Town of Palm Beach Shores

Town of Palm Beach Shores

Palm Beach County

Verified Aug. 5, 2026

Town of Palm Beach Shores is a town authority in the State of Florida, serving 1,330 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Town of Palm Beach Shores against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Town of Palm Beach Shores is the authority having jurisdiction 88% confidence
Holds
Building, electrical, plumbing, mechanical and zoning/site-plan permitting and inspection, performed by TOWN-EMPLOYED staff, not a contracted building-department-as-a-service vendor -- the opposite shape from the three other Palm Beach County towns already on file in this survey (Ocean Ridge, Hypoluxo, South Palm Beach), all of which buy their Building Official from Hy-Byrd Building Inspections. Town of Palm Beach Shores is independently listed on floridabuilding.org's 392-entry statewide register of issuing local governments ('Town of Palm Beach Shores', option value 2354, fetched live this run). The Town's own Building Department page names a Building Official (Jose Rodriguez) and a Building Department Clerk (Orlando Rodriguez) at the SAME phone number as the Town Hall switchboard (561-844-3457) -- the phone-match tell this survey uses to prove in-house staff, not a contracted number. The Town's FY2024 audited financial statements (Schedule of Departmental Expenditures, Budget to Actual, General Fund) show the Building Department's 'Personal services' line at $101,817 budget vs $107,327 ACTUAL spend -- REAL non-zero actual payroll, the inverse of the '$0.00 actual payroll against six-figure Professional Services' fingerprint that identified Ocean Ridge, Hypoluxo and South Palm Beach as bought-in-staff authorities. The same audit shows the Fire Department with its own real actual payroll ($572,894 budget / $578,309 actual Personal Services) and its own Fire Chief page -- Palm Beach Shores runs its own Fire Department too, unlike the PBCFR-delegated pattern seen elsewhere in this county in this survey. Tested and REJECTED this run: the single highest-yield lead in the standing brief (Hy-Byrd Building Inspections, which already staffs three other Palm Beach County towns) does NOT extend to Palm Beach Shores -- Hy-Byrd's own site (hybyrd.com, fetched live) lists zero mentions of Palm Beach Shores under either current or previous clients (though the site is itself stale, listing Hypoluxo only as a 'previous' client when other filed runs confirm Hy-Byrd currently staffs Hypoluxo -- so this is a weak negative, not a proof, and the finding rests on the Town's own payroll and staff-page evidence, not on Hy-Byrd's absence). This is the disconfirming case the brief warned to look for: a vendor pattern proven in three neighbouring towns does not generalize to a fourth.
Why not higher
Four independent town-side sources converge: (1) floridabuilding.org register presence (live fetch, value 2354); (2) the Town's own Building Department page naming an in-house Building Official and Clerk at the Town Hall's own switchboard number; (3) the FY2024 audited Schedule of Departmental Expenditures showing real, non-zero actual Building Department payroll ($107,327) alongside real Fire Department payroll ($578,309), the inverse of the bought-in-staff fingerprint found at every other Palm Beach County town checked in this survey; (4) the TIGERweb POP100 (1,330) exactly matches the briefed population, confirming the correct authority_id was researched (not South Palm Beach or Town of Palm Beach). Not scored higher because I did not independently obtain a personnel roster or FTE count beyond the two payroll lines, and did not confirm police staffing (the audit's Police function shows Operating Expenses + Debt Service with NO separate Personal Services line, which is a possible sign police is contracted out -- not confirmed this run and not part of the AHJ question, but flagged in extra_findings since it is the mirror-image data point).

https://www.floridabuilding.org/sc/sc_org_srch.aspx

Permit required
YES -- a rooftop PV system requires a permit under the Town's general electrical/building permit requirement.85%
Permit cost
Valuation-based, tiered by job value, per the Town's own 'Building Permit Fee Calculator' spreadsheet (revised at the August 2019 Commission Meeting): $30 flat for the first $1,000 of…85%
Plan review
The Town's OWN Code commits to issuing a single-family residential building permit within 30 WORKING days of application (Town Code Sec. 14-108, FBC Ch. 1 Sec.85%
Portal
My Government Online (MGO) -- mgoconnect.org -- named for inspection scheduling on both the Town's own Building Department page and its FAQ document.85%
Electrical code
NEC edition follows whatever the current Florida Building Code cycle incorporates via FBC Chapter 27 (electrical) -- Town Code Sec. 14-108 (FBC Ch. 1, Sec.70%
Booking an inspection
Portal -- inspections are scheduled through My Government Online (MGO), per the Town's own Building Department page and FAQ ('Please schedule inspections at My Government Online' / 'log in…85%
Permitting 5 steps · 28 questions

Whether a permit is needed — YES -- a rooftop PV system requires a permit under the Town's general electrical/building permit requirement. Q3 Electrical and building permits — Combined -- the Town's own Building Permit Application is a single form with 'Building', 'Electrical', 'Gas', 'Plumbing', 'Mechanical', Q4 Plan review — The Town's OWN Code commits to issuing a single-family residential building permit within 30 WORKING days of application (Town Code Sec. 14-108, FBC Ch. 1 Sec. Q18 Where you file — My Government Online (MGO) -- mgoconnect.org -- named for inspection scheduling on both the Town's own Building Department page and its FAQ document. Q20

Permit required
YES -- a rooftop PV system requires a permit under the Town's general electrical/building permit requirement.85% source
What it costs
Valuation-based, tiered by job value, per the Town's own 'Building Permit Fee Calculator' spreadsheet (revised at the August 2019 Commission Meeting): $30 flat for the first $1,000 of valuation;85% source
Plan review turnaround
The Town's OWN Code commits to issuing a single-family residential building permit within 30 WORKING days of application (Town Code Sec. 14-108, FBC Ch. 1 Sec.85% source
Key document
town department page + FY2024 audited financial statements cited by 6 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? YES 93% · statewide keyless registry, verified live this run
    • What does this authority permit itself, and what does it delegate? Building, electrical, plumbing, mechanical, and zoning/site-plan permitting and inspection all held and performed by the Town itself with town-employed staff (Building Official Jose Rodriguez; Building Department Clerk Orlando Rodriguez), not a contracted vendor. 85% · town department page + FY2024 audited financial statements
    • Is a permit required for a residential rooftop PV system? YES -- a rooftop PV system requires a permit under the Town's general electrical/building permit requirement. The Town's own 'General Building Permitting Information' guide lists 'Electrical' as requiring a permit (no PV-specific line item), and Florida Building Code Chapter 1 Sec. 105.1 (locally adopted verbatim as Town Code Sec. 14-108) requires a permit for anyone who intends to 'erect, install, enlarge, alter, repair, remove, convert or replace any ... electrical ... system ... the installation of which is regulated by this code.' 85% · town-published permitting-information guide + Town Code Sec. 14-108 (FBC Ch. 1 local amendments)
    • Is there a separate electrical permit, or is it combined? Combined -- the Town's own Building Permit Application is a single form with 'Building', 'Electrical', 'Gas', 'Plumbing', 'Mechanical', 'Roofing' and 'Driveway' as checkbox trade categories on one page; there is no separate standalone 'Electrical Permit Application' form in the Town's forms library. 80% · town permit application form, enumerated forms library
    • Is a HOA or architectural approval required first? NO co-signature or approval from an HOA/condo/property-owners association is required as a precondition of Town permit issuance. The Town's own Building Permit Application form has signature blocks ONLY for the Owner/Agent and the Contractor (each notarized) -- there is no HOA/POA/Co-Op/Condo Association signature line anywhere on the form, unlike the pattern found elsewhere in this Palm Beach County survey batch (e.g. South Palm Beach's application, which requires an HOA representative's printed name and signature). 80% · town's own current building permit application form + Town Code Sec. 14-108
    • Is there a historic-district review? Likely NO dedicated local historic-district/Certificate-of-Appropriateness regime -- no historic preservation board, overlay district, or COA process was found in the Town's own Zoning Appendix A, Chapter 14 Building Regulations, or Chapter 34 Flood Protection code (the flood code's only 'historic structure' references are a SHIELD -- an exemption from flood-resistant-construction requirements for structures eligible under FBC Existing Building Ch. 12 -- not a design-review trigger). 60% · municipal code, sections read in full (bounded, not a full-text enumeration)
    • Is a Specific Use Permit or Council approval ever required? Likely YES for exterior-visible work -- Town Code Sec. 14-62 (Chapter 14, Article II, Division 3, 'Building Construction and Site Plan Review, Approval') establishes an 'ARCHITECTURAL AND SITE PLAN REVIEW' process, and the Town's own Development Application package includes a dedicated 'Architectural & Aesthetic Review Request' form and criteria addressing 'compatibility of building height and scale' and consistency 'with established neighborhood character.' Separately, Municode's own full-text search surfaced Sec. 14-87 ('Review criteria for architectural and design features'), which ENCOURAGES (does not require) 'low voltage, solar powered, waterproof non-corrosive and UL rated fixtures' for exterior lighting -- the only 'solar' hit anywhere in the code, and it is a decoy (about solar-powered light fixtures, not PV). 55% · municipal code full-text search + town Development Application package
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? A State-licensed electrical contractor (FS ch. 489), or the homeowner acting as owner-builder under FS 489.103(7) if the owner personally appears, signs the application, and personally performs or supervises the work. 78% · town-published FAQ, quoting FS 489.103(7)
    • Is a homeowner permitted to self-install and self-permit? YES, the FS 489.103(7) owner-builder exemption is available and is described in the Town's own FAQ, with the statutory conditions (owner-occupied single-family only; owner must personally perform or supervise; owner must personally sign the permit application). 80% · town-published FAQ
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? A signed and notarized Building Permit Application (both owner and contractor); a copy of the contract/proposal/agreement showing job valuation; two copies of plans/specs and/or NOAs; a recorded Notice of Commencement for jobs over $2,500 ($7,500 for mechanical/A-C); for jobs over $5,000, a Construction Site Management Acknowledgment Form (per Ordinance O-6-25); and contractor/subcontractor registration with the Town before commencing work. 88% · town department page (permit submittal requirements)
    • How many copies, and in what format? Not fully online -- the Town's own Building Department page states the Permit Application 'must be signed and notarized by both the homeowner and the contractor' and the Construction Site Management Acknowledgment Form 'must be signed by both the homeowner and the contractor,' which implies a wet-signature/notarization step; inspections are scheduled through My Government Online (MGO), an online portal. 60% · town department page
    • Is a structural PE stamp required, and at what threshold? No general signed-and-sealed-plans mandate on every job was found; a Florida-registered-engineer seal is required specifically for an electrical (or plumbing, or A/C-refrigeration) system ONLY where BOTH: (A) the system's value exceeds $125,000, AND (B) it requires an aggregate residential electrical service capacity over 600 amperes (240V) (or, for commercial/industrial, over 800 amperes). A typical residential PV job (well under $125,000, standard 200A service) does not trigger this threshold. 88% · municipal code, Sec. 14-108 (FBC Ch. 1 Sec. 105.3.1.2), read in full
    • Is an electrical PE stamp required, and at what threshold? Electrical-specific PE-seal threshold: value over $125,000 AND residential service capacity over 600 amperes (240V) -- same clause as Q13, and it is stated for electrical systems specifically (not a general catch-all). 88% · municipal code, Sec. 14-108, read in full
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? My Government Online (MGO) -- mgoconnect.org -- named for inspection scheduling on both the Town's own Building Department page and its FAQ document. 85% · town department page + FAQ
    • Can the whole application be completed online? Partially -- inspections are scheduled online through MGO, but the Town's own Building Department page requires the Permit Application and Construction Site Management Acknowledgment Form to be signed and NOTARIZED by both homeowner and contractor, which is not a purely online step on the evidence available this run. 55% · town department page (bounded by portal capability limit)
    • What does a residential solar permit cost? Valuation-based, tiered by job value, per the Town's own 'Building Permit Fee Calculator' spreadsheet (revised at the August 2019 Commission Meeting): $30 flat for the first $1,000 of valuation; 3% of valuation from $1,000-$100,000 (e.g. $3,000 at $100,000); $3,000 + 2% of the amount over $100,000 from $100,000-$250,000; $6,000 + 1.5% of the amount over $250,000 from $250,000-$500,000; $9,750 + 1% of the amount over $500,000 above $500,000. The state surcharge is added on top at 2.5% of the BUILDING PERMIT FEE (not of job valuation), minimum $4.00. Example for a $37,000 residential PV job: 3% x $37,000 = $1,110.00 permit fee, plus surcharge 2.5% x $1,110 = $27.75 (above the $4 minimum) = $1,137.75 total. 85% · town-published fee calculator spreadsheet, formulas read directly
    • How is the fee calculated? Valuation (percentage of declared job cost, tiered/cumulative) -- not flat, not per-kW, not per-panel. 88% · town fee calculator, formulas read directly
    • Is there a separate plan-check fee? Likely no separate plan-review fee -- the fee calculator's only components are the tiered Building Permit Fee and the state surcharge; no distinct plan-review line exists in that document. 55% · town fee calculator (absence inference)
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? The Town's OWN Code commits to issuing a single-family residential building permit within 30 WORKING days of application (Town Code Sec. 14-108, FBC Ch. 1 Sec. 105.3.4), unless unusual circumstances require longer or the application fails to satisfy the code. This equals the FS 553.792(1)(a) statutory default for a structure under 7,500 sq ft (the limb that governs a typical $30-55k PV job, since it exceeds the $15,000 5-business-day threshold). 85% · municipal code, Sec. 14-108 (FBC Ch. 1 Sec. 105.3.4), read in full
    • How long is an issued permit valid before it expires? A permit application is deemed abandoned 6 months after filing if not pursued in good faith (one or more 3-month extensions available). Once issued, a permit expires if work is not started and a first inspection requested/passed within 180 days; after work commences, the permit expires if work is suspended/abandoned for 180 days; it becomes non-renewable 60 days after that expiration date. 82% · town FAQ + Town Code Sec. 14-108 (FBC Ch. 1 Sec. 105.3.2)
    • Which utility handles interconnection here? Florida Power & Light Company (FPL) -- named directly, repeatedly, and by the Town's own hand. 93% · town project page (naming FPL directly) + FY2024 audit Note 5 + EIA-861 county file
    • Where does the utility sit in the sequence? Not confirmed -- no Town document (permit application, fee calculator, FAQ) states an interconnection-sequencing rule. 40% · inference; FPL DG manual not fetched this run

28 questions answered against Town of Palm Beach Shores’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

YES

Why the confidence is not higherTown of Palm Beach Shores is independently listed on floridabuilding.org's 392-entry statewide register of local governments that issue building permits ('Town of Palm Beach Shores', option value 2354), confirmed by a live fetch this run (md5 of register page: be2155e7c70477948328f31fc596d5ed). The Town's own Building Department page, permit application, contractor registration form, and fee calculator all show it running its own building-permit process end to end with town-employed staff (see jurisdiction block for the payroll evidence). Not 100 because the register alone is evidence, not proof, per this survey's standing 'both directions' caveat about the register.

statewide keyless registry, verified live this run checked 2026-09-13 https://www.floridabuilding.org/sc/sc_org_srch.aspx

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Building, electrical, plumbing, mechanical, and zoning/site-plan permitting and inspection all held and performed by the Town itself with town-employed staff (Building Official Jose Rodriguez; Building Department Clerk Orlando Rodriguez), not a contracted vendor.

Why the confidence is not higherTown's own Building Department page names in-house staff at the Town Hall's own phone number (561-844-3457, matching the Town's general contact number). FY2024 audited financial statements show real actual Building Department payroll ($107,327 against a $101,817 budget) -- the opposite fingerprint from the three other Hy-Byrd-run Palm Beach County towns already filed in this survey. Not higher because I did not obtain a complete department staffing roster (e.g., number of inspectors, plan reviewer identity) beyond the two named staff.

town department page + FY2024 audited financial statements checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

YES -- a rooftop PV system requires a permit under the Town's general electrical/building permit requirement. The Town's own 'General Building Permitting Information' guide lists 'Electrical' as requiring a permit (no PV-specific line item), and Florida Building Code Chapter 1 Sec. 105.1 (locally adopted verbatim as Town Code Sec. 14-108) requires a permit for anyone who intends to 'erect, install, enlarge, alter, repair, remove, convert or replace any ... electrical ... system ... the installation of which is regulated by this code.'

Why the confidence is not higherDirectly read from the Town's own permitting-information guide and its own locally-adopted FBC Chapter 1 text (Sec. 105.1). Solar/photovoltaic is not named anywhere in the Town's code (proved by full-text search with controls -- see extra_findings), so this is coverage under the general electrical-permit requirement, not a PV-specific rule.

town-published permitting-information guide + Town Code Sec. 14-108 (FBC Ch. 1 local amendments) checked 2026-09-13 https://www.palmbeachshoresfl.us/General_Building_Permitting_Info%5B1%5D.pdf

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined -- the Town's own Building Permit Application is a single form with 'Building', 'Electrical', 'Gas', 'Plumbing', 'Mechanical', 'Roofing' and 'Driveway' as checkbox trade categories on one page; there is no separate standalone 'Electrical Permit Application' form in the Town's forms library.

Why the confidence is not higherDirectly read from the Town's own current Building Permit Application form. The Town's Building Department forms page was enumerated in full (31 distinct PDF/XLSX documents); none is titled or scoped as a standalone electrical permit application.

town permit application form, enumerated forms library checked 2026-09-13 https://www.palmbeachshoresfl.us/document_center/Departments/Documents%20%26%20Forms/Fillable%20Permit%20Application%20Revised%20December%202020%20(PSU%20language).pdf

Q5 Who is allowed to pull the electrical permit? Core Who may apply

A State-licensed electrical contractor (FS ch. 489), or the homeowner acting as owner-builder under FS 489.103(7) if the owner personally appears, signs the application, and personally performs or supervises the work.

Why the confidence is not higherThe Town's own FAQ document quotes FS 489.103(7) directly: an owner who occupies the property may act as their own contractor (not available to corporations, trusts, businesses, or multi-family units), but 'must perform and complete all of the work yourself, or ... personally supervise any work not done by you,' and licensed trades hired in (electrician, plumber, A/C, roofer) 'must be properly licensed in those trades.' Not higher because no PV-specific carve-out (of the kind found elsewhere in this survey, e.g. a town requiring a licensed electrical contractor for solar wiring even under an owner exemption) was found in Palm Beach Shores' own code.

town-published FAQ, quoting FS 489.103(7) checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Nothing published by this authority.

Where we lookedThe Town's own Contractor Registration form and Building Department page both state contractors/subs 'must all register with the Town before commencing any work,' but I did not find text stating registration must be complete BEFORE a permit APPLICATION can be filed, as distinct from before work commences.

https://www.palmbeachshoresfl.us/Contractor%20Registration%20Fillable%20.pdf

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

YES, the FS 489.103(7) owner-builder exemption is available and is described in the Town's own FAQ, with the statutory conditions (owner-occupied single-family only; owner must personally perform or supervise; owner must personally sign the permit application).

Why the confidence is not higherDirect quote from the Town's own FAQ document (see Q5). No town-specific narrowing or additional disclosure-form requirement beyond the statute was found.

town-published FAQ checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q8 What documents make up a complete submittal? Core Submittal package

A signed and notarized Building Permit Application (both owner and contractor); a copy of the contract/proposal/agreement showing job valuation; two copies of plans/specs and/or NOAs; a recorded Notice of Commencement for jobs over $2,500 ($7,500 for mechanical/A-C); for jobs over $5,000, a Construction Site Management Acknowledgment Form (per Ordinance O-6-25); and contractor/subcontractor registration with the Town before commencing work.

Why the confidence is not higherEnumerated directly from the Town's own Building Department page ('PERMIT SUBMITTAL' section) and the General Building Permitting Information guide, both fetched and read in full this run. Not higher because no solar-specific submittal checklist exists to confirm every item applies unchanged to a PV job.

town department page (permit submittal requirements) checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q9 How many copies, and in what format? Submittal package

Not fully online -- the Town's own Building Department page states the Permit Application 'must be signed and notarized by both the homeowner and the contractor' and the Construction Site Management Acknowledgment Form 'must be signed by both the homeowner and the contractor,' which implies a wet-signature/notarization step; inspections are scheduled through My Government Online (MGO), an online portal.

Why the confidence is not higherDirect quote from the Town's own Building Department page for the notarization requirement. Not higher because I could not confirm from any Town document whether the notarized application itself can be submitted as a scanned upload through a portal versus requiring an in-person/mailed original, and MGO's own public landing page is a login-gated JS shell that could not be enumerated this run (bounded capability limit).

town department page checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q10 Is a site plan required, and what must it show? Core Submittal package

Nothing published by this authority.

Where we lookedNo document defining a 'site plan' submittal requirement specific to a rooftop PV job was found; the Town's Development Application package defines a full site-plan-review process for new construction/additions, but whether a roof-mounted PV retrofit with no footprint change falls under it was not confirmed.

https://www.palmbeachshoresfl.us/Development%20Application%20Revised%2012.24.25.pdf

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Nothing published by this authority.

Where we lookedNo solar-specific checklist or code text requiring a one-line/three-line electrical diagram was found. Municode full-text search for 'solar', 'photovoltaic', 'renewable energy', 'energy storage', 'battery' returned 0-2 hits townwide (all decoys), none addressing diagrams.

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedSame limitation as Q11 -- no PV-specific submittal document exists to confirm a string/conductor calculation requirement by name.

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

No general signed-and-sealed-plans mandate on every job was found; a Florida-registered-engineer seal is required specifically for an electrical (or plumbing, or A/C-refrigeration) system ONLY where BOTH: (A) the system's value exceeds $125,000, AND (B) it requires an aggregate residential electrical service capacity over 600 amperes (240V) (or, for commercial/industrial, over 800 amperes). A typical residential PV job (well under $125,000, standard 200A service) does not trigger this threshold.

Why the confidence is not higherDirect quote of Town Code Sec. 14-108 (locally-adopted FBC Chapter 1, Sec. 105.3.1.2), read in full from Municode this run. This is the Town's own stated PE-stamp threshold, not an inference.

municipal code, Sec. 14-108 (FBC Ch. 1 Sec. 105.3.1.2), read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Electrical-specific PE-seal threshold: value over $125,000 AND residential service capacity over 600 amperes (240V) -- same clause as Q13, and it is stated for electrical systems specifically (not a general catch-all).

Why the confidence is not higherSame source as Q13 -- Town Code Sec. 14-108 / FBC Ch. 1 Sec. 105.3.1.2, read in full.

municipal code, Sec. 14-108, read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q15 What does a residential solar permit cost? Core Fees

Valuation-based, tiered by job value, per the Town's own 'Building Permit Fee Calculator' spreadsheet (revised at the August 2019 Commission Meeting): $30 flat for the first $1,000 of valuation; 3% of valuation from $1,000-$100,000 (e.g. $3,000 at $100,000); $3,000 + 2% of the amount over $100,000 from $100,000-$250,000; $6,000 + 1.5% of the amount over $250,000 from $250,000-$500,000; $9,750 + 1% of the amount over $500,000 above $500,000. The state surcharge is added on top at 2.5% of the BUILDING PERMIT FEE (not of job valuation), minimum $4.00. Example for a $37,000 residential PV job: 3% x $37,000 = $1,110.00 permit fee, plus surcharge 2.5% x $1,110 = $27.75 (above the $4 minimum) = $1,137.75 total.

Why the confidence is not higherExtracted directly from the live formulas (VLOOKUP and arithmetic cell formulas) inside the Town's own published Excel fee calculator, not a PDF summary -- the underlying spreadsheet logic was read cell-by-cell. Not higher because this spreadsheet may not be the Town's complete, currently-adopted fee resolution (no separate posted 'Fee Schedule' document was found on the Town's site -- see extra_findings), and the file itself is undated beyond its 2019 revision note, though it is the only fee document the Town publishes for this purpose.

town-published fee calculator spreadsheet, formulas read directly checked 2026-09-13 https://www.palmbeachshoresfl.us/BUILDING%20PERMIT%20FEE%20CALCULATOR%20081919.xlsx

Q16 How is the fee calculated? Core Fees

Valuation (percentage of declared job cost, tiered/cumulative) -- not flat, not per-kW, not per-panel.

Why the confidence is not higherDirectly read from the fee calculator's formula structure (see Q15).

town fee calculator, formulas read directly checked 2026-09-13 https://www.palmbeachshoresfl.us/BUILDING%20PERMIT%20FEE%20CALCULATOR%20081919.xlsx

Q17 Is there a separate plan-check fee? Fees

Likely no separate plan-review fee -- the fee calculator's only components are the tiered Building Permit Fee and the state surcharge; no distinct plan-review line exists in that document.

Why the confidence is not higherInferred from the absence of a plan-review line in the only fee document the Town publishes. Not higher because the calculator may not be the Town's complete fee schedule (see extra_findings) -- a separate, unpublished fee resolution could exist.

town fee calculator (absence inference) checked 2026-09-13 https://www.palmbeachshoresfl.us/BUILDING%20PERMIT%20FEE%20CALCULATOR%20081919.xlsx

Q18 What is the stated plan-review turnaround? Core Timeline & validity

The Town's OWN Code commits to issuing a single-family residential building permit within 30 WORKING days of application (Town Code Sec. 14-108, FBC Ch. 1 Sec. 105.3.4), unless unusual circumstances require longer or the application fails to satisfy the code. This equals the FS 553.792(1)(a) statutory default for a structure under 7,500 sq ft (the limb that governs a typical $30-55k PV job, since it exceeds the $15,000 5-business-day threshold).

Why the confidence is not higherDirect quote of Town Code Sec. 14-108 / FBC Ch. 1 Sec. 105.3.4, read in full from Municode. Note this is a TOWN commitment written into its own locally-adopted code (working days), not merely the state statutory default (business days) -- the two are closely aligned but not verified to be identical unit-for-unit.

municipal code, Sec. 14-108 (FBC Ch. 1 Sec. 105.3.4), read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q19 How long is an issued permit valid before it expires? Timeline & validity

A permit application is deemed abandoned 6 months after filing if not pursued in good faith (one or more 3-month extensions available). Once issued, a permit expires if work is not started and a first inspection requested/passed within 180 days; after work commences, the permit expires if work is suspended/abandoned for 180 days; it becomes non-renewable 60 days after that expiration date.

Why the confidence is not higherThe 6-month/3-month application-abandonment rule is a direct quote of Town Code Sec. 14-108 (FBC Ch. 1 Sec. 105.3.2). The 180-day issued-permit expiration and 60-day non-renewable window are a direct quote of the Town's own published FAQ document. Both are the Town's own words.

town FAQ + Town Code Sec. 14-108 (FBC Ch. 1 Sec. 105.3.2) checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q20 Which permit portal does this authority use? Core Portal & process

My Government Online (MGO) -- mgoconnect.org -- named for inspection scheduling on both the Town's own Building Department page and its FAQ document.

Why the confidence is not higherStated directly and repeatedly on the Town's own Building Department page and FAQ.

town department page + FAQ checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q21 Can the whole application be completed online? Core Portal & process

Partially -- inspections are scheduled online through MGO, but the Town's own Building Department page requires the Permit Application and Construction Site Management Acknowledgment Form to be signed and NOTARIZED by both homeowner and contractor, which is not a purely online step on the evidence available this run.

Why the confidence is not higherSee Q9. Bounded because MGOconnect.org's public landing page is login-gated JS content that could not be enumerated this run (2,xxx-byte shell to a plain fetch), so whether the notarized submittal itself is completed as a portal upload is unconfirmed.

town department page (bounded by portal capability limit) checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q22 Which utility handles interconnection here? Core Utility interconnection

Florida Power & Light Company (FPL) -- named directly, repeatedly, and by the Town's own hand.

Why the confidence is not higherThe Town's own 'Underground Utilities Project' page (departments/projects/undergrounding_project) lists, among its own published project documents, an 'FPL Project Proposal (Binding Cost Estimate)', 'FPL Binding Cost Estimate Initial Installation Plans: September 11 2018', and 'FPL Binding Cost Estimate Q&A September 24 2018' -- the Town naming FPL as the electric utility whose distribution lines were the subject of a Town-wide undergrounding referendum and bond issue (corroborated by the FY2024 audit's Note 5, which describes a CenterState Bank Note and General Obligation Bond issued in 2018 specifically 'to provide for payment of a portion of the costs of placing the electric, cable television and telephone utility facilities that serve the Town ... underground'). Independently corroborated at COUNTY level: EIA-861 Service_Territory_2024.xlsx (fetched and parsed first-hand) lists exactly TWO retail electric sellers for Palm Beach County -- Florida Power & Light Co (utility no. 6452) and City of Lake Worth Beach (utility no. 10620, a separate incorporated city's municipal utility, confined to its own city, several miles south). This is the first town in this survey's Palm Beach County batch where FPL is named directly by the authority's OWN site rather than being reached only by county-level elimination.

town project page (naming FPL directly) + FY2024 audit Note 5 + EIA-861 county file checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/projects/undergrounding_project/index.php

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Not confirmed -- no Town document (permit application, fee calculator, FAQ) states an interconnection-sequencing rule.

Why the confidence is not higherInferred from the general FAC 25-6.065 net-metering process for an FPL residential customer; FPL's own DG interconnection manual was not fetched this run.

inference; FPL DG manual not fetched this run checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q24 Is a HOA or architectural approval required first? Overlays & special cases

NO co-signature or approval from an HOA/condo/property-owners association is required as a precondition of Town permit issuance. The Town's own Building Permit Application form has signature blocks ONLY for the Owner/Agent and the Contractor (each notarized) -- there is no HOA/POA/Co-Op/Condo Association signature line anywhere on the form, unlike the pattern found elsewhere in this Palm Beach County survey batch (e.g. South Palm Beach's application, which requires an HOA representative's printed name and signature).

Why the confidence is not higherRead directly and completely from the Town's own current Building Permit Application form. Town Code Sec. 14-108 (FBC Ch. 1 Sec. 105.3.3) requires only the standard FS-mandated NOTICE language printed on/attached to the permit ('there may be additional restrictions ... such as the requirement for Home or Property Owners Association approval') -- a disclosure notice, not a permit precondition or co-signature requirement. This is a proved absence specific to Palm Beach Shores, not inherited from another town's finding.

town's own current building permit application form + Town Code Sec. 14-108 checked 2026-09-13 https://www.palmbeachshoresfl.us/document_center/Departments/Documents%20%26%20Forms/Fillable%20Permit%20Application%20Revised%20December%202020%20(PSU%20language).pdf

Q25 Is there a historic-district review? Overlays & special cases

Likely NO dedicated local historic-district/Certificate-of-Appropriateness regime -- no historic preservation board, overlay district, or COA process was found in the Town's own Zoning Appendix A, Chapter 14 Building Regulations, or Chapter 34 Flood Protection code (the flood code's only 'historic structure' references are a SHIELD -- an exemption from flood-resistant-construction requirements for structures eligible under FBC Existing Building Ch. 12 -- not a design-review trigger).

Why the confidence is not higherBased on the sections read this run (Chapter 14 Article III Building Standards in full, Chapter 34 Article II Definitions in full); a full-text search across the whole codified Code for 'historic' was NOT run this run (bounded), so this is not a proved zero by enumeration to the same standard as the PV/solar absence finding below.

municipal code, sections read in full (bounded, not a full-text enumeration) checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances

Q26 Is a wind or windstorm certification required? Overlays & special cases

Nothing published by this authority.

Where we lookedNo wind/windstorm certification requirement specific to solar (or generally) was found in the code sections read, fee calculator, or the 31-document forms library reached this run. A Roofing Contractor Affidavit exists in the forms library but was not opened this run and is not solar-specific.

https://www.palmbeachshoresfl.us/Roofing%20Contractor%20Affidavit.pdf

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Likely YES for exterior-visible work -- Town Code Sec. 14-62 (Chapter 14, Article II, Division 3, 'Building Construction and Site Plan Review, Approval') establishes an 'ARCHITECTURAL AND SITE PLAN REVIEW' process, and the Town's own Development Application package includes a dedicated 'Architectural & Aesthetic Review Request' form and criteria addressing 'compatibility of building height and scale' and consistency 'with established neighborhood character.' Separately, Municode's own full-text search surfaced Sec. 14-87 ('Review criteria for architectural and design features'), which ENCOURAGES (does not require) 'low voltage, solar powered, waterproof non-corrosive and UL rated fixtures' for exterior lighting -- the only 'solar' hit anywhere in the code, and it is a decoy (about solar-powered light fixtures, not PV).

Why the confidence is not higherBoth sources are the Town's own (Development Application package, and Municode full-text search of Sec. 14-62 and Sec. 14-87). Not higher because I did not read the Development Application's site-plan-review APPLICABILITY trigger section in full to confirm whether a rooftop-only PV retrofit (no footprint change) would actually be pulled into this review, versus only additions/new construction/exterior remodeling. Per FS 163.04, any such architectural review CANNOT be used to refuse a residential PV installation outright regardless (see extra_findings).

municipal code full-text search + town Development Application package checked 2026-09-13 https://library.municode.com/search?stateId=9&clientId=9333&searchText=solar&searchMode=CLIENTMODE&contentTypeId=CODES

Q28 Is there a system-size cap on residential generation? Overlays & special cases

Nothing published by this authority.

Where we lookedNo system-size cap on residential generation was found in the code sections read, fee calculator, or forms library reached this run; the Zoning Appendix A's district-by-district regulations were not read section-by-section in full.

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? NEC edition follows whatever the current Florida Building Code cycle incorporates via FBC Chapter 27 (electrical) -- Town Code Sec. 14-108 (FBC Ch. 1, Sec. 101.4.1): 'The provisions of Chapter 27 of the Florida Building Code, Building shall apply to the installation of electrical systems.' No Town document names a specific NEC edition/year by number. 70% · municipal code, Sec. 14-108, read in full
    • Which building code edition is in force? Florida Building Code, evergreen adoption -- 'as adopted by the state legislature,' with no fixed edition/year named in the Town's own code text. 82% · municipal code, Sec. 14-106, read in full
    • Are there local amendments to any of the above? YES -- Town Code Sec. 14-108 adopts extensive local administrative amendments to FBC Chapter 1 (reproduced in full text in the code, including local text at Sec. 105.1.1 annual facility permits, Sec. 105.3.3 the HOA-approval notice, Sec. 105.3.4 the 30-working-day SFR commitment, and Sec. 105.3.1.2 the PE-seal thresholds). Chapter 34 (Flood Protection and Control) is a further extensive local amendment/adoption specific to flood provisions. 88% · municipal code, read in full
    • What is the installation judged against? The Florida Building Code (evergreen, most current edition) and, for electrical work, FBC Chapter 27 (which incorporates the NEC) -- see Q29/Q30. The Florida Fire Prevention Code is referenced generally (Sec. 14-108 / FBC Ch.1 Sec. 101.4.6) for fire-prevention matters, edition not specified in the sections read. 72% · municipal code, Sec. 14-108
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for Town of Palm Beach Shores on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    Nothing recorded for Town of Palm Beach Shores on this step yet — 1 question checked and found unpublished. The guidance above is general.

  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    Nothing recorded for Town of Palm Beach Shores on this step yet — 6 questions checked and found unpublished. The guidance above is general.

  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Are batteries permitted, and under what conditions? No town-specific ESS/battery conditions were found -- full-text search of the codified Code for 'battery' returned 2 hits, both decoys (motor-vehicle repair battery-charging, and a vacation-rental smoke/CO-alarm battery requirement); 'energy storage' and 'photovoltaic' returned 0 hits. Absent a town-specific rule, FBC/NFPA 855 default requirements as incorporated by the evergreen FBC adoption (Sec. 14-106/14-108) would govern. 72% · full-text search across the codified Code of Ordinances, with controls
    • Is a ground mount treated as a structure? No PV/ground-mount-specific rule was found. Town Code Pf. 12.8 (Zoning Appendix A, Section XII General Provisions) requires an EMERGENCY ELECTRICAL GENERATOR to be screened by a wall/enclosure 'a minimum height equal to that of the generator plus six (6) inches, completely obscuring the visibility of the generator from the street and abutting neighbors' -- the closest analogous ground-equipment-placement rule in the code, but it names generators specifically, not solar equipment, and was not tested against a ground-mounted PV array or an ESS enclosure. 45% · municipal code full-text search (Pf. 12.8), not read to full section end

20 questions answered against Town of Palm Beach Shores’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

NEC edition follows whatever the current Florida Building Code cycle incorporates via FBC Chapter 27 (electrical) -- Town Code Sec. 14-108 (FBC Ch. 1, Sec. 101.4.1): 'The provisions of Chapter 27 of the Florida Building Code, Building shall apply to the installation of electrical systems.' No Town document names a specific NEC edition/year by number.

Why the confidence is not higherDirect quote of Town Code Sec. 14-108, read in full from Municode. Not higher because this is the evergreen statewide default reached via local incorporation, not a Town document naming 'NEC 2020' or any other edition by its own words.

municipal code, Sec. 14-108, read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, evergreen adoption -- 'as adopted by the state legislature,' with no fixed edition/year named in the Town's own code text.

Why the confidence is not higherTown Code Sec. 14-106 ("Florida Building Code incorporated by reference"), read in full and quoted verbatim: 'The Florida Building Code, as adopted by the state legislature, is hereby incorporated by reference as the building code for the Town of Palm Beach Shores.' No specific edition number (e.g. '8th Edition (2023)') appears anywhere in the Town's own documents reached this run (permit application, FAQ, general permitting guide, Chapter 14 code text) -- this is a genuine evergreen clause, not an unread specific edition.

municipal code, Sec. 14-106, read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-106FLBUCOINRE

Q31 Which fire code edition is in force? Code editions in force

Nothing published by this authority.

Where we lookedTown Code Sec. 14-108 (FBC Ch.1 Sec. 101.4.6) refers generally to 'the Florida Fire Prevention Code' without naming an edition/year; the Town runs its own Fire Department (see jurisdiction/extra_findings) but its own fire-code adoption ordinance was not fetched this run, and the FFPC itself is paywalled per the standing brief.

Q32 Are there local amendments to any of the above? Core Code editions in force

YES -- Town Code Sec. 14-108 adopts extensive local administrative amendments to FBC Chapter 1 (reproduced in full text in the code, including local text at Sec. 105.1.1 annual facility permits, Sec. 105.3.3 the HOA-approval notice, Sec. 105.3.4 the 30-working-day SFR commitment, and Sec. 105.3.1.2 the PE-seal thresholds). Chapter 34 (Flood Protection and Control) is a further extensive local amendment/adoption specific to flood provisions.

Why the confidence is not higherBoth instruments read directly and in full from Municode this run.

municipal code, read in full checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q33 What is the installation judged against? Core Electrical

The Florida Building Code (evergreen, most current edition) and, for electrical work, FBC Chapter 27 (which incorporates the NEC) -- see Q29/Q30. The Florida Fire Prevention Code is referenced generally (Sec. 14-108 / FBC Ch.1 Sec. 101.4.6) for fire-prevention matters, edition not specified in the sections read.

Why the confidence is not higherSame source as Q29/Q30, Town Code Sec. 14-108.

municipal code, Sec. 14-108 checked 2026-09-13 https://library.municode.com/fl/palm_beach_shores/codes/code_of_ordinances?nodeId=PTIICOOR_CH14BUBURE_ARTIIIBUST_S14-108LOAMCH1ADFLBUCOAD

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedNo town-specific rule on service-upgrade or busbar sizing was found in the code sections read or the forms library.

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Nothing published by this authority.

Where we lookedNo solar-specific mounting-system or attachment-spacing rule was found; general structural requirements would flow from the evergreen FBC adoption (Sec. 14-106) but no town-specific numeric standard was located.

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedFire-code ridge-setback/access-pathway requirements were not confirmed -- the Town's own fire-code adoption instrument (as opposed to the general Sec. 14-108 cross-reference) was not fetched this run; the FFPC itself is paywalled per the standing brief.

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Nothing published by this authority.

Where we lookedNo town-specific rapid-shutdown requirement or NEC-edition citation for it was found; NEC 690.12 would apply by default under whichever NEC edition is in force via FBC Ch. 27 (Q29), but that is inference, not a Town statement.

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedNo dedicated solar placard specification was found anywhere in the Town's code sections read, fee calculator, or the 31-document forms library (proved by enumeration -- see extra_findings).

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedNo town-specified placard wording was found (same enumeration as Q38).

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedNo town-specified placard letter height/colour/material was found (same enumeration as Q38).

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedNo site-plan/facility-map placard requirement (NEC 705.10) was found in any Town document reached this run.

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedFPL's own DG interconnection manual/placard specification was not fetched this run.

Q43 Where must the labels be placed? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedLabel placement requirement not confirmed beyond the general NEC default; no town-specific text found.

Q44 Must equipment be on a specific approved list? Equipment listing

Nothing published by this authority.

Where we lookedNo approved-equipment-list requirement was found in the code sections read, fee calculator, or forms library.

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

No town-specific ESS/battery conditions were found -- full-text search of the codified Code for 'battery' returned 2 hits, both decoys (motor-vehicle repair battery-charging, and a vacation-rental smoke/CO-alarm battery requirement); 'energy storage' and 'photovoltaic' returned 0 hits. Absent a town-specific rule, FBC/NFPA 855 default requirements as incorporated by the evergreen FBC adoption (Sec. 14-106/14-108) would govern.

Why the confidence is not higherEnumerated via full-text search with a fabricated-term control ('zzqqxplorp' = 0 hits, confirming a true zero is distinguishable from a broken search) and a positive control ('generator' = 10 hits across multiple chapters, confirming the search reaches the whole corpus).

full-text search across the codified Code of Ordinances, with controls checked 2026-09-13 https://library.municode.com/search?stateId=9&clientId=9333&searchText=battery&searchMode=CLIENTMODE&contentTypeId=CODES

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Nothing published by this authority.

Where we lookedNo dedicated ESS/battery permit type or inspection was identified in the Town's 31-document forms library or fee calculator, but the live MGO permit-type menu could not be checked (login-gated JS portal, a bounded capability limit -- see extra_findings), so this is a bounded absence, not a fully proved one.

https://mgoconnect.org/cp/portal

Q47 Is a ground mount treated as a structure? Core Ground mount

No PV/ground-mount-specific rule was found. Town Code Pf. 12.8 (Zoning Appendix A, Section XII General Provisions) requires an EMERGENCY ELECTRICAL GENERATOR to be screened by a wall/enclosure 'a minimum height equal to that of the generator plus six (6) inches, completely obscuring the visibility of the generator from the street and abutting neighbors' -- the closest analogous ground-equipment-placement rule in the code, but it names generators specifically, not solar equipment, and was not tested against a ground-mounted PV array or an ESS enclosure.

Why the confidence is not higherSec. Pf. 12.8 was read via Municode full-text search snippet (positive control for 'generator'); I did not read the full Section XII General Provisions end to end to confirm whether an analogous accessory-equipment screening/setback rule reaches ground-mounted solar racking or a battery enclosure. Recorded at low confidence as a bounded, not proved, absence/presence.

municipal code full-text search (Pf. 12.8), not read to full section end checked 2026-09-13 https://library.municode.com/search?stateId=9&clientId=9333&searchText=generator&searchMode=CLIENTMODE&contentTypeId=CODES

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Nothing published by this authority.

Where we lookedAC-disconnect placement relative to the meter was not confirmed -- FPL's own DG manual was not fetched this run, and no Town document addresses it.

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal -- inspections are scheduled through My Government Online (MGO), per the Town's own Building Department page and FAQ ('Please schedule inspections at My Government Online' / 'log in to www.mygovernmentonline.org'). 85% · town department page + FAQ
    • How much notice is required? Inspection requests must be received by 3:30 PM the day before, to be scheduled for the following business day. 90% · town department page, verbatim quote
    • Are same-day or AM/PM windows offered? Not stated -- no AM/PM inspection-window commitment was found in any Town document reached this run; inspections are scheduled 'for the following business day' with no time-of-day granularity given. 40% · town department page (absence)
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    Nothing recorded for Town of Palm Beach Shores on this step yet — 2 questions checked and found unpublished. The guidance above is general.

  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? Likely a Certificate of Completion (CC) rather than a full Certificate of Occupancy (CO) for a rooftop PV retrofit on an existing single-family home -- the Town's own FAQ states 'Upon request, a CC (Certificate of Completion) for minor projects can be obtained,' distinct from the CO issued 'for new dwellings, once all fees are paid and all required inspections are completed.' 50% · town FAQ, inference from general CO/CC framing
    • How are corrections issued and cleared? If the Building Official finds work stopped for a code violation, the applicant may be required to engage an architect/engineer and a licensed contractor; a Code Enforcement Officer issues a notice for working without a permit (permit fee plus a 4x penalty), and ignoring that notice leads to a citation before the Special Magistrate, who may fine or order removal of unpermitted work. No PV-specific correction/re-inspection workflow beyond this general process was found. 55% · town FAQ (partial match to the question asked)

14 questions answered against Town of Palm Beach Shores’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal -- inspections are scheduled through My Government Online (MGO), per the Town's own Building Department page and FAQ ('Please schedule inspections at My Government Online' / 'log in to www.mygovernmentonline.org').

Why the confidence is not higherDirect quote from the Town's own documents.

town department page + FAQ checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q50 How much notice is required? Core Booking & scheduling

Inspection requests must be received by 3:30 PM the day before, to be scheduled for the following business day.

Why the confidence is not higherDirect quote, verbatim, from the Town's own Building Department page: 'Inspection requests must be received by 3:30 PM the day before to schedule an inspection for the following business day.'

town department page, verbatim quote checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Not stated -- no AM/PM inspection-window commitment was found in any Town document reached this run; inspections are scheduled 'for the following business day' with no time-of-day granularity given.

Why the confidence is not higherAbsence noted from the same source as Q50 (Town's Building Department page) -- no separate document addressing inspection time windows was found.

town department page (absence) checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

YES, self-performed by the Town with town-employed staff -- NOT delegated to Palm Beach County and NOT contracted to a private building-department-as-a-service vendor (Hy-Byrd or otherwise).

Why the confidence is not higherSee jurisdiction block: named in-house Building Official/Clerk at the Town's own switchboard number; FY2024 audited actual payroll of $107,327 in the Building Department fund; presence on floridabuilding.org's issuing-government register; and Hy-Byrd's own site (tested directly this run) names no Palm Beach Shores relationship, current or former.

town department page + FY2024 audited financial statements + vendor-site negative check checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q53 If delegated, to whom? Core Who inspects

N/A -- building/electrical inspection is not delegated; it is performed by Town-employed staff.

Why the confidence is not higherSee Q52/jurisdiction.

town department page checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/index.php

Q54 Which inspections are required, and in what order? Core Stages & sequence

Nothing published by this authority.

Where we lookedThe full inspection sequence/order for a residential PV job specifically was not enumerated in any Town document reached this run.

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedRough-in/mid-roof inspection requirement for PV specifically was not confirmed.

Q56 Does the inspector verify labels and listings? Core What is checked

Nothing published by this authority.

Where we lookedNo torque affidavit or equipment-listing-verification document (of the kind found for other Palm Beach County towns in this survey) was found among the Town's 31-document forms library; whether the inspector personally verifies equipment listings at a site visit was not confirmed either way.

https://www.palmbeachshoresfl.us/departments/building_department/building_department_forms.php

Q57 Is there a published inspection checklist? Core What is checked

No PV/solar-specific inspection checklist exists among the Town's published forms.

Why the confidence is not higherProved by enumeration: the Town's Building Department forms page (31 distinct PDF/XLSX documents) and the separate Town Hall 'Forms and Permits' page (16 documents) were both fetched and enumerated in full this run; none is titled or scoped to solar/PV/ESS inspection, and none is a general PV inspection checklist of any kind.

town forms library, enumerated in full (31 documents) + Town Hall forms page (16 documents) checked 2026-09-13 https://www.palmbeachshoresfl.us/departments/building_department/building_department_forms.php

Q58 What must be on site at inspection? Core Documents on site

The complete permit card/placard must be attached to the front of the building where work is being performed, for the duration of construction; the list of required inspections is printed on the permit placard itself.

Why the confidence is not higherDirect quote from the Town's own FAQ document: 'The list of required inspections is located on the permit placard ... The permit placard must be attached to the front of the building where the work is being done.'

town FAQ, verbatim quote checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q59 Is there a re-inspection fee? Corrections & re-inspection

Nothing published by this authority.

Where we lookedNo re-inspection fee amount was found -- the Town's only published fee document (the Building Permit Fee Calculator spreadsheet) covers only the tiered Building Permit Fee and the state surcharge; it has no re-inspection, radon, or other special-fee line items, and no separate comprehensive 'Fee Schedule' document was found on the Town's Building Department forms page or the Town Hall forms page (31 + 16 documents enumerated, neither titled 'Fee Schedule').

https://www.palmbeachshoresfl.us/BUILDING%20PERMIT%20FEE%20CALCULATOR%20081919.xlsx

Q60 How are corrections issued and cleared? Corrections & re-inspection

If the Building Official finds work stopped for a code violation, the applicant may be required to engage an architect/engineer and a licensed contractor; a Code Enforcement Officer issues a notice for working without a permit (permit fee plus a 4x penalty), and ignoring that notice leads to a citation before the Special Magistrate, who may fine or order removal of unpermitted work. No PV-specific correction/re-inspection workflow beyond this general process was found.

Why the confidence is not higherDirect quote from the Town's own FAQ ('What happens if I choose not to obtain the required permits?'), which addresses UNPERMITTED work rather than a FAILED inspection on a permitted job specifically; the exact re-inspection/correction path for a failed inspection on an active permit was not separately confirmed.

town FAQ (partial match to the question asked) checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q61 What is issued on pass? Core Final sign-off & PTO

Likely a Certificate of Completion (CC) rather than a full Certificate of Occupancy (CO) for a rooftop PV retrofit on an existing single-family home -- the Town's own FAQ states 'Upon request, a CC (Certificate of Completion) for minor projects can be obtained,' distinct from the CO issued 'for new dwellings, once all fees are paid and all required inspections are completed.'

Why the confidence is not higherDirect quote from the Town's own FAQ, but it does not use the word 'solar' anywhere near the CO/CC distinction, so classifying a PV retrofit specifically as a 'minor project' eligible for a CC is my inference from the general framing, not a stated Town rule.

town FAQ, inference from general CO/CC framing checked 2026-09-13 https://www.palmbeachshoresfl.us/Frequently%20Asked%20Questions.pdf

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Nothing published by this authority.

Where we lookedWho notifies FPL for Permission to Operate was not confirmed -- FPL's own DG/interconnection manual was not fetched this run, and no Town document addresses PTO notification.

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording None%

Size, colour & material None%

Where they go None%

What the utility wants on top None%

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
Town
County
Palm Beach County
Regions covered
Authority Contact
Building Department
Direct Phone
(561) 844-3457
Booking & Scheduling