/Before-submitting-information-for-a-permit-003.pdf

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes for new construction/additions - 'Site Plan (2)' is one of the checklist items on the Building Permit Application - but what it must show is not specified anywhere in the Building Department's published material. A separate 'Zoning Compliance' line also appears on the same checklist, which is in tension with Madison County's own Land Development Code Section 1.5 stating the LDC applies only in unincorporated areas (see q2) - it is not established whether the county's generic Building Permit Application checklist, including this Zoning Compliance line, is applied literally inside Greenville's limits or is understood to be inapplicable there.

Why the confidence is not higherThe checklist items are quoted from the Building Permit Application PDF, read in full in this run. No site-plan specification document (what scale, what must be shown, setbacks, etc.) could be found on the Building Department's Forms, Permit Applications or Building Codes pages, all of which were enumerated in this run. Held at 55 because of the unresolved Zoning Compliance tension noted above, which is a genuine open question for a Greenville address rather than a settled fact.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Not required by the county's own building/electrical forms - no line diagram field or requirement appears on either the Building Permit Application or the Electrical Permit Packet. It IS required by the utility: Tri-County Electric Cooperative's own Interconnection Process states at step 3, 'Provide Supporting Documents - Submit a one-line diagram showing the electrical design of the generating installation, including equipment for interconnection with the Cooperative's system. TCEC's Engineering Department may require additional documents.' Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Why the confidence is not higherThe county-side absence is a proved absence on the controls described above - the Building Permit Application and Electrical Permit Packet were both read in full and contain no diagram requirement of any kind, PV or otherwise. The utility requirement is quoted verbatim from TCEC's own published Interconnection Process, read in full in this run. Held at 72 because which utility actually serves a given Greenville address is itself not fully settled (see q22), so this finding is firm for TCEC customers and unconfirmed for any Duke Energy customers inside the town.

utility interconnection process checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedMadison County Building Permit Application and Electrical Permit Packet (read in full, no calculation requirement of any kind), Building Department Forms page (20 items enumerated, no calculation worksheet), and Tri-County Electric Cooperative's Interconnection Process and Interconnection Agreement (both read in full - the Interconnection Process asks only for a one-line diagram, not string or conductor calculations). No document anywhere states whether string sizing or conductor/voltage-drop calculations must be submitted, so this is an unreachable requirement rather than a proved absence - a county reviewer may ask for calculations at the counter without publishing that fact.

https://madisoncountyfl.com/departments-services/building-department/forms/

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

No local structural PE-stamp threshold is published. What the Building Permit Application does say is that 'For Addition and New Construction Projects all plans and specifications are required to be sealed by an architect and/or engineer showing seal and signature with license number' - a trigger tied to project CLASSIFICATION (Addition/New Construction) rather than to a size, load or kW threshold. Whether a rooftop PV retrofit on an existing house counts as an 'Addition' for this purpose is not stated (see q8).

Why the confidence is not higherQuoted verbatim from the Building Permit Application, read in full from PDF in this run. Held at 58 because the trigger is by project type, not threshold, and because no separate structural or wind-engineering ordinance chapter comparable to other Florida counties' locally adopted building chapters could be found for Madison County - its Land Development Code (Chapters 1, 3, 4, 5, 6, 7 as listed on the county's own LDC page) contains no building/electrical chapter at all, unlike counties that fold building regulations into their code of ordinances.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

No local electrical PE-stamp requirement is published by Madison County. At state level, F.S. 471.003(2)(h) exempts a ch. 489-licensed electrical contractor from engineering licensure where the project 'Requires an electrical or plumbing or air-conditioning and refrigeration system with a value of $125,000 or less' and 'Requires an aggregate service capacity of 600 amperes (240 volts) or less on a residential electrical system' - which covers essentially every residential rooftop PV job.

Why the confidence is not higherThe statutory text was fetched and read from the Florida Legislature's own site in this run. The local absence rests on the same enumeration described at q11/q13 - no Madison County document imposes an electrical PE requirement of its own. Held at 68 because the statute answers who may DESIGN without a PE, not whether the Building Official ever asks for a stamped electrical drawing on a specific job, which is not published either way.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0471/Sections/0471.003.html

Q15 What does a residential solar permit cost? Core Fees

Nothing published by this authority.

Where we lookedThe Building Department's own pages (main department page, Contact Information, Permit Applications, Building Codes, Inspections, Forms) were all read in full and NONE of them link to or state a fee schedule for building or electrical permits - unlike Planning & Zoning, which publishes its own LDC application fee schedule (Resolution No. 2016-09-14A, OCR'd and read in full in this run) that covers subdivision, plat, variance and site-plan-compliance fees only, none of which are a building-permit valuation fee. The site's own WordPress search for 'fee schedule' returns only the Planning & Zoning fee page. The county's 'Before submitting information for a permit' guide says only 'Fees will apply for each permit required' with no amount, consistent with fees being calculated inside the Cloudpermit portal at submission rather than published as a static table. No dollar figure for a residential solar/building/electrical permit could be found anywhere.

https://madisoncountyfl.com/departments-services/building-department/

Q16 How is the fee calculated? Core Fees

Likely valuation-based, by inference. The general Building Permit Application asks for 'Value of Work: $' as a required field, which is the standard input for a valuation-table fee calculation, but no published fee schedule confirms this or gives the multiplier/table (see q15).

Why the confidence is not higherThe 'Value of Work' field is quoted from the Building Permit Application PDF, read in full in this run. Held at 55 because this is an inference from the presence of a valuation input field, not a stated fee methodology - no fee schedule document exists to confirm it (see q15's not_found).

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q17 Is there a separate plan-check fee? Fees

Nothing published by this authority.

Where we lookedSame search as q15 - Building Department pages and Forms enumerated in full, no fee schedule of any kind found, so whether a separate plan-check fee exists cannot be determined either way.

https://madisoncountyfl.com/departments-services/building-department/

Q18 What is the stated plan-review turnaround? Core Timeline & validity

No plan-review turnaround is published by the county. The statutory floor applies: F.S. 553.792(1)(a) sets 5 business days after a complete and sufficient application for an electrical or structural permit on an EXISTING single-family residential dwelling where the value of the work is under $15,000, and 30 business days for a residential unit or electrical permit where the structure is under 7,500 square feet. The county must give written notice within 5 business days of anything missing, or the application is automatically deemed complete under 553.792(1)(c).

Why the confidence is not higherThe statute was fetched and read from the Florida Legislature's own site in this run - it is the operative deadline because 553.792(1)(b) requires local governments to meet it 'unless the timeframes set by local ordinance are more stringent', and no Madison County ordinance setting its own timeframe could be found. Held at 65 because a statutory ceiling is not the same as a published service standard, and because whether a solar retrofit is treated as work on an 'existing' dwelling under $15,000 (5-day track) or the 30-day track is not settled by anything Madison-specific.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0500-0599/0553/Sections/0553.792.html

Q19 How long is an issued permit valid before it expires? Timeline & validity

No Madison County document (searched: Building Permit Application, Electrical Permit Packet, Notice of Commencement, Before-Submitting guide) states a local permit-validity period. The statutory floor is F.S. 553.79(1)(c): a building permit issued by a local government for a single-family dwelling expires 1 year after issuance, or on the effective date of the next Florida Building Code edition, whichever is later.

Why the confidence is not higherThe statute was fetched and read from the Legislature's own site in this run. Held at 55 - lower than the equivalent Washington County finding elsewhere in this project - because there Every county form itself stated a conflicting expiration window; here, Madison publishes NOTHING on the point at all, so the statutory floor is asserted with no local document to corroborate or contradict it either way.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0500-0599/0553/Sections/0553.79.html

Q20 Which permit portal does this authority use? Core Portal & process

Cloudpermit. The county's 'Before submitting information for a permit' guide directs applicants to 'us.cloudpermit.com/gov/dashboard or go to: Permit Applications on madisoncountyfl.com and click Online Permit', and the Permit Applications page itself is titled 'e permit application at US.CLOUDPERMIT.COM Online Permit Application' alongside a 'Print a Permit Application' route for paper forms.

Why the confidence is not higherBoth the guide PDF and the Permit Applications page were read in full in this run, and both name the same platform. Held at 85 rather than higher because the Cloudpermit dashboard itself requires an account to view, so its actual application screens, fee calculator and document requirements could not be inspected from outside a login in this run.

permit portal landing page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/permit-applications/

Q21 Can the whole application be completed online? Core Portal & process

Yes, by the county's own instructions. The 'Before submitting information for a permit' guide walks the applicant through completing the ENTIRE application inside Cloudpermit: select forms, complete and sign them, then 'Complete the New Application on us.cloudpermit.com/gov/dashboard and upload your completed forms when you reach the attachment section... Complete and submit your application.' This is a materially different process from counties that require an in-person or emailed submittal - Madison's own guidance describes a start-to-finish online flow, apart from any documents (like a notarized Notice of Commencement) that must still be recorded with the County Clerk separately.

Why the confidence is not higherQuoted and paraphrased from the 'Before submitting' PDF, read in full in this run. Held at 78 rather than higher because the Cloudpermit dashboard itself is login-gated and could not be inspected directly to confirm payment can also be completed online, only that the application and document upload can.

county guidance document checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2026/08/03163053/Before-submitting-information-for-a-permit-003.pdf

Q22 Which utility handles interconnection here? Core Utility interconnection

Uncertain between two named utilities. Madison County's own Building Permit Application and Electrical Permit Packet both carry the field 'Utility Company: [ ] DUKE [ ] TCEC' with no geographic guidance, confirming both Duke Energy Florida and Tri-County Electric Cooperative (TCEC) operate somewhere in the county. TCEC is headquartered in Madison, FL and was chartered in 1940 'to proceed with a program of rural electrification for Madison, Taylor, and Jefferson counties' - and its own published history names two of its nine founding trustees as being 'from Greenville' (James R. Laney, Sr. and J.E. Hagan), which is first-party (if historical) evidence tying the cooperative to the Greenville area specifically. No Greenville-specific service-territory statement from either utility could be found.

Why the confidence is not higherThe DUKE/TCEC checkbox is quoted from both PDF forms, read in full in this run. The TCEC history quote is from the cooperative's own History page, read in full. Held at 52, deliberately capped, because this is corroboration and historical association rather than a first-party 'we serve Greenville' statement of the kind found for other authorities in this project - an actual Greenville address could be on either utility's system, and this run could not resolve which.

utility own page checked 2026-09-14 https://www.tcec.com/history

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Parallel, with a hard AHJ-inspection gate before the utility will energize. TCEC's own published Interconnection Process lists 11 steps: sign the interconnection agreement and submit a one-line diagram (steps 2-3) can happen before or during construction; step 7 is 'Complete Construction' (install disconnect switch, warning/safety labels); step 8 is 'Inspection by County Inspector - The installation of the system must be inspected and approved by the county'; only after that does step 9 (notify TCEC of completion), step 10 (utility verification visit) and step 11 (TCEC signs and approves) follow. The member 'may not interconnect or initiate parallel operation until such conditions are corrected and written notification has been provided to TCEC at least 10 days in advance.'

Why the confidence is not higherQuoted and summarised from TCEC's own Interconnection Process document, read in full in this run - step 8 is the clearest evidence in this whole run that 'the county' (not Greenville) is understood as the inspecting authority even by a third party with no stake in the answer. Held at 75 rather than higher because this sequence is TCEC's; if the address is actually served by Duke Energy Florida (see q22), Duke's own interconnection sequence was not located in this run.

utility interconnection process checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

Not by the authority. Neither Greenville nor Madison County requires HOA or architectural approval for rooftop PV, and F.S. 163.04(2) voids any deed restriction or covenant that prohibits or has the effect of prohibiting solar collectors - such a body may only 'determine the specific location where solar collectors may be installed on the roof within an orientation to the south or within 45 degrees east or west of due south if such determination does not impair the effective operation of the solar collectors.'

Why the confidence is not higherThe statute was fetched and read from the Legislature's own site in this run. No Madison County or Greenville document imposes an HOA/ARC review step of its own - none was found among the Building Department's or Planning & Zoning's published material. Held at 65 because Greenville itself publishes nothing that could either confirm or rule out a town-level requirement, and because the LDC's territorial limit to unincorporated areas (q2) means the county's silence on this point does not necessarily describe Greenville's own practice.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0100-0199/0163/Sections/0163.04.html

Q25 Is there a historic-district review? Overlays & special cases

No historic-district review reaches Greenville from the county, and no Greenville historic ordinance of any kind could be found. Madison County's Land Development Code does have a historic/archaeological sites provision (LDC Section 6.3-5, 'Historic and/or Archaeological Sites', keyed to the county's own Natural Resource maps and National Register of Historic Places eligibility), but it sits inside the LDC, which by its own Section 1.5 applies only in unincorporated Madison County (see q2) - so this provision does not reach incorporated Greenville on its own terms.

Why the confidence is not higherLDC Chapter 6 was pulled as PDF and read in full (1,444 lines) in this run; Section 6.3-5 is quoted accurately. Held at 60 because Greenville has no website and no Municode presence, so a town-level historic designation or ordinance can be neither found nor ruled out - the absence proven here is the COUNTY's, not Greenville's own.

land development code chapter checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/28151412/Chapter-6-Environmental-Protection.pdf

Q26 Is a wind or windstorm certification required? Overlays & special cases

No county- or town-specific windstorm certificate or wind-speed-line ordinance could be found for Madison County (contrast some other Florida counties surveyed in this project, which have their own locally adopted wind-speed-line ordinance). What applies is the statewide Florida Building Code, 8th Edition (2023), which incorporates the ASCE 7-22 ultimate design wind speed maps. Neither the Building Permit Application nor the Electrical Permit Packet contains a 'Florida Product Approval' field of the kind other Florida counties print on their trade-permit forms.

Why the confidence is not higherBoth PDFs were read in full in this run and neither field is present. The Building Codes page was also read in full and does not mention wind speed, ASCE 7 or product approval at all - it addresses only the FBC and the 2020 NEC. Held at 58 because the absence of a product-approval field on the FORM is not proof the county does not require Florida Product Approval documentation for roofing/racking attachments at the counter; it is only proof that no such field is printed.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

No Special Use Permit or Council approval requirement for rooftop PV could be found at either the county or town level. Because Madison County's LDC (the instrument that would define Special Exception/SUP uses) applies only in unincorporated Madison County (q2), any such approval process for a Greenville address would have to be Greenville's own - and Greenville publishes no ordinances, zoning code, or council-approval process of any kind that could be found online.

Why the confidence is not higherSame LDC territorial-scope finding as q2/q25, cross-checked against a full-text search of LDC Chapters 1, 3, 4 and 6 for 'special exception', 'special use' and 'council approval' language tied to renewable energy, which returned only generic (non-solar) special-exception provisions inapplicable inside Greenville. Held at 55 because Greenville's own governance process - whether its Town Council has ever adopted anything requiring case-by-case approval of structures like a ground-mounted array - is genuinely unknown, not proven absent.

land development code chapter checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/28151409/Chapter-4-Land-Use-Districts-and-Development-Standards.pdf

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No cap from the county or town. The binding cap is functional rather than a fixed kW number, and comes from the utility: Tri-County Electric Cooperative's Interconnection Agreement states 'The RGS must have a GPR [Gross Power Rating] that does not exceed ninety percent (90%) of the Customer's utility distribution service rating at the Customer's location. If the GPR does exceed that ninety percent (90%) limit, the Customer shall be responsible to pay the cost of upgrades for that distribution service.' The agreement's own recital line leaves the specific kW figure blank ('rated at no more than ___ kilowatts (kW)'), to be filled in per application rather than fixed cooperative-wide.

Why the confidence is not higherQuoted verbatim from TCEC's own Interconnection Agreement template, extracted from PDF and read in full in this run. Held at 75 because this cap is TCEC's; if the relevant Greenville address is actually served by Duke Energy Florida (see q22), Duke's cap was not located in this run, and no Madison County LDC or building provision imposes any generation-size cap of its own (LDC full-text search for 'kW', 'kilowatt' and 'generation cap' in Chapters 1, 3, 4 and 6 returned no hits).

utility interconnection agreement checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/TCEC%20Interconnection%20Agreement.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? NEC 2020 (NFPA 70, 2020 edition). Madison County's own Building Codes page states this in its own words: 'Florida's current electrical code was adopted statewide and effective on work permitted after January 1, 2021 is the 2020 National Electric Code. It is also known as NFPA 70 2020.' This matches the statewide adoption at FAC 69A-60.005(2)(qq), '(qq) NFPA 70, 2020 edition, National Electrical Code', effective 31 December 2023. 90% · county department page
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023). FAC 61G20-1.001(1) currently reads: 'The Florida Building Code, 8th Edition (2023), as updated by the Florida Building Commission on June 20, 2023, April 16, 2024, August 13, 2024, December 10, 2024, December 20, 2024, April 15, 2025, and December 9, 2025, and incorporated herein by reference is hereby adopted as the building code for the State of Florida.' Madison County's own Building Codes page uses older, generic phrasing - 'The current Florida Building codes, effective on work permitted after December 31, 2017, can be accessed for free online' - that is stale as a description of the edition currently in force but does not contradict it, since the page just links out to whatever the current online code is rather than naming an edition. 82% · state administrative rule
    • Which fire code edition is in force? Florida Fire Prevention Code - NFPA 1, the Fire Code, Florida 2021 Edition, and NFPA 101, the Life Safety Code, Florida 2021 Edition, both adopted by FAC Chapter 69A-60 (69A-60.003 and .004) effective 31 December 2023. No Madison County or Greenville amendment to the fire code was found - the county's Building Codes page does not mention fire code at all, and no separate Fire Rescue department fire-code page was located with code-adoption content. 70% · state administrative rule
    • Are there local amendments to any of the above? No local amendments to the building, electrical or fire codes could be found for Madison County or Greenville. This is a genuine structural difference from many Florida counties: Madison County's Land Development Code (Chapters 1 through 7, as listed on the county's own LDC page: Status/Amendments, Language/Definitions, Administration, Land Use Districts/Development Standards, Subdivision Regulations, Environmental Protection, Concurrency) contains NO building or electrical chapter at all - unlike counties whose code of ordinances folds a locally-amended electrical/building article into the general code. The Building Codes webpage states only that the statewide FBC and 2020 NEC apply, with no mention of any local amendment. 60% · county department page
    • What is the installation judged against? The installation is judged against the Florida Building Code, 8th Edition (2023) and NFPA 70 (NEC), 2020 edition, both adopted statewide and both named in plain language on Madison County's own Building Codes page. The Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida 2021 Editions) applies by operation of state rule. No Madison County or Greenville local amendment to any of these could be found (q32). 80% · county department page
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for Town of Greenville on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Rapid shutdown is required, to NEC 2020 - that is, NEC 690.12 as it stands in the 2020 edition. Madison County's own Building Codes page states the 2020 NEC is in force (q29), and neither the county nor Greenville adds or subtracts anything from it. 78% · county department page
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? No AHJ-specific placard set. Neither Greenville nor Madison County specifies any placard, marking or label for a PV system at the service equipment - the Building Department's pages and forms are silent on the point entirely. The utility does require labelling: TCEC's Interconnection Process step 7 requires the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative to protect its personnel, facilities and operations' before energizing. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents. 62% · utility interconnection process
    • Does the authority specify placard wording of its own? No. Neither Greenville nor Madison County specifies placard wording of its own anywhere this run could find. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents. 68% · county department page
    • Does it specify letter height, colour or material? No. Neither Greenville nor Madison County specifies letter height, colour or material for any PV placard or label. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents. 60% · county department page
    • Is a site plan / facility map placard required, and what must it show? Not addressed by the AHJ. Madison County publishes no site-plan/facility-map placard requirement of its own for PV. By default, NEC 705.10 (Identification of Power Sources) requires a permanent plaque or directory at each service disconnecting means identifying all on-site sources of power, which applies here because the 2020 NEC is confirmed in force (q29) - but the substantive text of 705.10 itself could not be read in this run (same 403/JavaScript-viewer limitation affecting every NEC section cited in this survey), so this is the edition asserted, not the section quoted. 50% · county department page
    • Does the UTILITY specify placards beyond the AHJ's? Yes. Tri-County Electric Cooperative's own Interconnection Agreement requires, beyond anything the AHJ publishes: a UL 1741-listed, NRTL-certified, anti-islanding inverter ('The inverter shall be considered certified for interconnected operation if it has been submitted by a manufacturer to a nationally-recognized testing laboratory (NRTL) to comply with UL 1741'); a manual AC disconnect switch mounted separately from the meter socket, readily accessible to the Cooperative and capable of being locked in the open position by the Cooperative; Personal Injury and Property Damage Liability Insurance (at least $1,000,000 for systems above 10 kW); and a one-line diagram submitted before installation (q11). 80% · utility interconnection agreement
    • Where must the labels be placed? TCEC's Interconnection Agreement specifies only the disconnect switch's location, not a label's: 'mounted separately from the meter socket' and 'readily accessible at all times to the Cooperative.' No document, county or utility, specifies WHERE a placard or warning label itself must be placed (e.g. at the meter, at the main panel, at the disconnect) beyond that general accessibility requirement for the disconnect switch. 60% · utility interconnection agreement
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? Per the utility (TCEC): the AC disconnect must be mounted SEPARATELY from the meter socket, and must be readily accessible at all times to the Cooperative and capable of being locked in the open position by the Cooperative. No exact distance or side-of-meter rule is given - only that it is a distinct, separately-mounted switch. No AHJ (county or town) document adds anything further. 75% · utility interconnection agreement
    • Must equipment be on a specific approved list? Yes, at least for the inverter. TCEC's Interconnection Agreement requires 'interconnection system equipment that ceases to interconnect with the utility upon a loss of utility power' to be 'certified for interconnected operation' by having been 'submitted by a manufacturer to a nationally-recognized testing laboratory (NRTL) to comply with UL 1741', with the NRTL itself required to be OSHA-approved. No county-level approved-equipment list could be found - this requirement is the utility's, not the AHJ's. 75% · utility interconnection agreement
    • Are batteries permitted, and under what conditions? Presumably yes, under the general codes rather than any Madison-specific rule. Batteries/ESS are addressed generally by NEC 2020 (Article 706) and by the Florida Fire Prevention Code (NFPA 1, Florida 2021 Edition), both of which apply in Madison County via statewide adoption (q29, q31). Neither Madison County nor Greenville publishes any battery- or ESS-specific condition, permit note, or restriction of its own - the word 'battery', 'batteries', 'energy storage' and 'ESS' return zero hits across every Madison County Building Department document and every TCEC interconnection document read in this run. 55% · county department page
    • Is a ground mount treated as a structure? Unresolved, and genuinely so. Madison County's Land Development Code, which is where a definition of 'structure' triggering site-plan/zoning review would live, applies only in unincorporated Madison County (q2) and therefore does not reach a ground mount inside Greenville's limits on its own terms. The Building Department's general practice would almost certainly treat a ground-mounted array as requiring a building permit as a structure/accessory structure under the Florida Building Code (the Forms page lists an 'Accessory Structure Permit Application' as a distinct package), but whether Greenville's own (unpublished, unconfirmed) zoning - if any exists - treats it as a structure for setback/zoning purposes is not established. 55% · county department page
    • Is there a local rule on service upgrades or busbar sizing? No local rule on service upgrades or busbar sizing could be found. Madison County has no building/electrical chapter in its Land Development Code at all (see q32), and neither the Building Permit Application nor the Electrical Permit Packet states a local rule on service conductors, busbar or 120% sizing - what governs is NEC 2020 Article 705 (including 705.12) as adopted statewide, with no Madison-specific supplement found. 55% · permit application form
    • Is a specific mounting system or attachment spacing required? Not published. No mounting system, attachment spacing, rail, flashing or standoff requirement appears in the Building Permit Application, the Electrical Permit Packet, the Building Codes page, or the Forms page (20 items enumerated - none is a roofing/mounting spec). No 'Florida Product Approval' field appears on any Madison County form (contrast q26). Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents. 58% · county department page

20 questions answered against Town of Greenville’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

NEC 2020 (NFPA 70, 2020 edition). Madison County's own Building Codes page states this in its own words: 'Florida's current electrical code was adopted statewide and effective on work permitted after January 1, 2021 is the 2020 National Electric Code. It is also known as NFPA 70 2020.' This matches the statewide adoption at FAC 69A-60.005(2)(qq), '(qq) NFPA 70, 2020 edition, National Electrical Code', effective 31 December 2023.

Why the confidence is not higherThe county's own Building Codes page was read in full in this run and states the 2020 NEC in its own words - double-sourced against the actual state administrative rule document (69A-60.005.doc) downloaded from flrules.org and parsed, not a summary, in the same run. Held at 90 rather than higher only because 69A-60.005 is technically the Fire Prevention Code's referenced-publications list rather than the Building Code's, and the Florida Building Code's own electrical cross-reference could not itself be opened (codes.iccsafe.org returns 403/JavaScript-only in this environment) - but the county's own plain-English statement removes most of the doubt that caveat would otherwise carry.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023). FAC 61G20-1.001(1) currently reads: 'The Florida Building Code, 8th Edition (2023), as updated by the Florida Building Commission on June 20, 2023, April 16, 2024, August 13, 2024, December 10, 2024, December 20, 2024, April 15, 2025, and December 9, 2025, and incorporated herein by reference is hereby adopted as the building code for the State of Florida.' Madison County's own Building Codes page uses older, generic phrasing - 'The current Florida Building codes, effective on work permitted after December 31, 2017, can be accessed for free online' - that is stale as a description of the edition currently in force but does not contradict it, since the page just links out to whatever the current online code is rather than naming an edition.

Why the confidence is not higherThe rule text was downloaded as the actual 61G20-1.001.doc equivalent from flrules.org and read in this run (state fact re-verified same-day as the Ebro, FL run in this project, from the same primary source). Held at 82, not higher, because Madison County's own page does not itself name the 8th Edition - the county-specific confirmation is weaker here than it was for the NEC (q29), where the county page stated the edition explicitly.

state administrative rule checked 2026-09-14 https://www.flrules.org/gateway/ruleNo.asp?id=61G20-1.001

Q31 Which fire code edition is in force? Code editions in force

Florida Fire Prevention Code - NFPA 1, the Fire Code, Florida 2021 Edition, and NFPA 101, the Life Safety Code, Florida 2021 Edition, both adopted by FAC Chapter 69A-60 (69A-60.003 and .004) effective 31 December 2023. No Madison County or Greenville amendment to the fire code was found - the county's Building Codes page does not mention fire code at all, and no separate Fire Rescue department fire-code page was located with code-adoption content.

Why the confidence is not higherThe editions and effective dates were read from the Florida Administrative Code chapter listing for 69A-60 at flrules.org in this run (same state fact as verified in the companion Ebro, FL run today). Held at 70 because Madison County's own material is silent on fire code entirely, so this answer rests on state adoption alone with no local corroboration either way.

state administrative rule checked 2026-09-14 https://www.flrules.org/gateway/ChapterHome.asp?Chapter=69A-60

Q32 Are there local amendments to any of the above? Core Code editions in force

No local amendments to the building, electrical or fire codes could be found for Madison County or Greenville. This is a genuine structural difference from many Florida counties: Madison County's Land Development Code (Chapters 1 through 7, as listed on the county's own LDC page: Status/Amendments, Language/Definitions, Administration, Land Use Districts/Development Standards, Subdivision Regulations, Environmental Protection, Concurrency) contains NO building or electrical chapter at all - unlike counties whose code of ordinances folds a locally-amended electrical/building article into the general code. The Building Codes webpage states only that the statewide FBC and 2020 NEC apply, with no mention of any local amendment.

Why the confidence is not higherThe seven LDC chapter titles are taken from the Land Development Codes page, and Chapters 1, 3, 4 and 6 were pulled and read in full as PDFs in this run and contain no building/electrical local-amendment text of any kind. The Building Codes page was read in full and states only the base state codes. Held at 60 because a local amendment could in principle exist as a free-standing ordinance never folded into the LDC and never linked from the Building Department's pages - the search covered every document this run could find, not every ordinance the County Commission has ever passed.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q33 What is the installation judged against? Core Electrical

The installation is judged against the Florida Building Code, 8th Edition (2023) and NFPA 70 (NEC), 2020 edition, both adopted statewide and both named in plain language on Madison County's own Building Codes page. The Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida 2021 Editions) applies by operation of state rule. No Madison County or Greenville local amendment to any of these could be found (q32).

Why the confidence is not higherAssembled from the county's own Building Codes page (read in full) plus the state administrative rules verified in this run at q29-q31. Held at 80 because the NFPA 1 substantive text itself could not be opened (same 403/JavaScript-viewer problem as every other Florida authority surveyed in this project - see not_found q36).

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

No local rule on service upgrades or busbar sizing could be found. Madison County has no building/electrical chapter in its Land Development Code at all (see q32), and neither the Building Permit Application nor the Electrical Permit Packet states a local rule on service conductors, busbar or 120% sizing - what governs is NEC 2020 Article 705 (including 705.12) as adopted statewide, with no Madison-specific supplement found.

Why the confidence is not higherBoth PDF forms were read in full in this run and contain no local rule of this kind, and the LDC's absence of a building/electrical chapter (q32) independently supports the same conclusion. Held at 55 because this is an absence proven from the documents available to this run, not from an exhaustive search of every county resolution ever adopted, and because the substantive NEC 705.12 text itself could not be read to confirm what the DEFAULT rule (as opposed to a local rule) actually requires.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27130434/Electrical-Permit-Package-1.pdf

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Not published. No mounting system, attachment spacing, rail, flashing or standoff requirement appears in the Building Permit Application, the Electrical Permit Packet, the Building Codes page, or the Forms page (20 items enumerated - none is a roofing/mounting spec). No 'Florida Product Approval' field appears on any Madison County form (contrast q26). Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Why the confidence is not higherProved absence on the controls described above - every Building Department page and form this run could find was read in full and none addresses mounting or attachment. Held at 58 because a Building Official could still apply an unpublished practice at the counter, which this run cannot see.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/forms/

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedMadison County's Building Codes page (read in full) says nothing about fire-code setbacks or roof access pathways at all, and no Fire Rescue department page with code content could be found. The governing text is NFPA 1, the Fire Code, Florida 2021 Edition, adopted by FAC 69A-60.003 effective 31 December 2023 - and its ridge-setback and roof-access provisions could NOT be read: the adopted material is copyrighted NFPA text published by the state only through a read-only, non-printable, non-downloadable viewer, and NFPA/ICC hosts return hard 403s to every route available in this environment. An unreachable source, not a proved absence - do not record Greenville or Madison County as having no ridge setback on the strength of this.

https://www.flrules.org/gateway/ChapterHome.asp?Chapter=69A-60

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Rapid shutdown is required, to NEC 2020 - that is, NEC 690.12 as it stands in the 2020 edition. Madison County's own Building Codes page states the 2020 NEC is in force (q29), and neither the county nor Greenville adds or subtracts anything from it.

Why the confidence is not higherThe edition is proved at both ends in this run - the county's own plain-English statement, and the state rule document at flrules.org. Held at 78 rather than higher because the operative section text itself, NEC 690.12, could not be read here: NFPA and ICC both return hard 403s to every route available in this environment, so the substance of 690.12 is asserted from the edition in force rather than quoted - the same honest limit recorded for every Florida authority surveyed in this project.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

No AHJ-specific placard set. Neither Greenville nor Madison County specifies any placard, marking or label for a PV system at the service equipment - the Building Department's pages and forms are silent on the point entirely. The utility does require labelling: TCEC's Interconnection Process step 7 requires the member to 'install a disconnect switch, warning/safety labels, and other protective equipment as may be required by the Cooperative to protect its personnel, facilities and operations' before energizing. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Why the confidence is not higherProved absence on the AHJ side using the controls above; the TCEC quote is from its own Interconnection Process document, read in full in this run. Held at 62 because 'warning/safety labels... as may be required by the Cooperative' is not itself a specification of wording, size or placement - TCEC's own further detail, if any, was not published beyond that one clause, and because the applicable utility for a given Greenville address is not fully settled (q22).

utility interconnection process checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No. Neither Greenville nor Madison County specifies placard wording of its own anywhere this run could find. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Why the confidence is not higherProved absence on the controls above - Building Department Forms, Permit Applications, Building Codes and Contact Information pages, plus the Building Permit Application and Electrical Permit Packet, all read in full in this run, none containing placard wording of any kind. Greenville itself has no website or Municode entry from which any wording could come.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/forms/

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

No. Neither Greenville nor Madison County specifies letter height, colour or material for any PV placard or label. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Why the confidence is not higherSame proved absence as q39, same documents read in full, same controls.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/forms/

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Not addressed by the AHJ. Madison County publishes no site-plan/facility-map placard requirement of its own for PV. By default, NEC 705.10 (Identification of Power Sources) requires a permanent plaque or directory at each service disconnecting means identifying all on-site sources of power, which applies here because the 2020 NEC is confirmed in force (q29) - but the substantive text of 705.10 itself could not be read in this run (same 403/JavaScript-viewer limitation affecting every NEC section cited in this survey), so this is the edition asserted, not the section quoted.

Why the confidence is not higherThe county-side absence rests on the same full-text review as q38-q40. The NEC 705.10 reference is asserted from the edition-in-force chain (q29), not from reading the section, which is the same honest limit recorded at q37. Held at 50 - lower than q37/q38 - because unlike rapid shutdown, no Madison County or TCEC document even mentions a facility map or directory requirement to corroborate that the AHJ is aware of or enforces it.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes. Tri-County Electric Cooperative's own Interconnection Agreement requires, beyond anything the AHJ publishes: a UL 1741-listed, NRTL-certified, anti-islanding inverter ('The inverter shall be considered certified for interconnected operation if it has been submitted by a manufacturer to a nationally-recognized testing laboratory (NRTL) to comply with UL 1741'); a manual AC disconnect switch mounted separately from the meter socket, readily accessible to the Cooperative and capable of being locked in the open position by the Cooperative; Personal Injury and Property Damage Liability Insurance (at least $1,000,000 for systems above 10 kW); and a one-line diagram submitted before installation (q11).

Why the confidence is not higherAll requirements quoted verbatim from TCEC's own Interconnection Agreement template, extracted from PDF and read in full in this run. Held at 80 because this is TCEC's own requirement; the same requirement from Duke Energy Florida, if a Greenville address turns out to be Duke territory (q22), was not located in this run.

utility interconnection agreement checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/TCEC%20Interconnection%20Agreement.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

TCEC's Interconnection Agreement specifies only the disconnect switch's location, not a label's: 'mounted separately from the meter socket' and 'readily accessible at all times to the Cooperative.' No document, county or utility, specifies WHERE a placard or warning label itself must be placed (e.g. at the meter, at the main panel, at the disconnect) beyond that general accessibility requirement for the disconnect switch.

Why the confidence is not higherQuoted from TCEC's own Interconnection Agreement, read in full in this run. Held at 60 because the question asks about label placement specifically and the only placement rule found governs the disconnect switch, not a placard - the two are related but not the same thing, and this run found no placard placement rule at all.

utility interconnection agreement checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/TCEC%20Interconnection%20Agreement.pdf

Q44 Must equipment be on a specific approved list? Equipment listing

Yes, at least for the inverter. TCEC's Interconnection Agreement requires 'interconnection system equipment that ceases to interconnect with the utility upon a loss of utility power' to be 'certified for interconnected operation' by having been 'submitted by a manufacturer to a nationally-recognized testing laboratory (NRTL) to comply with UL 1741', with the NRTL itself required to be OSHA-approved. No county-level approved-equipment list could be found - this requirement is the utility's, not the AHJ's.

Why the confidence is not higherQuoted verbatim from TCEC's own Interconnection Agreement, read in full in this run. Held at 75 because it is a listing/certification requirement rather than a specific named product list, and because it is TCEC's requirement rather than the county's - no Madison County document imposes an equipment-listing rule of its own.

utility interconnection agreement checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/TCEC%20Interconnection%20Agreement.pdf

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Presumably yes, under the general codes rather than any Madison-specific rule. Batteries/ESS are addressed generally by NEC 2020 (Article 706) and by the Florida Fire Prevention Code (NFPA 1, Florida 2021 Edition), both of which apply in Madison County via statewide adoption (q29, q31). Neither Madison County nor Greenville publishes any battery- or ESS-specific condition, permit note, or restriction of its own - the word 'battery', 'batteries', 'energy storage' and 'ESS' return zero hits across every Madison County Building Department document and every TCEC interconnection document read in this run.

Why the confidence is not higherThe statewide code chain is the same as q29/q31, verified in this run. The zero-hit search covered the Building Permit Application, Electrical Permit Packet, Electrical Disclosure, Before-Submitting guide, Notice of Commencement, Driveway Permit form, all Building Department webpages, the LDC Chapters 1/3/4/6, and TCEC's Interconnection Process and Interconnection Agreement. Held at 55 because this is an inference from the general code chain plus a real but narrow absence search, not a document that addresses batteries by name.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/building-codes/

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Nothing published by this authority.

Where we lookedSame corpus as q45 (Building Department documents and pages, LDC chapters, TCEC interconnection documents) searched for 'battery', 'batteries', 'energy storage' and 'ESS' - zero hits anywhere, including on the Building Department's Forms page (20 items enumerated: no ESS-specific package exists among Building Permit, Cell Tower, Driveway, Electrical, Evacuation Plan, Mobile Home (new/used), New Construction, Non-conversion agreement, Notice of Commencement, Owner Builder Affidavit, Plumbing/Mechanical, Roofing, Shed Usage, Swimming Pool, Termination of Virtual Roofing Inspections, 911 Address). This proves no PUBLISHED ESS permit package exists, but does not answer whether the Building Official requires a separate ESS permit or inspection at the counter case by case, which nothing written addresses either way.

https://madisoncountyfl.com/departments-services/building-department/forms/

Q47 Is a ground mount treated as a structure? Core Ground mount

Unresolved, and genuinely so. Madison County's Land Development Code, which is where a definition of 'structure' triggering site-plan/zoning review would live, applies only in unincorporated Madison County (q2) and therefore does not reach a ground mount inside Greenville's limits on its own terms. The Building Department's general practice would almost certainly treat a ground-mounted array as requiring a building permit as a structure/accessory structure under the Florida Building Code (the Forms page lists an 'Accessory Structure Permit Application' as a distinct package), but whether Greenville's own (unpublished, unconfirmed) zoning - if any exists - treats it as a structure for setback/zoning purposes is not established.

Why the confidence is not higherThe LDC territorial-scope finding is the same as q2, and the existence of a distinct 'Accessory Structure Permit Application' was confirmed from the Building Department's Forms page, read in full in this run. Held at 55 because the building-permit half is a reasonable inference from the existence of that form, while the zoning half is a genuine unknown flagged rather than guessed at.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/forms/

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Per the utility (TCEC): the AC disconnect must be mounted SEPARATELY from the meter socket, and must be readily accessible at all times to the Cooperative and capable of being locked in the open position by the Cooperative. No exact distance or side-of-meter rule is given - only that it is a distinct, separately-mounted switch. No AHJ (county or town) document adds anything further.

Why the confidence is not higherQuoted verbatim from TCEC's own Interconnection Agreement, read in full in this run. Held at 75 because it is TCEC's rule specifically (see q22 caveat on which utility actually serves a given address), and because 'separately from the meter socket' does not by itself specify a maximum distance or exact relative position.

utility interconnection agreement checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/TCEC%20Interconnection%20Agreement.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Phone. The Building Department's own Inspections page states: 'Request an Inspection - To request an inspection, call (850) 973-6785 and provide the following information: Permit Number, Inspection Type Requested, Gate Codes (If Applicable), Contact Name and Phone Number.' Whether the Cloudpermit portal also supports scheduling inspections online was not confirmed - the portal is login-gated and this page describes only the phone route. 85% · county department page
    • How much notice is required? Effectively same-business-day if called in early, otherwise next business day. The Inspections page states: 'We need to receive the inspection request before 8:00 AM on the day the inspection is to be done, so please call during the working day before you want the inspection. Requests after 8:00 AM will be placed on the next working day's schedule.' 85% · county department page
    • Are same-day or AM/PM windows offered? Same-day booking is implied by the 8:00 AM cutoff rule (q50) - a request made before 8 AM is placed on that day's schedule, not a fixed AM/PM window. No AM/PM window split, or any narrower time-of-day commitment, is published. 68% · county department page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes. The Madison County Building Department performs its own final electrical/building inspections; this is confirmed independently by the utility TCEC's own Interconnection Process, whose step 8 is 'Inspection by County Inspector - The installation of the system must be inspected and approved by the county' before the utility will proceed to verification and interconnection approval (steps 9-11). 85% · utility interconnection process
    • If delegated, to whom? Madison County Building Department, 229 SW Pinckney Street, Suite 219, Madison, FL 32340, 850-973-6785. Building Official Dennis Pitts (850-464-7106); Pat O'Brian is listed as Single Family Dwelling Inspector (850-464-7009). 82% · county department page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    Nothing recorded for Town of Greenville on this step yet — 2 questions checked and found unpublished. The guidance above is general.

  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? No. No published inspection checklist of any kind (PV or general) could be found. The Building Department's Forms page enumerates 20 documents (911 Address Acknowledgement, Accessory Structure Permit Application, Agreement to submit NFIP elevation certificate, Building Permit Application, Cell Tower Permit Package, Declaration of Construction Debris Removal, Driveway Permit Application, Electrical Disclosure, Electrical Permit Package, Evacuation Plan Checklist, Mobile Home Pre-Inspection Application, New Construction Application, New Mobile Home Package, Non-conversion agreement, Notice of Commencement, Owner Builder Affidavit, Plumbing or Mechanical Permit Application, Roofing Package, Shed Usage Affidavit, Swimming Pool Permit Package, Termination of Virtual Roofing Inspections Acknowledgment, Used Mobile Home Package) and none of them is an inspection checklist. 75% · county department page
    • What must be on site at inspection? At minimum, a recorded and posted Notice of Commencement: the Building Permit Application itself warns 'A NOTICE OF COMMENCMENT MUST BE RECORDED AND POSTED ON THE JOB SITE BEFORE THE FIRST INSPECTION.' Beyond that, no published document lists what else (permit card, approved plans, product approval sheet) must physically be on site at inspection time. 60% · permit application form
    • Does the inspector verify labels and listings? Not documented either way for PV specifically. No published checklist states that the inspector verifies labels and listings on a solar job (see q57's absence). The generic expectation that an inspector confirms code-compliant, listed equipment is implicit in Florida Building Code/NEC enforcement generally, but Madison County publishes nothing that says so in words for any trade, let alone solar. 50% · county department page
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • Who notifies the utility for PTO? Installer or member notifies the utility, not the AHJ. TCEC's own Interconnection Process places the notification duty on the member: step 9, 'Notify TCEC of Completion - Notify the Cooperative in advance of energizing your small power generating installation... Upon completion of installation, please notify TCEC by sending an email to engineering@tcec.com.' The county inspection (step 8) is a precondition to that notification, not itself a notice to the utility. 75% · utility interconnection process

14 questions answered against Town of Greenville’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Phone. The Building Department's own Inspections page states: 'Request an Inspection - To request an inspection, call (850) 973-6785 and provide the following information: Permit Number, Inspection Type Requested, Gate Codes (If Applicable), Contact Name and Phone Number.' Whether the Cloudpermit portal also supports scheduling inspections online was not confirmed - the portal is login-gated and this page describes only the phone route.

Why the confidence is not higherQuoted verbatim from the Building Department's Inspections page, read in full in this run.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/inspections/

Q50 How much notice is required? Core Booking & scheduling

Effectively same-business-day if called in early, otherwise next business day. The Inspections page states: 'We need to receive the inspection request before 8:00 AM on the day the inspection is to be done, so please call during the working day before you want the inspection. Requests after 8:00 AM will be placed on the next working day's schedule.'

Why the confidence is not higherQuoted verbatim from the Building Department's Inspections page, read in full in this run.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/inspections/

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Same-day booking is implied by the 8:00 AM cutoff rule (q50) - a request made before 8 AM is placed on that day's schedule, not a fixed AM/PM window. No AM/PM window split, or any narrower time-of-day commitment, is published.

Why the confidence is not higherSame source as q49/q50, read in full in this run. Held at 68 because 'placed on the schedule' is not the same as a guaranteed same-day appointment, and no AM/PM windowing language appears anywhere on the page.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/inspections/

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes. The Madison County Building Department performs its own final electrical/building inspections; this is confirmed independently by the utility TCEC's own Interconnection Process, whose step 8 is 'Inspection by County Inspector - The installation of the system must be inspected and approved by the county' before the utility will proceed to verification and interconnection approval (steps 9-11).

Why the confidence is not higherThe county side is the same 'Obtaining a Permit' and Inspections-page material as q1/q49; the TCEC cross-check is from its own published Interconnection Process, read in full in this run - an independent third party naming 'the county' as the inspecting authority is strong corroboration that this is not merely how the county describes itself.

utility interconnection process checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf

Q53 If delegated, to whom? Core Who inspects

Madison County Building Department, 229 SW Pinckney Street, Suite 219, Madison, FL 32340, 850-973-6785. Building Official Dennis Pitts (850-464-7106); Pat O'Brian is listed as Single Family Dwelling Inspector (850-464-7009).

Why the confidence is not higherNames and numbers quoted from the Building Department's Contact Information page, read in full in this run. Held at 82 rather than higher because the page does not name a distinct electrical inspector separately from the Single Family Dwelling Inspector, so it is not certain the same person performs electrical final inspections on a PV job.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/contact-information/

Q54 Which inspections are required, and in what order? Core Stages & sequence

Nothing published by this authority.

Where we lookedThe Building Department's Inspections page (read in full) describes only how to REQUEST an inspection (q49) and the power-release condition ('Temporary and permanent power for new construction will only be granted when the required inspections have been passed and final septic and final driveway approvals have been received') - it does not list the individual inspection stages or their order (e.g. rough-in, service, final). No dedicated 'Inspection Procedures' document comparable to other Florida counties' published checklists could be found on the Building Department's Forms page (20 items enumerated, none titled anything like an inspection-stages guide).

https://madisoncountyfl.com/departments-services/building-department/inspections/

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedSame Inspections page and Forms page as q54 read in full - no rough-in or mid-roof inspection stage is named anywhere, but nothing rules one out either; the county's own material simply does not enumerate stages at all for this run to confirm or deny a mid-installation stage.

https://madisoncountyfl.com/departments-services/building-department/inspections/

Q56 Does the inspector verify labels and listings? Core What is checked

Not documented either way for PV specifically. No published checklist states that the inspector verifies labels and listings on a solar job (see q57's absence). The generic expectation that an inspector confirms code-compliant, listed equipment is implicit in Florida Building Code/NEC enforcement generally, but Madison County publishes nothing that says so in words for any trade, let alone solar.

Why the confidence is not higherBased on the same full review of the Building Department's pages and forms as q54-q55; no checklist of any kind (solar or general) exists to confirm or deny this. Held at 50 because this is closer to an assumption about ordinary code-enforcement practice than a sourced fact.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/inspections/

Q57 Is there a published inspection checklist? Core What is checked

No. No published inspection checklist of any kind (PV or general) could be found. The Building Department's Forms page enumerates 20 documents (911 Address Acknowledgement, Accessory Structure Permit Application, Agreement to submit NFIP elevation certificate, Building Permit Application, Cell Tower Permit Package, Declaration of Construction Debris Removal, Driveway Permit Application, Electrical Disclosure, Electrical Permit Package, Evacuation Plan Checklist, Mobile Home Pre-Inspection Application, New Construction Application, New Mobile Home Package, Non-conversion agreement, Notice of Commencement, Owner Builder Affidavit, Plumbing or Mechanical Permit Application, Roofing Package, Shed Usage Affidavit, Swimming Pool Permit Package, Termination of Virtual Roofing Inspections Acknowledgment, Used Mobile Home Package) and none of them is an inspection checklist.

Why the confidence is not higherThe Forms page was enumerated in full in this run - all 20+ document titles quoted above are read directly off the page.

county department page checked 2026-09-14 https://madisoncountyfl.com/departments-services/building-department/forms/

Q58 What must be on site at inspection? Core Documents on site

At minimum, a recorded and posted Notice of Commencement: the Building Permit Application itself warns 'A NOTICE OF COMMENCMENT MUST BE RECORDED AND POSTED ON THE JOB SITE BEFORE THE FIRST INSPECTION.' Beyond that, no published document lists what else (permit card, approved plans, product approval sheet) must physically be on site at inspection time.

Why the confidence is not higherThe Notice of Commencement warning is quoted verbatim from the Building Permit Application, read in full from PDF in this run. Held at 60 because it is the only on-site-document requirement this run could source; the Inspections page does not add to it.

permit application form checked 2026-09-14 https://madiscon-county-fl.s3.amazonaws.com/uploads/2025/05/27123653/Building-Permit-Application-1.pdf

Q59 Is there a re-inspection fee? Corrections & re-inspection

Nothing published by this authority.

Where we lookedNo fee schedule of any kind for the Building Department could be found (see q15) - the reinspection-fee amount, if any, is not published anywhere this run could reach.

https://madisoncountyfl.com/departments-services/building-department/

Q60 How are corrections issued and cleared? Corrections & re-inspection

Nothing published by this authority.

Where we lookedThe Inspections page (read in full) covers only how to request an inspection and the power-release condition; it says nothing about how a failed inspection's corrections are communicated or cleared, and no other Building Department document addresses it.

https://madisoncountyfl.com/departments-services/building-department/inspections/

Q61 What is issued on pass? Core Final sign-off & PTO

Nothing published by this authority.

Where we lookedNo Madison County document states what is issued on a passing final inspection (Certificate of Occupancy, passed-inspection status, green tag, or letter) for either new construction or a trade permit on an existing house. The Cloudpermit portal, which might show this in a permit's status history, is login-gated and could not be inspected in this run.

https://madisoncountyfl.com/departments-services/building-department/inspections/

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer or member notifies the utility, not the AHJ. TCEC's own Interconnection Process places the notification duty on the member: step 9, 'Notify TCEC of Completion - Notify the Cooperative in advance of energizing your small power generating installation... Upon completion of installation, please notify TCEC by sending an email to engineering@tcec.com.' The county inspection (step 8) is a precondition to that notification, not itself a notice to the utility.

Why the confidence is not higherQuoted verbatim from TCEC's own Interconnection Process, read in full in this run. Held at 75 because it is TCEC's process specifically, and the same caveat as q22/q23 applies if the address is actually Duke Energy Florida territory.

utility interconnection process checked 2026-09-14 https://www.tcec.com/sites/default/files/PDF/Interconnection%20Process.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 68%

No. Neither Greenville nor Madison County specifies placard wording of its own anywhere this run could find. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Size, colour & material 60%

No. Neither Greenville nor Madison County specifies letter height, colour or material for any PV placard or label. Proved absence, not a failure to look: the Madison County Building Department's Forms page (20 forms enumerated), Permit Applications page, Building Codes page, and the Building Permit Application and Electrical Permit Packet themselves were pulled and read in full in this run. Search controls on that corpus plus the county's Land Development Code (Chapters 1, 3, 4 and 6, pulled as PDF and OCR'd/extracted with pdftotext) and Tri-County Electric Cooperative's own Interconnection Process and Interconnection Agreement: 'electrical' returns hits in 5 of the documents (positive control passed); 'zzqqx' returns 0 (fabricated control passed); 'solar'/'photovoltaic' return 0 hits anywhere in the county's own building-department corpus (no PV-specific document of any kind is published); 'battery'/'batteries'/'energy storage'/'ESS' also return 0 hits across the same corpus plus the TCEC interconnection documents.

Where they go 60%

TCEC's Interconnection Agreement specifies only the disconnect switch's location, not a label's: 'mounted separately from the meter socket' and 'readily accessible at all times to the Cooperative.' No document, county or utility, specifies WHERE a placard or warning label itself must be placed (e.g. at the meter, at the main panel, at the disconnect) beyond that general accessibility requirement for the disconnect switch.

What the utility wants on top 80%

Yes. Tri-County Electric Cooperative's own Interconnection Agreement requires, beyond anything the AHJ publishes: a UL 1741-listed, NRTL-certified, anti-islanding inverter ('The inverter shall be considered certified for interconnected operation if it has been submitted by a manufacturer to a nationally-recognized testing laboratory (NRTL) to comply with UL 1741'); a manual AC disconnect switch mounted separately from the meter socket, readily accessible to the Cooperative and capable of being locked in the open position by the Cooperative; Personal Injury and Property Damage Liability Insurance (at least $1,000,000 for systems above 10 kW); and a one-line diagram submitted before installation (q11).

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Separate roof inspection
Madison County Building Department | Permits, Inspections & Codes Skip to content Search Website / Departments & Services Building Department The Madison County Building Department is dedicated to public safety and construction education. Through the enforcement of the Florida Building Codes, the sa
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
Town
County
Madison County
Regions covered
Authority Contact
Building Department
Direct Phone
850-973-6785
Booking & Scheduling