Town of Lake Clarke Shores

Palm Beach County · Florida ← All authorities

Town of Lake Clarke Shores

Palm Beach County

Verified Aug. 5, 2026

Town of Lake Clarke Shores is a town authority in the State of Florida, serving 3,564 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Town of Lake Clarke Shores against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Town of Lake Clarke Shores is the authority having jurisdiction 92% confidence
Holds
building and electrical permitting, plan review and inspection for residential solar inside the town limits, as one combined valuation-based permit
Overridden by
Not overridden, but materially shaped by four outside instruments. (1) PRIVATE OUTSOURCING: the Town remains the legal AHJ and issues the permit, but Building Official, plan review and inspection services have been performed under contract by Diversified Building Department Management since 1 November 2024 (replacing Hy-Byrd Inspections), on a percentage-of-fee rather than hourly basis. (2) FPL is the sole electric utility and holds the interconnection gate; on a UL 1741 inverter-based Tier 1 system FPL requires no AC disconnect, and the Town has no disconnect ordinance of its own, so the only mandatory signage is FPL's ESS XIII.A.6 meter-can placard. (3) State law: FS 553.792 sets the permit clock (5 business days under $15,000, otherwise 30), FS 553.79(1)(c) sets single-family permit expiry, FS 553.79(1)(f) bars inspection fees based on total project cost, FS 553.79(1)(g)2.b excludes all electrical work on single-family property from the $7,500 permit exemption, and FS 553.791(1)(r) now names solar and energy storage as single-trade private-provider work. (4) Palm Beach County holds the contractor Certificate of Competency licensing route, impact fees, and fire/rescue service through Palm Beach County Fire Rescue; the Town adopts the County's FBC amendments by reference at Sec. 10-20, though the codified reference is frozen at the 5th Edition (2014) version.
Why not higher
Code Sec. 10-19 acknowledges the Town's FS ch. 553 enforcement responsibility; the Town issues its own permits through MGO Connect and files its own FS 553.80(7)(b) utilization reports for FY2021-FY2025. The outsourcing is established from the Town's own adopted minutes of 8 Oct 2024 and the November 2024 Town Manager's Report. Not higher because the executed vendor contract is not published, so the boundary between Town staff and vendor duties cannot be stated precisely.

https://www.townoflcs.gov/media/26291

Permit required
Yes. Code Sec. 10-91(a) (as amended by Ord. No. 2025-02, 14 Oct 2025) requires a permit for any owner, agent or contractor who desires to 'erect, install, enlarge, alter, repair, remove,95%
Permit cost
Roughly $920-$950 on a $25,000 residential array, and the fee is dominated by the valuation percentage.88%
Plan review
The Town publishes no turnaround of its own. The statutory clock governs: FS 553.792(1)(a)1 — 5 business days for an electrical permit on an EXISTING single-family dwelling where the value…80%
Portal
MyGovernmentOnline (MGO Connect), at mgoconnect.org. The Building Permits page carries MGO's support numbers, 985.851.0760 and 866.957.3764,95%
Electrical code
NEC (NFPA 70) 2020 edition, in force through the Florida Building Code, 8th Edition (2023), whose effective date is 31 December 2023.88%
Own placard wording
No. The Town specifies no placard wording of its own — there is no electrical chapter, no fire chapter and no PV provision anywhere in its code or on its website ('photovoltaic' 0 in 1.4 M…90%
Booking an inspection
Portal. Inspections are requested through MGO Connect: 'All communications regarding permit status, required documentation, inspection scheduling,90%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes. Code Sec. 10-91(a) (as amended by Ord. No. 2025-02, 14 Oct 2025) requires a permit for any owner, agent or contractor who desires to 'erect, install, enlarge, Q3 Electrical and building permits — Combined. Code Sec. 10-98(b)(2): 'New buildings, additions, alterations, miscellaneous, Q4 Plan review — The Town publishes no turnaround of its own. The statutory clock governs: FS 553.792(1)(a)1 — 5 business days for an electrical permit on an EXISTING single-family… Q18 Where you file — MyGovernmentOnline (MGO Connect), at mgoconnect.org. The Building Permits page carries MGO's support numbers, 985.851.0760 and 866.957.3764, Q20

Permit required
Yes. Code Sec. 10-91(a) (as amended by Ord. No. 2025-02, 14 Oct 2025) requires a permit for any owner, agent or contractor who desires to 'erect, install, enlarge, alter, repair, remove,95% source
What it costs
Roughly $920-$950 on a $25,000 residential array, and the fee is dominated by the valuation percentage.88% source
Plan review turnaround
The Town publishes no turnaround of its own. The statutory clock governs: FS 553.792(1)(a)1 — 5 business days for an electrical permit on an EXISTING single-family dwelling where the value of the…80% source
Key document
portal landing page cited by 5 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes. The Town of Lake Clarke Shores is the AHJ for residential solar inside its municipal limits. Code Sec. 10-19: 'The town hereby acknowledges it responsibility pursuant to F.S. ch. 553, to enforce the provisions of the state building code as adopted by the state building commission.' The Town issues its own building permits through its own portal and files its own FS 553.80(7)(b) Building Permit and Inspection Utilization Report (FY2025: 470 applications, 430 permits issued, 1,040 inspections conducted). Palm Beach County is NOT the permitting AHJ here; the county holds contractor competency licensing, impact fees and fire/rescue only. 95% · adopting ordinance
    • What does this authority permit itself, and what does it delegate? Both — building and electrical, as one permit. BUT THE FUNCTION IS PRIVATELY OUTSOURCED: the Town remains the legal AHJ and issues the permit, while Building Official, plan review and inspection services are performed under contract by Diversified Building Department Management, signed effective 1 November 2024 (it replaced Hy-Byrd Inspections). Council minutes of 8 Oct 2024: 'the Town currently pays the building official service company on an hourly basis for work performed... the RFP requested that they bid on a percentage basis instead of an hourly fee... the evaluation committee ranked each company with Diversified Building Department Management scoring 22 points higher than the current company, Hy-Byrd Inspections' (motion approved 5-0). November 2024 Town Manager's Report: 'Staff negotiated the contract with Diversified Building Department Management down 5% on two tiers and signed it effective November 1, 2024.' Split elsewhere: Palm Beach County holds contractor Certificate of Competency licensing and impact fees; Palm Beach County Fire Rescue provides fire service. 92% · adopted council minutes
    • Is a permit required for a residential rooftop PV system? Yes. Code Sec. 10-91(a) (as amended by Ord. No. 2025-02, 14 Oct 2025) requires a permit for any owner, agent or contractor who desires to 'erect, install, enlarge, alter, repair, remove, convert or replace any required impact-resistant coverings, electrical, gas, mechanical or plumbing system, the installation of which is regulated by the Florida Building Code.' The Building Permits page confirms permits are required for 'electrical... work, as well as repairs to these systems', and that the permit must be posted on site before work begins. There is no $7,500 or other value floor: FS 553.79(1)(g)2.b excludes all electrical work on single-family property from the statutory small-works exemption. 95% · ordinance
    • Is there a separate electrical permit, or is it combined? Combined. Code Sec. 10-98(b)(2): 'New buildings, additions, alterations, miscellaneous, and single permit fees shall be based on the estimated value and will include the cost of all subpermits.' So one valuation-based master permit carries the electrical sub-permit; there is no separately priced electrical permit line anywhere on the adopted User Fees and Charges Schedule. 88% · ordinance
    • Is a HOA or architectural approval required first? No town-wide architectural review board and no codified association-consent rule — but HOA approval is an express submittal line on every checklist the Town publishes ('Homeowner's Association Approval (if applies)' on the driveway, fence and shed checklists), so where an association exists the Town will collect its approval. The zoning chapter has no consent rule: 'association' returns 12 hits across Chapter 125 and every one is a definition, a PUD documentation item, a zero-lot-line access easement, or a trade/standards body — none is an approval gate. FS 163.04(2)'s HOA-limiting language has NOT been re-enacted as a municipal restriction here: 'due south', '45 degrees' as an orientation and 'orientation' as a solar term all return nothing. The one discretionary aesthetic hook that does exist is Sec. 125-483: 'Exterior architectural features, design, and appearance of any building or structure within the town, including, but not limited to, color, shall be in conformity with good taste and shall not be of such inferior quality as to cause the nature of the local environment to materially depreciate in appearance and value.' 78% · published checklist
    • Is there a historic-district review? No. There is no historic district, no historic preservation ordinance and no certificate-of-appropriateness process. Every 'historic' hit in 1,403,416 characters of code is either the flood chapter's FBC-derived definition of 'historic structure' and the matching variance and substantial-improvement carve-outs (Secs. 105-25, 105-57), an archaeological-resources clause in the site-plan article, or an editor's note. 88% · ordinance
    • Is a wind or windstorm certification required? No separate Town windstorm certification. Wind resistance comes through the Florida Building Code and Florida Product Approval: FBC-R R324.4.1.2 requires rooftop PV panels, modules and their supports to be 'designed and installed for wind loads in accordance with ASCE 7', and Sec. 10-20 adopts the Palm Beach County amendments to the FBC, whose Figure 1609.3 material governs the wind-borne debris region. The only wind figure the Town itself prints is on the shed checklist: 'each must be designed to withstand the forces created by 140-mph wind'. Play structures 'must meet current windload requirements' (Sec. 125-291(b)(7)b). 70% · published checklist
    • Is a Specific Use Permit or Council approval ever required? Not for a rooftop array. Site plan review under Sec. 125-101 does not reach single-family residential alterations, and its fee ($3,500 plus Town engineer, Building Official, attorney 'and other related fees') never fires. The discretionary routes that do exist and could in principle be reached are the Zoning Board of Adjustment's special exception and variance powers (Secs. 125-68, 125-69; fee $475 single-family residential for either), which would only be needed if a ground mount fell foul of Sec. 125-293(1) or the setback/coverage limits. No Council approval step is published for any residential building permit. 75% · ordinance
    • Is there a system-size cap on residential generation? No cap in the Town's own instruments — proved. The cap is FPL's, and there are three of them, all in the filed Tier 1 agreement (Third Revised Sheet No. 9.050, effective 1 Jan 2026) Sec. 2.1: the Gross Power Rating (a) 'does not exceed 90% of the Customer's utility distribution service rating'; (b) 'is 10 kW AC or less'; and (c) 'has an AC generating capacity of less than 115% of the Customer's previous 12 months kilowatt-hour usage'. For inverter-based systems the AC rating is the installed DC nameplate x 0.85 (Sec. 1.1). Limb (c) is the one that catches people: it is independent of kW and will disqualify a new-build or low-usage household from Tier 1 no matter how small the array, so ask for 12 months of bills before sizing. Above 10 kW AC the job becomes Tier 2 (to 100 kW, $400 application fee) or Tier 3 (to 2 MW, $1,000). 90% · utility tariff
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? A contractor registered with the Town. The Building Permits page: 'If a homeowner chooses to obtain a permit as an Owner/Builder, they are required to sign an Owner/Builder Affidavit Statement. Additionally, all Electrical, Plumbing, and Mechanical work must be performed by licensed contractors.' So even on an owner/builder permit the PV electrical work must be done by a licensed contractor. Code Sec. 10-91(b): the application 'shall be signed by the owner or the contractor doing the proposed work.' 90% · department page
    • Must the contractor be registered with this authority before applying? Yes — and it is a hard gate. The New Resident Welcome Packet (Town-authored, created 21 May 2026): 'Lake Clarke Shores' registration certificates are required for all contractors and maintenance companies performing services in the town... Visit https://www.mgoconnect.org/auth/login to register your business.' The adopted fee schedule prices it: Contractor Registration $2.00 with a Palm Beach county-wide Tax Receipt, $30.00 without, and $0.00 with State of Florida competency. Proof of general liability and workers' compensation insurance is expected. 92% · town publication (New Resident Welcome Packet)
    • Is a homeowner permitted to self-install and self-permit? Partly. A homeowner may hold the permit as an Owner/Builder on signing an Owner/Builder Affidavit Statement, but may NOT self-perform the electrical work: 'all Electrical, Plumbing, and Mechanical work must be performed by licensed contractors.' For a PV array, which is electrical work on a single-family dwelling, that means the homeowner can be the applicant but not the installer of the electrical scope. 88% · department page
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? No PV-specific submittal checklist exists — proved. The Town's 'Checklists for Common Projects' covers only driveways, fences, irrigation and sheds. What a PV submittal will therefore be built from: (a) the application, filed electronically through MGO Connect (no paper accepted); (b) Sec. 10-94 — specifications and drawings to scale 'with sufficient clarity and detail to indicate the nature and character of the work', bearing 'the signature and address of the person responsible for the design'; (c) Sec. 10-95 — a plot diagram showing the proposed and every existing structure plus utility systems serving the lot; (d) Sec. 125-34(b) — plans showing actual lot dimensions and the location and dimensions of the proposed alteration; (e) Sec. 125-35(c) — an application for a certificate of zoning compliance must be made before any permit issues; (f) Homeowners' Association approval where one applies (an express line on every published Town checklist); (g) Palm Beach County's adopted FBC amendments, incorporated by Sec. 10-20, require the electrical plan content to show 'Electric service riser with wire sizes, conduit detail, and grounding detail' and 'Complete load calculations, Panel schedules'; (h) in a flood hazard area, Sec. 105-23 site plans and construction documents. FPL separately wants a single line diagram carrying the meter number. 70% · published checklist
    • How many copies, and in what format? Electronic only, through the MGO Connect portal: 'The Town uses an electronic permitting portal and does not accept paper permit applications.' The codified copy counts are dead letters in practice — Sec. 125-34(b) still requires 'plans in triplicate' and Sec. 10-94 'two or more copies'. 85% · department page
    • Is a site plan required, and what must it show? Yes. Every published Town checklist opens with 'a copy of the survey showing all property lines; all buildings on the property; all easements, swales, turnouts, water meters...; all streets & bodies of water abutting the property' and the location and dimensions of the proposed work. Sec. 10-95 requires the plot diagram to show 'the location of the proposed building or structure and every existing building or structure on the site or lot... existing and proposed roads, water mains and fire protection systems and any other utility systems serving the site or lot.' For a ground mount the lot-coverage test (35%, Sec. 125-297) and the setbacks (front 25 ft / side 10 ft / rear 15 ft, Sec. 125-295) have to be demonstrable off that survey. 80% · ordinance
    • Is a one-line / three-line diagram required? Not required by any Town document — the Town publishes no electrical or PV plan requirement at all. In substance yes, from two other instruments the job must satisfy: Palm Beach County's FBC amendments (adopted by Town Code Sec. 10-20) require electrical plan content showing 'Electric service riser with wire sizes, conduit detail, and grounding detail' plus 'Complete load calculations, Panel schedules'; and FPL requires a Single Line Diagram carrying the meter number for every net-metering interconnection (ESS XIII.A.3), with a three-line diagram possible on larger systems (XIII.A.7). 62% · county code amendments adopted by reference
    • Are string and conductor calculations required? Not stated by the Town. The county amendments the Town adopts require 'Complete load calculations, Panel schedules' and conductor 'wire sizes' on the electrical plan sheet, which is the practical equivalent for a PV interconnection; string-level DC calculations are nowhere required in writing. 60% · county code amendments adopted by reference
    • Is a structural PE stamp required, and at what threshold? No PV-specific structural PE threshold is published. What the Town does publish: site-built sheds require 'plans to be signed and sealed by a Florida Licensed Architect or Engineer'; play structures require plans 'designed and sealed by a registered engineer or architect' together with the method of attachment/anchoring (Sec. 125-291(b)(7)c); and Sec. 10-94 requires all drawings to 'bear the signature and address of the person responsible for the design' with no seal threshold. The governing standard is FBC-Residential 8th Ed. (2023) R324.4.1/R324.4.1.1/R324.4.1.2 — the array must be designed for gravity loads per Chapter 3, the roof designed to support them per Chapter 8, and wind loads per ASCE 7. 62% · published checklist
    • Is an electrical PE stamp required, and at what threshold? No local threshold. Statewide, FS 471.003(2)(h) exempts electrical work on a residential building from the PE requirement where the construction cost is $125,000 or less AND the electrical current is 600 amperes or less at 240 volts or less (800 amperes commercial). Nothing in the Town's code or on its pages sets a different or lower trigger — 'engineer' in the code corpus returns sign structures, towers, satellite-dish foundations, sheds and play structures only. 75% · ordinance
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? MyGovernmentOnline (MGO Connect), at mgoconnect.org. The Building Permits page carries MGO's support numbers, 985.851.0760 and 866.957.3764, and the Welcome Packet sends both contractors and owner/builders to https://www.mgoconnect.org/auth/login to register and apply. The same portal handles documentation, status, inspection scheduling and payment. Town website is CivicPlus on Drupal; utility billing is a separate vendor. 95% · portal landing page
    • Can the whole application be completed online? Yes, and paper is refused: 'The Town uses an electronic permitting portal and does not accept paper permit applications. The portal allow applicants to complete the entire permitting process remotely - without the need to visit Town Hall in person. All communications regarding permit status, required documentation, inspection scheduling, and payments is handled through the electronic permitting portal.' Fees are due at submittal and 'can be paid through the MGO portal'. One carve-out: permits opened before the portal go on under the old process until closed out. 95% · department page
    • What does a residential solar permit cost? Roughly $920-$950 on a $25,000 residential array, and the fee is dominated by the valuation percentage. Published Permit Fees page: minimum fee $90.00; 3% of $0-$100,000, plus 2% of $100,001-$200,000, plus 1% of valuation over $200,001. Plan review is charged ON TOP: 'New construction plan review fees are $350.00. Addition/remodel plan review fees are $150.00. These fees are added to the permit application fees.' Worked: $25,000 x 3% = $750 permit + $150 plan review (if a PV retrofit is read as 'remodel/addition') + state surcharge + a 3% credit-card convenience fee = approximately $923 before the card fee, ~$950 with it. *** THE TWO TOWN INSTRUMENTS DISAGREE ON THE SURCHARGE: adopted Resolution 2024-12 Exhibit A says 'State Surcharge 2.5% of permit fee'; the live Permit Fees page says 1.5% for the Building Code Administrators and Inspectors Fund PLUS 1.5% for enforcement of building codes, i.e. 3.0%. *** Re-inspection $75.00; revisions $40 residential with no cost change, or 3% of added cost + $40 with one; duplicate/replacement permit $25 + printing; change of contractor $100; starting work without a permit is four times the permit fee. 88% · fee schedule
    • How is the fee calculated? Valuation, tiered: 3% of the first $100,000 of job value, 2% of the next $100,000, 1% above $200,001, with a $90.00 minimum. 'Permit fees are based on the cost of the job.' Sec. 10-98(b)(3) lets the Building Official deny a permit where 'the valuation is underestimated on the application' unless the applicant produces a detailed cost estimate acceptable to him. *** This sits awkwardly against FS 553.79(1)(f), read first-hand this run: 'Inspection fees may not be based on the total cost of a project and may not exceed the actual inspection costs incurred by the local enforcement agency' — and Sec. 10-98(b)(5) provides for a minimum inspection fee set by resolution while the whole permit fee, inspections included, is priced off job cost. Flagged, not asserted as a violation. 95% · fee schedule
    • Is there a separate plan-check fee? Yes. $350.00 for new construction and $150.00 for an addition/remodel, 'added to the permit application fees'. A 'Major working drawing review fee' of $300.00 + $25.00 per page also exists and is expressly 'not applied to permit fee'. Note the codified Sec. 10-98(c) describes a different mechanism entirely — 'Fifty percent of the estimated permit fee must be paid upon filing the plan as a plan filing fee', credited against the permit fee if the permit issues within two months and forfeited if it does not — which the published flat plan-review fees have superseded in practice without the Code being conformed. 90% · adopted fee resolution (Res. 2024-12, 14 May 2024)
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? The Town publishes no turnaround of its own. The statutory clock governs: FS 553.792(1)(a)1 — 5 business days for an electrical permit on an EXISTING single-family dwelling where the value of the work is less than $15,000; (a)2 — 30 business days otherwise where the structure is under 7,500 sq ft. Most residential PV jobs exceed $15,000, so the realistic answer is 30 business days. (1)(c) gives the Town 5 business days to say what is missing or the application is automatically deemed complete; (1)(e)-(g) reduce the permit fee by 10% per business day late, and by 20% per business day on a late revision cycle. *** THE TOWN HAS ADOPTED AN EXPEDITED PROCESS AND NOT PUBLISHED IT: Resolution 2025-08, 'Establishing an Expedited/Coordinated Building Approval Process for Qualified Projects', was adopted on consent 8 April 2025 (minutes, item 6.B) — but the PDF attached to it on the Town's own resolutions index is Resolution 2025-09, appointing League of Cities representatives. The text of the expedited policy is therefore unavailable, and FS 553.792(1)(d) requires a local government to maintain that policy on its website. 80% · state statute
    • How long is an issued permit valid before it expires? Three layers that do not agree. Codified Sec. 125-34(d): a permit expires if work has not begun within six months of issuance, and again if the work is not substantially completed within one year, after which a 'special building permit' is needed. Statewide and later in time, FS 553.79(1)(c): 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later', and a local government may extend it. The Town has not conformed its ordinance or said which governs. 80% · ordinance
    • Which utility handles interconnection here? FLORIDA POWER & LIGHT (FPL), and it is the only electric seller in the Town. The Town's New Resident Welcome Packet, authored by the Town and created 21 May 2026, carries a who-to-call table with SPLIT ROWS BY FUNCTION: 'Electricity Provider - Florida Power & Light is the provider of electricity within the Town of Lake Clarke Shores'; 'Gas Provider - Florida Public Utilities is the provider of gas within the Town'; and water/wastewater split across THREE rows (the Town's own Utilities Department for about 700 homes, Palm Beach County Utilities, and the Village of Palm Springs Utilities). Exactly one electric row, no second seller. Corroborated Town-side twice more: the Community Development Services menu carries an 'FPL Report a Power Outage' item that redirects to fpl.com's outage landing page, and the Town's Storm Resources page lists 'FPL Power Tracker' and 'FPL Power Outage' under 'Report Power Outages and Service Updates'. 93% · town publication (New Resident Welcome Packet)
    • Where does the utility sit in the sequence? Parallel, with the AHJ's sign-off feeding the utility and FPL holding the last gate. From FPL's filed Tier 1 Interconnection Agreement (Third Revised Sheet No. 9.050, effective 1 January 2026), read first-hand: Sec. 2.3 the customer files a completed application to start the process; Sec. 3.4 'The Customer agrees to provide Local Building Code Official inspection and certification of installation. The certification shall reflect that the local code official has inspected and certified that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications'; Sec. 3.5 at least 10 calendar days' notice before initially placing the equipment in service; Sec. 3.6 FPL executes the agreement within 30 calendar days of a completed application. FPL's ESS adds that 'It is highly recommended that customers obtain FPL's written interconnection approval prior to procuring any material.' The Town's permit is not conditioned on FPL approval in any published instrument. 90% · utility tariff

28 questions answered against Town of Lake Clarke Shores’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes. The Town of Lake Clarke Shores is the AHJ for residential solar inside its municipal limits. Code Sec. 10-19: 'The town hereby acknowledges it responsibility pursuant to F.S. ch. 553, to enforce the provisions of the state building code as adopted by the state building commission.' The Town issues its own building permits through its own portal and files its own FS 553.80(7)(b) Building Permit and Inspection Utilization Report (FY2025: 470 applications, 430 permits issued, 1,040 inspections conducted). Palm Beach County is NOT the permitting AHJ here; the county holds contractor competency licensing, impact fees and fire/rescue only.

Why the confidence is not higherThree independent Town-side instruments say so: the codified adopting section, the Building Permits page, and the Town's own current statutory utilization report. Code text retrieved by curl from api.municode.com (clientId 8899, productId 12818, jobId 489787 = Supplement 2, 'Codified through Ordinance No. 2025-03, enacted December 9, 2025', posted online 24 Jun 2026); 1,252 documents / 1,403,416 characters harvested serially. Search controls on that corpus: electrical 60, 'building permit' 79, flood 404, accessory 72, solar 1, photovoltaic 0, fabricated term zzqqxvv 0.

adopting ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV1GE_S10-19STBUCOAD

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both — building and electrical, as one permit. BUT THE FUNCTION IS PRIVATELY OUTSOURCED: the Town remains the legal AHJ and issues the permit, while Building Official, plan review and inspection services are performed under contract by Diversified Building Department Management, signed effective 1 November 2024 (it replaced Hy-Byrd Inspections). Council minutes of 8 Oct 2024: 'the Town currently pays the building official service company on an hourly basis for work performed... the RFP requested that they bid on a percentage basis instead of an hourly fee... the evaluation committee ranked each company with Diversified Building Department Management scoring 22 points higher than the current company, Hy-Byrd Inspections' (motion approved 5-0). November 2024 Town Manager's Report: 'Staff negotiated the contract with Diversified Building Department Management down 5% on two tiers and signed it effective November 1, 2024.' Split elsewhere: Palm Beach County holds contractor Certificate of Competency licensing and impact fees; Palm Beach County Fire Rescue provides fire service.

Why the confidence is not higherThe award and the effective date come from the Town's own adopted minutes and the Town Manager's own report; the six-firm shortlist is in the Town's Evaluation Committee agenda of 27 Sep 2024 (Calvin Giordano & Associates; CAP Government; Diversified Building Department Management; Hybyrd Inspections; Joe Payne Inc.; Universal Engineering Sciences). Not 95 because the executed contract itself is not published, so the compensation percentages and the scope boundary between Town staff and the vendor are not on the record.

adopted council minutes checked 2026-09-13 https://www.townoflcs.gov/media/24226

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes. Code Sec. 10-91(a) (as amended by Ord. No. 2025-02, 14 Oct 2025) requires a permit for any owner, agent or contractor who desires to 'erect, install, enlarge, alter, repair, remove, convert or replace any required impact-resistant coverings, electrical, gas, mechanical or plumbing system, the installation of which is regulated by the Florida Building Code.' The Building Permits page confirms permits are required for 'electrical... work, as well as repairs to these systems', and that the permit must be posted on site before work begins. There is no $7,500 or other value floor: FS 553.79(1)(g)2.b excludes all electrical work on single-family property from the statutory small-works exemption.

Why the confidence is not higherCodified text plus the Town's own current department page; the statutory exclusion read first-hand. Note Lake Clarke Shores publishes nothing at all about HB 803 / FS 553.79(1)(g): a site search for '803' returns 3 hits, all a 2018-19 budget file and meeting index pages.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV3PECEOCIN_S10-91BUPERE

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined. Code Sec. 10-98(b)(2): 'New buildings, additions, alterations, miscellaneous, and single permit fees shall be based on the estimated value and will include the cost of all subpermits.' So one valuation-based master permit carries the electrical sub-permit; there is no separately priced electrical permit line anywhere on the adopted User Fees and Charges Schedule.

Why the confidence is not higherCodified text plus the absence of any electrical line on Resolution 2024-12 Exhibit A. Not higher because the Town's own codified satellite-dish rule (Sec. 125-624(1)) still says 'a licensed electrical contractor shall apply for a permit for his portion of the work', so a separate trade permit is conceivable in practice.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV3PECEOCIN_S10-98SCPEFECHEX

Q5 Who is allowed to pull the electrical permit? Core Who may apply

A contractor registered with the Town. The Building Permits page: 'If a homeowner chooses to obtain a permit as an Owner/Builder, they are required to sign an Owner/Builder Affidavit Statement. Additionally, all Electrical, Plumbing, and Mechanical work must be performed by licensed contractors.' So even on an owner/builder permit the PV electrical work must be done by a licensed contractor. Code Sec. 10-91(b): the application 'shall be signed by the owner or the contractor doing the proposed work.'

Why the confidence is not higherDirect quotation from the Town's own current Building Permits page, corroborated by the codified signature rule. Not higher because the Town does not say in writing whether a licensed electrical contractor must be the named applicant on the electrical portion or merely perform the work.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes — and it is a hard gate. The New Resident Welcome Packet (Town-authored, created 21 May 2026): 'Lake Clarke Shores' registration certificates are required for all contractors and maintenance companies performing services in the town... Visit https://www.mgoconnect.org/auth/login to register your business.' The adopted fee schedule prices it: Contractor Registration $2.00 with a Palm Beach county-wide Tax Receipt, $30.00 without, and $0.00 with State of Florida competency. Proof of general liability and workers' compensation insurance is expected.

Why the confidence is not higherTown-authored packet with a 2026 creation date plus the adopted fee resolution. Not 95 because no ordinance codifies the registration requirement — 'contractor' returns no registration provision anywhere in the code corpus; it is an administrative requirement carried on the packet, the fee schedule and the portal.

town publication (New Resident Welcome Packet) checked 2026-09-13 https://www.townoflcs.gov/media/27131

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Partly. A homeowner may hold the permit as an Owner/Builder on signing an Owner/Builder Affidavit Statement, but may NOT self-perform the electrical work: 'all Electrical, Plumbing, and Mechanical work must be performed by licensed contractors.' For a PV array, which is electrical work on a single-family dwelling, that means the homeowner can be the applicant but not the installer of the electrical scope.

Why the confidence is not higherDirect quotation from the Town's own department page. Not higher because the Owner/Builder Affidavit form itself is inside the login-gated MGO portal and could not be read, so the exact recitals (FS 489.103(7) / 489.503(6) disclosures) are unverified.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q8 What documents make up a complete submittal? Core Submittal package

No PV-specific submittal checklist exists — proved. The Town's 'Checklists for Common Projects' covers only driveways, fences, irrigation and sheds. What a PV submittal will therefore be built from: (a) the application, filed electronically through MGO Connect (no paper accepted); (b) Sec. 10-94 — specifications and drawings to scale 'with sufficient clarity and detail to indicate the nature and character of the work', bearing 'the signature and address of the person responsible for the design'; (c) Sec. 10-95 — a plot diagram showing the proposed and every existing structure plus utility systems serving the lot; (d) Sec. 125-34(b) — plans showing actual lot dimensions and the location and dimensions of the proposed alteration; (e) Sec. 125-35(c) — an application for a certificate of zoning compliance must be made before any permit issues; (f) Homeowners' Association approval where one applies (an express line on every published Town checklist); (g) Palm Beach County's adopted FBC amendments, incorporated by Sec. 10-20, require the electrical plan content to show 'Electric service riser with wire sizes, conduit detail, and grounding detail' and 'Complete load calculations, Panel schedules'; (h) in a flood hazard area, Sec. 105-23 site plans and construction documents. FPL separately wants a single line diagram carrying the meter number.

Why the confidence is not higherAssembled from five of the Town's own instruments plus the county amendments the Town adopts by reference; no single Town document states the PV package, so this is an inference from documents that each answer a neighbouring question. The county amendments the Town's Sec. 10-20 actually names are the 5th Edition (2014) version, which is not published anywhere; I read the current 8th Edition (2023) document.

published checklist checked 2026-09-13 https://www.townoflcs.gov/cds/page/checklists-common-projects

Q9 How many copies, and in what format? Submittal package

Electronic only, through the MGO Connect portal: 'The Town uses an electronic permitting portal and does not accept paper permit applications.' The codified copy counts are dead letters in practice — Sec. 125-34(b) still requires 'plans in triplicate' and Sec. 10-94 'two or more copies'.

Why the confidence is not higherDirect quotation from the Town's current page; the conflict with two codified provisions is recorded rather than resolved. Contractors and owner/builders with permits opened before the portal must still use the former paper process until those permits are closed out, per the same page.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q10 Is a site plan required, and what must it show? Core Submittal package

Yes. Every published Town checklist opens with 'a copy of the survey showing all property lines; all buildings on the property; all easements, swales, turnouts, water meters...; all streets & bodies of water abutting the property' and the location and dimensions of the proposed work. Sec. 10-95 requires the plot diagram to show 'the location of the proposed building or structure and every existing building or structure on the site or lot... existing and proposed roads, water mains and fire protection systems and any other utility systems serving the site or lot.' For a ground mount the lot-coverage test (35%, Sec. 125-297) and the setbacks (front 25 ft / side 10 ft / rear 15 ft, Sec. 125-295) have to be demonstrable off that survey.

Why the confidence is not higherChecklist wording is verbatim from the Town's own page but is written for driveways/fences/sheds, not PV; the codified plot-diagram duty is general and does apply.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV3PECEOCIN_S10-95PLDI

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Not required by any Town document — the Town publishes no electrical or PV plan requirement at all. In substance yes, from two other instruments the job must satisfy: Palm Beach County's FBC amendments (adopted by Town Code Sec. 10-20) require electrical plan content showing 'Electric service riser with wire sizes, conduit detail, and grounding detail' plus 'Complete load calculations, Panel schedules'; and FPL requires a Single Line Diagram carrying the meter number for every net-metering interconnection (ESS XIII.A.3), with a three-line diagram possible on larger systems (XIII.A.7).

Why the confidence is not higherInference from two documents neither of which is the Town's. Controls run on the Town corpus: 'one-line', 'single line' and 'three-line' return nothing PV-related in 1.4 M characters of code. townoflcs.gov sits behind a Cloudflare managed challenge that 403s plain curl and WebFetch on every dynamic path; all Town pages here were retrieved with curl_cffi impersonating Chrome, which passes. Town site search controls: electrical 42 results, flood 42, solar 5, demolition 10; photovoltaic / freeboard / SolarAPP / 163.04 / zzqqxvv all 0 results returning the same ~55.5 KB empty-result page.

county code amendments adopted by reference checked 2026-09-13 https://discover.pbcgov.org/pzb/building/BuildingCodes/PBC-Amendments-to-the-Florida-Building-Code-8th-Edition-2023.pdf

Q12 Are string and conductor calculations required? Drawings & calculations

Not stated by the Town. The county amendments the Town adopts require 'Complete load calculations, Panel schedules' and conductor 'wire sizes' on the electrical plan sheet, which is the practical equivalent for a PV interconnection; string-level DC calculations are nowhere required in writing.

Why the confidence is not higherSame basis and same limit as Q11 — a county document, not a Town one, and it is written for services generally rather than for PV. Recorded at 60 deliberately.

county code amendments adopted by reference checked 2026-09-13 https://discover.pbcgov.org/pzb/building/BuildingCodes/PBC-Amendments-to-the-Florida-Building-Code-8th-Edition-2023.pdf

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

No PV-specific structural PE threshold is published. What the Town does publish: site-built sheds require 'plans to be signed and sealed by a Florida Licensed Architect or Engineer'; play structures require plans 'designed and sealed by a registered engineer or architect' together with the method of attachment/anchoring (Sec. 125-291(b)(7)c); and Sec. 10-94 requires all drawings to 'bear the signature and address of the person responsible for the design' with no seal threshold. The governing standard is FBC-Residential 8th Ed. (2023) R324.4.1/R324.4.1.1/R324.4.1.2 — the array must be designed for gravity loads per Chapter 3, the roof designed to support them per Chapter 8, and wind loads per ASCE 7.

Why the confidence is not higherTwo published Town seal triggers exist and neither reaches rooftop PV, so the honest answer is 'no published threshold' rather than 'none required'. Deliberately at 62: the Building Official is contracted out and may impose a seal on a case-by-case basis with nothing published to constrain it.

published checklist checked 2026-09-13 https://www.townoflcs.gov/cds/page/checklists-common-projects

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

No local threshold. Statewide, FS 471.003(2)(h) exempts electrical work on a residential building from the PE requirement where the construction cost is $125,000 or less AND the electrical current is 600 amperes or less at 240 volts or less (800 amperes commercial). Nothing in the Town's code or on its pages sets a different or lower trigger — 'engineer' in the code corpus returns sign structures, towers, satellite-dish foundations, sheds and play structures only.

Why the confidence is not higherStatute is the operative instrument and the local absence was proved with controls; not higher because the statute text was read at leg.state.fl.us for 553.79/.791/.792 this run but 471.003 was not re-fetched, so the $125,000/600 A figures carry the Florida baseline's authority rather than this run's.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV3PECEOCIN_S10-94DRSP

Q15 What does a residential solar permit cost? Core Fees

Roughly $920-$950 on a $25,000 residential array, and the fee is dominated by the valuation percentage. Published Permit Fees page: minimum fee $90.00; 3% of $0-$100,000, plus 2% of $100,001-$200,000, plus 1% of valuation over $200,001. Plan review is charged ON TOP: 'New construction plan review fees are $350.00. Addition/remodel plan review fees are $150.00. These fees are added to the permit application fees.' Worked: $25,000 x 3% = $750 permit + $150 plan review (if a PV retrofit is read as 'remodel/addition') + state surcharge + a 3% credit-card convenience fee = approximately $923 before the card fee, ~$950 with it. *** THE TWO TOWN INSTRUMENTS DISAGREE ON THE SURCHARGE: adopted Resolution 2024-12 Exhibit A says 'State Surcharge 2.5% of permit fee'; the live Permit Fees page says 1.5% for the Building Code Administrators and Inspectors Fund PLUS 1.5% for enforcement of building codes, i.e. 3.0%. *** Re-inspection $75.00; revisions $40 residential with no cost change, or 3% of added cost + $40 with one; duplicate/replacement permit $25 + printing; change of contractor $100; starting work without a permit is four times the permit fee.

Why the confidence is not higherFigures are verbatim from the Town's own current Permit Fees page and from adopted Resolution 2024-12 (14 May 2024). Not higher for three reasons: (i) the two instruments give different surcharge totals; (ii) the schedule has no solar or PV line at all, so whether a rooftop array attracts the $150 'remodel/addition' plan review or none is unstated; (iii) the current fee instrument is Resolution 2025-07 (11 Mar 2025) and ITS PUBLISHED ATTACHMENT IS THE WRONG DOCUMENT — the Town's own resolutions index serves Resolution 2025-09 (League of Cities appointments) for it — so the newest adopted numbers cannot be read.

fee schedule checked 2026-09-13 https://www.townoflcs.gov/cds/page/permit-fees

Q16 How is the fee calculated? Core Fees

Valuation, tiered: 3% of the first $100,000 of job value, 2% of the next $100,000, 1% above $200,001, with a $90.00 minimum. 'Permit fees are based on the cost of the job.' Sec. 10-98(b)(3) lets the Building Official deny a permit where 'the valuation is underestimated on the application' unless the applicant produces a detailed cost estimate acceptable to him. *** This sits awkwardly against FS 553.79(1)(f), read first-hand this run: 'Inspection fees may not be based on the total cost of a project and may not exceed the actual inspection costs incurred by the local enforcement agency' — and Sec. 10-98(b)(5) provides for a minimum inspection fee set by resolution while the whole permit fee, inspections included, is priced off job cost. Flagged, not asserted as a violation.

Why the confidence is not higherVerbatim from the Town's own published schedule and the codified section.

fee schedule checked 2026-09-13 https://www.townoflcs.gov/cds/page/permit-fees

Q17 Is there a separate plan-check fee? Fees

Yes. $350.00 for new construction and $150.00 for an addition/remodel, 'added to the permit application fees'. A 'Major working drawing review fee' of $300.00 + $25.00 per page also exists and is expressly 'not applied to permit fee'. Note the codified Sec. 10-98(c) describes a different mechanism entirely — 'Fifty percent of the estimated permit fee must be paid upon filing the plan as a plan filing fee', credited against the permit fee if the permit issues within two months and forfeited if it does not — which the published flat plan-review fees have superseded in practice without the Code being conformed.

Why the confidence is not higherBoth figures verbatim from the Town's page and from Resolution 2024-12 Exhibit A. Not higher because neither instrument says which band a rooftop PV retrofit falls into.

adopted fee resolution (Res. 2024-12, 14 May 2024) checked 2026-09-13 https://www.townoflcs.gov/media/22566

Q18 What is the stated plan-review turnaround? Core Timeline & validity

The Town publishes no turnaround of its own. The statutory clock governs: FS 553.792(1)(a)1 — 5 business days for an electrical permit on an EXISTING single-family dwelling where the value of the work is less than $15,000; (a)2 — 30 business days otherwise where the structure is under 7,500 sq ft. Most residential PV jobs exceed $15,000, so the realistic answer is 30 business days. (1)(c) gives the Town 5 business days to say what is missing or the application is automatically deemed complete; (1)(e)-(g) reduce the permit fee by 10% per business day late, and by 20% per business day on a late revision cycle. *** THE TOWN HAS ADOPTED AN EXPEDITED PROCESS AND NOT PUBLISHED IT: Resolution 2025-08, 'Establishing an Expedited/Coordinated Building Approval Process for Qualified Projects', was adopted on consent 8 April 2025 (minutes, item 6.B) — but the PDF attached to it on the Town's own resolutions index is Resolution 2025-09, appointing League of Cities representatives. The text of the expedited policy is therefore unavailable, and FS 553.792(1)(d) requires a local government to maintain that policy on its website.

Why the confidence is not higherThe statute was read first-hand at leg.state.fl.us this run; the adoption of Res. 2025-08 is in the Town's own adopted minutes; the mis-attachment was verified by downloading the file the Town serves for it. Not higher because whether solar is a 'Qualified Project' under that unpublished resolution is unknown.

state statute checked 2026-09-13 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0500-0599/0553/Sections/0553.792.html

Q19 How long is an issued permit valid before it expires? Timeline & validity

Three layers that do not agree. Codified Sec. 125-34(d): a permit expires if work has not begun within six months of issuance, and again if the work is not substantially completed within one year, after which a 'special building permit' is needed. Statewide and later in time, FS 553.79(1)(c): 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later', and a local government may extend it. The Town has not conformed its ordinance or said which governs.

Why the confidence is not higherBoth texts read first-hand this run. Recorded as a conflict rather than resolved, because the Town publishes no expiration policy on any department page.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH125ZO_ARTIIAD_S125-34BUPE

Q20 Which permit portal does this authority use? Core Portal & process

MyGovernmentOnline (MGO Connect), at mgoconnect.org. The Building Permits page carries MGO's support numbers, 985.851.0760 and 866.957.3764, and the Welcome Packet sends both contractors and owner/builders to https://www.mgoconnect.org/auth/login to register and apply. The same portal handles documentation, status, inspection scheduling and payment. Town website is CivicPlus on Drupal; utility billing is a separate vendor.

Why the confidence is not higherNamed on two current Town instruments; the portal host resolves and is a login-gated Angular application.

portal landing page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q21 Can the whole application be completed online? Core Portal & process

Yes, and paper is refused: 'The Town uses an electronic permitting portal and does not accept paper permit applications. The portal allow applicants to complete the entire permitting process remotely - without the need to visit Town Hall in person. All communications regarding permit status, required documentation, inspection scheduling, and payments is handled through the electronic permitting portal.' Fees are due at submittal and 'can be paid through the MGO portal'. One carve-out: permits opened before the portal go on under the old process until closed out.

Why the confidence is not higherVerbatim from the Town's own current page.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q22 Which utility handles interconnection here? Core Utility interconnection

FLORIDA POWER & LIGHT (FPL), and it is the only electric seller in the Town. The Town's New Resident Welcome Packet, authored by the Town and created 21 May 2026, carries a who-to-call table with SPLIT ROWS BY FUNCTION: 'Electricity Provider - Florida Power & Light is the provider of electricity within the Town of Lake Clarke Shores'; 'Gas Provider - Florida Public Utilities is the provider of gas within the Town'; and water/wastewater split across THREE rows (the Town's own Utilities Department for about 700 homes, Palm Beach County Utilities, and the Village of Palm Springs Utilities). Exactly one electric row, no second seller. Corroborated Town-side twice more: the Community Development Services menu carries an 'FPL Report a Power Outage' item that redirects to fpl.com's outage landing page, and the Town's Storm Resources page lists 'FPL Power Tracker' and 'FPL Power Outage' under 'Report Power Outages and Service Updates'.

Why the confidence is not higherThe strongest rung available here and it is Town-authored and current. The lower rungs were all checked and are silent, which is why this is 93 and not 96: there is NO franchise appendix in the code (the Charter's franchise subsection was editorially deleted; 13 'franchise' hits, none a grant, and Ch. 117 refers only to 'the franchised utility' generically); the FY2025-26 adopted budget summary carries a single aggregate 'Franchise Fees $268,000' line with NO annotation column and no utility service tax line for electricity; there is no demolition-release table on the site; and THE COMPREHENSIVE PLAN IS NOT PUBLISHED AT ALL (Ordinance 2026-01 keeps copies 'available for public review... at Town Hall' and the fee schedule sells the Comprehensive Plan as a $100 book), so the Intergovernmental Coordination Element rung was unavailable. The ACFR principal-taxpayer schedule was not used, per the standing ban.

town publication (New Resident Welcome Packet) checked 2026-09-13 https://www.townoflcs.gov/media/27131

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Parallel, with the AHJ's sign-off feeding the utility and FPL holding the last gate. From FPL's filed Tier 1 Interconnection Agreement (Third Revised Sheet No. 9.050, effective 1 January 2026), read first-hand: Sec. 2.3 the customer files a completed application to start the process; Sec. 3.4 'The Customer agrees to provide Local Building Code Official inspection and certification of installation. The certification shall reflect that the local code official has inspected and certified that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications'; Sec. 3.5 at least 10 calendar days' notice before initially placing the equipment in service; Sec. 3.6 FPL executes the agreement within 30 calendar days of a completed application. FPL's ESS adds that 'It is highly recommended that customers obtain FPL's written interconnection approval prior to procuring any material.' The Town's permit is not conditioned on FPL approval in any published instrument.

Why the confidence is not higherVerbatim from FPL's filed tariff and its Electric Service Standards, both downloaded and extracted this run. Not higher because the Town publishes no sequencing statement of its own, so the ordering is inferred from the utility side only.

utility tariff checked 2026-09-13 https://www.fpl.com/rates/pdf/electric-tariff-section9.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No town-wide architectural review board and no codified association-consent rule — but HOA approval is an express submittal line on every checklist the Town publishes ('Homeowner's Association Approval (if applies)' on the driveway, fence and shed checklists), so where an association exists the Town will collect its approval. The zoning chapter has no consent rule: 'association' returns 12 hits across Chapter 125 and every one is a definition, a PUD documentation item, a zero-lot-line access easement, or a trade/standards body — none is an approval gate. FS 163.04(2)'s HOA-limiting language has NOT been re-enacted as a municipal restriction here: 'due south', '45 degrees' as an orientation and 'orientation' as a solar term all return nothing. The one discretionary aesthetic hook that does exist is Sec. 125-483: 'Exterior architectural features, design, and appearance of any building or structure within the town, including, but not limited to, color, shall be in conformity with good taste and shall not be of such inferior quality as to cause the nature of the local environment to materially depreciate in appearance and value.'

Why the confidence is not higherA clean negative on the code search with controls passing, against a positive on the Town's own checklists. Not higher because the checklists are for other trades and no Town document says whether a PV permit application triggers the HOA line.

published checklist checked 2026-09-13 https://www.townoflcs.gov/cds/page/checklists-common-projects

Q25 Is there a historic-district review? Overlays & special cases

No. There is no historic district, no historic preservation ordinance and no certificate-of-appropriateness process. Every 'historic' hit in 1,403,416 characters of code is either the flood chapter's FBC-derived definition of 'historic structure' and the matching variance and substantial-improvement carve-outs (Secs. 105-25, 105-57), an archaeological-resources clause in the site-plan article, or an editor's note.

Why the confidence is not higherProved absence with controls passing on the same corpus; qualified only by the codification date (Supplement 2, through Ordinance 2025-03 of 9 Dec 2025) and by the four uncodified ordinances since, none of which touches zoning: 2026-01 comprehensive plan/water supply, 2026-02 and 2026-05 charter, 2026-03 solid waste.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH105FL_ARTIIFLDAPR_DIV2DE_S105-57DE

Q26 Is a wind or windstorm certification required? Overlays & special cases

No separate Town windstorm certification. Wind resistance comes through the Florida Building Code and Florida Product Approval: FBC-R R324.4.1.2 requires rooftop PV panels, modules and their supports to be 'designed and installed for wind loads in accordance with ASCE 7', and Sec. 10-20 adopts the Palm Beach County amendments to the FBC, whose Figure 1609.3 material governs the wind-borne debris region. The only wind figure the Town itself prints is on the shed checklist: 'each must be designed to withstand the forces created by 140-mph wind'. Play structures 'must meet current windload requirements' (Sec. 125-291(b)(7)b).

Why the confidence is not higherThe Town's own 140 mph figure appears on a shed checklist only and is not tied to a code edition or a risk category, so it cannot be read as the design wind speed for a PV array; the county amendments' scoping note ('All of Unincorporated Palm Beach County is within the Wind-Borne Debris Region') is written for unincorporated areas, so whether Lake Clarke Shores sits in the WBDR is not settled by any document I read. Recorded at 70 for that reason.

published checklist checked 2026-09-13 https://www.townoflcs.gov/cds/page/checklists-common-projects

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Not for a rooftop array. Site plan review under Sec. 125-101 does not reach single-family residential alterations, and its fee ($3,500 plus Town engineer, Building Official, attorney 'and other related fees') never fires. The discretionary routes that do exist and could in principle be reached are the Zoning Board of Adjustment's special exception and variance powers (Secs. 125-68, 125-69; fee $475 single-family residential for either), which would only be needed if a ground mount fell foul of Sec. 125-293(1) or the setback/coverage limits. No Council approval step is published for any residential building permit.

Why the confidence is not higherNegative inference from the scope of the site-plan article and the absence of any council-approval step in the permit sections; the variance/special-exception route is real but conditional. Recorded at 75 because no Town document addresses solar directly, so a reviewer's classification decides it.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH125ZO_ARTIVSIPLRE_S125-101REAPRECEDI

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No cap in the Town's own instruments — proved. The cap is FPL's, and there are three of them, all in the filed Tier 1 agreement (Third Revised Sheet No. 9.050, effective 1 Jan 2026) Sec. 2.1: the Gross Power Rating (a) 'does not exceed 90% of the Customer's utility distribution service rating'; (b) 'is 10 kW AC or less'; and (c) 'has an AC generating capacity of less than 115% of the Customer's previous 12 months kilowatt-hour usage'. For inverter-based systems the AC rating is the installed DC nameplate x 0.85 (Sec. 1.1). Limb (c) is the one that catches people: it is independent of kW and will disqualify a new-build or low-usage household from Tier 1 no matter how small the array, so ask for 12 months of bills before sizing. Above 10 kW AC the job becomes Tier 2 (to 100 kW, $400 application fee) or Tier 3 (to 2 MW, $1,000).

Why the confidence is not higherVerbatim from FPL's filed tariff, downloaded and extracted this run; the local absence was proved on the full code corpus with controls passing.

utility tariff checked 2026-09-13 https://www.fpl.com/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? NEC (NFPA 70) 2020 edition, in force through the Florida Building Code, 8th Edition (2023), whose effective date is 31 December 2023. The Town's own codified adoption is out of date and should not be read as the answer: Sec. 10-19 names 'the Florida Building Code 5th Edition (2014)' (Ord. 15-08, 29 Sep 2015) but adopts it 'as may be amended from time to time by the state building commission', which carries it forward. The Town restates no NEC article: '705.10' returns two hits and both are FS 705.101 in the abandoned-vehicle definition; '690.', 'rapid shutdown' and the anchored token \bNEC\b all return zero; 'National Electrical Code' returns two hits, one in the sign-code definition and one in the waterways chapter requiring dock electrical service to conform to 'the current edition of the National Electrical Code'. 88% · adopting agency landing page
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023) — all volumes, effective statewide 31 December 2023. The Town's Code Requirements page says only 'The Town of Lake Clarke Shores follows the requirements of the Florida Building Code' and links to Florida Building Codes Online. Codified Sec. 10-19 still names the 5th Edition (2014) with a forward-carrying clause. 90% · department page
    • Which fire code edition is in force? Florida Fire Prevention Code, 8th Edition (2023), statewide — enforced here by Palm Beach County Fire Rescue, not by the Town. THE TOWN HAS NO FIRE CODE CHAPTER AT ALL: Chapter 22 'Emergency Services' is alarm systems and disasters only, and no adopting section for any fire code exists anywhere in the corpus. The Town's own page: 'The Town of Lake Clarke Shores is serviced for fire and rescue by Palm Beach County Fire Rescue.' The adopted fee schedule prices 'Fire and Safety inspections & re-inspections $55.00 per unit' under Police/Public Safety, which is a life-safety/occupancy inspection line, not a building plan-review line. 80% · department page
    • Are there local amendments to any of the above? Yes — and none of them is about solar. Three live local amendment instruments: (1) Sec. 10-24, administrative amendments adding FBC sections 104.10.1 (Building Official to coordinate with the Floodplain Administrator on requests to modify flood-resistant construction), 107.6.1 (affidavit-based permits may NOT extend to flood load and flood-resistant construction requirements) and 117.1 (flood variances per FS 553.73(5)); (2) Sec. 10-25, TECHNICAL amendments to FBC-Residential R322.2.1 and R322.3.2 — this is where the freeboard lives, see Q33; (3) Sec. 10-20, which adopts by reference 'the Local Technical Amendments to the state building code, as recommended by the county building code advisory board, which amendments are titled Palm Beach County Amendments to the Florida Building Code, 5th Edition (2014), and which amendments are on file in the town hall.' *** THAT REFERENCE IS FROZEN TWO CODE CYCLES BACK and the Town publishes neither document; the county's current instrument is the Palm Beach County Amendments to the Florida Building Code, 8th Edition (2023). *** I searched the current county document myself: 'electrical' 64 hits, fabricated term zzqqxvv 0, 'photovoltaic' 0, and all three 'solar' hits read individually are Solar Heat Gain Coefficient in an energy-inspection list and two renewable-energy limbs of the residential ERI compliance path — none is a PV regulation. Eight 'disconnect' hits, all unrelated (utility shut-off authority, demolition sequencing, unsafe- structure notices, and one 'Electrical exterior disconnect location' item that sits under Manufactured buildings/housing, not one- and two-family). 88% · adopting ordinance
    • What is the installation judged against? Against the Florida Building Code 8th Ed. (2023) — principally FBC-Residential R324 for the array itself and NFPA 70 (2020) for the wiring — plus the Palm Beach County FBC amendments adopted by Sec. 10-20, plus the Town's own two technical amendments, plus, in a flood hazard area, Town Code Chapter 105. FBC-R R324.3: 'Photovoltaic systems shall be designed and installed in accordance with Sections R324.3.1 through R324.7.1, NFPA 70 and the manufacturer's installation instructions.' R324.3.1: modules listed and labeled to UL 1703, inverters to UL 1741, grid-connected systems using inverters listed for utility interaction, mounting systems listed to UL 2703 installed per their listings. *** FREEBOARD IS BFE + 12 INCHES AND THE WORD 'FREEBOARD' NEVER APPEARS IN THE FLOOD CHAPTER. *** Code Sec. 10-25(1) amends R322.2.1 so that buildings in flood hazard areas 'shall have the lowest floors elevated to or above the base flood elevation plus one foot or the design flood elevation, whichever is higher' (coastal A zones the same; AO zones depth number plus one foot, minimum three feet; basements the same), and Sec. 10-25(2) amends R322.3.2 to BFE + 1 ft parallel / BFE + 2 ft perpendicular to wave approach in coastal high-hazard areas. The only two 'freeboard' hits in 1.4 M characters of code are a floating-dock decoy: 'The flotation shall be designed to provide a freeboard of more than six inches under a dead load plus live load of 60 pounds per square foot.' Sec. 105-119 adds a second, potentially higher design flood elevation basis — the GREATER of the FIRM BFE, the V-zone wave elevation, the AO depth, 'the 100-year inundation elevation established by SFWMD within specific sub-areas of the C-51 canal watershed pursuant to F.A.C. ch. 40E-41', or on-site 100-year three-day storage — and Sec. 105-20(f) provides that 'in the event of a conflict between this article and any other ordinances, the more restrictive shall govern.' 85% · adopting ordinance
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    • What ridge setback and access pathways are required? FBC-Residential 8th Ed. (2023) R324.6, unamended locally. R324.6.1: 'Not fewer than two pathways, on separate roof planes from lowest roof edge to ridge and not less than 36 inches wide, shall be provided on all buildings. Not fewer than one pathway shall be provided on the street or driveway side of the roof. For each roof plane with a photovoltaic array, a pathway not less than 36 inches wide shall be provided from the lowest roof edge to ridge on the same roof plane as the photovoltaic array, on an adjacent roof plane, or straddling the same and adjacent roof planes.' R324.6.2: an 18-inch clear setback both sides of a horizontal ridge where the array occupies not more than 33% of the plan-view roof area, 36 inches where it occupies more. R324.6.2.1: with an NFPA 13D / P2904 sprinkler system the 33% threshold becomes 66%. R324.6.2.2: no panels below an emergency escape and rescue opening, and a 36-inch pathway to it. Exceptions in R324.6: detached non-habitable structures; where the code official determines rooftop operations will not be employed; and roofs at 2:12 slope or less. The Town adds nothing — it has no fire chapter, and 'pathway', 'ridge setback' and 'access pathway' return nothing PV-related in its code. 80% · state building code
  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Yes — through NFPA 70. FBC-Residential R324.3 requires photovoltaic systems to be 'designed and installed in accordance with... NFPA 70', and the NEC edition in force in Florida is the 2020, so rapid shutdown is judged to NEC 2020 Art. 690.12. No local instrument restates or modifies it: 'rapid shutdown' returns zero across the Town's whole code corpus, zero on the Town's website search, and zero in the current Palm Beach County FBC amendments (controls passing in all three). 78% · state building code
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? FPL's placards, and only FPL's — the Town requires none of its own. FPL Electric Service Standards, Section XIII 'Distributed Generation' (section revision date 10-30-25, inside the manual stamped 5-19-26), item A.6 'Labeling', read first-hand by rendering pages 161-173 at 300 dpi and OCRing them because the section is garbled to pdftotext: 'All labels must be permanent and weatherproof/UV resistant placard with engraved letters. The customer is responsible for all labeling requirements. The following labels must be installed at the interconnecting meter can and the DER disconnect switch.' INTERCONNECTING METER CAN: 'WARNING / MULTI POWER SOURCES / ENTER SOURCES HERE / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. DER DISCONNECT SWITCH: 'GENERATION SYSTEM AC DISCONNECT / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. *** A.6 IS NOT TIER-SCOPED. *** Two items earlier, A.4 expressly is ('All tier 2 and tier 3 systems require an FPL approved visually open Distributed Energy Resource (DER) disconnect switch'), and the parallel labelling clauses in the SGIA section (B.6) and the V2X section (D.g) both say labels 'should' be permanent. A.6 says 'must'. So on a Tier 1 rooftop job with NO AC disconnect at all, the meter-can placard still lands. Add the FBC-R R324.3.1 listing labels (UL 1703 modules, UL 1741 inverters, UL 2703 mounting systems) and, if there is storage, the ESS XIII.C.1 battery placard. 88% · utility standards manual
    • Does the authority specify placard wording of its own? No. The Town specifies no placard wording of its own — there is no electrical chapter, no fire chapter and no PV provision anywhere in its code or on its website ('photovoltaic' 0 in 1.4 M characters of code and 0 results on the site search; the single 'solar' hit in the code is 'Marine grade solar lighting is acceptable' for dock safety lighting under Chapter 66 Waterways). All prescribed wording comes from FPL. 90% · ordinance
    • Does it specify letter height, colour or material? Material and durability only, and the specification is FPL's: 'permanent and weatherproof/UV resistant placard with engraved letters' (ESS XIII.A.6). FPL does NOT specify letter height or colour for the net-metering placards. The Town specifies nothing. 88% · utility standards manual
    • Is a site plan / facility map placard required, and what must it show? No local requirement — NEC 705.10 applies only through the state code. FBC-R R324.3 pulls in NFPA 70 wholesale, so the 2020 NEC's 705.10 plant/facility directory requirement rides in with it. The Town restates nothing: the only two '705.10' matches in its code are FS 705.101 in the abandoned-property definition and a state-law reference table row — the short-token trap, caught by reading both hits. 62% · state building code
    • Does the UTILITY specify placards beyond the AHJ's? Yes — three distinct utility signs, none of which any Town document mentions. (1) ESS XIII.A.6, above: the meter-can placard and the DER-disconnect placard, 'must', not tier-scoped. (2) FPL's filed Tier 1 agreement Sheet No. 9.051 Sec. 5.3: where FPL agrees the disconnect cannot practically sit adjacent to the meter socket and a different location is agreed, 'the customer shall install a permanent weather-proof plaque adjacent to FPL's meter socket indicating the location of the manual disconnect switch or switches.' This is the ONLY sign anywhere in tariff Section 9 — 'plaque' 3 hits, 'placard' 0 across the whole filed section. (3) ESS XIII.C.1, battery storage: 'A placard must be permanently affixed to the meter enclosure stating “Battery storage utilized in this facility.”' Battery equipment must be NRTL-certified to UL 1741, and non-certified storage 'must be DC coupled behind a UL 1741 listed device.' 92% · utility tariff
    • Where must the labels be placed? At the interconnecting meter can and at the DER disconnect switch (ESS XIII.A.6). Where a disconnect has been relocated by agreement, the weather-proof location plaque goes 'adjacent to FPL's meter socket' (tariff Sheet 9.051 Sec. 5.3). A battery-storage placard goes on the meter enclosure (ESS XIII.C.1). On a Tier 1 UL 1741 inverter-based system with no disconnect, the meter can is the only location. 92% · utility standards manual
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? On a normal Tier 1 residential job: NOWHERE — there is no AC disconnect to place, and there is no municipal rule to add one. Three independent instruments, all read first-hand this run: (1) FPL filed tariff Third Revised Sheet No. 9.050 / First Revised Sheet No. 9.051 Sec. 5.1: 'U.L.1741 Listed, inverter-based Tier 1 customer-owned renewable generation systems do not require a customer-installed manual disconnect switch.' (2) FPL ESS XIII.A.4: 'All tier 2 and tier 3 systems require an FPL approved visually open Distributed Energy Resource (DER) disconnect switch', and the standalone DER sheet at XIII: 7 of 13 says 'FPL requires a Distributed Energy Resource (DER) Disconnect Switch (on the AC side of the inverter) for all DER installations ranging from 10kW to 2MW.' (3) FPSC Rule 25-6.065(6)(a): 'Inverter-based Tier 1 customer-owned renewable generation systems shall be exempt from this requirement, unless the manual disconnect switch is installed at the investor-owned utility's expense.' *** TWO TRIGGERS PUT A SWITCH ON THE WALL ANYWAY, AND NEITHER IS TIER-SCOPED. *** ESS XIII.A.5: 'If the interconnection is performed on the line side of the customers main electrical panel (per NEC) a manual AC disconnect is required between AC generation output and the point of interconnection to FPL facilities.' And tariff Sec. 5.2 requires one for any Tier 1 system that is not UL 1741 inverter based. WHERE IT GOES WHEN IT IS REQUIRED: 'mounted separate from but adjacent to the FPL meter socket within 10 feet and must always remain accessible to FPL. Plans must show dimensions between the location of the meter socket and the DER disconnect switch. There shall be no locked gates, doors or fences between the meter socket and the DER disconnect switch' (ESS XIII.A.4). Switch spec: visible open with blades, jaws and air gap visible and not obscured by any dead-front or arc-shield; lockable in the open position; an FPL 3/8-inch padlock shank must fit the cover hasp and the switch may not be modified to accommodate an FPL lock; enclosure grounded; not usable as a raceway for anything but the switched phase conductors, neutral and equipment ground; blades de-energized when open per NEC 404.6(C). If FPL agrees to relocate it, tariff Sec. 5.3 requires the weather-proof location plaque adjacent to the meter socket. *** AND THE MUNICIPAL CHECK CAME BACK NEGATIVE: I grepped the entire 1,403,416-character Town code for 'disconnect' and found four hits, none an electrical ordinance (see Q34). Lake Clarke Shores has no outside- disconnect rule of its own, no ampacity floor, no height band and no distance-from-meter rule. 93% · utility tariff
    • Must equipment be on a specific approved list? Yes, on both sides. State code: FBC-R R324.3.1 requires modules listed and labeled to UL 1703, inverters to UL 1741, grid-connected systems to use inverters listed for utility interaction, and mounting systems listed to UL 2703 installed per their listings; roof and structural components additionally need Florida Product Approval. Utility: FPL ESS XIII.A.1 'The customer must utilize a certified UL 1741 SA and IEEE 1547 grid interactive inverter. Inverters that have not been certified to UL Standard will be denied interconnection', and the tariff Sec. 3.1 requires certification by a nationally recognized testing and certification laboratory to IEEE 1547, IEEE 1547.1 and UL 1741. (FPL's newer SGIA section prefers UL 1741 SB.) The Town maintains no list of its own. 80% · state building code
    • Are batteries permitted, and under what conditions? Permitted, under FPL's behind-the-meter policy; the Town's code is silent. FPL ESS XIII.C: storage 'must have a certification conducted by a Nationally Recognized Testing Laboratory (NRTL) to the current UL 1741 standard for safety. A placard must be permanently affixed to the meter enclosure stating “Battery storage utilized in this facility.” Battery storage that is not UL 1741 certified must be DC coupled behind a UL 1741 listed device.' C.2: where storage is integrated with customer-owned renewable generation, 'Energy stored by the battery is only for the customer's use... at this time the customer may not export power from the battery to the grid.' C.3: backup-only storage with no renewable system may charge from the grid and needs no interconnection agreement, but the customer must prevent back-feed. C.4: grid-charging, grid-interconnected storage must be notified to FPL, and 'Stand-alone battery storage systems are not included in the definition of “renewable energy” pursuant to Rule 25-6.065(2)(d), Florida Administrative Code, and the output from such systems is not net metered.' Town-side: 'battery' returns four hits in the code and 'energy storage' zero — none is an ESS provision. 82% · utility standards manual
    • Is a ground mount treated as a structure? Effectively yes, and the zoning route is the hard part of a ground mount here. Chapter 125 Division 2 lists the permitted accessory uses in the Single-Family Residential district exhaustively — 'Customary accessory uses; Swimming pools, located in rear yards only; Patios; Gazebos; Satellite television antenna systems; Detached sheds; Play structures' (Sec. 125-291(b)) — and Sec. 125-293(1) then closes the list: 'All uses other than those permitted or allowed as special exceptions are prohibited.' Solar is not named; the only residual limb is 'customary accessory uses', which is open but undefined, so a ground mount's lawfulness turns on a reviewer's reading of that phrase, with FS 163.04(1)'s bar on ordinances that 'prohibit or have the effect of prohibiting' solar collectors as the counter-argument. If it is an accessory structure it must clear front 25 ft / side 10 ft (7.5 ft on plats approved after 1 Jan 1980) / rear 15 ft setbacks (Sec. 125-295), count toward the 35% maximum lot coverage 'including accessory uses' (Sec. 125-297), and in a flood hazard area satisfy Sec. 105-94(a): anchored against flotation, built of flood damage-resistant materials, and with 'mechanical, plumbing, and electrical systems above the design flood elevation or meet the requirements of ASCE 24'. FBC-R R324.7.1 leaves ground-mount fire separation distance to 'the local jurisdiction', which has set none. *** The nearest codified analogue is a warning: the Town's only other regulated roof appurtenance, the satellite dish, is confined by Sec. 125-626 to 'rear yards only' and 'shall not be installed in front or side yards or on the roofs of houses', with Sec. 125-628 requiring it to be 'made as unobtrusive as possible'. That regime cannot lawfully be applied to solar (FS 163.04) but it is the template this Town's code supplies. 65% · ordinance
    • Is there a local rule on service upgrades or busbar sizing? No local rule — and the check that mattered here came back clean. THE TOWN HAS NO ELECTRICAL CHAPTER AND NO CODIFIED OUTSIDE-DISCONNECT ORDINANCE: I grepped the whole 1,403,416-character code corpus for 'disconnect' and got exactly four hits, none of them electrical-service rules — a recreational-vehicle 'quick-disconnect type utilities' definition, 'disconnected utilities' as evidence of vacancy in the vacant-property article, and Sec. 62-2, the water utility's authority to disconnect service for defective plumbing. No ampacity floor, no height band, no distance-from-meter rule, no lock requirement, no aluminium-wiring ban, no busbar or service- upgrade amendment. The only service-capacity limit that binds a job here is FPL's: Gross Power Rating must not exceed 90% of the utility distribution service rating (tariff Sheet 9.050 Sec. 2.1(a); ESS XIII.A.5 states it as 'Customer generation is limited to 90 percent of the FPL distribution service rating (Transformer)'). 80% · ordinance

20 questions answered against Town of Lake Clarke Shores’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

NEC (NFPA 70) 2020 edition, in force through the Florida Building Code, 8th Edition (2023), whose effective date is 31 December 2023. The Town's own codified adoption is out of date and should not be read as the answer: Sec. 10-19 names 'the Florida Building Code 5th Edition (2014)' (Ord. 15-08, 29 Sep 2015) but adopts it 'as may be amended from time to time by the state building commission', which carries it forward. The Town restates no NEC article: '705.10' returns two hits and both are FS 705.101 in the abandoned-vehicle definition; '690.', 'rapid shutdown' and the anchored token \bNEC\b all return zero; 'National Electrical Code' returns two hits, one in the sign-code definition and one in the waterways chapter requiring dock electrical service to conform to 'the current edition of the National Electrical Code'.

Why the confidence is not higherThe 8th Edition effective date was confirmed first-hand today on floridabuilding.org's own landing page: 'The Effective Date for the Florida Building Code, 8th Edition (2023), is December 31, 2023.' The NEC EDITION year is carried at 88 rather than 95 because FBC-R R324.3 and Chapter 27 cite 'NFPA 70' without repeating the year in the chapter text, and the referenced-standards table would not render to a fetch; the 2020 attribution rests on the Florida baseline's 70-run concordance and the NFPA enforcement map.

adopting agency landing page checked 2026-09-13 https://floridabuilding.org/c/default.aspx

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023) — all volumes, effective statewide 31 December 2023. The Town's Code Requirements page says only 'The Town of Lake Clarke Shores follows the requirements of the Florida Building Code' and links to Florida Building Codes Online. Codified Sec. 10-19 still names the 5th Edition (2014) with a forward-carrying clause.

Why the confidence is not higherState effective date confirmed first-hand on floridabuilding.org today; the Town's own page confirms it follows the state code without naming an edition. The 2014 reference in the Code is recorded as staleness, not as the answer.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/code-requirements

Q31 Which fire code edition is in force? Code editions in force

Florida Fire Prevention Code, 8th Edition (2023), statewide — enforced here by Palm Beach County Fire Rescue, not by the Town. THE TOWN HAS NO FIRE CODE CHAPTER AT ALL: Chapter 22 'Emergency Services' is alarm systems and disasters only, and no adopting section for any fire code exists anywhere in the corpus. The Town's own page: 'The Town of Lake Clarke Shores is serviced for fire and rescue by Palm Beach County Fire Rescue.' The adopted fee schedule prices 'Fire and Safety inspections & re-inspections $55.00 per unit' under Police/Public Safety, which is a life-safety/occupancy inspection line, not a building plan-review line.

Why the confidence is not higherThe absence of a fire chapter was proved on the full code corpus with controls; the service provider is named on the Town's own page. Not higher because no Town or county document I read says whether PBC Fire Rescue performs plan review on a single-family PV permit here — there is no PBC fire-review fee line on the Town's adopted schedule, which suggests it does not.

department page checked 2026-09-13 https://www.townoflcs.gov/police/page/fire-rescue-services

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes — and none of them is about solar. Three live local amendment instruments: (1) Sec. 10-24, administrative amendments adding FBC sections 104.10.1 (Building Official to coordinate with the Floodplain Administrator on requests to modify flood-resistant construction), 107.6.1 (affidavit-based permits may NOT extend to flood load and flood-resistant construction requirements) and 117.1 (flood variances per FS 553.73(5)); (2) Sec. 10-25, TECHNICAL amendments to FBC-Residential R322.2.1 and R322.3.2 — this is where the freeboard lives, see Q33; (3) Sec. 10-20, which adopts by reference 'the Local Technical Amendments to the state building code, as recommended by the county building code advisory board, which amendments are titled Palm Beach County Amendments to the Florida Building Code, 5th Edition (2014), and which amendments are on file in the town hall.' *** THAT REFERENCE IS FROZEN TWO CODE CYCLES BACK and the Town publishes neither document; the county's current instrument is the Palm Beach County Amendments to the Florida Building Code, 8th Edition (2023). *** I searched the current county document myself: 'electrical' 64 hits, fabricated term zzqqxvv 0, 'photovoltaic' 0, and all three 'solar' hits read individually are Solar Heat Gain Coefficient in an energy-inspection list and two renewable-energy limbs of the residential ERI compliance path — none is a PV regulation. Eight 'disconnect' hits, all unrelated (utility shut-off authority, demolition sequencing, unsafe- structure notices, and one 'Electrical exterior disconnect location' item that sits under Manufactured buildings/housing, not one- and two-family).

Why the confidence is not higherCodified text read in full and the county document downloaded and searched with controls this run. Note the prior Palm Beach County survey recorded 'solar' as 0 hits in the county amendments; it now returns 3, none of them PV — so the negative holds but the word count has moved, which is why each hit was read.

adopting ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV1GE_S10-20LOTEAMSTBUCOAD

Q33 What is the installation judged against? Core Electrical

Against the Florida Building Code 8th Ed. (2023) — principally FBC-Residential R324 for the array itself and NFPA 70 (2020) for the wiring — plus the Palm Beach County FBC amendments adopted by Sec. 10-20, plus the Town's own two technical amendments, plus, in a flood hazard area, Town Code Chapter 105. FBC-R R324.3: 'Photovoltaic systems shall be designed and installed in accordance with Sections R324.3.1 through R324.7.1, NFPA 70 and the manufacturer's installation instructions.' R324.3.1: modules listed and labeled to UL 1703, inverters to UL 1741, grid-connected systems using inverters listed for utility interaction, mounting systems listed to UL 2703 installed per their listings. *** FREEBOARD IS BFE + 12 INCHES AND THE WORD 'FREEBOARD' NEVER APPEARS IN THE FLOOD CHAPTER. *** Code Sec. 10-25(1) amends R322.2.1 so that buildings in flood hazard areas 'shall have the lowest floors elevated to or above the base flood elevation plus one foot or the design flood elevation, whichever is higher' (coastal A zones the same; AO zones depth number plus one foot, minimum three feet; basements the same), and Sec. 10-25(2) amends R322.3.2 to BFE + 1 ft parallel / BFE + 2 ft perpendicular to wave approach in coastal high-hazard areas. The only two 'freeboard' hits in 1.4 M characters of code are a floating-dock decoy: 'The flotation shall be designed to provide a freeboard of more than six inches under a dead load plus live load of 60 pounds per square foot.' Sec. 105-119 adds a second, potentially higher design flood elevation basis — the GREATER of the FIRM BFE, the V-zone wave elevation, the AO depth, 'the 100-year inundation elevation established by SFWMD within specific sub-areas of the C-51 canal watershed pursuant to F.A.C. ch. 40E-41', or on-site 100-year three-day storage — and Sec. 105-20(f) provides that 'in the event of a conflict between this article and any other ordinances, the more restrictive shall govern.'

Why the confidence is not higherEvery quoted sentence read first-hand: FBC-R R324 text from the current Florida code, the two Town technical amendments from the codified text, the freeboard decoy read in full. Not higher because the Town publishes no PV installation standard of its own and the county amendments in force are only identifiable by inference (the codified reference names the 2014 edition).

adopting ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV1GE_S10-25TEAMSTBUCO

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

No local rule — and the check that mattered here came back clean. THE TOWN HAS NO ELECTRICAL CHAPTER AND NO CODIFIED OUTSIDE-DISCONNECT ORDINANCE: I grepped the whole 1,403,416-character code corpus for 'disconnect' and got exactly four hits, none of them electrical-service rules — a recreational-vehicle 'quick-disconnect type utilities' definition, 'disconnected utilities' as evidence of vacancy in the vacant-property article, and Sec. 62-2, the water utility's authority to disconnect service for defective plumbing. No ampacity floor, no height band, no distance-from-meter rule, no lock requirement, no aluminium-wiring ban, no busbar or service- upgrade amendment. The only service-capacity limit that binds a job here is FPL's: Gross Power Rating must not exceed 90% of the utility distribution service rating (tariff Sheet 9.050 Sec. 2.1(a); ESS XIII.A.5 states it as 'Customer generation is limited to 90 percent of the FPL distribution service rating (Transformer)').

Why the confidence is not higherA proved absence on a controlled corpus, paired with a positive utility rule read first-hand. Recorded at 80 rather than higher because the Town's building function is contracted out and the vendor may apply county amendments the Town has not published.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH62UT_ARTIINGE_S62-2AUUTDEDI

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Nothing published by this authority.

Where we lookedSearched the whole 1,403,416-character codified corpus (Municode clientId 8899 / productId 12818 / jobId 489787, 1,252 documents harvested serially) for mounting, attachment, anchor, fastener, spacing, standoff, rack and ballast in a PV sense, with controls passing (electrical 60, 'building permit' 79, flood 404, zzqqxvv 0); read Chapter 10 Article II in full and both technical-amendment sections (Secs. 10-24, 10-25), which amend only the flood provisions; read the whole of the Town's Checklists for Common Projects page (driveway, fence, irrigation, shed only); searched the Town's Drupal site search for solar, photovoltaic and SolarAPP (0 results each against 42 for electrical and 42 for flood); and searched the current Palm Beach County Amendments to the Florida Building Code, 8th Edition (2023), which the Town adopts by reference at Sec. 10-20 (photovoltaic 0, zzqqxvv 0, all three 'solar' hits read individually and none is a PV rule). No Town or county mounting or attachment-spacing requirement exists; FBC-R R324.4.1 and R324.4.1.2 (structural per Chapters 3 and 8, wind per ASCE 7) and the UL 2703 listing requirement in R324.3.1 are the only standards that bind.

https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV1GE_S10-25TEAMSTBUCO

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

FBC-Residential 8th Ed. (2023) R324.6, unamended locally. R324.6.1: 'Not fewer than two pathways, on separate roof planes from lowest roof edge to ridge and not less than 36 inches wide, shall be provided on all buildings. Not fewer than one pathway shall be provided on the street or driveway side of the roof. For each roof plane with a photovoltaic array, a pathway not less than 36 inches wide shall be provided from the lowest roof edge to ridge on the same roof plane as the photovoltaic array, on an adjacent roof plane, or straddling the same and adjacent roof planes.' R324.6.2: an 18-inch clear setback both sides of a horizontal ridge where the array occupies not more than 33% of the plan-view roof area, 36 inches where it occupies more. R324.6.2.1: with an NFPA 13D / P2904 sprinkler system the 33% threshold becomes 66%. R324.6.2.2: no panels below an emergency escape and rescue opening, and a 36-inch pathway to it. Exceptions in R324.6: detached non-habitable structures; where the code official determines rooftop operations will not be employed; and roofs at 2:12 slope or less. The Town adds nothing — it has no fire chapter, and 'pathway', 'ridge setback' and 'access pathway' return nothing PV-related in its code.

Why the confidence is not higherThe code text was read first-hand from the current Florida residential code; the local absence was proved with controls on the Town corpus and re-proved on the current county amendments. Not higher because the second exception hands the decision to the code official — who here is a contracted vendor publishing nothing — so local practice on the 'rooftop operations' exception is unknown.

state building code checked 2026-09-13 https://up.codes/viewer/florida/fl-residential-code-2023/chapter/3/building-planning#R324

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Yes — through NFPA 70. FBC-Residential R324.3 requires photovoltaic systems to be 'designed and installed in accordance with... NFPA 70', and the NEC edition in force in Florida is the 2020, so rapid shutdown is judged to NEC 2020 Art. 690.12. No local instrument restates or modifies it: 'rapid shutdown' returns zero across the Town's whole code corpus, zero on the Town's website search, and zero in the current Palm Beach County FBC amendments (controls passing in all three).

Why the confidence is not higherThe FBC-R referral was read first-hand; the local absence is proved three ways. Carried at 78, not higher, because the NEC EDITION year is itself at 88 (see Q29) and 690.12's content differs materially between the 2017 and 2020 editions.

state building code checked 2026-09-13 https://up.codes/viewer/florida/fl-residential-code-2023/chapter/3/building-planning#R324

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

FPL's placards, and only FPL's — the Town requires none of its own. FPL Electric Service Standards, Section XIII 'Distributed Generation' (section revision date 10-30-25, inside the manual stamped 5-19-26), item A.6 'Labeling', read first-hand by rendering pages 161-173 at 300 dpi and OCRing them because the section is garbled to pdftotext: 'All labels must be permanent and weatherproof/UV resistant placard with engraved letters. The customer is responsible for all labeling requirements. The following labels must be installed at the interconnecting meter can and the DER disconnect switch.' INTERCONNECTING METER CAN: 'WARNING / MULTI POWER SOURCES / ENTER SOURCES HERE / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. DER DISCONNECT SWITCH: 'GENERATION SYSTEM AC DISCONNECT / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. *** A.6 IS NOT TIER-SCOPED. *** Two items earlier, A.4 expressly is ('All tier 2 and tier 3 systems require an FPL approved visually open Distributed Energy Resource (DER) disconnect switch'), and the parallel labelling clauses in the SGIA section (B.6) and the V2X section (D.g) both say labels 'should' be permanent. A.6 says 'must'. So on a Tier 1 rooftop job with NO AC disconnect at all, the meter-can placard still lands. Add the FBC-R R324.3.1 listing labels (UL 1703 modules, UL 1741 inverters, UL 2703 mounting systems) and, if there is storage, the ESS XIII.C.1 battery placard.

Why the confidence is not higherOCR of FPL's own current manual, fifth independent confirmation of A.6 in this survey and the first from this edition of the file. Not higher because the text is OCR-recovered rather than machine-extracted, and because the '** AMPS' / '** VOLTS' placeholders mean the wording is a template FPL expects to be completed.

utility standards manual checked 2026-09-13 https://www.fpl.com/content/dam/fplgp/us/en/partner/pdf/electric-service-standards.pdf

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No. The Town specifies no placard wording of its own — there is no electrical chapter, no fire chapter and no PV provision anywhere in its code or on its website ('photovoltaic' 0 in 1.4 M characters of code and 0 results on the site search; the single 'solar' hit in the code is 'Marine grade solar lighting is acceptable' for dock safety lighting under Chapter 66 Waterways). All prescribed wording comes from FPL.

Why the confidence is not higherProved absence with positive and fabricated controls on two independent search surfaces (the Municode content API over the whole corpus, and the Town's Drupal site search). townoflcs.gov sits behind a Cloudflare managed challenge that 403s plain curl and WebFetch on every dynamic path; all Town pages here were retrieved with curl_cffi impersonating Chrome, which passes. Town site search controls: electrical 42 results, flood 42, solar 5, demolition 10; photovoltaic / freeboard / SolarAPP / 163.04 / zzqqxvv all 0 results returning the same ~55.5 KB empty-result page.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH66WA

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Material and durability only, and the specification is FPL's: 'permanent and weatherproof/UV resistant placard with engraved letters' (ESS XIII.A.6). FPL does NOT specify letter height or colour for the net-metering placards. The Town specifies nothing.

Why the confidence is not higherVerbatim from the OCR'd ESS section; the absence of any height/colour limb was checked across all of Section XIII (11 'label' occurrences and 4 'placard' occurrences read).

utility standards manual checked 2026-09-13 https://www.fpl.com/content/dam/fplgp/us/en/partner/pdf/electric-service-standards.pdf

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

No local requirement — NEC 705.10 applies only through the state code. FBC-R R324.3 pulls in NFPA 70 wholesale, so the 2020 NEC's 705.10 plant/facility directory requirement rides in with it. The Town restates nothing: the only two '705.10' matches in its code are FS 705.101 in the abandoned-property definition and a state-law reference table row — the short-token trap, caught by reading both hits.

Why the confidence is not higherThe local absence is proved; the positive limb is an inference from the FBC's blanket NFPA 70 referral rather than from any document that names 705.10, and the NEC edition year is itself at 88. Recorded at 62 deliberately.

state building code checked 2026-09-13 https://up.codes/viewer/florida/fl-residential-code-2023/chapter/3/building-planning#R324

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes — three distinct utility signs, none of which any Town document mentions. (1) ESS XIII.A.6, above: the meter-can placard and the DER-disconnect placard, 'must', not tier-scoped. (2) FPL's filed Tier 1 agreement Sheet No. 9.051 Sec. 5.3: where FPL agrees the disconnect cannot practically sit adjacent to the meter socket and a different location is agreed, 'the customer shall install a permanent weather-proof plaque adjacent to FPL's meter socket indicating the location of the manual disconnect switch or switches.' This is the ONLY sign anywhere in tariff Section 9 — 'plaque' 3 hits, 'placard' 0 across the whole filed section. (3) ESS XIII.C.1, battery storage: 'A placard must be permanently affixed to the meter enclosure stating “Battery storage utilized in this facility.”' Battery equipment must be NRTL-certified to UL 1741, and non-certified storage 'must be DC coupled behind a UL 1741 listed device.'

Why the confidence is not higherAll three read first-hand this run — two by OCR of the ESS, one by clean text extraction of the filed tariff, with the placard/plaque counts run over the whole tariff section as a control.

utility tariff checked 2026-09-13 https://www.fpl.com/rates/pdf/electric-tariff-section9.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the interconnecting meter can and at the DER disconnect switch (ESS XIII.A.6). Where a disconnect has been relocated by agreement, the weather-proof location plaque goes 'adjacent to FPL's meter socket' (tariff Sheet 9.051 Sec. 5.3). A battery-storage placard goes on the meter enclosure (ESS XIII.C.1). On a Tier 1 UL 1741 inverter-based system with no disconnect, the meter can is the only location.

Why the confidence is not higherSame first-hand sources as Q42; the locations are stated in the operative sentences themselves.

utility standards manual checked 2026-09-13 https://www.fpl.com/content/dam/fplgp/us/en/partner/pdf/electric-service-standards.pdf

Q44 Must equipment be on a specific approved list? Equipment listing

Yes, on both sides. State code: FBC-R R324.3.1 requires modules listed and labeled to UL 1703, inverters to UL 1741, grid-connected systems to use inverters listed for utility interaction, and mounting systems listed to UL 2703 installed per their listings; roof and structural components additionally need Florida Product Approval. Utility: FPL ESS XIII.A.1 'The customer must utilize a certified UL 1741 SA and IEEE 1547 grid interactive inverter. Inverters that have not been certified to UL Standard will be denied interconnection', and the tariff Sec. 3.1 requires certification by a nationally recognized testing and certification laboratory to IEEE 1547, IEEE 1547.1 and UL 1741. (FPL's newer SGIA section prefers UL 1741 SB.) The Town maintains no list of its own.

Why the confidence is not higherBoth limbs read first-hand. Not higher because the Town itself publishes nothing, and because FPL's two sections name different UL 1741 supplements (SA in the net-metering section, 'SB Preferred' in the SGIA section) without saying which governs a Tier 1 residential job.

state building code checked 2026-09-13 https://up.codes/viewer/florida/fl-residential-code-2023/chapter/3/building-planning#R324

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Permitted, under FPL's behind-the-meter policy; the Town's code is silent. FPL ESS XIII.C: storage 'must have a certification conducted by a Nationally Recognized Testing Laboratory (NRTL) to the current UL 1741 standard for safety. A placard must be permanently affixed to the meter enclosure stating “Battery storage utilized in this facility.” Battery storage that is not UL 1741 certified must be DC coupled behind a UL 1741 listed device.' C.2: where storage is integrated with customer-owned renewable generation, 'Energy stored by the battery is only for the customer's use... at this time the customer may not export power from the battery to the grid.' C.3: backup-only storage with no renewable system may charge from the grid and needs no interconnection agreement, but the customer must prevent back-feed. C.4: grid-charging, grid-interconnected storage must be notified to FPL, and 'Stand-alone battery storage systems are not included in the definition of “renewable energy” pursuant to Rule 25-6.065(2)(d), Florida Administrative Code, and the output from such systems is not net metered.' Town-side: 'battery' returns four hits in the code and 'energy storage' zero — none is an ESS provision.

Why the confidence is not higherFPL's text is OCR-recovered from its own current manual; the local silence is proved with controls. Not higher because the fire side is unaddressed by any document that binds here — the Town has no fire chapter and no FFPC/NFPA 855 local amendment was found.

utility standards manual checked 2026-09-13 https://www.fpl.com/content/dam/fplgp/us/en/partner/pdf/electric-service-standards.pdf

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Nothing published by this authority.

Where we lookedSearched the full codified corpus for battery, batteries, 'energy storage', ESS, 'storage system' and lithium: 'battery' returns 4 hits (a police emergency backup context, alarm-system power, and two unrelated), 'energy storage' returns 0, with controls passing. Read the Town's whole Permit Fees page and adopted Resolution 2024-12 Exhibits A and B line by line — no ESS, battery or storage fee line exists. Read the Checklists for Common Projects page in full — no ESS checklist. Ran the Town site search for 'battery' (10 results, all disaster-kit, recycling-event, police-report and meeting-index pages) and 'storage' (10 results, all code-enforcement open-storage and meeting-index pages). The Town has no fire code chapter at all (Chapter 22 is alarms and disasters), so there is no local NFPA 855 amendment either. Storage is therefore permitted under the same combined building permit as the array, with FPL's ESS XIII.C policy the only instrument that adds conditions. Whether the contracted Building Official requires a separate ESS inspection is not published anywhere.

https://www.townoflcs.gov/cds/page/permit-fees

Q47 Is a ground mount treated as a structure? Core Ground mount

Effectively yes, and the zoning route is the hard part of a ground mount here. Chapter 125 Division 2 lists the permitted accessory uses in the Single-Family Residential district exhaustively — 'Customary accessory uses; Swimming pools, located in rear yards only; Patios; Gazebos; Satellite television antenna systems; Detached sheds; Play structures' (Sec. 125-291(b)) — and Sec. 125-293(1) then closes the list: 'All uses other than those permitted or allowed as special exceptions are prohibited.' Solar is not named; the only residual limb is 'customary accessory uses', which is open but undefined, so a ground mount's lawfulness turns on a reviewer's reading of that phrase, with FS 163.04(1)'s bar on ordinances that 'prohibit or have the effect of prohibiting' solar collectors as the counter-argument. If it is an accessory structure it must clear front 25 ft / side 10 ft (7.5 ft on plats approved after 1 Jan 1980) / rear 15 ft setbacks (Sec. 125-295), count toward the 35% maximum lot coverage 'including accessory uses' (Sec. 125-297), and in a flood hazard area satisfy Sec. 105-94(a): anchored against flotation, built of flood damage-resistant materials, and with 'mechanical, plumbing, and electrical systems above the design flood elevation or meet the requirements of ASCE 24'. FBC-R R324.7.1 leaves ground-mount fire separation distance to 'the local jurisdiction', which has set none. *** The nearest codified analogue is a warning: the Town's only other regulated roof appurtenance, the satellite dish, is confined by Sec. 125-626 to 'rear yards only' and 'shall not be installed in front or side yards or on the roofs of houses', with Sec. 125-628 requiring it to be 'made as unobtrusive as possible'. That regime cannot lawfully be applied to solar (FS 163.04) but it is the template this Town's code supplies.

Why the confidence is not higherEvery quoted provision read first-hand, but the classification question itself is unwritten: no Town document says whether a ground-mounted array is a 'customary accessory use'. Recorded at 65 because the closed-list clause and the open residual limb point in opposite directions and no local determination is published either way.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH125ZO_ARTVIDI_DIV2SIMIRESFDI_S125-291PEPRACUSST

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

On a normal Tier 1 residential job: NOWHERE — there is no AC disconnect to place, and there is no municipal rule to add one. Three independent instruments, all read first-hand this run: (1) FPL filed tariff Third Revised Sheet No. 9.050 / First Revised Sheet No. 9.051 Sec. 5.1: 'U.L.1741 Listed, inverter-based Tier 1 customer-owned renewable generation systems do not require a customer-installed manual disconnect switch.' (2) FPL ESS XIII.A.4: 'All tier 2 and tier 3 systems require an FPL approved visually open Distributed Energy Resource (DER) disconnect switch', and the standalone DER sheet at XIII: 7 of 13 says 'FPL requires a Distributed Energy Resource (DER) Disconnect Switch (on the AC side of the inverter) for all DER installations ranging from 10kW to 2MW.' (3) FPSC Rule 25-6.065(6)(a): 'Inverter-based Tier 1 customer-owned renewable generation systems shall be exempt from this requirement, unless the manual disconnect switch is installed at the investor-owned utility's expense.' *** TWO TRIGGERS PUT A SWITCH ON THE WALL ANYWAY, AND NEITHER IS TIER-SCOPED. *** ESS XIII.A.5: 'If the interconnection is performed on the line side of the customers main electrical panel (per NEC) a manual AC disconnect is required between AC generation output and the point of interconnection to FPL facilities.' And tariff Sec. 5.2 requires one for any Tier 1 system that is not UL 1741 inverter based. WHERE IT GOES WHEN IT IS REQUIRED: 'mounted separate from but adjacent to the FPL meter socket within 10 feet and must always remain accessible to FPL. Plans must show dimensions between the location of the meter socket and the DER disconnect switch. There shall be no locked gates, doors or fences between the meter socket and the DER disconnect switch' (ESS XIII.A.4). Switch spec: visible open with blades, jaws and air gap visible and not obscured by any dead-front or arc-shield; lockable in the open position; an FPL 3/8-inch padlock shank must fit the cover hasp and the switch may not be modified to accommodate an FPL lock; enclosure grounded; not usable as a raceway for anything but the switched phase conductors, neutral and equipment ground; blades de-energized when open per NEC 404.6(C). If FPL agrees to relocate it, tariff Sec. 5.3 requires the weather-proof location plaque adjacent to the meter socket. *** AND THE MUNICIPAL CHECK CAME BACK NEGATIVE: I grepped the entire 1,403,416-character Town code for 'disconnect' and found four hits, none an electrical ordinance (see Q34). Lake Clarke Shores has no outside- disconnect rule of its own, no ampacity floor, no height band and no distance-from-meter rule.

Why the confidence is not higherThree independent primary sources agreeing, all fetched and extracted in this run, plus a controlled negative on the whole municipal corpus. Not 96 because the line-side/load-side tap point is decided on the job, and because a contracted Building Official may still ask for a disconnect with nothing published to prevent it.

utility tariff checked 2026-09-13 https://www.fpl.com/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal. Inspections are requested through MGO Connect: 'All communications regarding permit status, required documentation, inspection scheduling, and payments is handled through the electronic permitting portal.' Town Hall is on (561) 964-1515 for the Building Department, 8am-4pm Monday to Friday, and residents and contractors 'who have appointments with the Community Development Department will have priority over people without appointments'. 90% · department page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes. The Town performs its own inspections — through its contracted Building Official and inspection provider rather than through another government. Its FY2025 Building Permit and Inspection Utilization Report, filed under FS 553.80(7)(b), records 470 building permit applications submitted, 430 permits issued, 1,040 inspections and re-inspections conducted, of which 2 were conducted by a private provider and 0 audits of private-provider inspections were performed, with 4 personnel dedicated to enforcing the Florida Code, issuing permits and conducting inspections. Direct and indirect costs $250,212.02 against fee revenue of $192,456.57 — a $57,755.45 shortfall for the year. The Town publishes these reports for FY2021 through FY2025. 90% · FS 553.80(7)(b) utilization report
    • If delegated, to whom? Not delegated to another government — contracted to a private firm. Diversified Building Department Management has held the Building Official, plan review and inspection services contract since 1 November 2024, replacing Hy-Byrd Inspections, which had held it since at least 2019. Six firms responded to the RFP and were evaluated on 27 September 2024. The compensation model changed with the contract: from hourly to a percentage basis, negotiated 'down 5% on two tiers'. The Town remains the legal AHJ and the permit issuer. Separately, FS 553.791 lets an owner elect a registered private provider on a single job, and PV is now expressly single-trade work under FS 553.791(1)(r) — see Q57 for what the Town publishes about that (nothing). 88% · town manager's report (Nov 2024)
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? Not published for PV. What the Town does say, generally: 'The required inspections are listed on the permit and must be passed in sequence before proceeding to the next phase of construction... A final inspection is required for all permits to ensure the project has been completed in full compliance with applicable codes and standards.' Its published per-trade checklists use a rough-then-final pattern (irrigation: 'Request a rough inspection once all pipes have been installed (before covering); request a final inspection after completion'). Sec. 10-97 adds that the Building Official inspects 'from time to time' during construction, may issue an immediate cease and desist order on any deviation from approved plans, and must make a final inspection and write a final inspection notice. 60% · department page
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? No. The Town publishes checklists for exactly four project types — Driveway, Fence, Irrigation and Shed — and no inspection checklist of any kind. There is no solar, PV, electrical or ESS checklist, no solar permit application, and no solar page. Controls: the Town's site search returns 5 results for 'solar' (a 2021 legislative-watch page, two manager's-report index pages and two meeting index pages, none regulatory), 0 for 'photovoltaic', 0 for 'SolarAPP', 0 for 'freeboard' and 0 for the fabricated 'zzqqxvv', against 42 for 'electrical' and 42 for 'flood'. *** SolarAPP+ IS NOT USED HERE *** despite Palm Beach County running it — third Palm Beach municipality in this survey to permit for itself and not take the county programme. 88% · published checklist
    • What must be on site at inspection? The permit itself, posted on site, and the approved plans. Building Permits page: 'A building permit must be obtained and posted on-site before starting any type of construction work.' Sec. 125-34(c): 'The approved copy of the plans shall remain on the job site available to the building official.' Sec. 10-22 additionally requires a temporary sanitary facility on site for workers, on pain of permit suspension or revocation. 88% · ordinance
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? A passed final inspection. 'A final inspection is required for all permits to ensure the project has been completed in full compliance with applicable codes and standards.' Sec. 10-97 requires the Building Official to make the final inspection and write 'a written final inspection notice' before any certificate of occupancy issues. A PV retrofit produces no certificate of occupancy, but Sec. 125-35(c) requires a certificate of zoning compliance to have been applied for before the permit issued and to be 'issued in conformity with the provisions of this article upon completion of the work' — so on paper a zoning-compliance certificate closes the file alongside the final. The document FPL needs is the Sec. 3.4 certification that 'the local code official has inspected and certified that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications.' 65% · ordinance
    • Who notifies the utility for PTO? The installer/customer, not the AHJ. FPL's filed Tier 1 agreement puts the duty on the customer twice: Sec. 3.4 'The Customer agrees to provide Local Building Code Official inspection and certification of installation', and Sec. 3.5 'The Customer shall notify FPL at least ten (10) calendar days prior to initially placing Customer's equipment and protective apparatus in service and FPL shall have the right to have personnel present on the in-service date.' Sec. 3.6 obliges FPL to execute the agreement within 30 calendar days of a completed application. Nothing in any Town instrument commits the Town to notifying FPL. 88% · utility tariff
    • Is there a re-inspection fee? $75.00, flat — not an escalating ladder. Permit Fees page: 'When an inspection has failed and a new inspection is needed, a $75.00 charge will be applied.' The same figure appears on adopted Resolution 2024-12 Exhibit A ('Re-Inspection fees $75.00'). Worth knowing alongside it: FS 553.79(7)(a) gives a 10% refund of permit AND inspection fees where work fails an inspection and no written code-based reason is given within 5 business days. 92% · fee schedule
    • How are corrections issued and cleared? Through the portal, with work stopped until the correction is made. 'If an inspector identifies issues with materials or workmanship, the deficiencies must be corrected before work can continue', and all communication runs through MGO Connect. A failed inspection costs $75.00 to re-book. For plan-review corrections the statutory cycle applies: FS 553.792(1)(f)-(g) — the Town must state in writing why the application fails, the applicant has 10 business days to submit revisions, and the Town then has 10 business days to approve or deny or lose 20% of the permit fee per business day. 70% · department page

14 questions answered against Town of Lake Clarke Shores’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal. Inspections are requested through MGO Connect: 'All communications regarding permit status, required documentation, inspection scheduling, and payments is handled through the electronic permitting portal.' Town Hall is on (561) 964-1515 for the Building Department, 8am-4pm Monday to Friday, and residents and contractors 'who have appointments with the Community Development Department will have priority over people without appointments'.

Why the confidence is not higherVerbatim from the Town's own current page. Not higher because no Town document says whether phone or email requests are accepted as an alternative.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q50 How much notice is required? Core Booking & scheduling

Nothing published by this authority.

Where we lookedRead the Town's Building Permits page, its Community Development Services landing page, its Checklists page and its Permit Fees page in full — none states an inspection notice period or a booking cut-off time. Ran the Town site search for 'inspection' (10 results, all read: the CDS landing page, the vacation-rental life-safety inspection page, the Building Permits page, the Checklists page, a code-enforcement page and five meeting index pages; none gives a notice period). Probed the MGO Connect portal at mgoconnect.org (/auth/login, /cp/portal, /cp/search): every path returns the same 2,648-byte Angular shell with no public permit or inspection search, so the inspection-type catalogue and any cut-off rule are behind a login. This is a capability limit, not an absence: the Town uses the portal for all inspection scheduling and the rule almost certainly exists inside it. One call to the Building Department on (561) 964-1515 would close it.

https://www.townoflcs.gov/cds/page/building-permits

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Nothing published by this authority.

Where we lookedSame sources and same limit as Q50 — the Building Permits page, the CDS landing page, the Checklists page and the site search return nothing about AM/PM windows, same-day inspections or time slots, and the MGO Connect portal is login-gated (2,648-byte Angular shell on every public path). Unlike some neighbouring Palm Beach authorities, the Town publishes no inspector directory or direct contact numbers, so there is no secondary route to the scheduling practice.

https://www.mgoconnect.org/auth/login

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes. The Town performs its own inspections — through its contracted Building Official and inspection provider rather than through another government. Its FY2025 Building Permit and Inspection Utilization Report, filed under FS 553.80(7)(b), records 470 building permit applications submitted, 430 permits issued, 1,040 inspections and re-inspections conducted, of which 2 were conducted by a private provider and 0 audits of private-provider inspections were performed, with 4 personnel dedicated to enforcing the Florida Code, issuing permits and conducting inspections. Direct and indirect costs $250,212.02 against fee revenue of $192,456.57 — a $57,755.45 shortfall for the year. The Town publishes these reports for FY2021 through FY2025.

Why the confidence is not higherThe Town's own current statutory report, downloaded and read this run — an unusually complete series; most Florida authorities in this survey publish none or a stale one. Not higher because the report does not distinguish PV from other inspections, and the 'personnel dedicated' figure does not separate Town employees from the contracted vendor's staff.

FS 553.80(7)(b) utilization report checked 2026-09-13 https://www.townoflcs.gov/media/26291

Q53 If delegated, to whom? Core Who inspects

Not delegated to another government — contracted to a private firm. Diversified Building Department Management has held the Building Official, plan review and inspection services contract since 1 November 2024, replacing Hy-Byrd Inspections, which had held it since at least 2019. Six firms responded to the RFP and were evaluated on 27 September 2024. The compensation model changed with the contract: from hourly to a percentage basis, negotiated 'down 5% on two tiers'. The Town remains the legal AHJ and the permit issuer. Separately, FS 553.791 lets an owner elect a registered private provider on a single job, and PV is now expressly single-trade work under FS 553.791(1)(r) — see Q57 for what the Town publishes about that (nothing).

Why the confidence is not higherThe award, the predecessor, the date and the pricing model all come from the Town's own adopted minutes and the Town Manager's own report. Not higher because the executed contract is not published, so the division of duties between the vendor and Town staff cannot be stated precisely.

town manager's report (Nov 2024) checked 2026-09-13 https://www.townoflcs.gov/media/24201

Q54 Which inspections are required, and in what order? Core Stages & sequence

Not published for PV. What the Town does say, generally: 'The required inspections are listed on the permit and must be passed in sequence before proceeding to the next phase of construction... A final inspection is required for all permits to ensure the project has been completed in full compliance with applicable codes and standards.' Its published per-trade checklists use a rough-then-final pattern (irrigation: 'Request a rough inspection once all pipes have been installed (before covering); request a final inspection after completion'). Sec. 10-97 adds that the Building Official inspects 'from time to time' during construction, may issue an immediate cease and desist order on any deviation from approved plans, and must make a final inspection and write a final inspection notice.

Why the confidence is not higherA real answer from the Town's own words, but it does not name the PV sequence; the inspection-type catalogue lives inside the login-gated MGO portal, which returns a 2.6 KB Angular shell with no public permit or inspection search. Recorded at 60 deliberately. One call to the Building Department on (561) 964-1515 would close this.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedRead the Building Permits page ('The required inspections are listed on the permit and must be passed in sequence before proceeding to the next phase of construction'), the whole Checklists for Common Projects page (which gives rough-and-final for irrigation and footing/framing/final for sheds but has no PV, roofing or electrical checklist) and Sec. 10-97. Nothing states whether a rough-in, mid-roof or in-progress electrical inspection is required on a PV retrofit. Searched the code corpus for 'rough', 'mid-roof', 'rough-in' and 'concealed' with controls passing — no inspection-stage provision exists in the code, which contains no electrical chapter at all. Bounded by the login-gated MGO portal, which holds the inspection-type list.

https://www.townoflcs.gov/cds/page/checklists-common-projects

Q56 Does the inspector verify labels and listings? Core What is checked

Nothing published by this authority.

Where we lookedNo Town document states what an inspector checks. Read the Building Permits page (which describes inspections generically — 'Inspections are conducted at various stages of the project to verify that installations are performed correctly and that appropriate materials are used'), Sec. 10-97, the Checklists page and the whole FY2021-FY2025 series of FS 553.80(7)(b) utilization reports, none of which describes inspection scope. There is no published inspection checklist (see Q57) and no electrical chapter in the code. Two indirect pressures exist and are worth stating without treating them as an answer: FPL's filed tariff Sec. 3.4 requires the customer to obtain a certification that 'the local code official has inspected and certified that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications', and FBC-R R324.3.1 makes the UL 1703 / UL 1741 / UL 2703 listing labels a code requirement — but whether the contracted inspector verifies the FPL placards is not published. Bounded further by the fact that inspections are performed by Diversified Building Department Management under a contract the Town does not publish.

https://www.townoflcs.gov/cds/page/building-permits

Q57 Is there a published inspection checklist? Core What is checked

No. The Town publishes checklists for exactly four project types — Driveway, Fence, Irrigation and Shed — and no inspection checklist of any kind. There is no solar, PV, electrical or ESS checklist, no solar permit application, and no solar page. Controls: the Town's site search returns 5 results for 'solar' (a 2021 legislative-watch page, two manager's-report index pages and two meeting index pages, none regulatory), 0 for 'photovoltaic', 0 for 'SolarAPP', 0 for 'freeboard' and 0 for the fabricated 'zzqqxvv', against 42 for 'electrical' and 42 for 'flood'. *** SolarAPP+ IS NOT USED HERE *** despite Palm Beach County running it — third Palm Beach municipality in this survey to permit for itself and not take the county programme.

Why the confidence is not higherProved absence on two independent search surfaces with positive and fabricated controls passing on both. townoflcs.gov sits behind a Cloudflare managed challenge that 403s plain curl and WebFetch on every dynamic path; all Town pages here were retrieved with curl_cffi impersonating Chrome, which passes. Town site search controls: electrical 42 results, flood 42, solar 5, demolition 10; photovoltaic / freeboard / SolarAPP / 163.04 / zzqqxvv all 0 results returning the same ~55.5 KB empty-result page.

published checklist checked 2026-09-13 https://www.townoflcs.gov/cds/page/checklists-common-projects

Q58 What must be on site at inspection? Core Documents on site

The permit itself, posted on site, and the approved plans. Building Permits page: 'A building permit must be obtained and posted on-site before starting any type of construction work.' Sec. 125-34(c): 'The approved copy of the plans shall remain on the job site available to the building official.' Sec. 10-22 additionally requires a temporary sanitary facility on site for workers, on pain of permit suspension or revocation.

Why the confidence is not higherBoth requirements read first-hand — one from the Town's current page, one codified. Not higher because nothing addresses PV-specific paperwork such as equipment listings or the FPL interconnection approval.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH125ZO_ARTIIAD_S125-34BUPE

Q59 Is there a re-inspection fee? Corrections & re-inspection

$75.00, flat — not an escalating ladder. Permit Fees page: 'When an inspection has failed and a new inspection is needed, a $75.00 charge will be applied.' The same figure appears on adopted Resolution 2024-12 Exhibit A ('Re-Inspection fees $75.00'). Worth knowing alongside it: FS 553.79(7)(a) gives a 10% refund of permit AND inspection fees where work fails an inspection and no written code-based reason is given within 5 business days.

Why the confidence is not higherSame figure on two Town instruments, one of them the adopted resolution. Not higher because the current fee instrument is Resolution 2025-07 (11 Mar 2025), whose published attachment is the wrong document, so a 2025 change to this figure cannot be ruled out.

fee schedule checked 2026-09-13 https://www.townoflcs.gov/cds/page/permit-fees

Q60 How are corrections issued and cleared? Corrections & re-inspection

Through the portal, with work stopped until the correction is made. 'If an inspector identifies issues with materials or workmanship, the deficiencies must be corrected before work can continue', and all communication runs through MGO Connect. A failed inspection costs $75.00 to re-book. For plan-review corrections the statutory cycle applies: FS 553.792(1)(f)-(g) — the Town must state in writing why the application fails, the applicant has 10 business days to submit revisions, and the Town then has 10 business days to approve or deny or lose 20% of the permit fee per business day.

Why the confidence is not higherThe Town's own sentence plus the statutory cycle read first-hand; no Town document describes a correction notice format or a re-submittal route, and the portal is login-gated. Recorded at 70.

department page checked 2026-09-13 https://www.townoflcs.gov/cds/page/building-permits

Q61 What is issued on pass? Core Final sign-off & PTO

A passed final inspection. 'A final inspection is required for all permits to ensure the project has been completed in full compliance with applicable codes and standards.' Sec. 10-97 requires the Building Official to make the final inspection and write 'a written final inspection notice' before any certificate of occupancy issues. A PV retrofit produces no certificate of occupancy, but Sec. 125-35(c) requires a certificate of zoning compliance to have been applied for before the permit issued and to be 'issued in conformity with the provisions of this article upon completion of the work' — so on paper a zoning-compliance certificate closes the file alongside the final. The document FPL needs is the Sec. 3.4 certification that 'the local code official has inspected and certified that the installation was permitted, has been approved, and has met all electrical and mechanical qualifications.'

Why the confidence is not higherAssembled from three instruments, none of which describes what a PV job actually receives; the Town publishes no sign-off artefact. Recorded at 65.

ordinance checked 2026-09-13 https://library.municode.com/fl/lake_clarke_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH10BUBURE_ARTIICOST_DIV3PECEOCIN_S10-97IN

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

The installer/customer, not the AHJ. FPL's filed Tier 1 agreement puts the duty on the customer twice: Sec. 3.4 'The Customer agrees to provide Local Building Code Official inspection and certification of installation', and Sec. 3.5 'The Customer shall notify FPL at least ten (10) calendar days prior to initially placing Customer's equipment and protective apparatus in service and FPL shall have the right to have personnel present on the in-service date.' Sec. 3.6 obliges FPL to execute the agreement within 30 calendar days of a completed application. Nothing in any Town instrument commits the Town to notifying FPL.

Why the confidence is not higherVerbatim from the filed tariff, extracted this run; the local silence was checked across the code corpus and the department pages.

utility tariff checked 2026-09-13 https://www.fpl.com/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 90%

No. The Town specifies no placard wording of its own — there is no electrical chapter, no fire chapter and no PV provision anywhere in its code or on its website ('photovoltaic' 0 in 1.4 M characters of code and 0 results on the site search; the single 'solar' hit in the code is 'Marine grade solar lighting is acceptable' for dock safety lighting under Chapter 66 Waterways). All prescribed wording comes from FPL.

Size, colour & material 88%

Material and durability only, and the specification is FPL's: 'permanent and weatherproof/UV resistant placard with engraved letters' (ESS XIII.A.6). FPL does NOT specify letter height or colour for the net-metering placards. The Town specifies nothing.

Where they go 92%

At the interconnecting meter can and at the DER disconnect switch (ESS XIII.A.6). Where a disconnect has been relocated by agreement, the weather-proof location plaque goes 'adjacent to FPL's meter socket' (tariff Sheet 9.051 Sec. 5.3). A battery-storage placard goes on the meter enclosure (ESS XIII.C.1). On a Tier 1 UL 1741 inverter-based system with no disconnect, the meter can is the only location.

What the utility wants on top 92%

Yes — three distinct utility signs, none of which any Town document mentions. (1) ESS XIII.A.6, above: the meter-can placard and the DER-disconnect placard, 'must', not tier-scoped. (2) FPL's filed Tier 1 agreement Sheet No. 9.051 Sec. 5.3: where FPL agrees the disconnect cannot practically sit adjacent to the meter socket and a different location is agreed, 'the customer shall install a permanent weather-proof plaque adjacent to FPL's meter socket indicating the location of the manual disconnect switch or switches.' This is the ONLY sign anywhere in tariff Section 9 — 'plaque' 3 hits, 'placard' 0 across the whole filed section. (3) ESS XIII.C.1, battery storage: 'A placard must be permanently affixed to the meter enclosure stating “Battery storage utilized in this facility.”' Battery equipment must be NRTL-certified to UL 1741, and non-certified storage 'must be DC coupled behind a UL 1741 listed device.'

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Notes
Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://www.townoflcs.com/cds/page/building-permits
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
Town
County
Palm Beach County
Regions covered
Authority Contact
Building Department
Direct Phone
985.851.0760
Booking & Scheduling