Union County

Union County

State of Florida

Verified Aug. 5, 2026

Union County is a county authority in the State of Florida, serving 16,147 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Union County against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Union County is the authority having jurisdiction 82% confidence
Holds
Building AND Electrical, in-house, held directly by the Union County Building Department (15 NE 1st Street, Lake Butler; Wilson Whidden/Whiddon named as "Union County Building Inspector" on the county's own site, spelled "Whiddon" on the City of Lake Butler's site — a minor spelling inconsistency across the two sites' own pages, not resolved). This county department is ALSO the AHJ inside the City of Lake Butler: Lake Butler's own Building Department page states verbatim "The City of Lake Butler's Building Department falls under the direction of the Union County Building Department" and lists the same Wilson Whiddon/county phone number/address as its building contact — an explicit, dated, first-party delegation of building AND electrical from the city to the county. Lake Butler's own site simultaneously lists "Planning and Zoning" as one of ITS OWN city departments (separate from the delegated Building Department), so Lake Butler delegates building/electrical but keeps zoning — the sixth county-to-town pattern named in the brief. Raiford and Worthington Springs have NO reachable website at all (DNS failure confirmed by curl on worthingtonspringsfl.com, townofworthingtonsprings.com, townofraiford.com, raifordfl.com, raifordflorida.com — all returned curl exit code 6, could not resolve host), so their reliance on the county is an INFERENCE FROM ABSENCE, not an independently confirmed fact for either town — flagged per the brief's own caution about that exact failure mode. Fire is NOT part of the Building Department: it is a separate County (historically all-volunteer) Fire-Rescue operation, funded by a $50/parcel special assessment plus (per the county's 2020 sales-tax FAQ, the newest fire material the county's own site currently publishes) an interlocal funding arrangement with the City of Lake Butler; the county's own current department list (checked via its 40-URL WordPress sitemap) contains no dedicated Fire Department/Fire-Rescue page, so current (2026) staffing/paid-vs-volunteer status could not be confirmed from the county's own site. The county's Emergency Management Director's listed email is on the @unionsheriff.us domain, which may indicate shared administration with the Union County Sheriff's Office for that specific function — noted as an observation, not confirmed as the Sheriff's Office running fire itself (unlike Cooper City's BSO Fire Rescue, which is explicit).
Overridden by
FL PSC Rule 25-6.065 does NOT govern interconnection here: the utility most clearly documented as serving this area, Clay Electric Cooperative, is a member-owned cooperative operating under Fla. Stat. 366.91, which sits outside PSC jurisdiction. Clay Electric's own current filed tariff sheet ("Interconnection Agreement for Customer-Owned Renewable Generation Systems," Form IGRG-1, Second/Third Revised Sheet Nos. 21.0-21.04, effective 30 April 2026 — fetched directly from clayelectric.com, a real text-layer PDF, not OCR'd) governs interconnection, disconnect, and battery-placard terms instead of the state floor. I could not confirm from a Union County-specific document (no franchise-appendix or permit-form utility checkbox was reachable this session) whether Duke Energy Florida or FPL also reach any part of the county; Clay is the utility documented with highest confidence but the picture may not be complete — see q22.
Why not higher
Direct evidence for county-level jurisdiction is the county's own Building Department page (buildingdept@unioncounty-fl.gov, Wilson Whidden named, Cloudpermit portal). Direct evidence for the Lake Butler delegation is Lake Butler's own Building Department page, which states the delegation in its own words and repeats the county's contact information. Confidence is not higher because: (a) Raiford's and Worthington Springs' actual legal relationship to the county could not be sourced at all (no website), so it rests on inference from absence; (b) the county's 348-page Land Development Regulations PDF (which would state jurisdiction/zoning boundaries explicitly) is hosted on a domain that is Cloudflare-gated to curl/WebFetch domain-wide (confirmed: HTTP 403 on the PDF, on the site's static wp-content assets, and even on /wp-sitemap.xml root before redirect) and, once loaded in a rendered browser, is a non-OCR'd, no-text-layer PDF; I could read only its page-4 Table of Contents (via a rendered-browser screenshot after several failed attempts) before this session's shared multi-agent browser tab group made further paging unreliable (the main PDF-viewer pane intermittently rendered blank/black across many attempts, consistent with the brief's documented tab-contention failure mode, while thumbnails — already pre-rendered — kept showing real content). That table of contents is recorded in q28/q47 not_found entries as the only thing recovered from that document.

https://unioncounty-fl.gov/building-department/

Permit required
Yes, almost certainly — no solar/PV exemption of any kind was found, and the county requires a standard Electrical Permit Application for electrical work generally.55%
Plan review
7-10 business days for the Building Official to complete any necessary plan reviews; if no review is necessary, the permit can be issued in as little as up to 2 business days.92%
Portal
Cloudpermit (us.cloudpermit.com) — a cloud-based permitting platform the county says it has "partnered with."95%
Electrical code
State floor: NEC 2020, effective 31 December 2023, under Florida Building Code 8th Edition (2023). Union's own material never states an NEC year by name.72%
Own placard wording
Clay Electric specifies exact wording for the ONE placard it requires (battery storage only): "Battery storage utilized in this facility." No general PV placard wording is specified by the…90%
Booking an inspection
Through the Cloudpermit portal, which the county's own page lists as supporting scheduling AND cancelling of inspections online; a phone/email route to the Building Department also exists.80%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes, almost certainly — no solar/PV exemption of any kind was found, and the county requires a standard Electrical Permit Application for electrical work generally. Q3 Electrical and building permits — Separate. The county lists 'Electrical Permit Application' as its own distinct application, Q4 Plan review — 7-10 business days for the Building Official to complete any necessary plan reviews; Q18 Where you file — Cloudpermit (us.cloudpermit.com) — a cloud-based permitting platform the county says it has "partnered with." Q20

Permit required
Yes, almost certainly — no solar/PV exemption of any kind was found, and the county requires a standard Electrical Permit Application for electrical work generally.55% source
Plan review turnaround
7-10 business days for the Building Official to complete any necessary plan reviews; if no review is necessary, the permit can be issued in as little as up to 2 business days.92% source
Key document
inference (state-level geography), not locally confirmed cited by 9 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes. Union County's own Building Department is the AHJ for building and electrical permitting for residential rooftop PV countywide, including inside the City of Lake Butler by explicit delegation from the city. 90% · department page
    • What does this authority permit itself, and what does it delegate? The County permits and inspects both Building and Electrical itself, in-house, countywide (including inside Lake Butler by delegation). It delegates nothing further outward that I could find. Zoning/Planning & Development is also run by the county for unincorporated areas, but Lake Butler keeps its OWN Planning and Zoning function separate from the delegated Building function. 80% · city department page (cross-referencing county)
    • Is a permit required for a residential rooftop PV system? Yes, almost certainly — no solar/PV exemption of any kind was found, and the county requires a standard Electrical Permit Application for electrical work generally. 55% · inference from general permit-application list
    • Is there a separate electrical permit, or is it combined? Separate. The county lists 'Electrical Permit Application' as its own distinct application, separate from 'Residential Home Building or Addition Permit Application,' 'Roofing Permit Application,' etc. 78% · department page
    • Is a wind or windstorm certification required? No wind/windstorm certification beyond the standard Florida Product Approval process is documented for this inland county; Union County is not in the Miami-Dade/Broward HVHZ and, being inland, is very unlikely to sit in the coastal ASCE 7 Wind-Borne Debris Region that some coastal counties are in. 50% · inference (state-level geography), not locally confirmed
    • Is there a system-size cap on residential generation? No AHJ/zoning-based system-size cap on residential generation was found (the LDR, where such a cap would be codified, could not be extracted). At the UTILITY level, Clay Electric's own interconnection agreement effectively caps RGS size to no more than 90% of the member's utility service-entrance rating or 90% of the cooperative's transformer kVA capacity at that location, whichever is less, and requires Clay's engineering pre-approval for any system 20kW or larger. 60% · utility filed tariff (zoning half unconfirmed)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? A Florida-licensed electrical contractor, per standard statewide practice — I could not confirm county-specific wording because the Electrical Permit Application PDF itself could not be extracted this session (see why). 45% · unreadable county PDF + general FL practice
    • Must the contractor be registered with this authority before applying? Yes. The county publishes and requires BOTH a 'Certified Contractor Application' (for state-certified contractors registering locally) and a separate 'Registered Contractor Application' (for county/locally-registered contractors) before a contractor pulls permits. Notably, both forms are still live and listed on the county's current site (page lastmod 29 Jul 2026, i.e. more than a year after the 1 July 2025 state-direct licensing shift), so — directly answering the brief's standing question — Union County has NOT eliminated its own local contractor registration step for this authority. 70% · department page + sitemap lastmod
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? A general (not solar-specific) checklist titled 'Items Required to Obtain a Building or Addition Permit' exists and includes, among items I could partly make out at low resolution: a survey and legal description of property, a 911 address application, and proof of ownership/special-assessment tax card. I could not reliably read the remainder of the numbered list. 45% · county PDF (partial low-resolution read)
    • How many copies, and in what format? Electronic only, via the Cloudpermit portal — the county's own description of Cloudpermit says applicants "complete the entire building permit process online on any mobile device," with no mention of a paper-copy option. 55% · department page
    • Is a structural PE stamp required, and at what threshold? State floor: FS 471.003(2)(h) — no PE stamp is required for electrical work by a licensed electrical contractor where the work is valued at $125,000 or less and aggregate service capacity is 600 amperes (240V) or less on a residential system. I could not confirm whether Union's own Land Development Regulations impose a stricter local threshold (as at least five other Florida jurisdictions in this survey do) because that document could not be extracted this session. 60% · Florida Statute (state floor)
    • Is an electrical PE stamp required, and at what threshold? Same state floor as q13: FS 471.003(2)(h), $125,000/600A. No stricter local rule confirmed. 60% · Florida Statute (state floor)
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Cloudpermit (us.cloudpermit.com) — a cloud-based permitting platform the county says it has "partnered with." 95% · department page
    • Can the whole application be completed online? Yes — per the county's own description, an applicant can apply for a permit, check permit/inspection status (with automatic email status-change alerts), schedule or cancel inspections, message the department, request permit changes, and pay by credit card, entirely online. 90% · department page
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? 7-10 business days for the Building Official to complete any necessary plan reviews; if no review is necessary, the permit can be issued in as little as up to 2 business days. 92% · department page
    • How long is an issued permit valid before it expires? Not stated by the county; the statewide FBC administrative floor (Chapter 1, e.g. work must commence and inspections must not lapse within 180 days or the permit becomes invalid) would apply absent a stricter or more lenient local rule, but no Union-specific figure was found. 50% · state/FBC administrative floor, not locally confirmed
    • Which utility handles interconnection here? Clay Electric Cooperative, Inc. is the utility documented with the highest confidence for this area (a member-owned cooperative under Fla. Stat. 366.91, headquartered in nearby Keystone Heights, with an active, current solar/net-metering program). I could NOT rule out Duke Energy Florida or FPL serving some parcels within the county, and could not confirm Clay specifically for Union County from a Union-specific source (no Franchises appendix in a Code of Ordinances was reachable, and the county's own Electrical Permit Application — which might carry a utility checkbox, the survey's best technique for this exact question — could not be read this session). 68% · utility website (own program pages)
    • Where does the utility sit in the sequence? The AHJ inspects first: Clay Electric's own current Interconnection Agreement requires the Member to provide Clay with WRITTEN CERTIFICATION from the local code official that the installation has been inspected, permitted, and approved, BEFORE the RGS may operate. The Member must also notify Clay at least 10 days before the intended in-service date; Clay then installs its net meter (incurring a $60 trip fee) and may witness testing. 90% · utility filed tariff (interconnection agreement)

28 questions answered against Union County’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes. Union County's own Building Department is the AHJ for building and electrical permitting for residential rooftop PV countywide, including inside the City of Lake Butler by explicit delegation from the city.

Why the confidence is not higherCounty's own Building Department page names itself as the department, lists all standard trade permit applications (including a dedicated Electrical Permit Application), and Lake Butler's own site independently confirms the delegation in its own words.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

The County permits and inspects both Building and Electrical itself, in-house, countywide (including inside Lake Butler by delegation). It delegates nothing further outward that I could find. Zoning/Planning & Development is also run by the county for unincorporated areas, but Lake Butler keeps its OWN Planning and Zoning function separate from the delegated Building function.

Why the confidence is not higherCounty's Building Department and Planning & Development pages list Building/Electrical permit applications and LDR/Comp Plan/Zoning Atlas documents respectively, both run by the county; Lake Butler's own department list shows 'Planning and Zoning' as a city department distinct from its delegated 'Building Department.'

city department page (cross-referencing county) checked 2026-09-12 https://cityoflakebutler.com/building-department/

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes, almost certainly — no solar/PV exemption of any kind was found, and the county requires a standard Electrical Permit Application for electrical work generally.

Why the confidence is not higherInferred from the absence of any PV-specific exemption anywhere in the county's own permit-application list and from the general presence of an Electrical Permit Application requirement; the county's own material never addresses solar/PV by name, so this is inference from the general framework, not a solar-specific statement.

inference from general permit-application list checked 2026-09-12 https://unioncounty-fl.gov/wp-content/uploads/Electrical-Applicaton-fillable.pdf

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Separate. The county lists 'Electrical Permit Application' as its own distinct application, separate from 'Residential Home Building or Addition Permit Application,' 'Roofing Permit Application,' etc.

Why the confidence is not higherDirectly from the county's own Building Department page listing of separately named, separately linked permit-application PDFs for each trade.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q5 Who is allowed to pull the electrical permit? Core Who may apply

A Florida-licensed electrical contractor, per standard statewide practice — I could not confirm county-specific wording because the Electrical Permit Application PDF itself could not be extracted this session (see why).

Why the confidence is not higherThis is a general-Florida inference, not a county-specific confirmation. unioncounty-fl.gov is Cloudflare-gated domain-wide (curl returns HTTP 403 on the PDF itself, confirmed), and in a rendered browser the PDF has no text layer reachable by this session's tools and its main viewer pane would not render a legible screenshot across repeated attempts (shared-browser tab contention, documented in jurisdiction.why).

unreadable county PDF + general FL practice checked 2026-09-12 https://unioncounty-fl.gov/wp-content/uploads/Electrical-Applicaton-fillable.pdf

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes. The county publishes and requires BOTH a 'Certified Contractor Application' (for state-certified contractors registering locally) and a separate 'Registered Contractor Application' (for county/locally-registered contractors) before a contractor pulls permits. Notably, both forms are still live and listed on the county's current site (page lastmod 29 Jul 2026, i.e. more than a year after the 1 July 2025 state-direct licensing shift), so — directly answering the brief's standing question — Union County has NOT eliminated its own local contractor registration step for this authority.

Why the confidence is not higherBoth application titles and their live links appear on the county's own current Building Department page; the page's own last-modified date (from the county's wp-sitemap) is 29 Jul 2026, after the 1 Jul 2025 statewide shift, showing the county's local registration requirement is still current practice as of that date. I could not read the forms' own text to confirm exactly what they require (same Cloudflare/PDF-rendering obstacle as q5).

department page + sitemap lastmod checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Nothing published by this authority.

Where we lookedCounty's own Building Department permit-application list (all 16 listed application titles) — no 'Owner Builder Affidavit' or equivalent form is listed, unlike some other Florida counties in this survey; the general statewide FS 489.103/489.503 owner-builder exemption likely still applies in principle but no county-specific statement or form was found

https://unioncounty-fl.gov/building-department/

Q8 What documents make up a complete submittal? Core Submittal package

A general (not solar-specific) checklist titled 'Items Required to Obtain a Building or Addition Permit' exists and includes, among items I could partly make out at low resolution: a survey and legal description of property, a 911 address application, and proof of ownership/special-assessment tax card. I could not reliably read the remainder of the numbered list.

Why the confidence is not higherThis document only rendered as a low-resolution browser thumbnail in this session (the county domain is Cloudflare-gated to curl, and the PDF viewer's full-resolution main pane would not render a legible screenshot across repeated attempts, a tab-contention issue documented in jurisdiction.why); a zoomed capture of the thumbnail was legible enough for the title and first few items only, so this is a partial, hedged read, not a full transcription, and it is NOT solar-specific.

county PDF (partial low-resolution read) checked 2026-09-12 https://unioncounty-fl.gov/wp-content/uploads/Residential-House-Application-fillable-2.5.25.pdf

Q9 How many copies, and in what format? Submittal package

Electronic only, via the Cloudpermit portal — the county's own description of Cloudpermit says applicants "complete the entire building permit process online on any mobile device," with no mention of a paper-copy option.

Why the confidence is not higherInferred from the county's own description of its Cloudpermit rollout; this is a general statement about the portal, not a solar-specific submittal-format rule, so held at moderate confidence.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q10 Is a site plan required, and what must it show? Core Submittal package

Nothing published by this authority.

Where we lookedResidential Home Building or Addition Permit Application PDF and the 'Items Required' checklist PDF — both are on the Cloudflare-gated unioncounty-fl.gov domain (curl returns HTTP 403 on the PDF bytes themselves) and, once opened in a rendered browser, are non-OCR'd image PDFs whose main viewer pane would not render a legible screenshot in this session's contended shared browser (see jurisdiction.why)

https://unioncounty-fl.gov/wp-content/uploads/Residential-House-Application-fillable-2.5.25.pdf

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Nothing published by this authority.

Where we lookedElectrical Permit Application PDF — same Cloudflare/rendering obstacle as q10

https://unioncounty-fl.gov/wp-content/uploads/Electrical-Applicaton-fillable.pdf

Q12 Are string and conductor calculations required? Drawings & calculations

Nothing published by this authority.

Where we lookedElectrical Permit Application PDF — same obstacle as q11

https://unioncounty-fl.gov/wp-content/uploads/Electrical-Applicaton-fillable.pdf

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

State floor: FS 471.003(2)(h) — no PE stamp is required for electrical work by a licensed electrical contractor where the work is valued at $125,000 or less and aggregate service capacity is 600 amperes (240V) or less on a residential system. I could not confirm whether Union's own Land Development Regulations impose a stricter local threshold (as at least five other Florida jurisdictions in this survey do) because that document could not be extracted this session.

Why the confidence is not higherStatewide statute, cited directly, applicable absent a stricter local rule; the LDR (where such a stricter rule would be codified) is the same Cloudflare-gated, non-OCR'd 348-page PDF described in jurisdiction.why, and only its table of contents could be read.

Florida Statute (state floor) checked 2026-09-12 http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&URL=0400-0499/0471/Sections/0471.003.html

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Same state floor as q13: FS 471.003(2)(h), $125,000/600A. No stricter local rule confirmed.

Why the confidence is not higherSame statute and same limitation as q13.

Florida Statute (state floor) checked 2026-09-12 http://www.leg.state.fl.us/Statutes/index.cfm?App_mode=Display_Statute&URL=0400-0499/0471/Sections/0471.003.html

Q15 What does a residential solar permit cost? Core Fees

Nothing published by this authority.

Where we lookedCounty's Building Department page and its full application list — no separate fee-schedule document is linked anywhere on the page or in the site's 40-URL sitemap; the individual permit-application PDFs (which might state fees) could not be extracted (Cloudflare/rendering obstacle)

https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q16 How is the fee calculated? Core Fees

Nothing published by this authority.

Where we lookedSame as q15 — no fee schedule reachable

https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q17 Is there a separate plan-check fee? Fees

Nothing published by this authority.

Where we lookedSame as q15 — no fee schedule reachable

https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q18 What is the stated plan-review turnaround? Core Timeline & validity

7-10 business days for the Building Official to complete any necessary plan reviews; if no review is necessary, the permit can be issued in as little as up to 2 business days.

Why the confidence is not higherQuoted verbatim from the county's own current Building Department page.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q19 How long is an issued permit valid before it expires? Timeline & validity

Not stated by the county; the statewide FBC administrative floor (Chapter 1, e.g. work must commence and inspections must not lapse within 180 days or the permit becomes invalid) would apply absent a stricter or more lenient local rule, but no Union-specific figure was found.

Why the confidence is not higherGeneral Florida Building Code administrative-chapter floor, not a county-specific confirmation; the county's Building Department page and its application list do not state a permit-validity period, and the LDR (where an amendment might live) could not be extracted.

state/FBC administrative floor, not locally confirmed checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q20 Which permit portal does this authority use? Core Portal & process

Cloudpermit (us.cloudpermit.com) — a cloud-based permitting platform the county says it has "partnered with."

Why the confidence is not higherDirectly named, with the login URL given, on the county's own Building Department page.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q21 Can the whole application be completed online? Core Portal & process

Yes — per the county's own description, an applicant can apply for a permit, check permit/inspection status (with automatic email status-change alerts), schedule or cancel inspections, message the department, request permit changes, and pay by credit card, entirely online.

Why the confidence is not higherDirectly listed, feature by feature, on the county's own Building Department page describing Cloudpermit.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q22 Which utility handles interconnection here? Core Utility interconnection

Clay Electric Cooperative, Inc. is the utility documented with the highest confidence for this area (a member-owned cooperative under Fla. Stat. 366.91, headquartered in nearby Keystone Heights, with an active, current solar/net-metering program). I could NOT rule out Duke Energy Florida or FPL serving some parcels within the county, and could not confirm Clay specifically for Union County from a Union-specific source (no Franchises appendix in a Code of Ordinances was reachable, and the county's own Electrical Permit Application — which might carry a utility checkbox, the survey's best technique for this exact question — could not be read this session).

Why the confidence is not higherClay Electric's own current (30 Apr 2026) tariff sheet and solar program pages are first-party and clearly cover this rural north-central Florida region, but nothing Union-County-specific (franchise table, permit-form checkbox) was reachable to pin the utility down to this exact authority the way the brief's preferred technique would. Confidence held below 80 for exactly that reason.

utility website (own program pages) checked 2026-09-12 https://www.clayelectric.com/solar-getting-started

Q23 Where does the utility sit in the sequence? Core Utility interconnection

The AHJ inspects first: Clay Electric's own current Interconnection Agreement requires the Member to provide Clay with WRITTEN CERTIFICATION from the local code official that the installation has been inspected, permitted, and approved, BEFORE the RGS may operate. The Member must also notify Clay at least 10 days before the intended in-service date; Clay then installs its net meter (incurring a $60 trip fee) and may witness testing.

Why the confidence is not higherQuoted/paraphrased directly from Clay Electric Cooperative's own current filed Interconnection Agreement (Form IGRG-1, Items 1 and 4) and its 'Solar Getting Started' page, both first-party and dated (tariff effective 30 April 2026).

utility filed tariff (interconnection agreement) checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

Nothing published by this authority.

Where we lookedCounty's Building Department and Planning & Development pages (full text read) — no mention of HOA/architectural-approval preconditions; the LDR, where such a rule might be codified, could not be extracted (Cloudflare/rendering obstacle)

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q25 Is there a historic-district review? Overlays & special cases

Nothing published by this authority.

Where we lookedCounty's full 40-URL sitemap (no Historic Preservation Board/district page exists) and the LDR's own Table of Contents (the only part of the 348-page document I could read, page 4) — it lists Articles One through Four only as far as visible (General Provisions; Definitions/Nonconforming; Administrative Mechanisms; Zoning Regulations through Section 4.18); no Historic Preservation article was visible in what I could read, but I could not read the rest of the document (Articles Five and beyond, if any) to run a proper positive/fabricated-term control, so this is NOT recorded as a proven absence

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q26 Is a wind or windstorm certification required? Overlays & special cases

No wind/windstorm certification beyond the standard Florida Product Approval process is documented for this inland county; Union County is not in the Miami-Dade/Broward HVHZ and, being inland, is very unlikely to sit in the coastal ASCE 7 Wind-Borne Debris Region that some coastal counties are in.

Why the confidence is not higherGeneral statewide/geographic inference from the HVHZ and WBDR being explicitly coastal/South-Florida phenomena, not a Union County document; no county-specific wind-certification requirement was found or could be searched (LDR inaccessible).

inference (state-level geography), not locally confirmed checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

Nothing published by this authority.

Where we lookedLDR Table of Contents (page 4) shows Article Three 'Administrative Mechanisms' Section 3.2 'Board of Adjustment' (variances) but no visible Special/Conditional Use Permit process by that name within what I could read; the underlying zoning-district text (Article Four) that would state whether ground-mount or larger PV triggers an SUP could not be extracted

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q28 Is there a system-size cap on residential generation? Overlays & special cases

No AHJ/zoning-based system-size cap on residential generation was found (the LDR, where such a cap would be codified, could not be extracted). At the UTILITY level, Clay Electric's own interconnection agreement effectively caps RGS size to no more than 90% of the member's utility service-entrance rating or 90% of the cooperative's transformer kVA capacity at that location, whichever is less, and requires Clay's engineering pre-approval for any system 20kW or larger.

Why the confidence is not higherThe zoning-cap half is an absence I could not fully prove (LDR unreadable, so this is closer to could-not-reach than a proven absence); the utility-level cap is directly quoted from Clay Electric's own current Interconnection Agreement, Item 9-10 and its 'Solar Getting Started' page.

utility filed tariff (zoning half unconfirmed) checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? State floor: NEC 2020, effective 31 December 2023, under Florida Building Code 8th Edition (2023). Union's own material never states an NEC year by name. 72% · city page (county-served) + statewide floor
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023), effective 31 December 2023. 85% · city page (county-served)
    • Which fire code edition is in force? State floor: Florida Fire Prevention Code, 8th Edition (2023). No county-specific fire-code document was reachable to confirm or contradict this locally (the county's own site has no dedicated Fire Department/Fire Code page). 50% · state floor; local absence checked via sitemap
    • What is the installation judged against? Florida Building Code 8th Edition (2023) and (state floor) NEC 2020 — see q29/q30. 75% · city page (county-served) + statewide floor
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    Nothing recorded for Union County on this step yet — 1 question checked and found unpublished. The guidance above is general.

  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Not stated locally. Under the state-floor NEC 2020 adoption, rapid shutdown at the module level (NEC 690.12) would apply, since 2020 carries the module-level requirement (module-level rapid shutdown was introduced after NEC 2014, which had only the array-boundary requirement — see the CORRECTED BY RUN 60 note in the baseline this run was briefed on). 55% · inference from state-floor NEC edition
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? No AHJ-specific placard requirement was found for Union County. At the UTILITY level, Clay Electric's current Interconnection Agreement requires a placard ONLY for battery storage: a label permanently affixed to the meter enclosure. No general PV/RGS placard is specified by either the AHJ or the utility. 80% · utility filed tariff
    • Does the authority specify placard wording of its own? Clay Electric specifies exact wording for the ONE placard it requires (battery storage only): "Battery storage utilized in this facility." No general PV placard wording is specified by the utility or found for the AHJ. 90% · utility filed tariff
    • Does it specify letter height, colour or material? No — Clay Electric's placard clause specifies wording only ("Battery storage utilized in this facility"), with no letter height, colour, or material requirement anywhere in the document. This is a genuine, directly-read absence, not a failure to find the document. 85% · utility filed tariff (proven absence)
    • Does the UTILITY specify placards beyond the AHJ's? Yes — the utility (Clay Electric) is the only source of a placard requirement found in this survey run at all; the AHJ has none confirmed. 85% · utility filed tariff
    • Where must the labels be placed? Clay Electric's battery-storage label must be "permanently affixed to the meter enclosure." No other AHJ or utility label-placement rule was found; the AC disconnect switch itself (not a label) must be "mounted separately from the meter socket" and "readily accessible at all times to the Cooperative" (see q48). 88% · utility filed tariff
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? Per Clay Electric's own current Interconnection Agreement (Item 8), a manual disconnect switch is REQUIRED on every interconnected RGS regardless of size — no Tier-1-style size exemption exists for this co-op. At the Member's expense, it must be mounted SEPARATELY from the meter socket, be readily accessible AT ALL TIMES to the Cooperative, and be capable of being locked in the open position by the Cooperative. No specific distance figure is given (unlike FPL's 10 feet or SECO's 5 feet) — only "mounted separately." 95% · utility filed tariff
    • Must equipment be on a specific approved list? At the utility-interconnection level: inverters/equipment must be certified by a Nationally Recognized Testing Laboratory (NRTL) to UL 1741 and comply with IEEE-1547 and the NEC; FSEC Std 203-05 approval is referenced as an applicable certification route where relevant. No separate AHJ-level equipment-listing requirement was confirmed. 85% · utility filed tariff
    • Are batteries permitted, and under what conditions? Yes, batteries are permitted alongside an RGS, subject to Clay Electric's own conditions: NRTL/UL-1741 certified equipment; a permanent meter-enclosure label ("Battery storage utilized in this facility"); the battery may NOT export power to the cooperative's grid (behind-the-meter use / backup only, disconnected from the grid during outages); a UL-listed automatic transfer switch or special inverter is required. A battery system WITHOUT an accompanying RGS may charge from the grid but may NOT interconnect, per Rule 25-6.065(2)(d) F.A.C. as cited within Clay's own agreement (batteries alone are not "renewable energy"). 90% · utility filed tariff

20 questions answered against Union County’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

State floor: NEC 2020, effective 31 December 2023, under Florida Building Code 8th Edition (2023). Union's own material never states an NEC year by name.

Why the confidence is not higherThis is the statewide baseline established across dozens of other Florida AHJ files and independently corroborated at floridabuilding.org. The one piece of Union-affiliated corroboration is the City of Lake Butler's own Building Department page (served by this same county department), which states verbatim: 'The new 8th Edition of the Florida Building Codes becomes effective December 31, 2023' — the same effective date as the statewide NEC 2020 adoption, though that sentence names the FBC cycle, not the NEC edition specifically, so it corroborates the date, not the NEC year directly.

city page (county-served) + statewide floor checked 2026-09-12 https://cityoflakebutler.com/building-department/

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023), effective 31 December 2023.

Why the confidence is not higherQuoted verbatim from the City of Lake Butler's Building Department page, which is administered by the Union County Building Department and states the effective date explicitly; consistent with the statewide floor.

city page (county-served) checked 2026-09-12 https://cityoflakebutler.com/building-department/

Q31 Which fire code edition is in force? Code editions in force

State floor: Florida Fire Prevention Code, 8th Edition (2023). No county-specific fire-code document was reachable to confirm or contradict this locally (the county's own site has no dedicated Fire Department/Fire Code page).

Why the confidence is not higherStatewide floor established across this survey; Union's own site was checked (full 40-URL sitemap) and contains no fire-code-specific page to corroborate or override it.

state floor; local absence checked via sitemap checked 2026-09-12 https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q32 Are there local amendments to any of the above? Core Code editions in force

Nothing published by this authority.

Where we lookedLDR full text — could not be extracted beyond its page-4 Table of Contents (Cloudflare-gated domain, non-OCR'd PDF, unreliable rendering in this session's shared browser)

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q33 What is the installation judged against? Core Electrical

Florida Building Code 8th Edition (2023) and (state floor) NEC 2020 — see q29/q30.

Why the confidence is not higherCombines the directly-quoted FBC citation (q30) with the statewide NEC floor (q29).

city page (county-served) + statewide floor checked 2026-09-12 https://cityoflakebutler.com/building-department/

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Nothing published by this authority.

Where we lookedElectrical Permit Application and LDR — both unreadable this session (same obstacle)

https://unioncounty-fl.gov/wp-content/uploads/Electrical-Applicaton-fillable.pdf

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Nothing published by this authority.

Where we lookedLDR (Article Four Zoning Regulations, where a mounting/attachment-spacing rule might sit) — unreadable this session

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

Nothing published by this authority.

Where we lookedLDR and the county's site generally — no fire code or ridge-setback/pathway document reachable; county has no dedicated Fire Department page at all (checked via full sitemap)

https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Not stated locally. Under the state-floor NEC 2020 adoption, rapid shutdown at the module level (NEC 690.12) would apply, since 2020 carries the module-level requirement (module-level rapid shutdown was introduced after NEC 2014, which had only the array-boundary requirement — see the CORRECTED BY RUN 60 note in the baseline this run was briefed on).

Why the confidence is not higherInference from the NEC-2020 state floor; no Union-specific document mentions rapid shutdown or NEC 690.12 by name (none was reachable to check either way).

inference from state-floor NEC edition checked 2026-09-12 https://cityoflakebutler.com/building-department/

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

No AHJ-specific placard requirement was found for Union County. At the UTILITY level, Clay Electric's current Interconnection Agreement requires a placard ONLY for battery storage: a label permanently affixed to the meter enclosure. No general PV/RGS placard is specified by either the AHJ or the utility.

Why the confidence is not higherThe utility half is directly quoted from Clay Electric's current filed tariff (Item 12(a)); the AHJ half is an absence I could not fully prove (county material unreadable), so it is closer to could-not-reach than a proven zero.

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

Clay Electric specifies exact wording for the ONE placard it requires (battery storage only): "Battery storage utilized in this facility." No general PV placard wording is specified by the utility or found for the AHJ.

Why the confidence is not higherQuoted verbatim from Clay Electric Cooperative's current Interconnection Agreement for Customer-Owned Renewable Generation Systems, Item 12(a), effective 30 April 2026 — a real text-layer PDF fetched and read directly (not OCR'd).

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

No — Clay Electric's placard clause specifies wording only ("Battery storage utilized in this facility"), with no letter height, colour, or material requirement anywhere in the document. This is a genuine, directly-read absence, not a failure to find the document.

Why the confidence is not higherThe full Interconnection Agreement (all 4 sheet pages, Items 1-21) was read in full via pdftotext with a real text layer; Item 12(a) is the only placard/label clause in the document and contains no formatting specification.

utility filed tariff (proven absence) checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedClay Electric's current Interconnection Agreement (read in full) and the county's reachable material — neither specifies a site-plan/facility-map placard

https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes — the utility (Clay Electric) is the only source of a placard requirement found in this survey run at all; the AHJ has none confirmed.

Why the confidence is not higherSame source as q38-40.

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

Clay Electric's battery-storage label must be "permanently affixed to the meter enclosure." No other AHJ or utility label-placement rule was found; the AC disconnect switch itself (not a label) must be "mounted separately from the meter socket" and "readily accessible at all times to the Cooperative" (see q48).

Why the confidence is not higherDirectly quoted from Clay Electric's current Interconnection Agreement, Items 8 and 12(a).

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q44 Must equipment be on a specific approved list? Equipment listing

At the utility-interconnection level: inverters/equipment must be certified by a Nationally Recognized Testing Laboratory (NRTL) to UL 1741 and comply with IEEE-1547 and the NEC; FSEC Std 203-05 approval is referenced as an applicable certification route where relevant. No separate AHJ-level equipment-listing requirement was confirmed.

Why the confidence is not higherDirectly quoted/paraphrased from Clay Electric's current Interconnection Agreement, Items 2 and 5, and its Solar Getting Started page.

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

Yes, batteries are permitted alongside an RGS, subject to Clay Electric's own conditions: NRTL/UL-1741 certified equipment; a permanent meter-enclosure label ("Battery storage utilized in this facility"); the battery may NOT export power to the cooperative's grid (behind-the-meter use / backup only, disconnected from the grid during outages); a UL-listed automatic transfer switch or special inverter is required. A battery system WITHOUT an accompanying RGS may charge from the grid but may NOT interconnect, per Rule 25-6.065(2)(d) F.A.C. as cited within Clay's own agreement (batteries alone are not "renewable energy").

Why the confidence is not higherDirectly quoted/paraphrased from Clay Electric's current Interconnection Agreement, Item 12(a)-(c), effective 30 April 2026.

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Q46 Is there a separate ESS permit or inspection? Battery / ESS

Nothing published by this authority.

Where we lookedCounty's Building Department page (no ESS-specific permit type listed among its 16 applications) and Clay Electric's Interconnection Agreement (battery clause, Item 12, adds conditions to the same RGS interconnection process rather than creating a separate permit/inspection)

https://unioncounty-fl.gov/building-department/

Q47 Is a ground mount treated as a structure? Core Ground mount

Nothing published by this authority.

Where we lookedLDR Table of Contents (page 4 only, readable) — ground mount / accessory-structure definitions would sit in Article Two Section 2.1 'Definitions' (pp.2-1 to 2-27) or Article Four Section 4.2 'Supplemental District Regulations' (pp.4-7 to 4-33), neither of which I could actually read (Cloudflare-gated, non-OCR'd, unreliable rendering in this session's contended shared browser — see jurisdiction.why)

https://unioncounty-fl.gov/wp-content/uploads/LDR_Union_20_Canary.pdf

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

Per Clay Electric's own current Interconnection Agreement (Item 8), a manual disconnect switch is REQUIRED on every interconnected RGS regardless of size — no Tier-1-style size exemption exists for this co-op. At the Member's expense, it must be mounted SEPARATELY from the meter socket, be readily accessible AT ALL TIMES to the Cooperative, and be capable of being locked in the open position by the Cooperative. No specific distance figure is given (unlike FPL's 10 feet or SECO's 5 feet) — only "mounted separately."

Why the confidence is not higherQuoted directly from Clay Electric Cooperative's own current filed tariff sheet (Second/Third Revised Sheet Nos. 21.0-21.02, 'Effective: April 30, 2026'), fetched and read in full via pdftotext (real text layer, not OCR). This is a fresh reproof of the survey's existing Clay reading, confirming the mandatory-disconnect finding still holds and adding the battery-placard detail the existing reading did not record (see q39-40).

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Through the Cloudpermit portal, which the county's own page lists as supporting scheduling AND cancelling of inspections online; a phone/email route to the Building Department also exists. 80% · department page
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes, in-house. The county names a single County-employed Building Inspector (Wilson Whidden/Whiddon, @unioncounty-fl.gov) and no private firm's name, letterhead, or staff email domain (e.g. SAFEbuilt, PDCS, CAP Government, JPI, M.T. Causley, Bureau Veritas, CGA Solutions, WILLDAN, ALPHA INSPECTIONS) was found anywhere on the county's or Lake Butler's own sites. 65% · named official + absence of private-firm signature (fallback test)
    • If delegated, to whom? N/A — not delegated to a private firm; performed by the County's own Building Department (see q52). Building/electrical IS however delegated FROM the City of Lake Butler TO this same county department — see jurisdiction.holds. 65% · department page
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    Nothing recorded for Union County on this step yet — 2 questions checked and found unpublished. The guidance above is general.

  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? A general (not solar-specific) checklist, 'Items Required to Obtain a Building or Addition Permit,' exists on the county's site, but I could not reliably transcribe its full contents this session (see q8) and no solar/PV-specific inspection checklist was found. 45% · county PDF (partial read)
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • Who notifies the utility for PTO? The Member (customer/installer), not the AHJ, is responsible for notifying the utility: Clay Electric's own Interconnection Agreement (Item 4) requires the Member to notify the Cooperative at least 10 days prior to the RGS's in-service date, and Clay may then witness testing before/after the RGS is placed in service. 85% · utility filed tariff
    • How are corrections issued and cleared? Likely via the Cloudpermit portal's messaging feature — the county's own description says Cloudpermit provides 'time-stamped messages' with the department and lets an applicant 'request and submit changes to an existing building permit.' Not solar-specific and not independently confirmed for corrections/re-inspection specifically. 55% · department page (general portal description)

14 questions answered against Union County’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Through the Cloudpermit portal, which the county's own page lists as supporting scheduling AND cancelling of inspections online; a phone/email route to the Building Department also exists.

Why the confidence is not higherDirectly from the county's own Building Department page description of Cloudpermit's capabilities.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q50 How much notice is required? Core Booking & scheduling

Nothing published by this authority.

Where we lookedCounty's Building Department page and Cloudpermit description — no notice-period figure stated

https://unioncounty-fl.gov/building-department/

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

Nothing published by this authority.

Where we lookedSame as q50 — no AM/PM or same-day window mentioned

https://unioncounty-fl.gov/building-department/

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes, in-house. The county names a single County-employed Building Inspector (Wilson Whidden/Whiddon, @unioncounty-fl.gov) and no private firm's name, letterhead, or staff email domain (e.g. SAFEbuilt, PDCS, CAP Government, JPI, M.T. Causley, Bureau Veritas, CGA Solutions, WILLDAN, ALPHA INSPECTIONS) was found anywhere on the county's or Lake Butler's own sites.

Why the confidence is not higherThis rests on a fallback test (a single named in-house government-domain employee, and the absence of any of the eight known private-provider firms' names or email domains) rather than on a published FS 553.80(7)(b) utilization report, which does not appear anywhere in the county's 40-URL site — an absence I could confirm via the full sitemap but which the brief itself notes is common and unremarkable for a small rural county (Union is Florida's smallest county by land area), so confidence is priced down accordingly rather than treated as proof of anything.

named official + absence of private-firm signature (fallback test) checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q53 If delegated, to whom? Core Who inspects

N/A — not delegated to a private firm; performed by the County's own Building Department (see q52). Building/electrical IS however delegated FROM the City of Lake Butler TO this same county department — see jurisdiction.holds.

Why the confidence is not higherFollows from q52.

department page checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q54 Which inspections are required, and in what order? Core Stages & sequence

Nothing published by this authority.

Where we lookedCounty's Building Department page and full application list — no inspection sequence (rough-in, final, etc.) published for any trade, solar or otherwise

https://unioncounty-fl.gov/building-department/

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Nothing published by this authority.

Where we lookedSame as q54

https://unioncounty-fl.gov/building-department/

Q56 Does the inspector verify labels and listings? Core What is checked

Nothing published by this authority.

Where we lookedSame as q54 — nothing describing what an inspector checks

https://unioncounty-fl.gov/building-department/

Q57 Is there a published inspection checklist? Core What is checked

A general (not solar-specific) checklist, 'Items Required to Obtain a Building or Addition Permit,' exists on the county's site, but I could not reliably transcribe its full contents this session (see q8) and no solar/PV-specific inspection checklist was found.

Why the confidence is not higherSame document and same extraction limitation as q8.

county PDF (partial read) checked 2026-09-12 https://unioncounty-fl.gov/wp-content/uploads/Residential-House-Application-fillable-2.5.25.pdf

Q58 What must be on site at inspection? Core Documents on site

Nothing published by this authority.

Where we lookedSame as q54 — no on-site document requirement published

https://unioncounty-fl.gov/building-department/

Q59 Is there a re-inspection fee? Corrections & re-inspection

Nothing published by this authority.

Where we lookedCounty's site generally — no fee schedule reachable at all (see q15), so no re-inspection fee figure either

https://unioncounty-fl.gov/wp-sitemap-posts-page-1.xml

Q60 How are corrections issued and cleared? Corrections & re-inspection

Likely via the Cloudpermit portal's messaging feature — the county's own description says Cloudpermit provides 'time-stamped messages' with the department and lets an applicant 'request and submit changes to an existing building permit.' Not solar-specific and not independently confirmed for corrections/re-inspection specifically.

Why the confidence is not higherInferred from the county's general description of Cloudpermit's feature set, not a dedicated corrections-process document.

department page (general portal description) checked 2026-09-12 https://unioncounty-fl.gov/building-department/

Q61 What is issued on pass? Core Final sign-off & PTO

Nothing published by this authority.

Where we lookedCounty's Building Department page and application list — nothing states what document is issued on a passed final (CO, green tag, etc.)

https://unioncounty-fl.gov/building-department/

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

The Member (customer/installer), not the AHJ, is responsible for notifying the utility: Clay Electric's own Interconnection Agreement (Item 4) requires the Member to notify the Cooperative at least 10 days prior to the RGS's in-service date, and Clay may then witness testing before/after the RGS is placed in service.

Why the confidence is not higherDirectly quoted/paraphrased from Clay Electric's current Interconnection Agreement, Item 4.

utility filed tariff checked 2026-09-12 https://www.clayelectric.com/sites/default/files/documents/solar/PhotovoltaicInterconnectionAgreement.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 90%

Clay Electric specifies exact wording for the ONE placard it requires (battery storage only): "Battery storage utilized in this facility." No general PV placard wording is specified by the utility or found for the AHJ.

Size, colour & material 85%

No — Clay Electric's placard clause specifies wording only ("Battery storage utilized in this facility"), with no letter height, colour, or material requirement anywhere in the document. This is a genuine, directly-read absence, not a failure to find the document.

Where they go 88%

Clay Electric's battery-storage label must be "permanently affixed to the meter enclosure." No other AHJ or utility label-placement rule was found; the AC disconnect switch itself (not a label) must be "mounted separately from the meter socket" and "readily accessible at all times to the Cooperative" (see q48).

What the utility wants on top 85%

Yes — the utility (Clay Electric) is the only source of a placard requirement found in this survey run at all; the AHJ has none confirmed.

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Notes
Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/ --- Fetch failed: HTTPError: 403 Client Error: Forbidden for url: https://unioncounty-fl.gov/building-department/
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.

About this authority
Type
County
County
Union County
Regions covered
Authority Contact
Building Department
Direct Phone
(386) 496-2676
Booking & Scheduling