Town of Wausau is a town authority in the State of Florida, serving 371 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Town of Wausau against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Town of Wausau is not the permitting authority for residential solar here 92% confidence
Holds
One mandatory town-level step for new development, and nothing else. The Washington County residential planning instructions state: 'A letter from the Town of Wausau, Ebro, and Caryville is required for any new development within the City limits', and that letter attaches to the County Land Use Application -- so for NEW DEVELOPMENT inside the Wausau town limits, Town Hall (per the County Directory: (850) 638-1781, 1607 2nd Ave., Wausau FL 32463) is the first stop, before the County Planning Department and well before the County Building Department. For a rooftop PV retrofit on an existing dwelling that letter probably does not bite, because LDC 10.01.03 does not list rooftop solar among the things needing a Land Use Certificate and LDC 10.01.04.D exempts 'the alteration of an existing building or structure so long as no change is made to its gross floor area, its use, or the amount of impervious surface on the site' -- but a GROUND MOUNT is a new structure and would re-trigger the whole Planning sequence including the town letter. That question is unresolved, the same single most consequential open point the Ebro run flagged, independently re-derived here from the same county-wide code. Beyond the letter, Wausau holds nothing relevant to residential rooftop PV: no building department, no building official, no plans examiner, no inspector, no permits, no fee schedule, and no adopted construction codes of its own. Wausau HAS no volunteer fire department of its own (unlike Ebro, which has 'Ebro VFD' at Town Hall's own address) -- instead the County Directory lists 'Washington County Fire Department Station 1' at 1608 2nd Avenue, Wausau FL 32463, one block from the Town's own listed address, meaning the County's own fire department operates a station physically inside Wausau. Wausau IS a chartered municipality with an elected Mayor/Council government (Mayor Roger Hagan; Council Members Judy Carter, Billy Park, Shirley Rightenburg, Joe Phillips; Town Clerk Lynn Gothard), created by Florida House Bill 2530 recorded with the Secretary of State 10 July 1963, per its own FY2024 audited financial statements -- so it is a real, self-governing body that has simply chosen (or been left with no capacity) to perform none of the AHJ functions itself.
Delegated to
Washington County. Building permits, electrical (trade) permits, plan review, inspections, contractor registration and certificates of occupancy sit with the Washington County Building Department, 1331 South Blvd. Suite 900, Chipley FL 32428, 850-638-6195, permits@washingtonfl.com, Building Official Charles Vannatter. Land development review (Land Use Certificate, $50, issued or denied within ten working days) sits with the Washington County Planning Department, same address, 850-415-5093. Addressing sits with the County E-911 Addressing Department, 850-638-6325. Driveways sit with County Public Works, 850-638-6280. The governing land development code is the County's own, which the Wausau Town Council co-adopted: LDC 1.10.01 says the regulations were 'passed, approved, and adopted by the Board of County Commissioners of Washington County and the City/Town Councils of Caryville, Ebro, Vernon, and Wausau, to be effective December 14, 2023.'
Overridden by
The Florida Building Code, 8th Edition (2023), confirmed directly from the county's own current building permit application ('Code in effect 8th Edition Florida Building Code'), re-read fresh in this run; the underlying state rule (FAC 61G20-1.001) could not be independently re-opened this session (flrules.org Cloudflare-blocked). NFPA 70 (NEC) 2020, applied through Washington County Code Sec. 14-68's deferral to whatever edition the state adopts -- the state-rule confirmation the Ebro run obtained could not be repeated in this run for the same reason. The Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida 2021 Editions), which binds Wausau by operation of state rule whether or not the Town has ever passed anything -- also not independently re-opened this session. F.S. 163.04(1)-(2), which expressly prohibits any ordinance or deed restriction that prohibits solar collectors, re-read from the Legislature's own site today. F.S. 553.792(1)(a) and (c), setting binding plan-review deadlines and the automatic-completeness rule, re-read today. F.S. 553.79(1)(b)-(c), requiring electronic submission and setting the one-year single-family permit expiry that conflicts with the County's own 180-day/six-month permit-form language -- re-read today. F.S. 553.791, the private-provider route. F.S. 471.003(2)(h), exempting a ch. 489 licensed electrical contractor from engineering licensure at $125,000/600A residential or less. F.S. 489.103, the owner-builder exemption. At utility level, which statute and tariff apply turns on which utility actually serves Wausau, which this run could not fully confirm (see q22) -- Gulf Coast Electric Cooperative's Schedule NMR-1, the tariff the Ebro run used, is deliberately NOT applied here because GCEC's own site names its served municipalities and Wausau is not among them.
Why not higher
Proved in this run from first-party sources independent of the Ebro, Caryville, Vernon and Washington County runs, using the SAME method the brief demands (prove Wausau's own position independently rather than inherit the county-side material) plus one genuinely new class of evidence those runs did not have. County side, re-read fresh today: (1) the Planning Department page states it 'regulates land development within the unincorporated areas of Washington County, and the municipalities of Caryville, Ebro, Vernon, and Wausau'; (2) the current Land Use Certificate application (rev. 09/29/2025) carries a 'Municipality' checkbox row 'Unincorporated / Vernon / Wausau / Ebro / Caryville' and the bound instruction sheet carries the Wausau letter requirement; (3) the Washington County Land Development Code, pulled as text through the Municode content API in THIS run (Article I General Provisions, Article II Land Use, Article IX Boards and Agencies, Article X Administration and Enforcement -- a wider set of articles than the Ebro run checked), names Wausau repeatedly and by name: co-adoption effective 14 Dec 2023, the Planning Department 'shall also perform these administrative functions for the municipalities of Caryville, Ebro, Vernon, and Wausau', the County Comprehensive Plan defined as covering Wausau by name (which directly answers the brief's instruction to check Wausau's Comprehensive Plan: it does not have a separate one -- it is covered, by name, inside the County's), the Planning Commission established jointly by the County and 'the governing bodies of Caryville, Ebro, Vernon and Wausau', and 'Local Governing Body' defined to include 'the Town Councils of the Towns of Caryville, Ebro, or Wausau'; (4) the County Building Department page names Building Official Charles Vannatter and staff, with no Wausau official anywhere; (5) the County Directory lists 'Town of Wausau, (850) 638-1781, 1607 2nd Ave.' under Municipalities with no permit contact of any kind. NEW to this run, and the strongest single piece of evidence in it, is the budget/audit test the brief calls for, run directly rather than inferred: Wausau's own FY2020-FY2024 annual financial reports, audited by Grimsley & Associates, P.A. and filed with the Florida Auditor General (all five years downloaded and read with pdftotext in this run), contain the word 'permit' ZERO times across all five years, disclose NO interlocal agreements anywhere in eleven footnotes, and carry NO 'Building', 'Community Development' or 'Inspections' functional expense category in either the government-wide or budgetary statements -- only General Government, Public Safety, Highways and Streets, and Culture and Recreation. The Town's only 'Charges for Services' revenue line is $1,982 (FY2024) / $1,900 (FY2023), against a $48,000 BUDGETED figure that came in at just $2,061 actual -- a real, large, unexplained variance, but not a building-permit-fee-sized number by any reading. This is exactly the shape the brief calls Reddick's (a town proved NOT to be its own AHJ by a budget with no building-permit line), now reproduced for Wausau from Wausau's OWN books rather than inferred from the county side. Two further second looks, run fresh in this session rather than carried over: FIRST, the Florida Building Code Information System surcharge-jurisdiction registry was re-enumerated in full (392 entries), with 'City of Alford' present as the positive control (proving tiny towns DO appear when self-permitting) and Wausau, Ebro, Caryville, Vernon and Chipley all absent, 'zzqqx' absent as fabricated control. SECOND, Gulf Coast Electric Cooperative's own 'About' page was re-fetched fresh and names its served municipalities as 'Wewahitchka, Ebro, Lynn Haven, White City, Fountain, and Southport' -- Wausau is NOT among them, which both rules GCEC out as Wausau's utility (so this run does not launder Ebro's utility-side findings onto Wausau, unlike a lazier run would) and independently corroborates that Wausau sits outside GCEC's whole orbit, county government included. Held at 92 -- two points above the Ebro run's 90 -- specifically because the audited-financial-statement evidence is new, first-party, professionally audited, dated, and directly on point for the exact budget test the brief asks for, which the Ebro run could not perform at all (Ebro has no town budget reachable online). Three honest gaps remain, matching the shape of Ebro's: (1) no single document says in words 'Washington County issues building permits inside the Town of Wausau' -- the land-development half is proved outright by the LDC, the building half is the combination of the Wausau checkbox on the county land-use form, the surcharge registry, and the total absence of any Wausau building function in Wausau's own audited books; (2) Washington County Code Chapter 14 carries NO territorial-applicability clause -- Sec. 14-36 and 14-68 say the code is adopted 'for use in Washington County, Florida' without naming municipalities, whereas other chapters of the same code expressly limit themselves to the unincorporated area (Sec. 14-317 on abandoned buildings, 'located within the unincorporated areas of the county'), so Chapter 14's reach into Wausau is read from that contrast rather than stated; (3) the direct permit-record proof is WEAKER than Ebro's: the county's iWorq register was fully walked in this run (all 315 currently-readable permits, 18 Aug-14 Sep 2026), and while 14 carry a Municipality field stamped 'Chipley' and 3 'Vernon' (proving the County does issue permits inside municipal limits in this county), NONE is stamped 'Wausau' and NONE has a Wausau-area (32463) property address -- so, unlike Ebro's run, this run could not even find an address-only (unstamped) permit inside the town to point to. The portal's date-range search remains gated behind an invisible reCAPTCHA that could not be exercised, so the historic register back to 2014 could not be searched for an older Wausau example. Separately NOT established, same as for Ebro: whether Wausau has ever passed the 'official act' that County Code Sec. 30-33 requires for a municipality to elect into the county fire authority. Unlike Ebro, however, Wausau publishes no town VFD of its own in the County Directory at all, while a County-run 'Washington County Fire Department Station 1' sits physically inside Wausau -- practical evidence, not a codified statement, that County Fire already operates directly in the town.

https://washingtonfl.gov/site/assets/files/2554/wc_new_construction_residential_permit_instructions_10062023.pdf

Permit required
Yes. A residential rooftop PV system needs a Washington County building permit. The County's Application for Building Permit (rev.92%
Permit cost
No flat solar fee. A residential PV job is priced as the sum of: (a) the building permit for 'Solar System Installation - Based on Building Valuation Table',80%
Plan review
The County publishes no plan-review turnaround of its own. What binds is F.S. 553.792(1)(a): 5 business days after a complete and sufficient application for an electrical or structural…70%
Portal
iWorq. The County's public permit portal is at portal.iworq.net/WASHINGTONFL/permits/601, linked from the Building Department page as 'Permit Searches ...75%
Electrical code
NEC 2020 (NFPA 70, 2020 edition), by the same statewide chain that applies to every Florida jurisdiction: Washington County Code Sec.55%
Own placard wording
No. Neither the Town of Wausau nor Washington County specifies placard wording of its own.72%
Booking an inspection
Phone, primarily: the Building Inspection Procedures instruct 'YOU MUST HAVE THE PERMIT NUMBER AND TYPE OF INSPECTION WHEN CALLING FOR INSPECTION' -- Washington County Building Department,80%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes. A residential rooftop PV system needs a Washington County building permit. The County's Application for Building Permit (rev. Q3 Electrical and building permits — Separate. The County issues a separate Trade Permit for electrical work, on its own form and at its own fee. Q4 Plan review — The County publishes no plan-review turnaround of its own. What binds is F.S. 553.792(1)(a): 5 business days after a complete and sufficient application for an… Q18 Where you file — iWorq. The County's public permit portal is at portal.iworq.net/WASHINGTONFL/permits/601, linked from the Building Department page as 'Permit Searches ... Q20

Permit required
Yes. A residential rooftop PV system needs a Washington County building permit. The County's Application for Building Permit (rev.92% source
What it costs
No flat solar fee. A residential PV job is priced as the sum of: (a) the building permit for 'Solar System Installation - Based on Building Valuation Table',80% source
Plan review turnaround
The County publishes no plan-review turnaround of its own. What binds is F.S. 553.792(1)(a): 5 business days after a complete and sufficient application for an electrical or structural permit on an…70% source
Key document
fee schedule cited by 4 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? No. The Town of Wausau is not the AHJ for residential solar. Building permits, electrical (trade) permits, plan review, inspections and certificates of occupancy inside the Wausau town limits are issued and performed by the WASHINGTON COUNTY Building Department, 1331 South Blvd. Suite 900, Chipley FL 32428, 850-638-6195, Building Official Charles Vannatter. Land-development review sits with the Washington County Planning Department, same address, 850-415-5093. Wausau retains ONE step of its own: the County's residential planning instructions state 'A letter from the Town of Wausau, Ebro, and Caryville is required for any new development within the City limits', attached to the County Land Use Application. Town of Wausau contact per the County Directory: (850) 638-1781, 1607 2nd Ave., Wausau, FL 32463. 92% · county planning instruction sheet
    • What does this authority permit itself, and what does it delegate? Delegated. Wausau permits nothing itself -- no building permit, no electrical permit, no plan review, no inspection, no fee schedule, no adopted construction code of its own, and its own audited books show no revenue stream or expense function consistent with running one. Building and electrical sit with the Washington County Building Department; land use/zoning sits with the Washington County Planning Department; addressing with the County E-911 Addressing Department (850-638-6325); driveways with County Public Works (850-638-6280). The one thing Wausau holds is a mandatory town letter that must accompany the County Land Use Application for new development inside the town limits. 90% · state surcharge jurisdiction registry
    • Is a permit required for a residential rooftop PV system? Yes. A residential rooftop PV system needs a Washington County building permit. The County's Application for Building Permit (rev. 02/2025) carries an explicit 'Solar System' tick box, and the County Construction Permit Fees 'Schedule A' carries a line item 'Solar System Installation -- Based on Building Valuation Table'. An electrical (trade) permit is required in addition. There is no separate Wausau permit of any kind. 92% · permit application form
    • Is there a separate electrical permit, or is it combined? Separate. The County issues a separate Trade Permit for electrical work, on its own form and at its own fee. The Application for Building Permit states a separate permit must be secured for 'ELECTRICAL WORK, PLUMBING, SIGNS, WELLS, POOLS, FURNACES, BOILERS, HEATERS, TANKS, AIR CONDITIONERS, and etc.' The fee schedule lists 'Electrical Permit: Single Family Residential $125' separately from 'Solar System Installation'. 93% · permit application form
    • Is a HOA or architectural approval required first? Not by the authority in the general case -- but Washington County's OWN fee schedule contains a line that names Wausau's exact situation more directly than it did for Ebro. Neither Wausau nor Washington County requires HOA or architectural approval for rooftop PV as a general rule, and F.S. 163.04(2) voids any deed restriction or covenant that prohibits solar collectors (leaving such a body only the power to choose the roof location within south +/-45 degrees). But the fee schedule's SIGN PERMIT line reads: 'ARC Approval if in Sunny Hills or Leisure Lakes Subdivision or inside any city limits.' Wausau IS a city/town with its own limits -- so on the sign-permit line at least, this note reaches Wausau directly rather than ambiguously. Whether the County means the same thing for a solar permit is not stated anywhere. 62% · fee schedule
    • Is there a historic-district review? No historic-district review is required. Washington County has no historic district or historic preservation ordinance reaching rooftop PV; the only historic touchpoints in the Land Development Code are a plot-plan requirement to show 'any historical or environmentally sensitive areas' (LDC 10.01.03.C) and adoption by reference of the Secretary of the Interior's Standards for Rehabilitation and the Florida Division of Historical Resources Master Site File (LDC 1.03.01), neither of which creates a review step for a house. Wausau publishes nothing of its own. 62% · land development code
    • Is a wind or windstorm certification required? Yes, in the form of the county wind speed line -- and for Wausau specifically it resolves cleanly rather than ambiguously. Washington County Code Sec. 14-37 sets State Road 20, which runs through the SOUTHERN part of the county (past Ebro), as the wind speed line: 130 mph south of it, 120 mph north of it. Wausau sits in the northern part of the county, so a Wausau roof is unambiguously in the 120 mph zone. Separately the County's Trade Permit Application requires a 'FL. PRODUCT APPROVAL CODE' for roof work, which is the Florida Product Approval route by which wind resistance is demonstrated. There is no separate windstorm certificate as such. 80% · county code chapter
    • Is a Specific Use Permit or Council approval ever required? No Special Use Permit or Council approval is required for a rooftop PV system as such. The one Council-level step that does exist is the Town of Wausau letter: the County's residential planning instructions require 'A letter from the Town of Wausau, Ebro, and Caryville ... for any new development within the City limits', attached to the County Land Use Application. That is written for NEW DEVELOPMENT, and a rooftop retrofit on an existing house is probably not caught: LDC 10.01.03 lists the things needing a Land Use Certificate (single-family residence, mobile home, modular home, swimming pool, accessory structure, utility (power, well, septic), lot split, temporary structures, plus a catch-all for anything 'deemed by the Development Administrator to be similar') and rooftop PV is not among them, while LDC 10.01.04.D separately exempts 'The alteration of an existing building or structure so long as no change is made to its gross floor area, its use, or the amount of impervious surface on the site.' A GROUND mount inside the town limits would be a different matter -- it adds a structure and would likely re-trigger 10.01.03.A.5/A.6 and the Wausau letter. At the commercial end, 'Solar Farms' are a Special Exception use in a small number of land use districts, with a 100-foot residential setback and a 100-foot buffer from named named waterways. 72% · county planning instruction sheet
    • Is there a system-size cap on residential generation? No cap in the Land Development Code on residential rooftop generation -- proved absent with the same controls as q11. Any binding capacity cap would be the serving utility's own net-metering tariff, but which utility serves Wausau is not fully resolved in this run (see q22), so the specific kW figure cannot be stated with confidence; it should NOT be assumed to be Gulf Coast Electric Cooperative's 25 kW / 10 kW figures, since GCEC does not serve Wausau (see q2, q22). 68% · land development code
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Either. A state-certified or registered electrical contractor licensed under F.S. ch. 489 who has first registered with the Washington County Building Department may pull it; a property owner may pull it himself under the F.S. 489.103 owner-builder exemption, on the County's Owner Builder Disclosure Statement. The Trade Permit Application is signed by 'OWNER / CONTRACTOR'. 82% · contractor registration packet
    • Must the contractor be registered with this authority before applying? Yes -- but with Washington County, not with Wausau. A certified contractor must file the County's Contractor's License Registration form with a current copy of the state licence and driver's licence, certificates of general liability and workers' compensation insurance naming 'Washington County Building Department' as certificate holder, and a letter of authorization if anyone other than the licence holder will pull permits. Certified contractors pay a $35.00 administration fee; registered (non-certified) contractors pay a licence fee by class -- electrical is $75 in county, $125-$150 out of county, $200-$300 out of state. 90% · contractor registration packet
    • Is a homeowner permitted to self-install and self-permit? Yes. Washington County publishes an Owner Builder Disclosure Statement (2024) for the F.S. 489.103 exemption. The owner may build or improve a one-family or two-family residence for his own use or occupancy, must provide direct onsite supervision, may not hire an unlicensed person to act as contractor or supervisor, and becomes the responsible party of record on the permit. Sale or lease within 1 year is presumed to violate the exemption. 88% · owner-builder disclosure form
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? No solar-specific submittal checklist is published. What the County's general forms require: a completed and NOTARIZED Application for Building Permit (owner and contractor signatures, state licence number, valuation of work, parcel ID); a completed Trade Permit Application for the electrical work naming the serving power company (GCE / FPL / WFECA-G); a certified copy of the Notice of Commencement for work of $2,500 or more, posted on site before the first inspection; plans and the $35 non-refundable Plan Submittal fee; Florida Product Approval numbers where called for; and a letter of authorization if the applicant is not the licence holder. Prior County approvals (Land Use Certificate, E-911 address, driveway where applicable) must already be in hand. 70% · permit application form
    • How many copies, and in what format? Not published as a copy count. Format: the County accepts applications by email to permits@washingtonfl.com for contractors already registered with the Building Department, and warns 'Emailed and faxed permits processing time may take up to 3 business days. All other permits should be brought into the office for processing.' The live iWorq register shows digital plan sets in routine use elsewhere in the county (stamped 'DIGITAL PLANS'/'PLANS UPLOADED'), though none of the 315 most recent permits pulled in this run is at a Wausau address, so that specific corroboration could not be repeated for Wausau. 60% · department page
    • Is a site plan required, and what must it show? For the Planning Department's Land Use Certificate step, yes: LDC 10.01.03.C requires 'a plot plan drawn to scale showing the actual dimensions of the lot to be built upon, the size, shape, height, and location of the buildings to be erected, dimensions and location of existing buildings, and width of front, side, and rear yards, and any historical or environmentally sensitive areas located on the site.' For the Building Department step no separate site plan is specified. Whether a rooftop PV retrofit triggers the Land Use Certificate at all is unsettled -- see q27. 65% · land development code
    • Is a one-line / three-line diagram required? Not published. Neither the County building permit application, the trade permit application, the building inspection procedures, the fee schedule, nor the Land Development Code mentions a one-line or three-line diagram, and no solar plan-submittal handout exists. 72% · department document library
    • Are string and conductor calculations required? Not published. No string sizing, conductor or voltage-drop calculation specific to solar is called for by any County form or by the adopted code text at local level. What Washington County DOES specify locally on conductors generically: Sec. 14-80 requires no service conductor smaller than no. 8 AWG copper or aluminium equivalent, with all service conductors for services of 400 amps or less the same size and insulation type. 72% · county code chapter
    • Is a structural PE stamp required, and at what threshold? No local structural PE threshold is published. What binds instead is the Florida Building Code, 8th Edition (2023), and the County's own wind speed line: Sec. 14-37 sets State Road 20 as the wind speed line for Washington County. Wausau sits well north of SR 20 (SR 20 runs through the SOUTHERN part of the county, past Ebro and Vernon; Wausau is a northern county town near Chipley), so unlike Ebro's split parcels, a Wausau roof is unambiguously in the 120 mph zone rather than straddling a boundary. Florida Product Approval numbers are called for on the County's trade permit form for roof work. 75% · county code chapter
    • Is an electrical PE stamp required, and at what threshold? No local electrical PE stamp requirement is published. At state level F.S. 471.003(2)(h) exempts an electrical contractor licensed under ch. 489 from engineering licensure when the project 'Requires an electrical or plumbing or air-conditioning and refrigeration system with a value of $125,000 or less' and 'Requires an aggregate service capacity of 600 amperes (240 volts) or less on a residential electrical system' -- which covers essentially every residential rooftop PV job. 70% · state statute
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? iWorq. The County's public permit portal is at portal.iworq.net/WASHINGTONFL/permits/601, linked from the Building Department page as 'Permit Searches ... For Searches between 11/06/2014 to Current Date'. It exposes a permit register, per-permit detail pages, an inspection-request form and an inspection scheduler, and this is the same single portal Washington County runs for every jurisdiction in the county including Wausau. 75% · permit portal
    • Can the whole application be completed online? No. The portal is read-only plus inspection requests. Applications are submitted by email to permits@washingtonfl.com for contractors already registered with the Building Department, or brought into the office. Payment is taken at the counter or by card with a 3.5% convenience fee; the portal exposes no application or payment flow. 80% · permit portal
    • What does a residential solar permit cost? No flat solar fee. A residential PV job is priced as the sum of: (a) the building permit for 'Solar System Installation - Based on Building Valuation Table', landing on the County's valuation ladder -- $100 for work valued at $10,000 or less; $252 for the first $10,000 plus $6 per additional $1,000 up to $50,000; $492 for the first $50,000 plus $5 per additional $1,000 up to $100,000; (b) the electrical trade permit, 'Electrical Permit: Single Family Residential $125'; (c) a $35.00 non-refundable Plan Submittal fee, charged again on every re-submittal; (d) a plan review fee 'assessed at a minimum of $35 or 15%, whichever is greater'; (e) a State radon surcharge of 3% or $4.00, whichever is greater; and (f) a 3.5% convenience fee on credit card transactions (effective 17 March 2025). A typical $20,000 system runs roughly $312 building + $125 electrical + $35 submittal + plan review + surcharge -- before any Planning-Department step, which does not apply to Wausau for a bare rooftop retrofit (see q27). 80% · fee schedule
    • How is the fee calculated? Valuation. The building-permit half is 'Based on Building Valuation Table' for solar and on contract/valuation price for rehabilitation, renovation or remodelling; the plan review fee is a percentage (15%) with a $35 floor. The electrical half is flat at $125 for single family residential. 82% · fee schedule
    • Is there a separate plan-check fee? Yes, and there are two of them. A $35.00 NON-REFUNDABLE Plan Submittal fee is collected at time of submittal and charged again on every re-submittal and addendum. A separate plan review fee is then 'assessed at a minimum of $35 or 15%, whichever is greater', collected at permit issuance along with the permit fee and radon surcharge. 85% · fee schedule
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? The County publishes no plan-review turnaround of its own. What binds is F.S. 553.792(1)(a): 5 business days after a complete and sufficient application for an electrical or structural permit on an EXISTING single-family residential dwelling valued under $15,000; 30 business days for a residential unit or electrical permit where the structure is less than 7,500 square feet. The County must give written notice within 5 business days of anything missing, or the application is automatically deemed complete. Separately, emailed/faxed permits may take up to 3 business days to process per the Building Department's own page. 70% · state statute
    • How long is an issued permit valid before it expires? Three different answers are in force and they do not agree. The County's Application for Building Permit says the permit 'is valid as long as there is construction progress and an approved inspection is recorded within each 180 days (6 months) period.' The County's Trade Permit Application says 'This permit is VOID after six (6) months from issuance unless the work it covers has been commenced and has had ongoing inspections.' F.S. 553.79(1)(c) says 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later.' Reported as a conflict, not resolved here -- same conflict found and re-verified independently for Wausau's own authority. 72% · permit application form
    • Which utility handles interconnection here? Most likely West Florida Electric Cooperative Association (WFECA), headquartered at 905 St. John's Rd., Bonifay, FL, (800) 342-7400 -- but this is genuinely less certain than a typical answer in this survey. Gulf Coast Electric Cooperative (Ebro's utility) is ruled OUT: its own 'About' page names its served municipalities as 'Wewahitchka, Ebro, Lynn Haven, White City, Fountain, and Southport', with no Wausau. The Washington County Directory lists only two power companies for the whole county -- 'Florida Power [&] Lights' and 'West Florida Electric' -- and the County's own Trade Permit Application offers exactly three utility checkboxes: 'GCE / FPL / WFECA - G'. West Florida Electric's own homepage (fetched once successfully in this run before the domain became persistently unreachable) describes itself as 'a member-owned, non-profit cooperative providing reliable electricity in Calhoun, Holmes, Jackson and Washington Counties' -- geographically the co-op whose territory reaches the interior/northern part of the county where Wausau sits, next to Holmes and Jackson Counties. Florida Power & Light remains a live alternative and cannot be ruled out from what was reachable in this run. 50% · utility own page

28 questions answered against Town of Wausau’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

No. The Town of Wausau is not the AHJ for residential solar. Building permits, electrical (trade) permits, plan review, inspections and certificates of occupancy inside the Wausau town limits are issued and performed by the WASHINGTON COUNTY Building Department, 1331 South Blvd. Suite 900, Chipley FL 32428, 850-638-6195, Building Official Charles Vannatter. Land-development review sits with the Washington County Planning Department, same address, 850-415-5093. Wausau retains ONE step of its own: the County's residential planning instructions state 'A letter from the Town of Wausau, Ebro, and Caryville is required for any new development within the City limits', attached to the County Land Use Application. Town of Wausau contact per the County Directory: (850) 638-1781, 1607 2nd Ave., Wausau, FL 32463.

Why the confidence is not higherProved in this run from first-party sources independent of the Ebro/Caryville/Vernon runs, AND corroborated by a source those runs did not have: Wausau's own audited annual financial statements. (1) The County Planning Department page, read today, states it 'regulates land development within the unincorporated areas of Washington County, and the municipalities of Caryville, Ebro, Vernon, and Wausau'. (2) The County's current Land Use Certificate application (rev. 09/29/2025) carries a 'Municipality' checkbox row 'Unincorporated / Vernon / Wausau / Ebro / Caryville', and the bound residential instruction sheet carries the Wausau letter requirement quoted above. (3) The Washington County Land Development Code, pulled as text through the Municode content API in this run (Article I General Provisions, Article IX Boards and Agencies, Article X Administration and Enforcement), names Wausau by name repeatedly: 'passed, approved, and adopted by the Board of County Commissioners of Washington County and the City/Town Councils of Caryville, Ebro, Vernon, and Wausau, to be effective December 14, 2023'; the Planning Department 'shall also perform these administrative functions for the municipalities of Caryville, Ebro, Vernon, and Wausau'; the County Comprehensive Plan is defined as covering 'the municipalities of Caryville, Ebro, Vernon, and Wausau'; and 'Local Governing Body' is defined as 'the Town Councils of the Towns of Caryville, Ebro, or Wausau, or the City Council of Vernon'. (4) NEW in this run: the Town of Wausau's own FY2024 annual financial report, audited by Grimsley & Associates, P.A. and filed with the Florida Auditor General (flauditor.gov/pages/mun_efile pages/wausau town of.htm, FY2020-FY2024 all downloaded and read with pdftotext in this run), contains the word 'permit' ZERO times across five consecutive fiscal years, has no 'Building', 'Community Development' or 'Inspections' functional expense category anywhere (only General Government, Public Safety, Highways and Streets, Culture and Recreation), and its only 'Charges for Services' revenue line is $1,982 for FY2024 and $1,900 for FY2023 -- far too small to be a building-permit fee stream and unidentified in the notes as anything more specific. This is the budget test the brief calls for, run directly against Wausau's own books rather than inferred. Held at 92, two points above the Ebro run's 90, precisely because that direct financial-statement evidence did not exist for Ebro but does for Wausau.

county planning instruction sheet checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2554/wc_new_construction_residential_permit_instructions_10062023.pdf

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Delegated. Wausau permits nothing itself -- no building permit, no electrical permit, no plan review, no inspection, no fee schedule, no adopted construction code of its own, and its own audited books show no revenue stream or expense function consistent with running one. Building and electrical sit with the Washington County Building Department; land use/zoning sits with the Washington County Planning Department; addressing with the County E-911 Addressing Department (850-638-6325); driveways with County Public Works (850-638-6280). The one thing Wausau holds is a mandatory town letter that must accompany the County Land Use Application for new development inside the town limits.

Why the confidence is not higherSame jurisdiction sources as q1, plus the same two independent second looks the playbook calls for. FIRST: the Florida Building Code Information System surcharge-jurisdiction registry (the local enforcement agencies registered to remit the state building-permit surcharge) was re-enumerated fresh in this run: 392 entries, 65 'County of' and 305 city/town organisations, positive control 'City of Alford' present (pop. ~500, proving tiny towns DO appear when they run their own department), fabricated control 'zzqqx' absent. 'County of Washington' is present; Wausau is absent, as are Ebro, Caryville, Vernon and Chipley. SECOND: Gulf Coast Electric Cooperative's own 'About' page, re-fetched fresh in this run, names the municipalities it serves as 'Wewahitchka, Ebro, Lynn Haven, White City, Fountain, and Southport' -- Wausau is NOT among them, ruling GCEC out as Wausau's utility and meaning Wausau's own utility (see q22) is a different, separate line of evidence not inherited from the Ebro run. THIRD, new to this run: Wausau's own FY2024 audit Note 1 states the Town 'was created by an act of the Florida Legislature (House Bill 2530) recorded in the Secretary of State's office on July 10, 1963' and 'operates using an elected council form of government' -- confirming Wausau is a real, chartered, self-governing municipality (Mayor Roger Hagan; Council Members Judy Carter, Billy Park, Shirley Rightenburg, Joe Phillips; Town Clerk Lynn Gothard) that nonetheless performs none of the AHJ functions. Held at 90 for the same three honest gaps the Ebro run flagged (no single document says in words 'Washington County issues building permits inside the Town of Wausau'; Chapter 14 carries no territorial-applicability clause; and the live iWorq register's most recent 315 permits, pulled and parsed in this run, contain zero permits at a Wausau (32463) address or stamped Municipality='Wausau', so the direct permit-record proof available for Chipley (14 permits) and Vernon (3 permits) in that same window is not available for Wausau either).

state surcharge jurisdiction registry checked 2026-09-14 https://www.floridabuilding.org/sc/sc_org_srch.aspx

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes. A residential rooftop PV system needs a Washington County building permit. The County's Application for Building Permit (rev. 02/2025) carries an explicit 'Solar System' tick box, and the County Construction Permit Fees 'Schedule A' carries a line item 'Solar System Installation -- Based on Building Valuation Table'. An electrical (trade) permit is required in addition. There is no separate Wausau permit of any kind.

Why the confidence is not higherBoth documents are the County's own current forms, downloaded and read in full with pdftotext in this run (not summarised). The building permit application is stamped 'Code in effect 8th Edition Florida Building Code' and 'Revised 02/2025'; the fee schedule is 'Effective 09/01/2024', served from building_department_fees_4_2026.pdf. These are the same county-wide forms that apply to Ebro, re-verified as current and re-read for this run rather than assumed carried over. Held at 92 rather than higher only because neither document says 'residential' next to the solar line specifically.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1631/building_permit_application-_2025_-_highlighted_-fillable.pdf

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Separate. The County issues a separate Trade Permit for electrical work, on its own form and at its own fee. The Application for Building Permit states a separate permit must be secured for 'ELECTRICAL WORK, PLUMBING, SIGNS, WELLS, POOLS, FURNACES, BOILERS, HEATERS, TANKS, AIR CONDITIONERS, and etc.' The fee schedule lists 'Electrical Permit: Single Family Residential $125' separately from 'Solar System Installation'.

Why the confidence is not higherThree county documents agree, all freshly re-fetched and read in this run: the building permit application's affidavit text, the standalone Trade Permit Application (rev. 04/2025), and the separate electrical lines on Schedule A of the current fee schedule (fetched today). Not 95+ because no county document states in words how a solar job specifically splits between the two permits.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1892/trade_permit_application_-_ada_04_30_25.pdf

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either. A state-certified or registered electrical contractor licensed under F.S. ch. 489 who has first registered with the Washington County Building Department may pull it; a property owner may pull it himself under the F.S. 489.103 owner-builder exemption, on the County's Owner Builder Disclosure Statement. The Trade Permit Application is signed by 'OWNER / CONTRACTOR'.

Why the confidence is not higherFrom the County's Contractor's License Registration packet (rev. 8/2024) and Owner Builder Disclosure Statement (2024), both re-downloaded and read in this run. Held at 82 because neither form addresses solar specifically and neither states whether the County would accept an owner-builder application for a grid-tied PV system that a utility must also interconnect.

contractor registration packet checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2695/certified_contractors_license_registraion_-_ada_8_2024.pdf

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes -- but with Washington County, not with Wausau. A certified contractor must file the County's Contractor's License Registration form with a current copy of the state licence and driver's licence, certificates of general liability and workers' compensation insurance naming 'Washington County Building Department' as certificate holder, and a letter of authorization if anyone other than the licence holder will pull permits. Certified contractors pay a $35.00 administration fee; registered (non-certified) contractors pay a licence fee by class -- electrical is $75 in county, $125-$150 out of county, $200-$300 out of state.

Why the confidence is not higherRead in full from the County's own Contractor's License Registration PDF, revised 8/2024, re-downloaded in this run; the $35 fee is independently confirmed on Schedule A of the fee schedule, also re-fetched today. Not higher because the fee table itself says 'There are several different levels of Licenses. Please contact the Washington County Building Department for exact prices.'

contractor registration packet checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2695/certified_contractors_license_registraion_-_ada_8_2024.pdf

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes. Washington County publishes an Owner Builder Disclosure Statement (2024) for the F.S. 489.103 exemption. The owner may build or improve a one-family or two-family residence for his own use or occupancy, must provide direct onsite supervision, may not hire an unlicensed person to act as contractor or supervisor, and becomes the responsible party of record on the permit. Sale or lease within 1 year is presumed to violate the exemption.

Why the confidence is not higherQuoted from the County's own disclosure form, extracted from PDF in this run. Held at 88 because the form is generic to the exemption and says nothing about solar or about whether Wausau's serving utility (see q22) will interconnect a self-installed array.

owner-builder disclosure form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2730/owner-builder_disclosure_statement_2024.pdf

Q8 What documents make up a complete submittal? Core Submittal package

No solar-specific submittal checklist is published. What the County's general forms require: a completed and NOTARIZED Application for Building Permit (owner and contractor signatures, state licence number, valuation of work, parcel ID); a completed Trade Permit Application for the electrical work naming the serving power company (GCE / FPL / WFECA-G); a certified copy of the Notice of Commencement for work of $2,500 or more, posted on site before the first inspection; plans and the $35 non-refundable Plan Submittal fee; Florida Product Approval numbers where called for; and a letter of authorization if the applicant is not the licence holder. Prior County approvals (Land Use Certificate, E-911 address, driveway where applicable) must already be in hand.

Why the confidence is not higherAssembled from the County's own forms, all re-downloaded and read in this run, and from LDC 10.01.03 and 10.01.04, pulled fresh through the Municode content API today. Held at 70 because there is genuinely no published checklist: the Building Department document library (12 files) was re-enumerated in this run and holds no submittal checklist, let alone a solar one -- same finding as the Ebro run, independently re-confirmed rather than carried over.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1631/building_permit_application-_2025_-_highlighted_-fillable.pdf

Q9 How many copies, and in what format? Submittal package

Not published as a copy count. Format: the County accepts applications by email to permits@washingtonfl.com for contractors already registered with the Building Department, and warns 'Emailed and faxed permits processing time may take up to 3 business days. All other permits should be brought into the office for processing.' The live iWorq register shows digital plan sets in routine use elsewhere in the county (stamped 'DIGITAL PLANS'/'PLANS UPLOADED'), though none of the 315 most recent permits pulled in this run is at a Wausau address, so that specific corroboration could not be repeated for Wausau.

Why the confidence is not higherThe email route and 3-business-day note are quoted from the Building Department page, re-fetched today. Held at 60, slightly below the Ebro run's 62, because the direct Wausau-address confirmation of digital plans that the Ebro run had is not available here (no Wausau-address permits in the current 315-permit window). F.S. 553.79(1)(b) independently requires electronic submission including PDF by email statewide.

department page checked 2026-09-14 https://washingtonfl.gov/departments/building/about/

Q10 Is a site plan required, and what must it show? Core Submittal package

For the Planning Department's Land Use Certificate step, yes: LDC 10.01.03.C requires 'a plot plan drawn to scale showing the actual dimensions of the lot to be built upon, the size, shape, height, and location of the buildings to be erected, dimensions and location of existing buildings, and width of front, side, and rear yards, and any historical or environmentally sensitive areas located on the site.' For the Building Department step no separate site plan is specified. Whether a rooftop PV retrofit triggers the Land Use Certificate at all is unsettled -- see q27.

Why the confidence is not higherQuoted from LDC Article X, pulled fresh through the Municode content API in this run, and from the current Land Use Certificate application form (rev. 09/29/2025), re-downloaded today. Held at 65 for the same reason as the Ebro run: the plot-plan description is written for a building being erected on a lot and reads oddly against a panel array on an existing roof.

land development code checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTIILADECO_ARTXADEN

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Not published. Neither the County building permit application, the trade permit application, the building inspection procedures, the fee schedule, nor the Land Development Code mentions a one-line or three-line diagram, and no solar plan-submittal handout exists.

Why the confidence is not higherProved absence, not a failure to look. All county documents used in this file were re-downloaded and extracted with pdftotext this run; the Land Development Code (Articles I, II, IX, X) and Chapter 14 were pulled as text through the Municode content API and searched with controls in this run: 'electrical' 27 hits in Chapter 14 alone (positive control passed), 'zzqqx' 0 hits across every article fetched (fabricated control passed), 'photovoltaic' 0 hits everywhere, 'solar' 0 in Chapter 14/Article I/Article IX/Article X/Article VII (Signs), 6 in Article II and all 6 are about commercial solar FARMS, never rooftop PV. Held at 72 for the same reason as Ebro: the Building Official will almost certainly ask for a line diagram at the counter whether or not anything is published.

department document library checked 2026-09-14 https://washingtonfl.gov/departments/building/about/

Q12 Are string and conductor calculations required? Drawings & calculations

Not published. No string sizing, conductor or voltage-drop calculation specific to solar is called for by any County form or by the adopted code text at local level. What Washington County DOES specify locally on conductors generically: Sec. 14-80 requires no service conductor smaller than no. 8 AWG copper or aluminium equivalent, with all service conductors for services of 400 amps or less the same size and insulation type.

Why the confidence is not higherSame enumeration and controls as q11, re-run in this session rather than inherited. Sec. 14-80 quoted from Chapter 14 text pulled fresh through the Municode content API today. NEC 2020 calculations apply through Sec. 14-68's deferral to 'The National Electric Code, as it adopted by the State of Florida.'

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

No local structural PE threshold is published. What binds instead is the Florida Building Code, 8th Edition (2023), and the County's own wind speed line: Sec. 14-37 sets State Road 20 as the wind speed line for Washington County. Wausau sits well north of SR 20 (SR 20 runs through the SOUTHERN part of the county, past Ebro and Vernon; Wausau is a northern county town near Chipley), so unlike Ebro's split parcels, a Wausau roof is unambiguously in the 120 mph zone rather than straddling a boundary. Florida Product Approval numbers are called for on the County's trade permit form for roof work.

Why the confidence is not higherSec. 14-37 was read in full from the code text pulled fresh in this run: 'The wind speed line for Washington County, Florida, shall be State Road 20, which runs through southern Washington County, and passes through Ebro, Florida.' Wausau is not named in this section at all (checked: 0 'Wausau' hits in Chapter 14, against 2 'Ebro' hits, both in this clause) -- consistent with Wausau lying entirely on the north side of the line, which this run treats as a genuine finding (no split-parcel ambiguity) rather than an absence. Held at 75, higher than the Ebro run's 60, precisely because Wausau's position removes the boundary ambiguity that capped Ebro's confidence; not higher still because the 120/130 mph figures are from 2001/2007 ordinances that predate the ASCE 7-22 maps the 8th Edition FBC actually uses, and no kW or attachment-count PE threshold is published anywhere.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

No local electrical PE stamp requirement is published. At state level F.S. 471.003(2)(h) exempts an electrical contractor licensed under ch. 489 from engineering licensure when the project 'Requires an electrical or plumbing or air-conditioning and refrigeration system with a value of $125,000 or less' and 'Requires an aggregate service capacity of 600 amperes (240 volts) or less on a residential electrical system' -- which covers essentially every residential rooftop PV job.

Why the confidence is not higherStatutory text fetched and read from the Florida Legislature's own site in this run. The local absence rests on the same enumeration and controls as q11-q12, re-run today. Held at 70 because the statute answers who may design without a PE, not whether the Building Official ever asks for a stamped drawing.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0400-0499/0471/Sections/0471.003.html

Q15 What does a residential solar permit cost? Core Fees

No flat solar fee. A residential PV job is priced as the sum of: (a) the building permit for 'Solar System Installation - Based on Building Valuation Table', landing on the County's valuation ladder -- $100 for work valued at $10,000 or less; $252 for the first $10,000 plus $6 per additional $1,000 up to $50,000; $492 for the first $50,000 plus $5 per additional $1,000 up to $100,000; (b) the electrical trade permit, 'Electrical Permit: Single Family Residential $125'; (c) a $35.00 non-refundable Plan Submittal fee, charged again on every re-submittal; (d) a plan review fee 'assessed at a minimum of $35 or 15%, whichever is greater'; (e) a State radon surcharge of 3% or $4.00, whichever is greater; and (f) a 3.5% convenience fee on credit card transactions (effective 17 March 2025). A typical $20,000 system runs roughly $312 building + $125 electrical + $35 submittal + plan review + surcharge -- before any Planning-Department step, which does not apply to Wausau for a bare rooftop retrofit (see q27).

Why the confidence is not higherEvery figure is from the County's own Construction Permit Fees 'Schedule A' (effective 09/01/2024) and the fee-change memo (effective 22 July 2024), both re-downloaded and extracted with pdftotext in this run. Held at 80 for the same genuine ambiguity the Ebro run flagged: the ICC Square Foot Construction Costs table underlying 'Based on Building Valuation Table' is expressly 'not intended to apply to alterations or repairs to existing buildings', so in practice the fee likely falls back to the contract-valuation ladder; and the 15% plan-review base is not stated.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q16 How is the fee calculated? Core Fees

Valuation. The building-permit half is 'Based on Building Valuation Table' for solar and on contract/valuation price for rehabilitation, renovation or remodelling; the plan review fee is a percentage (15%) with a $35 floor. The electrical half is flat at $125 for single family residential.

Why the confidence is not higherRead off Schedule A, re-downloaded today. The County's building permit application independently asks for 'Valuation of Work: $', confirming the valuation basis at application. Held at 82 for the same table-versus-ladder ambiguity as q15.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q17 Is there a separate plan-check fee? Fees

Yes, and there are two of them. A $35.00 NON-REFUNDABLE Plan Submittal fee is collected at time of submittal and charged again on every re-submittal and addendum. A separate plan review fee is then 'assessed at a minimum of $35 or 15%, whichever is greater', collected at permit issuance along with the permit fee and radon surcharge.

Why the confidence is not higherQuoted verbatim from the County's fee-change memo (effective 22 July 2024), re-downloaded and read in this run as page 1 of building_department_fees_4_2026.pdf. Held at 85 because the 15% base is not defined anywhere in the document.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q18 What is the stated plan-review turnaround? Core Timeline & validity

The County publishes no plan-review turnaround of its own. What binds is F.S. 553.792(1)(a): 5 business days after a complete and sufficient application for an electrical or structural permit on an EXISTING single-family residential dwelling valued under $15,000; 30 business days for a residential unit or electrical permit where the structure is less than 7,500 square feet. The County must give written notice within 5 business days of anything missing, or the application is automatically deemed complete. Separately, emailed/faxed permits may take up to 3 business days to process per the Building Department's own page.

Why the confidence is not higherThe statute was fetched and read from the Florida Legislature's own site in this run. Held at 70 because a statutory ceiling is not the same as a published service standard, and the 5-versus-30 day split turns on whether the reviewer treats a PV retrofit as work on an existing dwelling under $15,000 -- unresolved by anything published.

state statute checked 2026-09-14 http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0500-0599/0553/Sections/0553.792.html

Q19 How long is an issued permit valid before it expires? Timeline & validity

Three different answers are in force and they do not agree. The County's Application for Building Permit says the permit 'is valid as long as there is construction progress and an approved inspection is recorded within each 180 days (6 months) period.' The County's Trade Permit Application says 'This permit is VOID after six (6) months from issuance unless the work it covers has been commenced and has had ongoing inspections.' F.S. 553.79(1)(c) says 'A building permit issued by a local government for a single-family dwelling expires 1 year after the issuance of the permit or on the effective date of the next edition of the Florida Building Code, whichever is later.' Reported as a conflict, not resolved here -- same conflict found and re-verified independently for Wausau's own authority.

Why the confidence is not higherAll three texts re-read in full in this run: the two county forms from their PDFs (re-downloaded today), the statute from the Legislature's own site. Held at 72 because which instrument a permit technician applies at the counter is not published, and it is arguable whether a PV permit on an existing house is a permit 'for a single-family dwelling' within the statute.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1631/building_permit_application-_2025_-_highlighted_-fillable.pdf

Q20 Which permit portal does this authority use? Core Portal & process

iWorq. The County's public permit portal is at portal.iworq.net/WASHINGTONFL/permits/601, linked from the Building Department page as 'Permit Searches ... For Searches between 11/06/2014 to Current Date'. It exposes a permit register, per-permit detail pages, an inspection-request form and an inspection scheduler, and this is the same single portal Washington County runs for every jurisdiction in the county including Wausau.

Why the confidence is not higherThe portal was fetched and walked fresh in this run: all 21 result pages retrieved (315 permit IDs) and all 315 permit detail pages pulled and parsed. Held at 75, below the Ebro run's 88, because this run could not find a single Wausau-address (32463) or Wausau-municipality-stamped permit anywhere in the readable window (18 Aug-14 Sep 2026) to directly confirm the portal is actually used for Wausau jobs specifically, as opposed to being merely the county-wide system that in principle covers it -- the same date-range search is gated behind an invisible reCAPTCHA that could not be exercised here, so the historic register back to 06 Nov 2014 could not be searched for an older Wausau example.

permit portal checked 2026-09-14 https://portal.iworq.net/WASHINGTONFL/permits/601

Q21 Can the whole application be completed online? Core Portal & process

No. The portal is read-only plus inspection requests. Applications are submitted by email to permits@washingtonfl.com for contractors already registered with the Building Department, or brought into the office. Payment is taken at the counter or by card with a 3.5% convenience fee; the portal exposes no application or payment flow.

Why the confidence is not higherThe portal landing page was re-fetched and read in full in this run; its only forms are permit search, inspection request and inspection scheduler. The email/in-office routes are quoted from the Building Department page, re-fetched today. F.S. 553.79(1)(b) obliges electronic submission by email in PDF, so 'cannot be completed online' is true of the portal but not of the process as a whole.

permit portal checked 2026-09-14 https://portal.iworq.net/WASHINGTONFL/permits/601

Q22 Which utility handles interconnection here? Core Utility interconnection

Most likely West Florida Electric Cooperative Association (WFECA), headquartered at 905 St. John's Rd., Bonifay, FL, (800) 342-7400 -- but this is genuinely less certain than a typical answer in this survey. Gulf Coast Electric Cooperative (Ebro's utility) is ruled OUT: its own 'About' page names its served municipalities as 'Wewahitchka, Ebro, Lynn Haven, White City, Fountain, and Southport', with no Wausau. The Washington County Directory lists only two power companies for the whole county -- 'Florida Power [&] Lights' and 'West Florida Electric' -- and the County's own Trade Permit Application offers exactly three utility checkboxes: 'GCE / FPL / WFECA - G'. West Florida Electric's own homepage (fetched once successfully in this run before the domain became persistently unreachable) describes itself as 'a member-owned, non-profit cooperative providing reliable electricity in Calhoun, Holmes, Jackson and Washington Counties' -- geographically the co-op whose territory reaches the interior/northern part of the county where Wausau sits, next to Holmes and Jackson Counties. Florida Power & Light remains a live alternative and cannot be ruled out from what was reachable in this run.

Why the confidence is not higherwestfloridaelectric.com resolved and served real content (its own description, and nav links to /solar-energy, /rates-and-fees, /service-requirements) exactly once early in this run; every subsequent attempt in this session -- repeated curl retries, a WebFetch call, and independent DNS-over-HTTPS lookups against Google's and Cloudflare's public resolvers -- returned NXDOMAIN for that domain, so its solar/interconnection subpages could not be reached and are booked separately as not_found (q23, q42) rather than guessed or backfilled from Gulf Coast Electric's tariff, which would be citing the wrong utility's document. wfeca.com and wfeca.coop, checked as possible short-form domains, resolve but to unrelated/placeholder content (a bare 'Hello World!' Wayback capture for wfeca.com), so they were not used as sources. Held at only 50 -- below the survey's normal floor for a headline finding -- because the county-vs-Wausau-specific-address distinction the playbook demands (no permits in this county's own register are readable at a Wausau address in the current window) could not be closed, and because FPL genuinely remains possible; this is reported as the best-supported inference rather than a proved fact, per the instruction to say so rather than substitute a confident-looking wrong answer.

utility own page checked 2026-09-14 https://westfloridaelectric.com/

Q23 Where does the utility sit in the sequence? Core Utility interconnection

Nothing published by this authority.

Where we lookedWashington County's Trade Permit Application (utility checkbox GCE/FPL/WFECA-G) and Gulf Coast Electric Cooperative's own Schedule NMR-1 tariff (ruled out as Wausau's utility, see q22 and q2 why); West Florida Electric Cooperative Association's own site (westfloridaelectric.com), which would carry its net-metering/interconnection sequence, resolved once early in this run but returned NXDOMAIN on every subsequent attempt (repeated curl retries, WebFetch, and DNS-over-HTTPS lookups against Google and Cloudflare's public resolvers all failed after the first successful homepage fetch); Florida PSC's ElectricNaturalGas/ElectricTerritories page returned only an Angular JS shell with no static content. Genuinely unreachable in this run, not a proved absence -- do not assume GCEC's 'inspected by local code officials prior to operation' sequence carries over to whichever utility actually serves Wausau.

https://westfloridaelectric.com/

Q24 Is a HOA or architectural approval required first? Overlays & special cases

Not by the authority in the general case -- but Washington County's OWN fee schedule contains a line that names Wausau's exact situation more directly than it did for Ebro. Neither Wausau nor Washington County requires HOA or architectural approval for rooftop PV as a general rule, and F.S. 163.04(2) voids any deed restriction or covenant that prohibits solar collectors (leaving such a body only the power to choose the roof location within south +/-45 degrees). But the fee schedule's SIGN PERMIT line reads: 'ARC Approval if in Sunny Hills or Leisure Lakes Subdivision or inside any city limits.' Wausau IS a city/town with its own limits -- so on the sign-permit line at least, this note reaches Wausau directly rather than ambiguously. Whether the County means the same thing for a solar permit is not stated anywhere.

Why the confidence is not higherThe statute was fetched and read from the Legislature's own site in this run. The fee-schedule line was re-read from building_department_fees_4_2026.pdf, freshly downloaded today. Held at 62, similar to the Ebro run's 65, because the note sits on the SIGN permit line specifically and nothing published extends it to solar; but flagged as a sharper finding than Ebro's, because Wausau -- unlike Ebro's case discussion -- unambiguously IS 'inside any city limits' as an incorporated municipality (see audit Note 1: created by FL House Bill 2530, 1963, elected council government), so if the County ever does apply this note beyond signs, Wausau is squarely inside its reach rather than a borderline case.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q25 Is there a historic-district review? Overlays & special cases

No historic-district review is required. Washington County has no historic district or historic preservation ordinance reaching rooftop PV; the only historic touchpoints in the Land Development Code are a plot-plan requirement to show 'any historical or environmentally sensitive areas' (LDC 10.01.03.C) and adoption by reference of the Secretary of the Interior's Standards for Rehabilitation and the Florida Division of Historical Resources Master Site File (LDC 1.03.01), neither of which creates a review step for a house. Wausau publishes nothing of its own.

Why the confidence is not higherBoth LDC citations re-read from code text pulled fresh through the Municode content API in this run, with the same controls as q11. Held at 62, slightly below the Ebro run's 65, because Wausau -- unlike Ebro -- IS a documented incorporated municipality with its own elected council (per its own audit) and could in principle have passed a local historic designation that would appear nowhere in the county's documents or on any codifier; Wausau has no website and no code on Municode/eCode360/American Legal (checked fresh in this run), so such a designation can neither be found nor ruled out.

land development code checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTIILADECO_ARTIGEPR

Q26 Is a wind or windstorm certification required? Overlays & special cases

Yes, in the form of the county wind speed line -- and for Wausau specifically it resolves cleanly rather than ambiguously. Washington County Code Sec. 14-37 sets State Road 20, which runs through the SOUTHERN part of the county (past Ebro), as the wind speed line: 130 mph south of it, 120 mph north of it. Wausau sits in the northern part of the county, so a Wausau roof is unambiguously in the 120 mph zone. Separately the County's Trade Permit Application requires a 'FL. PRODUCT APPROVAL CODE' for roof work, which is the Florida Product Approval route by which wind resistance is demonstrated. There is no separate windstorm certificate as such.

Why the confidence is not higherSec. 14-37 was re-read in full from the code text pulled fresh through the Municode API in this run. Held at 80, above the Ebro run's 82 for a different reason than that number suggests -- here the gain is that Wausau does NOT sit astride the line the way Ebro does (0 'Wausau' hits anywhere in the section, consistent with the town being entirely on one side), so there is no split-parcel ambiguity to resolve for an installer; held below 85 only because the 120/130 mph figures are from 2001/2007 ordinances that sit awkwardly against the ASCE 7-22 maps the current 8th Edition FBC actually uses.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

No Special Use Permit or Council approval is required for a rooftop PV system as such. The one Council-level step that does exist is the Town of Wausau letter: the County's residential planning instructions require 'A letter from the Town of Wausau, Ebro, and Caryville ... for any new development within the City limits', attached to the County Land Use Application. That is written for NEW DEVELOPMENT, and a rooftop retrofit on an existing house is probably not caught: LDC 10.01.03 lists the things needing a Land Use Certificate (single-family residence, mobile home, modular home, swimming pool, accessory structure, utility (power, well, septic), lot split, temporary structures, plus a catch-all for anything 'deemed by the Development Administrator to be similar') and rooftop PV is not among them, while LDC 10.01.04.D separately exempts 'The alteration of an existing building or structure so long as no change is made to its gross floor area, its use, or the amount of impervious surface on the site.' A GROUND mount inside the town limits would be a different matter -- it adds a structure and would likely re-trigger 10.01.03.A.5/A.6 and the Wausau letter. At the commercial end, 'Solar Farms' are a Special Exception use in a small number of land use districts, with a 100-foot residential setback and a 100-foot buffer from named named waterways.

Why the confidence is not higherEvery clause read from first-party text re-fetched in this run: the residential instruction sheet PDF, LDC 10.01.03 and 10.01.04 (Article X, pulled fresh through the Municode content API), and the Article II use table and solar-farm standards (also pulled fresh). This is the identical LDC mechanism the Ebro run flagged as its single most consequential open point, now independently re-derived for Wausau from the same county-wide code text (which by its own terms co-governs Wausau, see q1) rather than assumed to transfer. Held at 72, matching Ebro's confidence, because nothing published states this in words for a solar job specifically; the Planning Department (850-415-5093) decides in practice.

county planning instruction sheet checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2554/wc_new_construction_residential_permit_instructions_10062023.pdf

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No cap in the Land Development Code on residential rooftop generation -- proved absent with the same controls as q11. Any binding capacity cap would be the serving utility's own net-metering tariff, but which utility serves Wausau is not fully resolved in this run (see q22), so the specific kW figure cannot be stated with confidence; it should NOT be assumed to be Gulf Coast Electric Cooperative's 25 kW / 10 kW figures, since GCEC does not serve Wausau (see q2, q22).

Why the confidence is not higherThe LDC absence rests on the same enumeration and controls as q11, re-run fresh in this session: 0 'photovoltaic' hits, 6 'solar' hits in Article II and all 6 about commercial solar farms, 'electrical' 27 hits as positive control, 'zzqqx' 0 as fabricated control. Held at 68 -- lower than the Ebro run's 80 -- specifically because Ebro's figure came from GCEC's own tariff and Wausau's utility could not be confirmed in this run (q22), so only the county-code half of this answer is solid; the utility-cap half is honestly unresolved rather than guessed.

land development code checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTIILADECO_ARTIILAUSVEBU

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? NEC 2020 (NFPA 70, 2020 edition), by the same statewide chain that applies to every Florida jurisdiction: Washington County Code Sec. 14-68 adopts 'The National Electric Code, as it adopted by the State of Florida, as it may be amended and updated from time to time', and the state's own edition is NFPA 70, 2020, via FAC 69A-60.005(2)(qq). 55% · county code chapter
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023). Confirmed directly from the County's OWN current building permit application, which is the actual document a Wausau applicant fills out: it is stamped 'Code in effect 8th Edition Florida Building Code'. Washington County Code Sec. 14-36 adopts 'The Florida Building Code, as it may be amended and updated from time to time ... for use in Washington County, Florida.' A 9th Edition (2026) exists in draft only. 85% · permit application form
    • Which fire code edition is in force? Almost certainly the Florida Fire Prevention Code -- NFPA 1, Florida 2021 Edition, and NFPA 101, Florida 2021 Edition -- by the same statewide mechanism as every other Florida authority, since Washington County Code Sec. 30-32 adopts 'F.S. ch. 633, Fire Prevention and Control, and F.A.C. ch. 4A, Florida Fire Prevention Code' by reference without naming a current edition (the 'ch. 4A' and 'Standard Fire Prevention Code' citations in the county code are stale, retired designations, not a different code in force). 50% · county code chapter
    • Are there local amendments to any of the above? Yes. Washington County has real local amendments in Chapter 14, and they reach residential electrical work identically to how they reach Ebro's, since it is the same county-wide chapter. Article III (Electrical Code) is a local ordinance code of its own dating from Ord. No. 80-2 (1980); Sec. 14-67 makes its priority explicit ('The National Electrical Code standards and regulations shall apply to the extent they are not in conflict with this article'). Article II adds the SR 20 wind speed line (Sec. 14-37), which for Wausau resolves to a flat 120 mph figure (see q13, q26) rather than a split-parcel question. Wausau itself has no amendments of its own. 80% · county code chapter
    • What is the installation judged against? The installation is judged against the Florida Building Code, 8th Edition (2023) and NFPA 70 (NEC) 2020 as adopted by the state, plus Washington County Code Chapter 14 Article III, a live local electrical ordinance with its own prescriptive rules on services, meters, disconnects, grounding and conductor sizes. Chapter 14 Article II sets the county wind speed line at SR 20, which resolves for Wausau to a flat 120 mph (see q13). The Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida 2021 Editions) applies by operation of state rule. The Land Development Code is the county's, co-adopted by the Wausau Town Council effective 14 December 2023. 78% · county code chapter
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for Town of Wausau on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Rapid shutdown is very likely required, to NEC 2020 -- i.e. NEC 690.12 as it stands in the 2020 edition -- by the same chain as every other Florida authority: Sec. 14-68 adopts the NEC as adopted by the state, and the state edition is NFPA 70, 2020. Neither Wausau nor Washington County adds or subtracts anything locally. 50% · county code chapter
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? No AHJ-specific placard set. Neither Wausau nor Washington County specifies any placard, marking or label for a PV system at the service equipment. Local marking rules in Chapter 14 that do exist are generic: Sec. 14-79 requires all electrical materials/devices to bear the manufacturer's identification with voltage/current/wattage markings and the underwriter's label, and Sec. 14-78(e) requires the INSPECTOR to place a notice or certificate at the service switch on passing. Whether Wausau's utility adds its own marking spec (as GCEC does for Ebro) could not be determined -- see q22, q42. 55% · county code chapter
    • Does the authority specify placard wording of its own? No. Neither the Town of Wausau nor Washington County specifies placard wording of its own. 72% · land development code
    • Does it specify letter height, colour or material? No. No letter height, colour, material or durability specification is set by Wausau or by Washington County. 70% · county code chapter
    • Is a site plan / facility map placard required, and what must it show? Nothing beyond NEC 705.10 as it stands in the 2020 edition. No County or Town requirement for a site plan, facility map or directory placard exists locally, and no local rule specifies what one must show. 48% · county code chapter
    • Where must the labels be placed? No local placement rule for PV labels specifically. What is fixed locally is the equipment they attach to: Sec. 14-73 puts all residential meters outside, centre of meter four to six feet above grade; Sec. 14-72 puts the service-disconnecting means at a readily accessible location nearest the point of entrance; Sec. 14-80 caps the main service switch handle at six feet, floors it at 3-1/2 feet; Sec. 14-81 requires all service disconnects/panels readily accessible and never in or behind a bathroom. Where Wausau's own utility would add a label-location requirement (as GCEC does for Ebro) could not be determined in this run. 55% · county code chapter
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? Washington County's own rules fix the meter's position rather than any disconnect-to-meter distance: Sec. 14-73 puts residential meters outside with the meter centre four to six feet above grade, and Sec. 14-72 puts the service-disconnecting means at a readily accessible location nearest the point of entrance of the service entrance conductors. No County document states a distance between a PV AC disconnect and the meter. Whether Wausau's serving utility adds a disconnect-to-meter rule of its own (as Gulf Coast Electric Cooperative does for Ebro, requiring a lockable, tagging-accessible grid-side disconnect) could not be confirmed for Wausau's own utility in this run. 55% · county code chapter
    • Must equipment be on a specific approved list? Yes, in two county-level respects. Florida Product Approval: the Trade Permit Application has a 'FL. PRODUCT APPROVAL CODE' field and the inspection procedures require the Product Approval Sheet be on file before inspection. Listing: Sec. 14-79 requires all electrical materials/apparatus/fittings/appliances/devices to bear the manufacturer's identification, voltage/current/wattage markings, 'and shall bear the underwriter's label.' Whether Wausau's serving utility adds its own listing standard (as GCEC requires UL 1741/IEEE 1547 for Ebro) could not be confirmed. 65% · inspection procedures
    • Are batteries permitted, and under what conditions? Batteries are not addressed by the Town of Wausau or by Washington County. No local ESS provision exists in Chapter 14, Chapter 30, or the Land Development Code. What governs is the Florida Fire Prevention Code (NFPA 1, Florida 2021 Edition) and the Florida Building Code 8th Edition, both applying by operation of state law regardless of anything the town or county has passed. 55% · county code chapter
    • Is there a separate ESS permit or inspection? No separate ESS permit or ESS inspection is published. The County's fee schedule has no energy storage or battery line -- its residential electrical products are single family residential, single family rewire, multi-family per unit, addition, service upgrade/temp pole, and mobile homes/power poles/swimming pools -- and the inspection procedures list no ESS stage. In practice a battery would ride on the electrical trade permit and, if structural work is involved, the building permit. 62% · fee schedule
    • Is a ground mount treated as a structure? Yes -- a ground mount is treated as a structure, and this is where being inside the Wausau town limits starts to matter, exactly as it does for Ebro. LDC 10.01.03.A requires a Land Use Certificate 'Before any structure or use listed below shall be added to, erected, reconstructed, structurally altered, moved, or demolished', and the list includes 'Accessory structure' and 'Utility (power, well, septic, etc.)'. The 10.01.04.D alteration exemption that arguably covers a rooftop retrofit does not reach a new ground-mounted structure, because a ground mount adds a structure and changes impervious surface. So for a ground mount inside Wausau the sequence is: Town of Wausau letter, then $50 Land Use Certificate with plot plan (issued or denied within ten working days), then the County building permit and electrical trade permit. 62% · land development code
    • Is there a local rule on service upgrades or busbar sizing? No busbar or 120% rule is published locally -- that comes through NEC 2020 705.12. What Washington County DOES set locally, applying identically inside Wausau: Sec. 14-80 -- no service conductor smaller than no. 8 AWG copper or aluminium equivalent, main service switch handle no higher than six feet nor lower than 3-1/2 feet from grade/platform; Sec. 14-72 -- service conductors in metal conduit from the point of attachment to the master disconnect, disconnect at a readily accessible location nearest the point of entrance, no more than 25 feet of unprotected run, and 'New services and relocation of services must be acceptable to the power company and to the county'; Sec. 14-73 -- residential meters mounted outside, centre of meter four to six feet above grade/floor, never in bathrooms, toilet rooms, restaurant kitchens or stairways; Sec. 14-81 -- disconnects/panels 'readily accessible', never in or behind a bathroom, and 'No service shall be considered complete until legibly indexed'; Sec. 14-83 -- copper grounding conductor, not smaller than no. 8 AWG, on the supply side of the service disconnect; Sec. 14-74 -- a new or altered service 'shall not be connected until a local utility company has received an authorized inspection certificate.' 80% · county code chapter
    • Is a specific mounting system or attachment spacing required? Not published. No mounting system, attachment spacing, rail, flashing or standoff requirement appears in any County form, in Chapter 14, or in the Land Development Code. What does apply is Florida Product Approval -- the County's Trade Permit Application requires a 'FL. PRODUCT APPROVAL CODE' for roof work and the inspection procedures require the Product Approval Sheet be on file before inspection. 65% · permit application form

20 questions answered against Town of Wausau’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

NEC 2020 (NFPA 70, 2020 edition), by the same statewide chain that applies to every Florida jurisdiction: Washington County Code Sec. 14-68 adopts 'The National Electric Code, as it adopted by the State of Florida, as it may be amended and updated from time to time', and the state's own edition is NFPA 70, 2020, via FAC 69A-60.005(2)(qq).

Why the confidence is not higherSec. 14-68 was re-read from the code text pulled fresh through the Municode content API in this run. The state-rule half could NOT be independently re-verified today: flrules.org, which the Ebro run used to download and read the actual .doc rule file, returned a Cloudflare 'Just a moment...' JS challenge to every route tried in this run (the ruleNo.asp HTML page and the readFile.asp direct .doc download alike), so the 2020 figure here rests on Sec. 14-68's deferral plus the same-day knowledge that this is a slow-moving triennial state rule cycle, not on a document opened in this run. Held at 55, well below the Ebro run's 85, to be honest about that gap rather than silently reuse a citation this run could not itself confirm.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023). Confirmed directly from the County's OWN current building permit application, which is the actual document a Wausau applicant fills out: it is stamped 'Code in effect 8th Edition Florida Building Code'. Washington County Code Sec. 14-36 adopts 'The Florida Building Code, as it may be amended and updated from time to time ... for use in Washington County, Florida.' A 9th Edition (2026) exists in draft only.

Why the confidence is not higherThe county form was re-downloaded and read with pdftotext in this run -- a first-party, dated, directly-applicable source for Wausau's own permitting authority, which does not depend on flrules.org (which 403'd/Cloudflare-challenged every route in this session, see q29). Sec. 14-36 read from the code text pulled fresh through the Municode content API. Held at 85 rather than the Ebro run's 92 because the underlying FAC rule text itself (61G20-1.001) could not be independently opened in this run to confirm the exact amendment-history list, so this answer rests on the county's own form plus the code chapter rather than the state rule document directly.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1631/building_permit_application-_2025_-_highlighted_-fillable.pdf

Q31 Which fire code edition is in force? Code editions in force

Almost certainly the Florida Fire Prevention Code -- NFPA 1, Florida 2021 Edition, and NFPA 101, Florida 2021 Edition -- by the same statewide mechanism as every other Florida authority, since Washington County Code Sec. 30-32 adopts 'F.S. ch. 633, Fire Prevention and Control, and F.A.C. ch. 4A, Florida Fire Prevention Code' by reference without naming a current edition (the 'ch. 4A' and 'Standard Fire Prevention Code' citations in the county code are stale, retired designations, not a different code in force).

Why the confidence is not higherSec. 30-32 was re-read from Chapter 30 (Fire Prevention and Protection), pulled fresh through the Municode content API in this run. The state edition/effective-date confirmation that the Ebro run obtained from flrules.org's chapter listing for 69A-60 could NOT be repeated in this run: every route into flrules.org returned a Cloudflare JS challenge today (see q29). Held at 50 -- markedly below the Ebro run's 85 -- to be transparent that this is inference from a stale county cross-reference plus same-day general knowledge, not a document read in this session; the substance also could not be read (see q36, not_found).

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH30FIPRPR

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes. Washington County has real local amendments in Chapter 14, and they reach residential electrical work identically to how they reach Ebro's, since it is the same county-wide chapter. Article III (Electrical Code) is a local ordinance code of its own dating from Ord. No. 80-2 (1980); Sec. 14-67 makes its priority explicit ('The National Electrical Code standards and regulations shall apply to the extent they are not in conflict with this article'). Article II adds the SR 20 wind speed line (Sec. 14-37), which for Wausau resolves to a flat 120 mph figure (see q13, q26) rather than a split-parcel question. Wausau itself has no amendments of its own.

Why the confidence is not higherChapter 14 was pulled as text through the Municode content API and re-read section by section in this run; Sec. 14-67 and Sec. 14-37 quoted verbatim from that fresh fetch. Held at 80, matching the Ebro run, because Sec. 14-67's purported subordination of the NEC to a 1980 county ordinance sits in tension with F.S. 553.73's exclusive state adoption of the building code -- the amendments are on the books and administered, but their current legal force is not something this run can settle.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q33 What is the installation judged against? Core Electrical

The installation is judged against the Florida Building Code, 8th Edition (2023) and NFPA 70 (NEC) 2020 as adopted by the state, plus Washington County Code Chapter 14 Article III, a live local electrical ordinance with its own prescriptive rules on services, meters, disconnects, grounding and conductor sizes. Chapter 14 Article II sets the county wind speed line at SR 20, which resolves for Wausau to a flat 120 mph (see q13). The Florida Fire Prevention Code (NFPA 1 and NFPA 101, Florida 2021 Editions) applies by operation of state rule. The Land Development Code is the county's, co-adopted by the Wausau Town Council effective 14 December 2023.

Why the confidence is not higherAssembled from first-party text re-read in this run: Sec. 14-36, 14-37, 14-66 to 14-89, Sec. 30-32, LDC 1.10.01, all pulled fresh through the Municode content API today. Held at 78, slightly below the Ebro run's 82, because the NFPA 1 text and the FAC rule confirming NEC/FBC edition dates could not be independently re-opened this session (flrules.org Cloudflare-blocked throughout, see q29/q31).

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

No busbar or 120% rule is published locally -- that comes through NEC 2020 705.12. What Washington County DOES set locally, applying identically inside Wausau: Sec. 14-80 -- no service conductor smaller than no. 8 AWG copper or aluminium equivalent, main service switch handle no higher than six feet nor lower than 3-1/2 feet from grade/platform; Sec. 14-72 -- service conductors in metal conduit from the point of attachment to the master disconnect, disconnect at a readily accessible location nearest the point of entrance, no more than 25 feet of unprotected run, and 'New services and relocation of services must be acceptable to the power company and to the county'; Sec. 14-73 -- residential meters mounted outside, centre of meter four to six feet above grade/floor, never in bathrooms, toilet rooms, restaurant kitchens or stairways; Sec. 14-81 -- disconnects/panels 'readily accessible', never in or behind a bathroom, and 'No service shall be considered complete until legibly indexed'; Sec. 14-83 -- copper grounding conductor, not smaller than no. 8 AWG, on the supply side of the service disconnect; Sec. 14-74 -- a new or altered service 'shall not be connected until a local utility company has received an authorized inspection certificate.'

Why the confidence is not higherAll quoted from Chapter 14 text re-pulled through the Municode content API and directly grep-verified against the raw extracted text in this run (not carried over from the Ebro file). The fee schedule independently confirms the service-upgrade route is a distinct product: 'Electrical Permit: Residential Service Upgrade/Temp Pole $100 minimum', re-read from the fee schedule fetched today. Held at 80, matching Ebro, for the same Sec. 14-67 legal-force caveat as q32.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Not published. No mounting system, attachment spacing, rail, flashing or standoff requirement appears in any County form, in Chapter 14, or in the Land Development Code. What does apply is Florida Product Approval -- the County's Trade Permit Application requires a 'FL. PRODUCT APPROVAL CODE' for roof work and the inspection procedures require the Product Approval Sheet be on file before inspection.

Why the confidence is not higherProved absence on the same enumeration and controls as q11, re-run fresh this session. The product approval requirement is quoted from the County's trade permit form and inspection procedures, both re-downloaded and extracted from PDF today. Held at 65, matching Ebro, because the product approval lines are written for roofing/structural components generally rather than PV racking specifically.

permit application form checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1892/trade_permit_application_-_ada_04_30_25.pdf

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedWashington County Code Chapter 30 (Fire Prevention and Protection) in full, re-pulled as text through the Municode content API in this run -- Sec. 30-32 adopts the fire code by reference and names no setback; Chapter 14 (Buildings and Building Regulations) in full, including the wind speed line ordinance Sec. 14-37; the Land Development Code Articles I, II, IX and X as text, where the only 6 'solar' hits are all about commercial solar FARMS and 'photovoltaic' returns 0 -- with 'electrical' at 27 hits as the positive control and 'zzqqx' at 0 as the fabricated control, both passing in this run; the Building Department document library (12 files) and Planning Department library (17 files), each re-enumerated, neither containing any fire, setback or roof-access document. The governing text is NFPA 1, the Fire Code, Florida 2021 Edition -- and its ridge-setback and roof-access provisions could NOT be read: flrules.org, which the Ebro run used successfully, returned a Cloudflare 'Just a moment...' JS-challenge page to every route attempted in THIS run, and NFPA/ICC hosts return hard 403s independently of that. An unreachable source, NOT a proved absence -- do not record Wausau as having no ridge setback on the strength of this.

https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH30FIPRPR

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Rapid shutdown is very likely required, to NEC 2020 -- i.e. NEC 690.12 as it stands in the 2020 edition -- by the same chain as every other Florida authority: Sec. 14-68 adopts the NEC as adopted by the state, and the state edition is NFPA 70, 2020. Neither Wausau nor Washington County adds or subtracts anything locally.

Why the confidence is not higherSec. 14-68 re-read from the county code text pulled fresh in this run. Unlike the Ebro run, THIS run could not independently re-open the FAC rule document confirming the 2020 edition (flrules.org Cloudflare-blocked throughout, see q29) or the substance of NEC 690.12 itself (NFPA/ICC 403 consistently). Held at 50, well below the Ebro run's 78, to be honest that neither the edition chain nor the section text was independently verified in this session -- this is inference from Sec. 14-68 plus general knowledge of the statewide NEC cycle, not a document read today.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

No AHJ-specific placard set. Neither Wausau nor Washington County specifies any placard, marking or label for a PV system at the service equipment. Local marking rules in Chapter 14 that do exist are generic: Sec. 14-79 requires all electrical materials/devices to bear the manufacturer's identification with voltage/current/wattage markings and the underwriter's label, and Sec. 14-78(e) requires the INSPECTOR to place a notice or certificate at the service switch on passing. Whether Wausau's utility adds its own marking spec (as GCEC does for Ebro) could not be determined -- see q22, q42.

Why the confidence is not higherProved absence at local level on the same enumeration and controls as q11, re-run fresh this session, plus Sec. 14-79/14-78(e) quoted from Chapter 14 text pulled today. Held at 55, below the Ebro run's 62, because the utility half of the answer -- which the Ebro run could state confidently from GCEC's own tariff -- is unresolved here (see q22, q42 not_found) and this run declines to substitute GCEC's requirements, which do not apply to Wausau.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No. Neither the Town of Wausau nor Washington County specifies placard wording of its own.

Why the confidence is not higherProved absence on the same enumeration and controls as q11, now run across a WIDER set of articles than the Ebro check: Chapter 14 (0 'placard'/'photovoltaic' hits), LDC Articles I, II, IX, X (0 hits), and additionally Article VII (Sign Regulations) specifically, pulled fresh and checked in this run -- 0 'solar'/'photovoltaic' hits there either, ruling out a placard rule hiding in the sign chapter. Wausau has no code of its own on any codifier: the complete Florida Municode client list (416 entries) was re-pulled from the Municode API in this run, with Chipley present as positive control and Wausau, Ebro, Caryville and Vernon all absent. Held at 72, matching Ebro, because a wording sheet handed over a counter would leave no published trace.

land development code checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTIILADECO_ARTVIISIRE

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

No. No letter height, colour, material or durability specification is set by Wausau or by Washington County.

Why the confidence is not higherSame enumeration and controls as q39, including the added Article VII (Signs) check. The nearest thing in the county code is Sec. 14-79's requirement that equipment bear the manufacturer's markings and the underwriter's label, which is a listing requirement rather than a placard specification. Held at 70, matching Ebro.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing beyond NEC 705.10 as it stands in the 2020 edition. No County or Town requirement for a site plan, facility map or directory placard exists locally, and no local rule specifies what one must show.

Why the confidence is not higherProved absence at local level on the same enumeration and controls as q39/q40. Held at only 48, below the Ebro run's 55, because the governing NEC 2020 705.10 text itself could not be read in this environment at all in this session (NFPA/ICC 403s, and flrules.org fully Cloudflare-blocked, see q29/q37) -- lower even than Ebro's already-reduced confidence because Ebro's run at least had the state-rule-edition chain independently confirmed, which this run does not.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedWashington County's Trade Permit Application and Chapter 14 (no utility-specific marking clause of its own); Gulf Coast Electric Cooperative's tariff, deliberately NOT used since GCEC does not serve Wausau (see q2, q22); West Florida Electric Cooperative Association's own site (westfloridaelectric.com), which would carry any additional utility marking/disconnect spec, resolved once early in this run (real homepage content fetched) but returned NXDOMAIN on every subsequent attempt including WebFetch and DNS-over-HTTPS lookups against two independent public resolvers. Genuinely unreachable in this run.

https://westfloridaelectric.com/

Q43 Where must the labels be placed? Core Labels Signage & labelling

No local placement rule for PV labels specifically. What is fixed locally is the equipment they attach to: Sec. 14-73 puts all residential meters outside, centre of meter four to six feet above grade; Sec. 14-72 puts the service-disconnecting means at a readily accessible location nearest the point of entrance; Sec. 14-80 caps the main service switch handle at six feet, floors it at 3-1/2 feet; Sec. 14-81 requires all service disconnects/panels readily accessible and never in or behind a bathroom. Where Wausau's own utility would add a label-location requirement (as GCEC does for Ebro) could not be determined in this run.

Why the confidence is not higherThe county sections re-quoted from Chapter 14 text pulled fresh through the Municode content API today. Held at 55, below Ebro's 60, because the utility-side half of the question is unresolved (see q22, q42 not_found) rather than answered from a different utility's tariff.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q44 Must equipment be on a specific approved list? Equipment listing

Yes, in two county-level respects. Florida Product Approval: the Trade Permit Application has a 'FL. PRODUCT APPROVAL CODE' field and the inspection procedures require the Product Approval Sheet be on file before inspection. Listing: Sec. 14-79 requires all electrical materials/apparatus/fittings/appliances/devices to bear the manufacturer's identification, voltage/current/wattage markings, 'and shall bear the underwriter's label.' Whether Wausau's serving utility adds its own listing standard (as GCEC requires UL 1741/IEEE 1547 for Ebro) could not be confirmed.

Why the confidence is not higherAll county sources re-read first-party in this run -- the trade permit form and inspection procedures from PDF (re-downloaded today), Sec. 14-79 from the code text pulled fresh through the Municode content API. Held at 65, below Ebro's 70, because the utility-standard half is unresolved (see q22) and this run does not substitute GCEC's UL 1741/IEEE 1547 clause, which is that utility's tariff, not Wausau's.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Batteries are not addressed by the Town of Wausau or by Washington County. No local ESS provision exists in Chapter 14, Chapter 30, or the Land Development Code. What governs is the Florida Fire Prevention Code (NFPA 1, Florida 2021 Edition) and the Florida Building Code 8th Edition, both applying by operation of state law regardless of anything the town or county has passed.

Why the confidence is not higherThe local absence is proved on the same enumeration and controls as q11, re-run fresh this session, with 'photovoltaic' returning 0 hits and all 6 'solar' hits about solar farms. Held at 55, below the Ebro run's 60, because the substantive state ESS rules (NFPA 1 Chapter 52 and its Florida amendments) could NOT be read in this run at all: the flrules.org route the Ebro run used to at least name the chapter and effective date returned a Cloudflare JS challenge to every route tried today, on top of the pre-existing NFPA/ICC 403s.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH30FIPRPR

Q46 Is there a separate ESS permit or inspection? Battery / ESS

No separate ESS permit or ESS inspection is published. The County's fee schedule has no energy storage or battery line -- its residential electrical products are single family residential, single family rewire, multi-family per unit, addition, service upgrade/temp pole, and mobile homes/power poles/swimming pools -- and the inspection procedures list no ESS stage. In practice a battery would ride on the electrical trade permit and, if structural work is involved, the building permit.

Why the confidence is not higherThe fee schedule and inspection procedures were both re-downloaded and extracted from PDF and read line by line in this run, and the whole set of code articles was searched with controls as described in q11. Held at 62, matching Ebro, because the absence of a fee line is not the same as the absence of a practice: 'Construction cost may be based on valuation, determined by group & type of construction' leaves the Building Official room to price and stage an ESS job however he chooses.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q47 Is a ground mount treated as a structure? Core Ground mount

Yes -- a ground mount is treated as a structure, and this is where being inside the Wausau town limits starts to matter, exactly as it does for Ebro. LDC 10.01.03.A requires a Land Use Certificate 'Before any structure or use listed below shall be added to, erected, reconstructed, structurally altered, moved, or demolished', and the list includes 'Accessory structure' and 'Utility (power, well, septic, etc.)'. The 10.01.04.D alteration exemption that arguably covers a rooftop retrofit does not reach a new ground-mounted structure, because a ground mount adds a structure and changes impervious surface. So for a ground mount inside Wausau the sequence is: Town of Wausau letter, then $50 Land Use Certificate with plot plan (issued or denied within ten working days), then the County building permit and electrical trade permit.

Why the confidence is not higherBuilt from LDC 10.01.03, 10.01.04 and the Land Use Certificate application form, all re-read first-party in this run through the Municode content API and the freshly re-downloaded PDF form. Held at 62, matching Ebro, because no Washington County document says the words 'ground mounted solar' anywhere; whether the Development Administrator classes an array as an accessory structure, a utility, or under the catch-all determines both setbacks and whether the Wausau letter is demanded. Confirm with the Planning Department (850-415-5093) before quoting a ground mount inside Wausau.

land development code checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTIILADECO_ARTXADEN

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Washington County's own rules fix the meter's position rather than any disconnect-to-meter distance: Sec. 14-73 puts residential meters outside with the meter centre four to six feet above grade, and Sec. 14-72 puts the service-disconnecting means at a readily accessible location nearest the point of entrance of the service entrance conductors. No County document states a distance between a PV AC disconnect and the meter. Whether Wausau's serving utility adds a disconnect-to-meter rule of its own (as Gulf Coast Electric Cooperative does for Ebro, requiring a lockable, tagging-accessible grid-side disconnect) could not be confirmed for Wausau's own utility in this run.

Why the confidence is not higherChapter 14 sections re-quoted from text pulled fresh through the Municode content API today. Held at 55, below Ebro's 75, specifically because the utility half of this answer is unresolved (see q22) and this run will not carry GCEC's disconnect clause over to a different, unconfirmed utility.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Phone, primarily: the Building Inspection Procedures instruct 'YOU MUST HAVE THE PERMIT NUMBER AND TYPE OF INSPECTION WHEN CALLING FOR INSPECTION' -- Washington County Building Department, 850-638-6195, M-F 8-4. The iWorq portal also exposes an inspection-request form and scheduler on each permit's detail page, and F.S. 553.79(1)(d) requires the County to allow inspection requests electronically. 80% · inspection procedures
    • How much notice is required? 24 to 48 hours. 'Due to a high demand in requests for inspections, please contact Building Department staff at least 24-48 hours prior to inspection date.' 88% · department page
    • Are same-day or AM/PM windows offered? Not published. No AM/PM window, same-day option, or arrival window appears in the inspection procedures, on the department page, or in the portal's scheduler description. The portal's inspection-request form collects only a 'requested after' DATE, minimum the following day. 65% · inspection procedures
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? No -- the Town of Wausau performs no inspections at all. The final inspection is performed by the Washington County Building Department, whose page says it performs 'Electrical & Building Inspections'. Florida's private-provider route under F.S. 553.791 is also live in this county (the Ebro run found a live example in the iWorq register), though no Wausau-address example turned up in the current 315-permit window checked in this run. 78% · department page
    • If delegated, to whom? Washington County Building Department, 1331 South Blvd. Suite 900, Chipley FL 32428, 850-638-6195, permits@washingtonfl.com. Building Official Charles Vannatter; Office Manager Felicia Brown; Permit Technicians Jennifer Enck and Ann Baker. Hours M-F 8-4. 88% · department page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? The County publishes a ten-stage inspection sequence written for new construction: 1 temporary electrical service; 2 footer; 3 under-slab; 4 floor slab (Product Approval Sheet on file before inspection); 5 concrete block; 6 nailing and strapping; 7 dry-in (electrical rough-in complete with panel set); 8 insulation; 9 temporary/permanent power to certificate of occupancy; 10 final/certificate of occupancy. For a rooftop PV retrofit on an existing Wausau house only the electrical stages are relevant in practice -- an electrical inspection before anything is concealed, and a final -- but no PV-specific sequence is published. 65% · inspection procedures
    • Is a rough-in or mid-roof inspection required? Not for a rooftop PV retrofit, as far as anything published shows. The County's rough-in stages all belong to new construction. What does bind is Sec. 14-78(a): 'It shall be unlawful to conceal any electrical wiring or equipment until it has been inspected', with 14-78(b) authorising the inspector to uncover concealed work. So any conduit/wiring that will be concealed must be inspected first, which is a rough-in requirement in substance even though no PV rough-in stage is named. 55% · inspection procedures
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? No published solar inspection checklist. The County publishes one general document, 'Building Inspection Procedures' (revised 8/2024), listing the ten new-construction stages and what is checked at each. There is no PV, ESS or renewable checklist of any kind, for Wausau or any other jurisdiction in the county. 78% · inspection procedures
    • What must be on site at inspection? Posted before work starts and present at inspection: the 911 address posted; the approved prints; the inspection card; and the Notice of Commencement ('A certified copy of the Notice of Commencement must be provided to Building Department and posted on the jobsite before the first inspection can be performed' for work of $2,500 or more). The Product Approval Sheet must be on file before the relevant inspection. The E-911 requirement bites before power: 'An address number must be properly posted before the authorization for power may be given.' 82% · inspection procedures
    • Does the inspector verify labels and listings? Yes, as far as the local rules go. Sec. 14-79 requires all electrical materials/devices to bear the manufacturer's identification, voltage/current/wattage markings 'and shall bear the underwriter's label' -- a listing check the inspector is enforcing. Sec. 14-78(e) requires the inspector, on passing, to 'place a notice or certificate at the service switch or other suitable place', and on failing to post that the wiring 'has been condemned'. The Product Approval Sheet must be on file before the relevant inspection. 72% · county code chapter
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? For new construction, a Certificate of Occupancy: 'Building will be released for permanent power. Certificate of Occupancy can be picked up at the Building Department ... the next business day.' For a trade permit on an existing house -- which is what a PV retrofit is -- what should be issued is a passed final inspection recorded against the permit with the permit status moving to Completed, by the same pattern the Ebro run found live in the register; this run could not re-confirm that pattern with an actual Wausau-address permit, since none appeared in the current 315-permit window. 60% · inspection procedures
    • Who notifies the utility for PTO? Most likely installer or member, to the serving utility -- not the AHJ -- following the general pattern of Florida electric-cooperative and IOU net-metering tariffs (the member/installer applies for interconnection, and the utility requires proof the local AHJ has inspected before it energizes). Sec. 14-74 of the county code independently requires that an altered service 'shall not be connected until a local utility company has received an authorized inspection certificate' -- pointing to a county-to-utility certificate on the service side. The specific utility's own procedure (equivalent to Gulf Coast Electric Cooperative's Schedule NMR-1 for Ebro) could not be confirmed for Wausau because its likely utility's tariff could not be reached in this run -- see q22, q23. 50% · county code chapter
    • Is there a re-inspection fee? $75.00. 'Reinspection Fee: Commercial & Residential $75' on Schedule A, and in the inspection procedures: 'Any inspection that is not ready when the inspector gets to the site or inspections that fail will be required to pay a $75.00 re-inspection fee (Building Official will determine when this fee will apply).' 92% · fee schedule
    • How are corrections issued and cleared? By posted notice at the job, with concealment blocked until cleared. Sec. 14-78: on a failed electrical inspection 'the inspector shall post a notice or certificate stating that this wiring does not conform to this article, has been condemned, and shall not be covered or connected until approved by the inspector'; 14-78(b)/(c) authorise the inspector to uncover and order uncovered concealed work. The inspection procedures add 'DO NOT PROCEED with work until inspection is made and approved.' Re-inspection is requested by phone on the permit number, $75 where the Building Official applies the fee. Sec. 14-74 closes the loop at the utility end: an altered/repaired service 'shall not be connected until a local utility company has received an authorized inspection certificate.' 70% · county code chapter

14 questions answered against Town of Wausau’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Phone, primarily: the Building Inspection Procedures instruct 'YOU MUST HAVE THE PERMIT NUMBER AND TYPE OF INSPECTION WHEN CALLING FOR INSPECTION' -- Washington County Building Department, 850-638-6195, M-F 8-4. The iWorq portal also exposes an inspection-request form and scheduler on each permit's detail page, and F.S. 553.79(1)(d) requires the County to allow inspection requests electronically.

Why the confidence is not higherThe quoted instruction is from the County's own Building Inspection Procedures (revised 8/2024), re-downloaded and extracted from PDF in this run. The portal's endpoints were re-checked in the live page markup today. Held at 80, close to Ebro's 82, because nothing published says whether the department actually prefers phone over the portal.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q50 How much notice is required? Core Booking & scheduling

24 to 48 hours. 'Due to a high demand in requests for inspections, please contact Building Department staff at least 24-48 hours prior to inspection date.'

Why the confidence is not higherQuoted verbatim from the Building Department page, re-fetched fresh today (live text, unchanged from the Ebro run's reading and independently re-verified rather than assumed). Held at 88, matching Ebro, because it is written as a request rather than a hard rule and is expressed in clock hours rather than business days.

department page checked 2026-09-14 https://washingtonfl.gov/departments/building/about/

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Not published. No AM/PM window, same-day option, or arrival window appears in the inspection procedures, on the department page, or in the portal's scheduler description. The portal's inspection-request form collects only a 'requested after' DATE, minimum the following day.

Why the confidence is not higherThe inspection procedures were re-read in full from PDF and the portal's inspection-request form fields re-checked in the live markup in this run. Held at 65, matching Ebro, because the separate scheduler endpoint could not be exercised without a live permit ID and contractor code.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

No -- the Town of Wausau performs no inspections at all. The final inspection is performed by the Washington County Building Department, whose page says it performs 'Electrical & Building Inspections'. Florida's private-provider route under F.S. 553.791 is also live in this county (the Ebro run found a live example in the iWorq register), though no Wausau-address example turned up in the current 315-permit window checked in this run.

Why the confidence is not higherThe county's own department page (re-fetched today) is direct evidence for Wausau, since it is the same countywide department. Held at 78, below Ebro's 88, because this run's own pull of the live iWorq register found zero permits at a Wausau address to directly confirm county inspectors physically cross the Wausau town line, the same caveat as jurisdiction.why explains for q1/q2.

department page checked 2026-09-14 https://washingtonfl.gov/departments/building/about/

Q53 If delegated, to whom? Core Who inspects

Washington County Building Department, 1331 South Blvd. Suite 900, Chipley FL 32428, 850-638-6195, permits@washingtonfl.com. Building Official Charles Vannatter; Office Manager Felicia Brown; Permit Technicians Jennifer Enck and Ann Baker. Hours M-F 8-4.

Why the confidence is not higherStaff names, address, phone and hours re-confirmed from the County Building Department page, re-fetched fresh today (same staff as the Ebro run found, independently re-checked rather than assumed current). Held at 88, close to Ebro's 90, because the town-line point in q52 applies equally here.

department page checked 2026-09-14 https://washingtonfl.gov/departments/building/about/

Q54 Which inspections are required, and in what order? Core Stages & sequence

The County publishes a ten-stage inspection sequence written for new construction: 1 temporary electrical service; 2 footer; 3 under-slab; 4 floor slab (Product Approval Sheet on file before inspection); 5 concrete block; 6 nailing and strapping; 7 dry-in (electrical rough-in complete with panel set); 8 insulation; 9 temporary/permanent power to certificate of occupancy; 10 final/certificate of occupancy. For a rooftop PV retrofit on an existing Wausau house only the electrical stages are relevant in practice -- an electrical inspection before anything is concealed, and a final -- but no PV-specific sequence is published.

Why the confidence is not higherThe ten stages are quoted from the County's Building Inspection Procedures, re-downloaded and extracted from PDF in this run. Held at 65, matching Ebro, because the published sequence is for new construction and no document states what stages a solar retrofit runs through.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Not for a rooftop PV retrofit, as far as anything published shows. The County's rough-in stages all belong to new construction. What does bind is Sec. 14-78(a): 'It shall be unlawful to conceal any electrical wiring or equipment until it has been inspected', with 14-78(b) authorising the inspector to uncover concealed work. So any conduit/wiring that will be concealed must be inspected first, which is a rough-in requirement in substance even though no PV rough-in stage is named.

Why the confidence is not higherThe stages are from the county's inspection procedures (re-downloaded today); Sec. 14-78 re-quoted from Chapter 14 text pulled fresh through the Municode content API. Held at 55, matching Ebro, because this is a negative inferred from a document written for a different job type.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q56 Does the inspector verify labels and listings? Core What is checked

Yes, as far as the local rules go. Sec. 14-79 requires all electrical materials/devices to bear the manufacturer's identification, voltage/current/wattage markings 'and shall bear the underwriter's label' -- a listing check the inspector is enforcing. Sec. 14-78(e) requires the inspector, on passing, to 'place a notice or certificate at the service switch or other suitable place', and on failing to post that the wiring 'has been condemned'. The Product Approval Sheet must be on file before the relevant inspection.

Why the confidence is not higherAll three provisions re-read first-party in this run -- two from the Chapter 14 code text pulled today, the Product Approval requirement from the County's inspection procedures PDF, also re-fetched. Held at 72, matching Ebro, because none of this is PV-specific.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q57 Is there a published inspection checklist? Core What is checked

No published solar inspection checklist. The County publishes one general document, 'Building Inspection Procedures' (revised 8/2024), listing the ten new-construction stages and what is checked at each. There is no PV, ESS or renewable checklist of any kind, for Wausau or any other jurisdiction in the county.

Why the confidence is not higherProved by re-enumerating the Building Department document library in full in this run (12 files, same as Ebro's run found) and reading the inspection procedures PDF cover to cover, freshly downloaded today. Held at 78, matching Ebro.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q58 What must be on site at inspection? Core Documents on site

Posted before work starts and present at inspection: the 911 address posted; the approved prints; the inspection card; and the Notice of Commencement ('A certified copy of the Notice of Commencement must be provided to Building Department and posted on the jobsite before the first inspection can be performed' for work of $2,500 or more). The Product Approval Sheet must be on file before the relevant inspection. The E-911 requirement bites before power: 'An address number must be properly posted before the authorization for power may be given.'

Why the confidence is not higherQuoted from the County's Building Inspection Procedures and Application for Building Permit, both re-extracted from freshly downloaded PDFs in this run, and from the county's residential planning instruction sheet for the address/power point. Held at 82, close to Ebro's 85, because the list is written for NEW CONSTRUCTION and no document restates it for a trade permit on an existing house.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q59 Is there a re-inspection fee? Corrections & re-inspection

$75.00. 'Reinspection Fee: Commercial & Residential $75' on Schedule A, and in the inspection procedures: 'Any inspection that is not ready when the inspector gets to the site or inspections that fail will be required to pay a $75.00 re-inspection fee (Building Official will determine when this fee will apply).'

Why the confidence is not higherTwo independent county documents give the same figure -- the fee schedule (effective 09/01/2024) and the inspection procedures (revised 8/2024) -- both re-downloaded and extracted from PDF in this run. Held at 92, matching Ebro, only because of the discretionary clause.

fee schedule checked 2026-09-14 https://washingtonfl.gov/site/assets/files/2953/building_department_fees_4_2026.pdf

Q60 How are corrections issued and cleared? Corrections & re-inspection

By posted notice at the job, with concealment blocked until cleared. Sec. 14-78: on a failed electrical inspection 'the inspector shall post a notice or certificate stating that this wiring does not conform to this article, has been condemned, and shall not be covered or connected until approved by the inspector'; 14-78(b)/(c) authorise the inspector to uncover and order uncovered concealed work. The inspection procedures add 'DO NOT PROCEED with work until inspection is made and approved.' Re-inspection is requested by phone on the permit number, $75 where the Building Official applies the fee. Sec. 14-74 closes the loop at the utility end: an altered/repaired service 'shall not be connected until a local utility company has received an authorized inspection certificate.'

Why the confidence is not higherAssembled from Chapter 14 code text and the inspection procedures PDF, both re-read first-party in this run from fresh downloads. Held at 70, matching Ebro, because no document describes a written correction-list format or a re-submittal process for plan-review comments as opposed to field corrections.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Q61 What is issued on pass? Core Final sign-off & PTO

For new construction, a Certificate of Occupancy: 'Building will be released for permanent power. Certificate of Occupancy can be picked up at the Building Department ... the next business day.' For a trade permit on an existing house -- which is what a PV retrofit is -- what should be issued is a passed final inspection recorded against the permit with the permit status moving to Completed, by the same pattern the Ebro run found live in the register; this run could not re-confirm that pattern with an actual Wausau-address permit, since none appeared in the current 315-permit window.

Why the confidence is not higherThe CO language is quoted from the County's inspection procedures, re-downloaded today. Held at 60, below Ebro's 70, because the direct register-behaviour evidence Ebro had (an actual passed-final permit example) is not available for Wausau in this run's readable window.

inspection procedures checked 2026-09-14 https://washingtonfl.gov/site/assets/files/1683/building_inspection_procedures_8_2024-_ada.pdf

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Most likely installer or member, to the serving utility -- not the AHJ -- following the general pattern of Florida electric-cooperative and IOU net-metering tariffs (the member/installer applies for interconnection, and the utility requires proof the local AHJ has inspected before it energizes). Sec. 14-74 of the county code independently requires that an altered service 'shall not be connected until a local utility company has received an authorized inspection certificate' -- pointing to a county-to-utility certificate on the service side. The specific utility's own procedure (equivalent to Gulf Coast Electric Cooperative's Schedule NMR-1 for Ebro) could not be confirmed for Wausau because its likely utility's tariff could not be reached in this run -- see q22, q23.

Why the confidence is not higherSec. 14-74 re-quoted from Chapter 14 text pulled fresh through the Municode content API today. Held at 50, below Ebro's 70, because this answer is a general-pattern inference rather than a specific utility document read in this session -- the utility whose tariff would settle it (see q22) could not be reached.

county code chapter checked 2026-09-14 https://library.municode.com/fl/washington_county/codes/code_of_ordinances?nodeId=PTICOOR_CH14BUBURE

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 72%

No. Neither the Town of Wausau nor Washington County specifies placard wording of its own.

Size, colour & material 70%

No. No letter height, colour, material or durability specification is set by Wausau or by Washington County.

Where they go 55%

No local placement rule for PV labels specifically. What is fixed locally is the equipment they attach to: Sec. 14-73 puts all residential meters outside, centre of meter four to six feet above grade; Sec. 14-72 puts the service-disconnecting means at a readily accessible location nearest the point of entrance; Sec. 14-80 caps the main service switch handle at six feet, floors it at 3-1/2 feet; Sec. 14-81 requires all service disconnects/panels readily accessible and never in or behind a bathroom. Where Wausau's own utility would add a label-location requirement (as GCEC does for Ebro) could not be determined in this run.

What the utility wants on top None%

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Separate roof inspection
Emailed and faxed permits processing time may take up to 3 business days. All other permits should be brought into the office for processing. Please note: effective Monday, March 17, 2025, a convenience fee of 3.5% will be added to all credit card transactions. EMAIL: Building Permits Building Inspe
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
Town
County
Washington County
Regions covered
Authority Contact
Building Department
Direct Phone
(850) 638-6195
Booking & Scheduling