Town of Howey-in-the-Hills is a town authority in the State of Florida, serving 1,643 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.
Jurisdiction & key facts
The standing 62-question set, answered for Town of Howey-in-the-Hills against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.
Town of Howey-in-the-Hills is the authority having jurisdiction 92% confidence
- Holds
- building and electrical (AHJ of record; contracted Building Official/inspection staff -- Willdan Engineering Company -- performs the day-to-day function)
- Overridden by
- FS 163.04 limits what the Town's own stated HOA-approval requirement may lawfully withhold for a compliant solar installation (see q24); Lake County retains a separate, undetermined-scope fee obligation ('Lake County fees must be paid to them directly') that runs alongside, not instead of, the Town's own permitting authority.
- Why not higher
- Town's own current Building Services page plus an independent, controlled floridabuilding.org registry entry (Town of Howey in the Hills, value=3091, separate from County of Lake, value=2275) both agree the Town issues its own permits; the building official function itself is contracted to Willdan Engineering Company under an active, currently-cited contract.
- Permit required
- Yes. The Town's iWorQ Citizen Portal lists a dedicated 'PV Solar Permit Checklist' distinct from the Electrical Installation Permit Checklist, and the current fee schedule (eff.95%
- Permit cost
- $450.00 (see q4 for the full citation).95%
- Plan review
- No Howey-specific review clock was found published anywhere reached (fee schedule, checklists, Building Services page, or the reachable LDC chapters).65%
- Portal
- Yes -- the Town's Citizen Portal is hosted on iWorQ (howey.portal.iworq.net/portalhome/howey), open with no login required to browse checklists and the general application form;93%
- Electrical code
- 2020 NEC, in force statewide via the current Florida Building Code cycle. No Howey-specific edition year is printed anywhere in the Town's own reached documents (the PV and electrical…70%
- Booking an inspection
- Online only, through the portal -- the Building Services page states explicitly: 'Inspections must be requested through the portal and can not be requested via other means.'92%
Permitting 5 steps · 28 questions
Whether a permit is needed — Yes. The Town's iWorQ Citizen Portal lists a dedicated 'PV Solar Permit Checklist' distinct from the Electrical Installation Permit Checklist, Q3 Electrical and building permits — $450.00 flat -- identical figure appears twice in the 8/10/2026 fee schedule, once under 'Commercial' and once under 'Residential Building', Q4 Plan review — No Howey-specific review clock was found published anywhere reached (fee schedule, checklists, Building Services page, or the reachable LDC chapters). Q18 Where you file — Yes -- the Town's Citizen Portal is hosted on iWorQ (howey.portal.iworq.net/portalhome/howey), Q20
- Permit required
- Yes. The Town's iWorQ Citizen Portal lists a dedicated 'PV Solar Permit Checklist' distinct from the Electrical Installation Permit Checklist, and the current fee schedule (eff.95% source
- What it costs
- $450.00 (see q4 for the full citation).95% source
- Plan review turnaround
- No Howey-specific review clock was found published anywhere reached (fee schedule, checklists, Building Services page, or the reachable LDC chapters).65% source
- Key document
- permit checklist + fee schedule, name-matched cited by 6 open the document
-
Confirm who has a say over your address
A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.
- Is this authority the AHJ for residential solar at this address? Yes -- the Town of Howey-in-the-Hills is the AHJ of record for building and electrical permitting, including residential solar PV, within the town limits. It does not delegate to Lake County; the Town's own Building Services page states it issues the permits itself ('within the town limits'), the Town's Citizen Portal (iWorQ) is the actual permit-issuance system, and floridabuilding.org's statewide registry lists 'Town of Howey in the Hills' (value=3091) as an entity separate from 'County of Lake' (value=2275) -- positive control passed (Polk City, Frostproof, Eagle Lake, Dade City present; negative control passed: Bowling Green, Wauchula, Zolfo Springs, St. Leo, San Antonio all absent, 0 hits each). 96% · AHJ's own department page + statewide registry, cross-checked
- What does this authority permit itself, and what does it delegate? AHJ OF RECORD WITH BOUGHT-IN STAFF (the third shape: self-run authority, contracted staff). The Town's Building Services page states verbatim: 'The Town of Howey-in-the-Hills has an active contract with Alpha, Willdan Engineering Company, to provide oversight of all new construction projects (commercial and residential), additions and alterations of existing structures, through permitting, plan review, and inspection services within the town limits.' Named contact: Matt Fretwell, Willdan Engineering Company (permits@willdan.com, 352-874-3121). Budget fingerprint from the Town's own FY2021 FS 553.80(7) report: real personnel-services cost ($44,489, 2 FTE 'dedicated by the local government') alongside 1,150 of 1,202 (95.7%) building inspections performed 'by a private provider' -- a small in-house presence plus a majority-outsourced inspection function. Willdan joins SAFEbuilt, EPCI, PDCS, CAP Government and Universal Engineering as contracted-AHJ vendors already on file in this survey (and per the brief, Willdan already appears in other Lake County cities). 92% · AHJ's own department page
- Is a permit required for a residential rooftop PV system? Yes. The Town's iWorQ Citizen Portal lists a dedicated 'PV Solar Permit Checklist' distinct from the Electrical Installation Permit Checklist, and the current fee schedule (eff. 8/10/2026) carries a standalone 'Solar Permit Fee' line under both Commercial and Residential Building, separate from the generic Electrical Permit Fee line. The Building Services page also separately lists 'Solar photovoltaic' among the items needing 'permits and zoning clearance.' 95% · permit checklist + fee schedule, name-matched
- Is there a separate electrical permit, or is it combined? $450.00 flat -- identical figure appears twice in the 8/10/2026 fee schedule, once under 'Commercial' and once under 'Residential Building', both captioned 'Solar Permit Fee'. It is NOT tied to declared system valuation (contrast the schedule's Building Permit Fee lines, which ARE priced per square foot); no separate PV plan-review fee is charged since 'Plan Review Fee ... Included' for both commercial and residential. 95% · adopted fee schedule, dated 8/10/2026
- Is a HOA or architectural approval required first? Yes, and it is an FS 163.04 finding. The Town's own Building Services page states verbatim: 'HOA approval is required to be submitted with permit applications.' Per this survey's standing, first-hand-verified reading of FS 163.04(2), an HOA or similar deed-restriction body may not withhold approval of a compliant solar installation -- its only lawfully reserved discretion is WHERE on the roof, within a 45-degree arc of due south, and only if that siting choice does not impair the system's operation. The Town's page states the HOA-approval requirement as an unqualified precondition with no such carve-out, so as applied to a 163.04(2)-compliant solar application, the stated requirement is enforceable only to the extent the HOA's own refusal would itself be lawful under the statute -- the Town's page does not say so. The prevailing party in a dispute is entitled to costs and fees under 163.04(3). 85% · AHJ's own department page, read against FS 163.04 verbatim text
- Is a wind or windstorm certification required? Yes for wind/exposure and structural attachment (see q12); for statewide product approval, the Town's generic Product Approval Specification Sheet (form R-1305, citing FS 553.842 and FAC 9B-72) lists six standard categories (exterior doors, windows, panel wall, roofing products, structural components, new exterior envelope products) with NO dedicated PV/solar module line -- a PV racking/module system would have to be justified under category 6 ('NEW EXTERIOR ENVELOPE PRODUCTS', a single blank line) or via the PV checklist's own engineer-of-record/FSEC route, not through a solar-specific statewide product-approval category. 80% · Town's own statewide-form Product Approval Specification Sheet
- Is a Specific Use Permit or Council approval ever required? Proved zero, by enumeration, not by an unreachable code. All 11 chapters of the Town's own Land Development Code (Ch.1 General Provisions, Ch.2 Zoning Districts, Ch.3 Environmental & Resource Protection, Ch.4 Development Review Procedures, Ch.5 Accessory & Temporary Uses, Ch.6 Supplemental Standards, Ch.7 Landscaping/Irrigation/Hardscape, Ch.8 Development Standards, Ch.9 Boards & Committees, Ch.10 Concurrency, plus the LDC Table of Contents) were downloaded directly from the Town's own DocumentCenter as individual dated PDFs (bypassing the Municode outage entirely) and grepped for 'solar', 'photovoltaic', 'renewable', and 'energy device': zero hits in any chapter except two unrelated matches (a telecom-antenna 'backup power/generator' definition in Ch.1, and a wastewater lift-station 'backup generator' clause in Ch.8) -- neither about PV. The LDC contains no solar-specific zoning provision of any kind. 90% · Town's own LDC chapters, complete enumeration
- Is there a system-size cap on residential generation? Same finding as q27 -- no LDC definition of 'solar collector', 'photovoltaic system', or 'renewable energy device' exists anywhere in the Town's own Ch.1 General Provisions definitions article (the article was read in full) or any other chapter. 90% · Town's own LDC Ch.1 definitions article
-
Check who is allowed to apply
Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.
- Who is allowed to pull the electrical permit? A Florida-licensed contractor (the Building Permit Application has a single signature line captioned 'CONTRACTOR OR OWNER/BUILDER SIGNATURE'), or the property owner under the standard FS 489.103(7) owner-builder exemption (see q7). The PV Solar Permit Checklist separately requires the submitted plan set to be 'digitally signed by the engineer of record, or approved by the FSEC [Florida Solar Energy Center]' -- FSEC certification accepted in lieu of a professional engineer's seal, matching a pattern already on file elsewhere in this survey. 88% · permit checklist + application, name-matched
- Must the contractor be registered with this authority before applying? None found beyond the Florida state license. The Town's own Contractor Registration form lists 'Required Documents' as: State License, Certificate of Liability, and Workers' Comp Exemption or Certificate -- no Lake County or Town-specific competency card, local registration exam, or additional local certificate is requested anywhere on the form. 80% · Town's own contractor registration form
- Is a homeowner permitted to self-install and self-permit? Yes. The Building Permit Application's signature block reads 'CONTRACTOR OR OWNER/BUILDER SIGNATURE' (no separate form required to be filed alongside for the signature itself), and the Town separately publishes the standard statewide 'Owner Builder Disclosure Statement' citing FS 489.103(7)(a) verbatim ('I may build or improve a one-family or two-family residence ... must provide direct, onsite supervision'). No solar-specific carve-out or exclusion appears in either document -- this is the generic owner-builder exemption, not the (now-dead) SunShot-conditional solar-specific limb of 489.103(7)(a)3. 88% · Town's own Owner Builder Disclosure Statement form
-
Build the submittal package
Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.
- What documents make up a complete submittal? Yes -- a dedicated PV Solar Permit Checklist exists (Revision Date 10/01/24) requiring: wind zone/exposure category called out on the plans; a roof plan showing all penetrations with panel overlay; an attachment/spacing detail; an NEC-compliant electrical schematic; a single digitally-signed (engineer-of-record or FSEC-approved) plan set; final-inspection photos of the support system, combiner boxes and attic conductor runs; a completed permit application; contractor license/WC/insurance copies; an NOC for jobs over $2,500; and a property record card. 95% · Town's own PV permit checklist
- How many copies, and in what format? Digital/online. Permits are submitted through the iWorQ Citizen Portal ('Submit applications via the online portal'); the PV checklist itself requires plans be 'submitted as one file ... unlocked so that digital stamps can be installed', i.e. a single digital PDF, not paper sets. 85% · AHJ's own department page
- Is a site plan required, and what must it show? Yes -- the PV checklist requires plans 'digitally signed by the engineer of record, or approved by the FSEC.' No dollar-value threshold is stated; the requirement appears to apply to every PV submittal regardless of size. 85% · Town's own PV permit checklist
- Is a one-line / three-line diagram required? Implied but not itemized by name: the checklist requires 'an electrical schematic that complies with the NEC' and the fee schedule/Building Services page treat electrical wiring work as requiring its own review; no document uses the specific term 'one-line diagram.' 65% · Town's own PV permit checklist
- Are string and conductor calculations required? Yes -- the PV checklist requires 'an attachment detail for the panel to the roof with spacing of supports' and 'required structural connection locations' on the roof layout, plus wind zone (140 mph) and exposure category (C, or justify otherwise) on the plans. 90% · Town's own PV permit checklist
-
Apply and pay
Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.
- Which permit portal does this authority use? Yes -- the Town's Citizen Portal is hosted on iWorQ (howey.portal.iworq.net/portalhome/howey), open with no login required to browse checklists and the general application form; a one-time contractor access code is issued after a new permit is first applied for. 93% · Town's own permit portal, verified live
- Can the whole application be completed online? Yes -- per the Building Services page: 'all permit payments, inspection requests, and access to all your current permits can be made via the online portal.' A credit-card surcharge of 3.5% or $2 (whichever is greater) is passed through on card payments made online or at Town Hall; check/cash accepted at Town Hall only. 92% · AHJ's own department page
- What does a residential solar permit cost? $450.00 (see q4 for the full citation). 95% · adopted fee schedule, dated 8/10/2026
- How is the fee calculated? Flat, not valuation-based -- the Solar Permit Fee is a single fixed dollar figure ($450.00) with no per-square-foot or percent-of-value component, unlike the schedule's general Building Permit Fee lines (priced per sq ft). No FS 553.79(1)(f) exposure on this line. 92% · adopted fee schedule, dated 8/10/2026
- Is there a separate plan-check fee? None separately charged -- the fee schedule states 'Plan Review Fee ... Included' for both Commercial and Residential Building, meaning it is bundled into the base permit fee rather than billed as a second line for solar. 90% · adopted fee schedule, dated 8/10/2026
-
Plan review — and start the utility in parallel
Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.
- What is the stated plan-review turnaround? No Howey-specific review clock was found published anywhere reached (fee schedule, checklists, Building Services page, or the reachable LDC chapters). The applicable STATE default is FS 553.792(1)(a): a typical single-family PV job (under 7,500 sq ft, but the work itself commonly exceeds the $15,000 5-business-day threshold) falls to the 30-business-day limb, not the 5-day limb, unless the job value is under $15,000. 65% · state statute (no town override found)
- Which utility handles interconnection here? TWO sellers, both evidenced (not the geographic-inference-only shape recorded for neighbouring Astatula): Duke Energy Florida and SECO Energy (Sumter Electric Cooperative). EIA-861 Service_Territory_2024.xlsx (FL/Lake) lists five county-level candidates (Clay Electric Cooperative, Duke Energy Florida, City of Leesburg, City of Mount Dora, SECO Energy). Closed with SECO Energy's OWN authoritative ArcGIS service-territory layer (FS_Service_Territory_2020_with_Mask, layers 5 'Other Utility's Service Area' and 6 'SECO Energy Service Territory'), sampled against the TIGERweb layer-25 place polygon for 'Howey-in-the-Hills town' (POP100 1,643 -- exact match to the brief's population figure, the same free cross-check used elsewhere in this survey) with a 40x40 grid (631 interior sample points): 385/631 (61.0%) fall in SECO's 'Other Utility' layer, 246/631 (39.0%) fall inside SECO's own territory polygon -- a clean two-way partition with zero points landing in neither layer (spot-checked all 246 'not-SECO' points against layer 6 directly: 246/246 confirmed inside SECO territory). 'Other Utility' is identified as Duke Energy Florida from a named, dated local-news source: GrowthSpotter/Orlando Sentinel (29 Apr 2026) reports the Town brought in Duke Energy for a $25M undergrounding cost estimate covering 'about 1,100 customers in Howey', quoting Duke's own Director of Project Management by name -- i.e. Duke is the incumbent overhead-line utility, not a new entrant. SECO Energy's own Facebook outage post independently names '211 SECO members served by our Howey-in-the-hills [area]', confirming SECO also serves real customers inside the town, consistent with the 39% GIS share. This closes the Lake County five-candidate list to two for THIS town (City of Leesburg and City of Mount Dora's municipal utilities are, as elsewhere in this survey, confined to their own city limits and are excluded by the same two-way GIS partition finding no room for a third seller by area; Clay Electric Cooperative's footprint lies further north/northeast and is likewise excluded by the same exhaustive partition). 82% · utility's own authoritative GIS layer, area-intersected against the Census place polygon
- Where does the utility sit in the sequence? Write-in blank, not a checkbox: the general Building Permit Application does not carry a utility field at all; no dedicated PV-specific application form was found with utility checkboxes. The Town's own budget independently corroborates an external seller: the FY26 financial report shows non-zero 'U.S.T. - Electricity' ($208,000 annual budget) and 'Franchise Fee - Electric' ($152,000 annual budget) revenue lines -- both single aggregate lines, so this alone cannot distinguish one seller from two (see q22 for the split itself). 80% · Town's own monthly financial report
28 questions answered against Town of Howey-in-the-Hills’s own published documents
Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope
Yes -- the Town of Howey-in-the-Hills is the AHJ of record for building and electrical permitting, including residential solar PV, within the town limits. It does not delegate to Lake County; the Town's own Building Services page states it issues the permits itself ('within the town limits'), the Town's Citizen Portal (iWorQ) is the actual permit-issuance system, and floridabuilding.org's statewide registry lists 'Town of Howey in the Hills' (value=3091) as an entity separate from 'County of Lake' (value=2275) -- positive control passed (Polk City, Frostproof, Eagle Lake, Dade City present; negative control passed: Bowling Green, Wauchula, Zolfo Springs, St. Leo, San Antonio all absent, 0 hits each).
Why the confidence is not higherTown's own current department page plus an independent, keyless, controlled statewide registry both agree; the only complication is that the day-to-day building official/inspectors are a contracted firm rather than town employees (see q2), which does not change who holds the authority.
AHJ's own department page + statewide registry, cross-checked checked 2026-09-13 https://www.howey.org/236/Building-Services
Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope
AHJ OF RECORD WITH BOUGHT-IN STAFF (the third shape: self-run authority, contracted staff). The Town's Building Services page states verbatim: 'The Town of Howey-in-the-Hills has an active contract with Alpha, Willdan Engineering Company, to provide oversight of all new construction projects (commercial and residential), additions and alterations of existing structures, through permitting, plan review, and inspection services within the town limits.' Named contact: Matt Fretwell, Willdan Engineering Company (permits@willdan.com, 352-874-3121). Budget fingerprint from the Town's own FY2021 FS 553.80(7) report: real personnel-services cost ($44,489, 2 FTE 'dedicated by the local government') alongside 1,150 of 1,202 (95.7%) building inspections performed 'by a private provider' -- a small in-house presence plus a majority-outsourced inspection function. Willdan joins SAFEbuilt, EPCI, PDCS, CAP Government and Universal Engineering as contracted-AHJ vendors already on file in this survey (and per the brief, Willdan already appears in other Lake County cities).
Why the confidence is not higherThe Town's own current page names the firm and the contract outright -- the cheapest tell in this survey's method. The FY2021 utilization report is 5 fiscal years old (report itself undated beyond 'Fiscal Year 2021'); no newer FS 553.80(7) report was found on the Town's site, so the FTE/private-provider SPLIT could be stale even though the Willdan contract itself is corroborated by a live 2025-dated statutory form (q2 supplement) and the current fee schedule.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope
Yes. The Town's iWorQ Citizen Portal lists a dedicated 'PV Solar Permit Checklist' distinct from the Electrical Installation Permit Checklist, and the current fee schedule (eff. 8/10/2026) carries a standalone 'Solar Permit Fee' line under both Commercial and Residential Building, separate from the generic Electrical Permit Fee line. The Building Services page also separately lists 'Solar photovoltaic' among the items needing 'permits and zoning clearance.'
Why the confidence is not higherThree of the Town's own current documents agree and each is solar-specific by name.
permit checklist + fee schedule, name-matched checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope
$450.00 flat -- identical figure appears twice in the 8/10/2026 fee schedule, once under 'Commercial' and once under 'Residential Building', both captioned 'Solar Permit Fee'. It is NOT tied to declared system valuation (contrast the schedule's Building Permit Fee lines, which ARE priced per square foot); no separate PV plan-review fee is charged since 'Plan Review Fee ... Included' for both commercial and residential.
Why the confidence is not higherRead directly off the Town's current, dated fee schedule; the flat/valuation distinction is verified by contrasting it against the adjacent per-square-foot lines in the same document.
adopted fee schedule, dated 8/10/2026 checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q5 Who is allowed to pull the electrical permit? Core Who may apply
A Florida-licensed contractor (the Building Permit Application has a single signature line captioned 'CONTRACTOR OR OWNER/BUILDER SIGNATURE'), or the property owner under the standard FS 489.103(7) owner-builder exemption (see q7). The PV Solar Permit Checklist separately requires the submitted plan set to be 'digitally signed by the engineer of record, or approved by the FSEC [Florida Solar Energy Center]' -- FSEC certification accepted in lieu of a professional engineer's seal, matching a pattern already on file elsewhere in this survey.
Why the confidence is not higherBoth documents are the Town's own current forms; the FSEC-in-lieu-of-PE-seal clause is explicit and unambiguous.
permit checklist + application, name-matched checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q6 Must the contractor be registered with this authority before applying? Core Who may apply
None found beyond the Florida state license. The Town's own Contractor Registration form lists 'Required Documents' as: State License, Certificate of Liability, and Workers' Comp Exemption or Certificate -- no Lake County or Town-specific competency card, local registration exam, or additional local certificate is requested anywhere on the form.
Why the confidence is not higherProved by enumeration of the Town's own one-page registration form's complete document list, not by absence of a search hit.
Town's own contractor registration form checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/23466066-Contractor%20Registration.pdf
Q7 Is a homeowner permitted to self-install and self-permit? Who may apply
Yes. The Building Permit Application's signature block reads 'CONTRACTOR OR OWNER/BUILDER SIGNATURE' (no separate form required to be filed alongside for the signature itself), and the Town separately publishes the standard statewide 'Owner Builder Disclosure Statement' citing FS 489.103(7)(a) verbatim ('I may build or improve a one-family or two-family residence ... must provide direct, onsite supervision'). No solar-specific carve-out or exclusion appears in either document -- this is the generic owner-builder exemption, not the (now-dead) SunShot-conditional solar-specific limb of 489.103(7)(a)3.
Why the confidence is not higherBoth are the Town's own current forms; the statute citation was independently verified against the enacted text per this survey's standing statute section.
Town's own Owner Builder Disclosure Statement form checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/24617882-Builder%20Owner%20Affadavit.pdf
Q8 What documents make up a complete submittal? Core Submittal package
Yes -- a dedicated PV Solar Permit Checklist exists (Revision Date 10/01/24) requiring: wind zone/exposure category called out on the plans; a roof plan showing all penetrations with panel overlay; an attachment/spacing detail; an NEC-compliant electrical schematic; a single digitally-signed (engineer-of-record or FSEC-approved) plan set; final-inspection photos of the support system, combiner boxes and attic conductor runs; a completed permit application; contractor license/WC/insurance copies; an NOC for jobs over $2,500; and a property record card.
Why the confidence is not higherFull text of the Town's own current, dated, signed checklist -- complete enumeration, not a keyword hit.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q9 How many copies, and in what format? Submittal package
Digital/online. Permits are submitted through the iWorQ Citizen Portal ('Submit applications via the online portal'); the PV checklist itself requires plans be 'submitted as one file ... unlocked so that digital stamps can be installed', i.e. a single digital PDF, not paper sets.
Why the confidence is not higherTown's own current Building Services page plus its own PV checklist agree.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q10 Is a site plan required, and what must it show? Core Submittal package
Yes -- the PV checklist requires plans 'digitally signed by the engineer of record, or approved by the FSEC.' No dollar-value threshold is stated; the requirement appears to apply to every PV submittal regardless of size.
Why the confidence is not higherTown's own current PV checklist, read in full; no threshold language found anywhere in it.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q11 Is a one-line / three-line diagram required? Core Drawings & calculations
Implied but not itemized by name: the checklist requires 'an electrical schematic that complies with the NEC' and the fee schedule/Building Services page treat electrical wiring work as requiring its own review; no document uses the specific term 'one-line diagram.'
Why the confidence is not higherThe checklist's own wording is 'electrical schematic', not 'one-line diagram' -- read the line rather than assume the industry-standard term was used.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q12 Are string and conductor calculations required? Drawings & calculations
Yes -- the PV checklist requires 'an attachment detail for the panel to the roof with spacing of supports' and 'required structural connection locations' on the roof layout, plus wind zone (140 mph) and exposure category (C, or justify otherwise) on the plans.
Why the confidence is not higherVerbatim from the Town's own current, dated checklist.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps
Nothing published by this authority.
Where we lookedPV Solar Permit Checklist (full text) and general Building Permit Application -- neither states a dollar-value threshold for when the engineer/FSEC-sealed plan requirement applies; the checklist reads as applying to every PV submittal regardless of value.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps
Nothing published by this authority.
Where we lookedSame documents as q13 -- no separate structural-engineering-threshold clause found.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q15 What does a residential solar permit cost? Core Fees
$450.00 (see q4 for the full citation).
Why the confidence is not higherSame source as q4.
adopted fee schedule, dated 8/10/2026 checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q16 How is the fee calculated? Core Fees
Flat, not valuation-based -- the Solar Permit Fee is a single fixed dollar figure ($450.00) with no per-square-foot or percent-of-value component, unlike the schedule's general Building Permit Fee lines (priced per sq ft). No FS 553.79(1)(f) exposure on this line.
Why the confidence is not higherDirect read of the current fee schedule; contrasted against the adjacent valuation-based lines in the same document.
adopted fee schedule, dated 8/10/2026 checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q17 Is there a separate plan-check fee? Fees
None separately charged -- the fee schedule states 'Plan Review Fee ... Included' for both Commercial and Residential Building, meaning it is bundled into the base permit fee rather than billed as a second line for solar.
Why the confidence is not higherDirect read of the current fee schedule.
adopted fee schedule, dated 8/10/2026 checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q18 What is the stated plan-review turnaround? Core Timeline & validity
No Howey-specific review clock was found published anywhere reached (fee schedule, checklists, Building Services page, or the reachable LDC chapters). The applicable STATE default is FS 553.792(1)(a): a typical single-family PV job (under 7,500 sq ft, but the work itself commonly exceeds the $15,000 5-business-day threshold) falls to the 30-business-day limb, not the 5-day limb, unless the job value is under $15,000.
Why the confidence is not higherNo town-specific override found by enumeration of the reachable documents; falling back to the statute text this survey has already verified first-hand. Confidence held to the statutory default rather than a town-confirmed number.
state statute (no town override found) checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q19 How long is an issued permit valid before it expires? Timeline & validity
Nothing published by this authority.
Where we lookedBuilding Permit Application (full text), fee schedule, PV checklist, and Building Services page -- none states a permit-expiration or inspection-activity window; the Renewal Fees section of the fee schedule prices renewing an EXPIRED permit ($100/$500 by fee tier) but never states the expiration trigger itself (e.g., 180 days without inspection).
Q20 Which permit portal does this authority use? Core Portal & process
Yes -- the Town's Citizen Portal is hosted on iWorQ (howey.portal.iworq.net/portalhome/howey), open with no login required to browse checklists and the general application form; a one-time contractor access code is issued after a new permit is first applied for.
Why the confidence is not higherPortal fetched directly, no authentication wall on the browsing tier.
Town's own permit portal, verified live checked 2026-09-13 https://howey.portal.iworq.net/portalhome/howey
Q21 Can the whole application be completed online? Core Portal & process
Yes -- per the Building Services page: 'all permit payments, inspection requests, and access to all your current permits can be made via the online portal.' A credit-card surcharge of 3.5% or $2 (whichever is greater) is passed through on card payments made online or at Town Hall; check/cash accepted at Town Hall only.
Why the confidence is not higherTown's own current department page, verbatim.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q22 Which utility handles interconnection here? Core Utility interconnection
TWO sellers, both evidenced (not the geographic-inference-only shape recorded for neighbouring Astatula): Duke Energy Florida and SECO Energy (Sumter Electric Cooperative). EIA-861 Service_Territory_2024.xlsx (FL/Lake) lists five county-level candidates (Clay Electric Cooperative, Duke Energy Florida, City of Leesburg, City of Mount Dora, SECO Energy). Closed with SECO Energy's OWN authoritative ArcGIS service-territory layer (FS_Service_Territory_2020_with_Mask, layers 5 'Other Utility's Service Area' and 6 'SECO Energy Service Territory'), sampled against the TIGERweb layer-25 place polygon for 'Howey-in-the-Hills town' (POP100 1,643 -- exact match to the brief's population figure, the same free cross-check used elsewhere in this survey) with a 40x40 grid (631 interior sample points): 385/631 (61.0%) fall in SECO's 'Other Utility' layer, 246/631 (39.0%) fall inside SECO's own territory polygon -- a clean two-way partition with zero points landing in neither layer (spot-checked all 246 'not-SECO' points against layer 6 directly: 246/246 confirmed inside SECO territory). 'Other Utility' is identified as Duke Energy Florida from a named, dated local-news source: GrowthSpotter/Orlando Sentinel (29 Apr 2026) reports the Town brought in Duke Energy for a $25M undergrounding cost estimate covering 'about 1,100 customers in Howey', quoting Duke's own Director of Project Management by name -- i.e. Duke is the incumbent overhead-line utility, not a new entrant. SECO Energy's own Facebook outage post independently names '211 SECO members served by our Howey-in-the-hills [area]', confirming SECO also serves real customers inside the town, consistent with the 39% GIS share. This closes the Lake County five-candidate list to two for THIS town (City of Leesburg and City of Mount Dora's municipal utilities are, as elsewhere in this survey, confined to their own city limits and are excluded by the same two-way GIS partition finding no room for a third seller by area; Clay Electric Cooperative's footprint lies further north/northeast and is likewise excluded by the same exhaustive partition).
Why the confidence is not higherThe area split itself is a direct, controlled GIS measurement against the co-op's OWN published service-territory data (not a third-party or HIFLD layer, which this survey's brief flags as unreliable) intersected with the correct TIGERweb polygon, cross-checked by an exact population match. The remaining uncertainty is the '61%=Duke' identity label itself, which is not printed on SECO's own map (its neighbouring layer is only named 'Other Utility's Service Area') -- that identity rests on a named, dated, on-the-record local news source plus the town's own non-zero electric franchise/utility-tax revenue lines (see q23), not on a franchise ordinance located by number (Municode is down; no dedicated franchise-ordinance PDF was found on the Town's own site search). Held below 85 for that reason.
utility's own authoritative GIS layer, area-intersected against the Census place polygon checked 2026-09-13 https://services3.arcgis.com/d06OFHvJIJqOZ5tk/arcgis/rest/services/FS_Service_Territory_2020_with_Mask/FeatureServer/6
Q23 Where does the utility sit in the sequence? Core Utility interconnection
Write-in blank, not a checkbox: the general Building Permit Application does not carry a utility field at all; no dedicated PV-specific application form was found with utility checkboxes. The Town's own budget independently corroborates an external seller: the FY26 financial report shows non-zero 'U.S.T. - Electricity' ($208,000 annual budget) and 'Franchise Fee - Electric' ($152,000 annual budget) revenue lines -- both single aggregate lines, so this alone cannot distinguish one seller from two (see q22 for the split itself).
Why the confidence is not higherApplication form read in full; the two franchise/tax lines are the Town's own current (Period 05-26, Jul 2026) monthly financial report.
Town's own monthly financial report checked 2026-09-13 https://www.howey.org/DocumentCenter/View/730
Q24 Is a HOA or architectural approval required first? Overlays & special cases
Yes, and it is an FS 163.04 finding. The Town's own Building Services page states verbatim: 'HOA approval is required to be submitted with permit applications.' Per this survey's standing, first-hand-verified reading of FS 163.04(2), an HOA or similar deed-restriction body may not withhold approval of a compliant solar installation -- its only lawfully reserved discretion is WHERE on the roof, within a 45-degree arc of due south, and only if that siting choice does not impair the system's operation. The Town's page states the HOA-approval requirement as an unqualified precondition with no such carve-out, so as applied to a 163.04(2)-compliant solar application, the stated requirement is enforceable only to the extent the HOA's own refusal would itself be lawful under the statute -- the Town's page does not say so. The prevailing party in a dispute is entitled to costs and fees under 163.04(3).
Why the confidence is not higherThe requirement is on the Town's own current, live department page (not an inferred zoning clause) and the statute text has already been verified first-hand for this survey; no separate line on the actual PDF application form itself was found repeating the HOA requirement, so the webpage is the sole located instrument stating it.
AHJ's own department page, read against FS 163.04 verbatim text checked 2026-09-13 https://www.howey.org/236/Building-Services
Q25 Is there a historic-district review? Overlays & special cases
Nothing published by this authority.
Where we lookedTown's 'History'/'About' pages, Comprehensive Plan links off the Building Services and LDC pages -- no Comprehensive Plan document or Area-of-Critical-State-Concern designation was located on the Town's own site search (searched 'comprehensive plan', 'FLUM', and 'critical state concern'); Lake County is not among Florida's designated Areas of Critical State Concern (Apalachicola Bay, Big Cypress, Florida Keys, Green Swamp -- the Green Swamp ACSC does reach into south/central Lake County but was not confirmed to reach Howey-in-the-Hills's corporate limits specifically in the time available).
Q26 Is a wind or windstorm certification required? Overlays & special cases
Yes for wind/exposure and structural attachment (see q12); for statewide product approval, the Town's generic Product Approval Specification Sheet (form R-1305, citing FS 553.842 and FAC 9B-72) lists six standard categories (exterior doors, windows, panel wall, roofing products, structural components, new exterior envelope products) with NO dedicated PV/solar module line -- a PV racking/module system would have to be justified under category 6 ('NEW EXTERIOR ENVELOPE PRODUCTS', a single blank line) or via the PV checklist's own engineer-of-record/FSEC route, not through a solar-specific statewide product-approval category.
Why the confidence is not higherBoth are the Town's own current forms, read in full; the product-approval form's category list is complete (proved by enumeration, not a missed keyword).
Town's own statewide-form Product Approval Specification Sheet checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/28344766-Product%20Approval%20Form.pdf
Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases
Proved zero, by enumeration, not by an unreachable code. All 11 chapters of the Town's own Land Development Code (Ch.1 General Provisions, Ch.2 Zoning Districts, Ch.3 Environmental & Resource Protection, Ch.4 Development Review Procedures, Ch.5 Accessory & Temporary Uses, Ch.6 Supplemental Standards, Ch.7 Landscaping/Irrigation/Hardscape, Ch.8 Development Standards, Ch.9 Boards & Committees, Ch.10 Concurrency, plus the LDC Table of Contents) were downloaded directly from the Town's own DocumentCenter as individual dated PDFs (bypassing the Municode outage entirely) and grepped for 'solar', 'photovoltaic', 'renewable', and 'energy device': zero hits in any chapter except two unrelated matches (a telecom-antenna 'backup power/generator' definition in Ch.1, and a wastewater lift-station 'backup generator' clause in Ch.8) -- neither about PV. The LDC contains no solar-specific zoning provision of any kind.
Why the confidence is not higherComplete enumeration of the Town's own current, individually-dated LDC chapters -- the denominator is named (11 chapters, ~2.9 MB of text-layer PDF) and every chapter was actually read by machine grep, not assumed absent from an unreachable Municode page.
Town's own LDC chapters, complete enumeration checked 2026-09-13 https://www.howey.org/DocumentCenter/View/219
Q28 Is there a system-size cap on residential generation? Overlays & special cases
Same finding as q27 -- no LDC definition of 'solar collector', 'photovoltaic system', or 'renewable energy device' exists anywhere in the Town's own Ch.1 General Provisions definitions article (the article was read in full) or any other chapter.
Why the confidence is not higherSame complete-enumeration method as q27.
Town's own LDC Ch.1 definitions article checked 2026-09-13 https://www.howey.org/DocumentCenter/View/219
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Install 5 steps · 20 questions
-
Build to the code editions actually in force here
The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.
- Which NEC edition is in force? 2020 NEC, in force statewide via the current Florida Building Code cycle. No Howey-specific edition year is printed anywhere in the Town's own reached documents (the PV and electrical checklists both say only 'must follow the latest edition of the Florida Building Code' -- floating, undated language) -- this is the statewide default, not a town-confirmed figure. 70% · Town's own checklist (floating citation) + statewide code-cycle default
- Which building code edition is in force? Florida Building Code, 8th Edition (2023), statewide -- same floating-citation caveat as q29: the Town's own documents say 'the latest edition' without a year. 70% · Town's own checklist (floating citation) + statewide code-cycle default
-
Fire access, setbacks and pathways
Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.
- What ridge setback and access pathways are required? Yes -- the PV Solar Permit Checklist itself requires the roof layout to show 'Fire department access location' and 'Fire department access pathways' as line items on the submitted plans, verbatim. 90% · Town's own PV permit checklist
-
Rapid shutdown
Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.
- Is rapid shutdown required, and to which NEC edition? Not named explicitly -- the checklist requires only that the electrical schematic 'complies with the NEC', without naming NEC 690.12 (rapid shutdown) specifically. Since the applicable statewide NEC edition is 2020 (q29), which mandates 690.12 rapid shutdown for PV systems, the requirement is necessarily incorporated by the general NEC-compliance clause even though the Town's own document never uses the term. 65% · Town's own PV permit checklist, read against the statewide NEC edition
-
Labels and placards
The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.
Nothing recorded for Town of Howey-in-the-Hills on this step yet — 6 questions checked and found unpublished. The guidance above is general.
-
Disconnect, storage and listed equipment
Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.
- Where must the AC disconnect be, relative to the meter? No -- the general Building Permit Application has no utility field of any kind (no write-in blank, no checkbox); the specific serving utility is not name-checked anywhere on any Town form reached. 78% · Town's own Building Permit Application, complete read
- Are batteries permitted, and under what conditions? No PV-specific ground-mount rule exists (q27's zero holds for ground mounts too). A ground-mounted PV array on a residential lot would fall to the LDC's GENERAL accessory-structure provisions (Ch.5, Accessory and Temporary Uses and Structures) -- setback and height limits that vary by the parcel's zoning district -- rather than to any solar-specific standard, since none exists. 70% · Town's own LDC Ch.5, complete enumeration
- Is there a separate ESS permit or inspection? No dedicated Energy Storage System/battery permit type or inspection line exists anywhere in the fee schedule, the iWorQ checklist library, or the LDC (grepped for 'battery', 'ESS', 'energy storage' -- zero hits across all reached documents). 82% · fee schedule + LDC, complete enumeration
- Is a ground mount treated as a structure? The Town's Code of Ordinances is nominally hosted on Municode (library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances) but that route is PROVED UNREACHABLE, not merely unread: the URL returns the same byte-identical 6,095-byte generic client-side shell this survey has logged network-wide for Municode as of 13 Sep 2026. Separately and workably, the Town's own site hosts its ENTIRE Land Development Code as individually dated PDF chapters directly under its own DocumentCenter (bypassing Municode entirely) -- this is how q27/28/45/46 were actually proved rather than left unreached. 85% · Town's own DocumentCenter (LDC) vs. Municode (Code of Ordinances)
- Is a specific mounting system or attachment spacing required? No dedicated fire setback/spacing rule for PV arrays was found in any reached document (LDC chapters or checklists); a general fire-code setback, if any, would sit in the unreachable Code of Ordinances (see q31). 55% · Town's own LDC chapters, complete enumeration (bounded by Municode outage)
20 questions answered against Town of Howey-in-the-Hills’s own published documents
Q29 Which NEC edition is in force? Core Code editions in force
2020 NEC, in force statewide via the current Florida Building Code cycle. No Howey-specific edition year is printed anywhere in the Town's own reached documents (the PV and electrical checklists both say only 'must follow the latest edition of the Florida Building Code' -- floating, undated language) -- this is the statewide default, not a town-confirmed figure.
Why the confidence is not higherStatute-cycle default per this survey's already-verified statutory reading; the Town's own documents float the citation rather than naming a year, so confidence is held below the 'own document says it plainly' band.
Town's own checklist (floating citation) + statewide code-cycle default checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q30 Which building code edition is in force? Core Code editions in force
Florida Building Code, 8th Edition (2023), statewide -- same floating-citation caveat as q29: the Town's own documents say 'the latest edition' without a year.
Why the confidence is not higherSame basis as q29.
Town's own checklist (floating citation) + statewide code-cycle default checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q31 Which fire code edition is in force? Code editions in force
Nothing published by this authority.
Where we lookedAll 11 LDC chapters (see q27) contain no fire-code adoption clause; the codified Code of Ordinances (where a fire-prevention chapter would normally sit) is unreachable -- library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances returns the SAME byte-identical 6,095-byte generic client-side-rendering shell this survey has already logged network-wide for Municode as of 13 Sep 2026.
https://library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances
Q32 Are there local amendments to any of the above? Core Code editions in force
Nothing published by this authority.
Where we lookedSame as q31 -- local technical amendments to the FBC, if any, would be codified in the unreachable Code of Ordinances.
https://library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances
Q33 What is the installation judged against? Core Electrical
Nothing published by this authority.
Where we lookedSame as q31.
https://library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances
Q34 Is there a local rule on service upgrades or busbar sizing? Electrical
Nothing published by this authority.
Where we lookedSame as q31 -- a service-upgrade/busbar (120%) rule, if locally addressed at all beyond the NEC default, would be in the unreachable codified ordinances or a solar-specific handout that was not found on the Town's own site.
https://library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances
Q35 Is a specific mounting system or attachment spacing required? Structural & mounting
No dedicated fire setback/spacing rule for PV arrays was found in any reached document (LDC chapters or checklists); a general fire-code setback, if any, would sit in the unreachable Code of Ordinances (see q31).
Why the confidence is not higherProved absent from the reached LDC and checklists, but the Code of Ordinances itself could not be checked (Municode outage) -- held to a bounded, not a proved, absence.
Town's own LDC chapters, complete enumeration (bounded by Municode outage) checked 2026-09-13 https://www.howey.org/DocumentCenter/View/219
Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks
Yes -- the PV Solar Permit Checklist itself requires the roof layout to show 'Fire department access location' and 'Fire department access pathways' as line items on the submitted plans, verbatim.
Why the confidence is not higherDirect quote from the Town's own current, dated PV checklist.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown
Not named explicitly -- the checklist requires only that the electrical schematic 'complies with the NEC', without naming NEC 690.12 (rapid shutdown) specifically. Since the applicable statewide NEC edition is 2020 (q29), which mandates 690.12 rapid shutdown for PV systems, the requirement is necessarily incorporated by the general NEC-compliance clause even though the Town's own document never uses the term.
Why the confidence is not higherInference from the adopted NEC edition combined with the checklist's general compliance clause -- the Town's own document does not use the term 'rapid shutdown' anywhere.
Town's own PV permit checklist, read against the statewide NEC edition checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedNo Town-specific placard requirement was found in any reached document (checklists, fee schedule, LDC). A utility-mandated placard, if any, would be specific to whichever of the two sellers identified at q22 serves the particular parcel -- since the Town has two sellers by area (not one), this cannot be resolved to a single town-wide answer without knowing the job address.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as q38 -- utility placard content is utility-specific, and this town has two utilities (q22), so no single town-wide answer exists.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as q38 -- AC-disconnect type/placement is utility-specific under FAC 25-6.065 and this town has two possible sellers.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame as q38.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame cluster as q38-41 -- AC-disconnect-specific requirements are utility-specific under FAC 25-6.065 and this town has two possible sellers (q22); neither Duke's nor SECO's own Tier-1 interconnection tariff was pulled and OCR'd this run.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q43 Where must the labels be placed? Core Labels Signage & labelling
Nothing published by this authority.
Where we lookedSame cluster as q38-42.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q44 Must equipment be on a specific approved list? Equipment listing
Nothing published by this authority.
Where we lookedSame as q38 -- equipment certification/interconnection agreement clauses are utility-specific.
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q45 Are batteries permitted, and under what conditions? Core Battery / ESS
No PV-specific ground-mount rule exists (q27's zero holds for ground mounts too). A ground-mounted PV array on a residential lot would fall to the LDC's GENERAL accessory-structure provisions (Ch.5, Accessory and Temporary Uses and Structures) -- setback and height limits that vary by the parcel's zoning district -- rather than to any solar-specific standard, since none exists.
Why the confidence is not higherProved absent by the same complete LDC enumeration as q27/28; the district-by-district accessory setback table itself was not individually reproduced here.
Town's own LDC Ch.5, complete enumeration checked 2026-09-13 https://www.howey.org/DocumentCenter/View/223
Q46 Is there a separate ESS permit or inspection? Battery / ESS
No dedicated Energy Storage System/battery permit type or inspection line exists anywhere in the fee schedule, the iWorQ checklist library, or the LDC (grepped for 'battery', 'ESS', 'energy storage' -- zero hits across all reached documents).
Why the confidence is not higherProved by enumeration across the fee schedule, the full iWorQ checklist/document list, and all 11 LDC chapters.
fee schedule + LDC, complete enumeration checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q47 Is a ground mount treated as a structure? Core Ground mount
The Town's Code of Ordinances is nominally hosted on Municode (library.municode.com/fl/howey-in-the-hills/codes/code_of_ordinances) but that route is PROVED UNREACHABLE, not merely unread: the URL returns the same byte-identical 6,095-byte generic client-side shell this survey has logged network-wide for Municode as of 13 Sep 2026. Separately and workably, the Town's own site hosts its ENTIRE Land Development Code as individually dated PDF chapters directly under its own DocumentCenter (bypassing Municode entirely) -- this is how q27/28/45/46 were actually proved rather than left unreached.
Why the confidence is not higherBoth the failure (Municode) and the workaround (Town's own LDC PDF library) were tested directly this session, not inherited from a prior run's claim.
Town's own DocumentCenter (LDC) vs. Municode (Code of Ordinances) checked 2026-09-13 https://www.howey.org/DocumentCenter/View/219
Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment
No -- the general Building Permit Application has no utility field of any kind (no write-in blank, no checkbox); the specific serving utility is not name-checked anywhere on any Town form reached.
Why the confidence is not higherApplication form read in full; absence proved by reading the whole document, not a missed field.
Town's own Building Permit Application, complete read checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/23466065-Building%20Permit%20Application%20w%20Notarized%20Signature.pdf
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
Inspection 5 steps · 14 questions
-
Book it
Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.
- How is an inspection booked? Online only, through the portal -- the Building Services page states explicitly: 'Inspections must be requested through the portal and can not be requested via other means.' 92% · AHJ's own department page
-
Know who turns up
Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.
- Does this AHJ perform its own final solar inspection? Willdan Engineering Company, under its active contract with the Town, per the Town's own Building Services page and the FY2021 utilization report showing 1,150 of 1,202 (95.7%) inspections performed 'by a private provider' (see q2). 88% · AHJ's own department page
- If delegated, to whom? Building and electrical are NOT delegated to Lake County -- the Town is the AHJ of record (see q1/q2) and issues, plan-reviews and inspects through its own contracted staff. The Town's own page does note that 'Lake County fees must be paid to them directly, and proof of payment must be provided as part of the permitting process' -- i.e. the County retains a SEPARATE fee obligation (most plausibly county impact fees on new construction/added floor area) that runs alongside, not instead of, the Town's own building-permit process. No document reached identifies whether that county-side fee applies to a simple equipment retrofit like rooftop PV on an existing home. 82% · AHJ's own department page
-
Work the stages in order
A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.
- Which inspections are required, and in what order? No dedicated 'Solar PV Final' inspection type exists in isolation; instead the PV checklist itself specifies exactly what the final inspection must document by photograph: the roof support system before panel placement (with a tape measure showing fastener spacing), the combiner boxes after all conductors are installed, and the attic conductor runs -- i.e. PV is closed out through the ordinary Building/Electrical Final inspection process but with a PV-specific photographic evidence requirement layered on top. 82% · Town's own PV permit checklist
-
Have the paperwork on site
The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.
- What must be on site at inspection? A recorded Notice of Commencement is required for PV jobs valued over $2,500, per the PV checklist's own item 3 ('The NOC must be on site prior to the first inspection') and the general Building Permit Application's own boldface warning about recording an NOC before the first inspection. $2,500 matches the statewide FS 713.132 general threshold. 90% · Town's own PV permit checklist
-
Sign-off, and permission to operate
Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.
- Is there a re-inspection fee? $75.00 flat re-inspection fee, per the current fee schedule's 'Administrative Fees' section ('Re-Inspection Fee ... 75.00'); no escalating second/third-reinspection tier is stated (unlike a neighbouring Lake County town's escalating $50/$75/... schedule already on file in this survey) -- Howey's is a single flat figure for every re-inspection. 90% · adopted fee schedule, dated 8/10/2026
14 questions answered against Town of Howey-in-the-Hills’s own published documents
Q49 How is an inspection booked? Core Booking & scheduling
Online only, through the portal -- the Building Services page states explicitly: 'Inspections must be requested through the portal and can not be requested via other means.'
Why the confidence is not higherVerbatim from the Town's own current department page.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q50 How much notice is required? Core Booking & scheduling
Nothing published by this authority.
Where we lookedBuilding Services page and iWorQ portal home -- neither states an inspection-request cutoff time (e.g., a prior-day 3pm cutoff) or how far in advance a request must be made.
Q51 Are same-day or AM/PM windows offered? Booking & scheduling
Nothing published by this authority.
Where we lookedSame as q50 -- no AM/PM or same-day scheduling language found.
Q52 Does this AHJ perform its own final solar inspection? Core Who inspects
Willdan Engineering Company, under its active contract with the Town, per the Town's own Building Services page and the FY2021 utilization report showing 1,150 of 1,202 (95.7%) inspections performed 'by a private provider' (see q2).
Why the confidence is not higherSame sources as q2.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q53 If delegated, to whom? Core Who inspects
Building and electrical are NOT delegated to Lake County -- the Town is the AHJ of record (see q1/q2) and issues, plan-reviews and inspects through its own contracted staff. The Town's own page does note that 'Lake County fees must be paid to them directly, and proof of payment must be provided as part of the permitting process' -- i.e. the County retains a SEPARATE fee obligation (most plausibly county impact fees on new construction/added floor area) that runs alongside, not instead of, the Town's own building-permit process. No document reached identifies whether that county-side fee applies to a simple equipment retrofit like rooftop PV on an existing home.
Why the confidence is not higherTown's own current page states this plainly for the core building/electrical function; the 'Lake County fees' clause is genuine but its applicability to solar specifically was not confirmed by a primary source, so that narrower point is flagged rather than assumed.
AHJ's own department page checked 2026-09-13 https://www.howey.org/236/Building-Services
Q54 Which inspections are required, and in what order? Core Stages & sequence
No dedicated 'Solar PV Final' inspection type exists in isolation; instead the PV checklist itself specifies exactly what the final inspection must document by photograph: the roof support system before panel placement (with a tape measure showing fastener spacing), the combiner boxes after all conductors are installed, and the attic conductor runs -- i.e. PV is closed out through the ordinary Building/Electrical Final inspection process but with a PV-specific photographic evidence requirement layered on top.
Why the confidence is not higherDirect read of the Town's own current PV checklist; no separate numbered 'PV Final' inspection code was found in any inspection catalogue (none was located published -- see q57).
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q55 Is a rough-in or mid-roof inspection required? Stages & sequence
Nothing published by this authority.
Where we lookedPV checklist and iWorQ checklist library -- no separate rough-in/mid-installation PV inspection is named; the checklist's only inspection touchpoint described is the final photographic requirement (see q54).
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q56 Does the inspector verify labels and listings? Core What is checked
Nothing published by this authority.
Where we lookedSame documents as q55 -- no statement on whether equipment UL/product listings are checked at inspection beyond the general Product Approval form process (see q26).
https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q57 Is there a published inspection checklist? Core What is checked
Nothing published by this authority.
Where we lookediWorQ Citizen Portal home page and the Town's DocumentCenter/Forms & Applications page -- no numbered, complete inspection catalogue (of the kind published by name in other authorities on file in this survey, e.g. Astatula's ~50-line list) was found published anywhere on the Town's own site.
Q58 What must be on site at inspection? Core Documents on site
A recorded Notice of Commencement is required for PV jobs valued over $2,500, per the PV checklist's own item 3 ('The NOC must be on site prior to the first inspection') and the general Building Permit Application's own boldface warning about recording an NOC before the first inspection. $2,500 matches the statewide FS 713.132 general threshold.
Why the confidence is not higherDirect quote from the Town's own current PV checklist and application form.
Town's own PV permit checklist checked 2026-09-13 https://s3.amazonaws.com/iworq-upload/HOWEY/5/22876401-PV%20Solar%20Permit%20Checklist.pdf
Q59 Is there a re-inspection fee? Corrections & re-inspection
$75.00 flat re-inspection fee, per the current fee schedule's 'Administrative Fees' section ('Re-Inspection Fee ... 75.00'); no escalating second/third-reinspection tier is stated (unlike a neighbouring Lake County town's escalating $50/$75/... schedule already on file in this survey) -- Howey's is a single flat figure for every re-inspection.
Why the confidence is not higherDirect read of the current, dated fee schedule.
adopted fee schedule, dated 8/10/2026 checked 2026-09-13 https://www.howey.org/DocumentCenter/View/712
Q60 How are corrections issued and cleared? Corrections & re-inspection
Nothing published by this authority.
Where we lookedBuilding Services page, iWorQ portal home, Residential/PV checklists -- none states HOW inspection pass/fail results are communicated back to the applicant (portal status update, email, phone call).
Q61 What is issued on pass? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedAll reached Town documents -- no statement on whether a formal Certificate of Completion/Occupancy, or a lesser sign-off, is issued specifically for a PV-only permit (as opposed to new-construction CO).
Q62 Who notifies the utility for PTO? Core Final sign-off & PTO
Nothing published by this authority.
Where we lookedCould not fully resolve to a single answer: the Town has TWO electric sellers by area (q22, Duke Energy Florida ~61%, SECO Energy ~39%), and neither utility's own Tier-1 interconnection tariff, PTO process, or placard requirement was pulled and OCR'd this run (time-bounded) -- so whether the installer/contractor or the Town notifies the utility for PTO could not be settled to a town-wide certainty without knowing which of the two sellers a given job address falls under.
Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.
No change record for this authority yet. Values arrive here as they are researched, and each one is dated.
Labels & placards for this authority
Wording None%
Size, colour & material None%
Where they go None%
What the utility wants on top None%
Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.
Their website
Solar Requirements
Average approval time — application to PTO
From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.