Village of Wellington is a village authority in the State of Florida, serving 61,637 residents. This page is the permit route for that jurisdiction: the fifteen steps from working out who has a say over an address through to permission to operate, the documents this authority publishes, and 62 answers taken from those documents and dated.

Jurisdiction & key facts

The standing 62-question set, answered for Village of Wellington against this authority’s own published documents. Every answer carries the confidence it was recorded at and the document it came from. Where nothing is published we say so and show where we looked — a blank here is a finding, not a gap.

Village of Wellington is the authority having jurisdiction 93% confidence
Holds
Both — Building and Electrical are permitted, plan-reviewed and inspected directly by the Village of Wellington's own Planning, Zoning and Building Department (Building Official Matt Mills, CBO; electrical inspector David Bardin). Fire plan review and fire inspection are NOT held by the Village: Wellington's own Public Safety and Building Inspections pages state plainly that 'Wellington has its Fire/EMS services provided by Palm Beach County Fire Rescue (PBCFR)' and list a 'Palm Beach County Fire Inspector' (Jeffrey Miller) as a Building-division inspection contact. Zoning/Planning sits in the same department as Building (it is one combined department at Wellington, unlike the brief's caution about Alameda), so no separate delegation exists there for rooftop PV.
Delegated to
Fire: Palm Beach County Fire Rescue (Battalion 2). Law enforcement (not relevant to solar): Palm Beach County Sheriff's Office under contract.
Overridden by
FS 553.791 (private-provider plan review/inspection, opt-in by the applicant) and FS 553.7913 (2-business-day notice for private-provider inspections); HB 803 (2026) amends FS 125.56(4)(d)/553.79(1)(c) to a 1-year permit-validity floor effective 1 Jul 2026, which is longer than Wellington's currently-published 180-day permit renewal window (Fee Schedule item 12) — a live conflict, not resolved here. HB 803's $7,500 permit-fee exemption (FS 553, effective 1 Jul 2026) explicitly EXCLUDES electrical work, so it does not reach residential PV (Wellington's own HB 803 page confirms the exclusion list includes 'Electrical').
Why not higher
Wellington's own Building Permits, Building, and Guide to Permitting pages (wellingtonfl.gov/214, /252, /269) show the Village running its own ProjectDox e-plan portal and its own Tyler EnerGov Self-Service system, its own fee schedule, its own named Building Official and inspectors, and its own solar-specific checklist bundle (BuildingDocs@WellingtonFL.gov). This is a directly-operated municipal building department, not a county pass-through — Wellington is NOT one of the Palm Beach County Building Division's contract municipalities (confirmed by the presence of Wellington's own independent building permit application, fee schedule and portal; no county co-branding appears anywhere in Wellington's own building pages). The one genuine split is Fire, which is stated in the Village's own words to be delivered by Palm Beach County Fire Rescue.

https://www.wellingtonfl.gov/2116/Palm-Beach-County-Fire-Rescue-Battalion-2

Permit required
Yes, a permit is required95%
Permit cost
Valuation-based: $150 minimum fee (projects $0.01-$7,500), then 2.00% of construction value from $7,500.01-$100,000 (declining percentage above that);82%
Plan review
4 working days for first review by Building, plus 1 working day per resubmission/consecutive review round ('5 Day Turnaround')95%
Portal
Two systems in sequence: ProjectDox / Avolve Cloud (plans.wellingtonfl.gov, wellington-fl-us.avolvecloud.com) for electronic plan review and document upload/download,90%
Electrical code
Not specified by name/edition in any of Wellington's own solar, electrical, or code-amendment documents — all of them cite only 'FBC 8th Edition (2023)' and never name an NFPA 70/NEC year.45%
Own placard wording
No — Wellington's own documents specify no placard wording of their own; all specific placard wording found is FPL's (utility), not the Village's68%
Booking an inspection
Portal (Tyler EnerGov Self Service) is the primary route; phone (561-753-2430) is used to confirm/inquire about time-of-arrival the morning of an inspection82%
Permitting 5 steps · 28 questions

Whether a permit is needed — Yes, a permit is required Q3 Electrical and building permits — Combined (best evidence) — the Village's Plan Review Time-Frame Chart lists a single application type 'Solar Panel Installation' (Building, 4-day review, Q4 Plan review — 4 working days for first review by Building, plus 1 working day per resubmission/consecutive review round ('5 Day Turnaround') Q18 Where you file — Two systems in sequence: ProjectDox / Avolve Cloud (plans.wellingtonfl.gov, wellington-fl-us.avolvecloud.com) for electronic plan review and document… Q20

Permit required
Yes, a permit is required95% source
What it costs
Valuation-based: $150 minimum fee (projects $0.01-$7,500), then 2.00% of construction value from $7,500.01-$100,000 (declining percentage above that);82% source
Plan review turnaround
4 working days for first review by Building, plus 1 working day per resubmission/consecutive review round ('5 Day Turnaround')95% source
Key document
Village solar permit packet, Policies & Procedures page cited by 9 open the document
  1. Confirm who has a say over your address

    A city address is usually permitted by the city, not the county — but not always, and some authorities keep building and hand electrical to someone else. Getting this wrong costs the whole submittal, because every requirement below belongs to whoever actually holds jurisdiction. Check the overlays in the same pass: an HOA, a historic district, a windstorm certification or a system-size cap can reshape the design, and all of them are cheaper to find now than after the array is laid out.

    • Is this authority the AHJ for residential solar at this address? Yes — the Village of Wellington's own Planning, Zoning and Building Department is the AHJ for residential solar at addresses within the Village 95% · Village solar permit packet (rev. 5/24)
    • What does this authority permit itself, and what does it delegate? Both — Building and Electrical are both permitted/inspected directly by the Village (one combined Planning-Zoning-Building department). Fire is delegated to Palm Beach County Fire Rescue and is not part of the Village's own permitting authority 88% · Village department page
    • Is a permit required for a residential rooftop PV system? Yes, a permit is required 95% · Village department page (HB 803 notice)
    • Is there a separate electrical permit, or is it combined? Combined (best evidence) — the Village's Plan Review Time-Frame Chart lists a single application type 'Solar Panel Installation' (Building, 4-day review, 5-day turnaround) rather than separate 'Solar Structural' and 'Solar Electrical' rows, suggesting one filed permit covers both trades 65% · Village Plan Review Time-Frame Chart
    • Is a HOA or architectural approval required first? No — the Village does NOT consult or require sign-off from private Homeowners Associations before issuing a permit, and says so explicitly, though the applicant remains contractually responsible for their own HOA/deed-restriction compliance separately from the permit 92% · Village Miscellaneous Improvements Affidavit/Checklist
    • Is there a historic-district review? No — no historic-district review is published for Wellington 82% · site search with controls
    • Is a wind or windstorm certification required? Yes — the mounting system must be site-specifically engineered to a Design Wind Speed of 170vult MPH, Exposure B or C 90% · Village solar permit packet
    • Is a Specific Use Permit or Council approval ever required? No specific-use permit or Council approval is published for ordinary residential rooftop PV; Wellington's Equestrian Overlay Zoning District (EOZD, adopted 2003) governs a separate ~9,000-acre Equestrian Preserve Area but is not invoked by the Village's own rooftop-solar checklist/affidavit route 60% · Village FAQ (Equestrian Overlay Zoning District)
  2. Check who is allowed to apply

    Several authorities require the electrical permit to be pulled by a licensed electrician, or require the contractor to be registered with them BEFORE applying. Registration is not same-day. This is second on the list rather than fourth because it is the step most likely to stop the job before the drawings matter.

    • Who is allowed to pull the electrical permit? Either — a licensed contractor (Qualifier) or the homeowner as owner-builder 75% · Village solar permit packet
    • Must the contractor be registered with this authority before applying? Yes — contractors must register with Wellington (submit PBC business tax receipt, PBC Certificate of Competency/DBPR license, driver's license, liability and workers' comp insurance naming the Village as certificate holder) before they can be issued ProjectDox/Self-Service login credentials to apply 85% · Village Contractor Registration Packet (rev. 5/24)
    • Is a homeowner permitted to self-install and self-permit? Yes — an Owner/Builder Affidavit route exists and is listed as an applicable submittal document on the solar checklist 72% · Village solar permit packet
  3. Build the submittal package

    Almost everywhere wants a site plan, a one-line or three-line electrical diagram, equipment cut sheets with listings, and a structural attachment detail. Build it against the published checklist rather than the last jurisdiction you worked in — the checklist is what the reviewer marks against.

    • What documents make up a complete submittal? Completed Building Permit Application; full set of construction documents/plans by a registered/authorized design professional (signed, sealed, dated, digitally verifiable signature if by an RDP); Owner/Builder Affidavit if applicable; Notice of Commencement if applicable; scope of work with total replacement value per FBC 8th Ed. 109.3; Sub Trade Permit Application if applicable; Solar PV Worksheet if applicable — PLUS a completed 'Solar PV (Photovoltaic) Installation Checklist Form' covering structural specs (mounting/bracket manufacturer with product approval, engineered attachment details) and electrical specs (total PV output amps, conductor size, point-of-connection method per NEC 705.12 table), with a Qualifier's affidavit certifying compliance 92% · Village solar permit packet (rev. 5/24)
    • How many copies, and in what format? Electronic only — application submitted by email to BuildingDocs@wellingtonfl.gov, then plans/documents uploaded to ProjectDox (PDF preferred, one drawing page per file, named exactly as shown on the sheet, e.g. A-00, E-01); after permit issuance, applicant must print ONE physical set of approved plans, in legible size, in color if it contains markups, for the Permit Box/job site 82% · Village department page (Guide to Permitting)
    • Is a one-line / three-line diagram required? Yes — a one-line diagram is required 95% · Village solar permit packet
    • Are string and conductor calculations required? Yes — the checklist requires stating total PV output amps, open-circuit conductor size, service conductor size, inverter output conductor size, and requires selecting the correct wire/OCPD/busbar/breaker combination from a table matching NEC 705.12; it also limits the array to '4 series strings or less, per Inverter' 82% · Village solar permit packet
    • Is a structural PE stamp required, and at what threshold? A structural PE stamp is not stated at a fixed valuation/size threshold, but a SITE-SPECIFICALLY ENGINEERED mounting system to 170vult MPH wind pressure is required on every job, and the Village explicitly will NOT accept a contractor affidavit or an engineering certification in place of prior Building Official approval: 'THE VILLAGE OF WELLINGTON DOES NOT ACCEPT CONTRACTOR AFFIDAVITS NOR ENGINEERING CERTIFICATIONS WITHOUT PRIOR APPROVAL OF THE BUILDING OFFICIAL AS PER FBC-B 8TH ED., 2023 CHAPTER 1 - SECTION 110.1.3' 85% · Village solar permit packet, Policies & Procedures page
    • Is an electrical PE stamp required, and at what threshold? Not stated as a distinct PE-stamp threshold; the checklist instead requires the system be 'FSEC Certified or ... designed by an appropriate licensed professional' with all equipment listed/labeled for PV use 55% · Village solar permit packet
  4. Apply and pay

    Most authorities now take the whole application through a portal, and several states cap or constrain what a residential solar permit may cost. Check whether plan check is billed separately before you quote the job.

    • Which permit portal does this authority use? Two systems in sequence: ProjectDox / Avolve Cloud (plans.wellingtonfl.gov, wellington-fl-us.avolvecloud.com) for electronic plan review and document upload/download, and Tyler Technologies EnerGov 'Self Service' (wellingtonfl-energovweb.tylerhost.net/apps/SelfService) for fee payment, inspection scheduling and permit-status lookup, branded on the Village's site as 'CSS' 90% · Village department page + portal redirect target
    • Can the whole application be completed online? No — the initial Building Permit application itself must be emailed to BuildingDocs@wellingtonfl.gov (a human Permit Technician enters it into the system); only the subsequent plan upload/review/correction cycle and fee payment happen online, via ProjectDox and the EnerGov Self-Service portal 85% · Village department page (Guide to Permitting)
    • What does a residential solar permit cost? Valuation-based: $150 minimum fee (projects $0.01-$7,500), then 2.00% of construction value from $7,500.01-$100,000 (declining percentage above that); PLUS a 1% DBPR surcharge (FS 553.721, min $2), a 1.5% Building Code Administrators & Inspectors Fund surcharge (FS 468.631, min $2), a Building Plan Review Fee of the greater of 50% of the permit fee or $75, and a Zoning Review Fee of $75 (single family). Example: a $20,000 residential PV system ≈ $400 building permit fee + $200 plan review + $75 zoning + ~$10 state surcharges ≈ $685 total, before any Special/Expedited review 82% · Village Permit Fee Schedule (live page)
    • How is the fee calculated? Valuation (tiered percentage of construction value, with a flat minimum) 95% · Village Permit Fee Schedule (live page)
    • Is there a separate plan-check fee? Yes — a separate Building Plan Review Fee applies, the greater of 50% of the calculated Building Permit Fee or a $75.00 minimum, paid at time of application; refundable per the schedule's refund section if the permit is withdrawn before review 90% · Village Permit Fee Schedule (live page)
  5. Plan review — and start the utility in parallel

    Interconnection is a separate process from the permit and usually the longer pole. Where the utility does not depend on the permit being issued, running both at once is the single biggest saving available on a residential job.

    • What is the stated plan-review turnaround? 4 working days for first review by Building, plus 1 working day per resubmission/consecutive review round ('5 Day Turnaround') 95% · Village Plan Review Time-Frame Chart
    • How long is an issued permit valid before it expires? 180 days — the Village's fee schedule states a permit 'is automatically extended for a period of One-Hundred-Eighty (180) days from a received Approved inspection,' with 30-day no-charge extensions at the Building Official's discretion, or a paid extension (30% of permit fee, min $75). NOTE A LIVE CONFLICT: Florida HB 803 (2026), amending FS 125.56(4)(d) and FS 553.79(1)(c), sets a state-law floor of 1 YEAR permit validity effective 1 Jul 2026, which appears longer than what this page currently publishes 75% · Village Permit Fee Schedule (live page)
    • Which utility handles interconnection here? Florida Power & Light (FPL) 88% · Village department page (Engineering & Construction)
    • Where does the utility sit in the sequence? After permit / before energization — FPL's tariff requires 'the Customer ... provide Local Building Code Official inspection and certification of installation' (Sheet 9.050 §3.4) confirming the installation 'was permitted, has been approved, and has met all electrical and mechanical qualifications,' and the customer must notify FPL at least 10 calendar days before initially placing the system in service (§3.5) 85% · FPL PSC-filed electric tariff, Section 9, eff. 1 Jan 2026

28 questions answered against Village of Wellington’s own published documents

Q1 Is this authority the AHJ for residential solar at this address? Core Jurisdiction & scope

Yes — the Village of Wellington's own Planning, Zoning and Building Department is the AHJ for residential solar at addresses within the Village

Why the confidence is not higherWellington's Solar Panel permit packet is issued and stamped by 'Village of Wellington ... 12300 Forest Hill Boulevard ... BuildingDocs@WellingtonFL.Gov'; the Village runs its own fee schedule, portal and inspectors for building/electrical

Village solar permit packet (rev. 5/24) checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q2 What does this authority permit itself, and what does it delegate? Core Jurisdiction & scope

Both — Building and Electrical are both permitted/inspected directly by the Village (one combined Planning-Zoning-Building department). Fire is delegated to Palm Beach County Fire Rescue and is not part of the Village's own permitting authority

Why the confidence is not higherThe Village's Universal Building Permit Application (bundled in the solar packet) lists ELECTRICAL as one of its own trade checkboxes processed by Wellington; separately, the Village's own Public Safety page states fire/EMS is provided by Palm Beach County Fire Rescue

Village department page checked 2026-09-12 https://www.wellingtonfl.gov/2116/Palm-Beach-County-Fire-Rescue-Battalion-2

Q3 Is a permit required for a residential rooftop PV system? Core Jurisdiction & scope

Yes, a permit is required

Why the confidence is not higherThe Solar (Electric or Plumbing) Checklist Form and Solar PV Installation Checklist Form both exist specifically to process a required permit; the Village's HB 803 exemption page explicitly EXCLUDES 'Electrical ... structural or mechanical' work from its $7,500 no-permit exemption, so PV (which is electrical/structural) cannot be exempted

Village department page (HB 803 notice) checked 2026-09-12 https://www.wellingtonfl.gov/2412/House-Bill-803---Permit-Exemption

Q4 Is there a separate electrical permit, or is it combined? Core Jurisdiction & scope

Combined (best evidence) — the Village's Plan Review Time-Frame Chart lists a single application type 'Solar Panel Installation' (Building, 4-day review, 5-day turnaround) rather than separate 'Solar Structural' and 'Solar Electrical' rows, suggesting one filed permit covers both trades

Why the confidence is not higherInference from the Village's own Plan-Review Time-Frame Chart, which lists 'Solar Panel Installation' as one row under reviewing department 'Building' — general 'Electric' work has its own separate row on the same chart, so this is not fully conclusive for PV specifically, and the bundled Universal Permit Application's trade box says 'CHECK ONE' which could imply sub-permits

Village Plan Review Time-Frame Chart checked 2026-09-12 https://www.wellingtonfl.gov/228/Plan-Review-Time-Frame-Chart

Q5 Who is allowed to pull the electrical permit? Core Who may apply

Either — a licensed contractor (Qualifier) or the homeowner as owner-builder

Why the confidence is not higherThe solar checklist packet lists 'Owner/Builder Affidavit, if applicable' among required submittal items alongside the Qualifier's affidavit/signature block, so both routes exist; Florida owner-builder rights derive from Fla. Stat. 489.103(7)

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q6 Must the contractor be registered with this authority before applying? Core Who may apply

Yes — contractors must register with Wellington (submit PBC business tax receipt, PBC Certificate of Competency/DBPR license, driver's license, liability and workers' comp insurance naming the Village as certificate holder) before they can be issued ProjectDox/Self-Service login credentials to apply

Why the confidence is not higherVillage's own Contractor Registration Packet states these are the items 'Contractors Must Submit ... With the Registration Application' emailed to BuildingDocs@WellingtonFL.gov, and the Guide to Permitting confirms the contractor's registered email is what is used for ProjectDox login

Village Contractor Registration Packet (rev. 5/24) checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4914/Contractor-Registration-Packet_FINAL-es

Q7 Is a homeowner permitted to self-install and self-permit? Who may apply

Yes — an Owner/Builder Affidavit route exists and is listed as an applicable submittal document on the solar checklist

Why the confidence is not higherListed as 'Owner/Builder Affidavit, if applicable' on the Solar (Electric or Plumbing) Checklist; the bundled Universal Permit Application has a full Owner-Builder box (Fla. Stat. 489) with notary requirements — but the solar Policies & Procedures document is written mainly around a licensed 'Qualifier,' so the self-install route is not emphasized for PV specifically

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q8 What documents make up a complete submittal? Core Submittal package

Completed Building Permit Application; full set of construction documents/plans by a registered/authorized design professional (signed, sealed, dated, digitally verifiable signature if by an RDP); Owner/Builder Affidavit if applicable; Notice of Commencement if applicable; scope of work with total replacement value per FBC 8th Ed. 109.3; Sub Trade Permit Application if applicable; Solar PV Worksheet if applicable — PLUS a completed 'Solar PV (Photovoltaic) Installation Checklist Form' covering structural specs (mounting/bracket manufacturer with product approval, engineered attachment details) and electrical specs (total PV output amps, conductor size, point-of-connection method per NEC 705.12 table), with a Qualifier's affidavit certifying compliance

Why the confidence is not higherVerbatim from the Village's current bundled Solar Panel packet (checklist form + Universal Building Permit Application + Solar PV Installation Checklist + Policies & Procedures for Solar PV), all dated 'May 24' / masthead 'Rev.10-03-23' for the NOC page

Village solar permit packet (rev. 5/24) checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q9 How many copies, and in what format? Submittal package

Electronic only — application submitted by email to BuildingDocs@wellingtonfl.gov, then plans/documents uploaded to ProjectDox (PDF preferred, one drawing page per file, named exactly as shown on the sheet, e.g. A-00, E-01); after permit issuance, applicant must print ONE physical set of approved plans, in legible size, in color if it contains markups, for the Permit Box/job site

Why the confidence is not higherFrom the Village's Guide to Permitting ('Preparing Files for Submittal' and Step 5 'Print Your Permit Card & Plans') — this is the general electronic-permitting process description, not a solar-specific copies/format statement, so it is an inference applied to solar

Village department page (Guide to Permitting) checked 2026-09-12 https://www.wellingtonfl.gov/269/Guide-to-Permitting

Q10 Is a site plan required, and what must it show? Core Submittal package

Nothing published by this authority.

Where we lookedVillage's Solar (Electric or Plumbing) Checklist and Solar PV Installation Checklist Form (both pages of the bundled solar packet) for a site-plan requirement/content list specific to rooftop PV; found none — the checklist covers only structural/electrical specs, no site-plan line item, unlike Alameda County's ground-mount checklist which does itemize one

https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q11 Is a one-line / three-line diagram required? Core Drawings & calculations

Yes — a one-line diagram is required

Why the confidence is not higherSolar PV Installation Checklist / Policies & Procedures document: qualifier must certify 'The Qualifier has provided a one (1) line diagram & system design'

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q12 Are string and conductor calculations required? Drawings & calculations

Yes — the checklist requires stating total PV output amps, open-circuit conductor size, service conductor size, inverter output conductor size, and requires selecting the correct wire/OCPD/busbar/breaker combination from a table matching NEC 705.12; it also limits the array to '4 series strings or less, per Inverter'

Why the confidence is not higherThe Solar PV Installation Checklist Form's Electrical Specs section and the qualifier's certification list both require these sizing entries, though the document does not separately demand a signed string/voltage-drop calculation sheet beyond filling in this table

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q13 Is a structural PE stamp required, and at what threshold? Core Engineering & stamps

A structural PE stamp is not stated at a fixed valuation/size threshold, but a SITE-SPECIFICALLY ENGINEERED mounting system to 170vult MPH wind pressure is required on every job, and the Village explicitly will NOT accept a contractor affidavit or an engineering certification in place of prior Building Official approval: 'THE VILLAGE OF WELLINGTON DOES NOT ACCEPT CONTRACTOR AFFIDAVITS NOR ENGINEERING CERTIFICATIONS WITHOUT PRIOR APPROVAL OF THE BUILDING OFFICIAL AS PER FBC-B 8TH ED., 2023 CHAPTER 1 - SECTION 110.1.3'

Why the confidence is not higherVerbatim from the Village's Policies & Procedures for Solar Photovoltaic (PV) document bundled with the solar packet

Village solar permit packet, Policies & Procedures page checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q14 Is an electrical PE stamp required, and at what threshold? Engineering & stamps

Not stated as a distinct PE-stamp threshold; the checklist instead requires the system be 'FSEC Certified or ... designed by an appropriate licensed professional' with all equipment listed/labeled for PV use

Why the confidence is not higherInference — the Village's own document conflates structural and electrical engineering language under one 'Qualifier certifies' section and does not carve out a separate electrical PE threshold

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q15 What does a residential solar permit cost? Core Fees

Valuation-based: $150 minimum fee (projects $0.01-$7,500), then 2.00% of construction value from $7,500.01-$100,000 (declining percentage above that); PLUS a 1% DBPR surcharge (FS 553.721, min $2), a 1.5% Building Code Administrators & Inspectors Fund surcharge (FS 468.631, min $2), a Building Plan Review Fee of the greater of 50% of the permit fee or $75, and a Zoning Review Fee of $75 (single family). Example: a $20,000 residential PV system ≈ $400 building permit fee + $200 plan review + $75 zoning + ~$10 state surcharges ≈ $685 total, before any Special/Expedited review

Why the confidence is not higherFormula taken verbatim from the Village's current live Permit Fee Schedule page; no PV-specific flat fee line exists — PV is charged like any other valuation-based building permit; the page carries no visible effective-date stamp, which is a minor deduction

Village Permit Fee Schedule (live page) checked 2026-09-12 https://www.wellingtonfl.gov/282/permit-fee-schedule

Q16 How is the fee calculated? Core Fees

Valuation (tiered percentage of construction value, with a flat minimum)

Why the confidence is not higherSame source as q15

Village Permit Fee Schedule (live page) checked 2026-09-12 https://www.wellingtonfl.gov/282/permit-fee-schedule

Q17 Is there a separate plan-check fee? Fees

Yes — a separate Building Plan Review Fee applies, the greater of 50% of the calculated Building Permit Fee or a $75.00 minimum, paid at time of application; refundable per the schedule's refund section if the permit is withdrawn before review

Why the confidence is not higherVerbatim from Permit Fee Schedule item 4

Village Permit Fee Schedule (live page) checked 2026-09-12 https://www.wellingtonfl.gov/282/permit-fee-schedule

Q18 What is the stated plan-review turnaround? Core Timeline & validity

4 working days for first review by Building, plus 1 working day per resubmission/consecutive review round ('5 Day Turnaround')

Why the confidence is not higherVerbatim row 'Solar Panel Installation | Building | 4 | 1 | 5 Day Turnaround' on the Village's own Plan Review Time-Frame Chart for electronic permit submittals — this is a genuine solar-specific line item, not a general default

Village Plan Review Time-Frame Chart checked 2026-09-12 https://www.wellingtonfl.gov/228/Plan-Review-Time-Frame-Chart

Q19 How long is an issued permit valid before it expires? Timeline & validity

180 days — the Village's fee schedule states a permit 'is automatically extended for a period of One-Hundred-Eighty (180) days from a received Approved inspection,' with 30-day no-charge extensions at the Building Official's discretion, or a paid extension (30% of permit fee, min $75). NOTE A LIVE CONFLICT: Florida HB 803 (2026), amending FS 125.56(4)(d) and FS 553.79(1)(c), sets a state-law floor of 1 YEAR permit validity effective 1 Jul 2026, which appears longer than what this page currently publishes

Why the confidence is not higherVerbatim from Permit Fee Schedule item 12 (checked 12 Sep 2026, after the 1 Jul 2026 HB 803 effective date) — the page may not yet reflect the new state floor; both the local figure and the state conflict are recorded rather than resolved, per instruction

Village Permit Fee Schedule (live page) checked 2026-09-12 https://www.wellingtonfl.gov/282/permit-fee-schedule

Q20 Which permit portal does this authority use? Core Portal & process

Two systems in sequence: ProjectDox / Avolve Cloud (plans.wellingtonfl.gov, wellington-fl-us.avolvecloud.com) for electronic plan review and document upload/download, and Tyler Technologies EnerGov 'Self Service' (wellingtonfl-energovweb.tylerhost.net/apps/SelfService) for fee payment, inspection scheduling and permit-status lookup, branded on the Village's site as 'CSS'

Why the confidence is not higherThe Village's own Guide to Permitting names ProjectDox by URL; the 'Self Service Portal' / 'CSS' link (wellingtonfl.gov/SelfService) 301-redirects to the Tyler EnerGov hostname, confirmed by following the redirect directly

Village department page + portal redirect target checked 2026-09-12 https://www.wellingtonfl.gov/269/Guide-to-Permitting

Q21 Can the whole application be completed online? Core Portal & process

No — the initial Building Permit application itself must be emailed to BuildingDocs@wellingtonfl.gov (a human Permit Technician enters it into the system); only the subsequent plan upload/review/correction cycle and fee payment happen online, via ProjectDox and the EnerGov Self-Service portal

Why the confidence is not higherGuide to Permitting Step 1: 'Submit your completed Building Permit application to the Village by email'; login credentials for ProjectDox are only issued after that email is processed ADDITIONAL NOTE on SolarAPP+: solarapp.org itself was unreachable by every method tried (curl with browser UA, headless Chrome dump-DOM) at time of check — appears to be a live infrastructure outage rather than a block — so the official SolarAPP+ adopter list could not be independently checked. Wellington's own site search for 'SolarAPP' returned zero real hits in the same session as working positive ('electrical'=10) and fabricated ('zzqqx'=0) controls, and the confirmed portal identity is ProjectDox + Tyler EnerGov, not SolarAPP+ — a reasonably strong but not fully independently verified negative.

Village department page (Guide to Permitting) checked 2026-09-12 https://www.wellingtonfl.gov/269/Guide-to-Permitting

Q22 Which utility handles interconnection here? Core Utility interconnection

Florida Power & Light (FPL)

Why the confidence is not higherThe Village's own Private Utility Companies page names FPL as the electric-power franchise utility operating within Wellington's right-of-way; this matches FPL's own PSC-filed tariff territory and is NOT a PowerToChoose-only inference

Village department page (Engineering & Construction) checked 2026-09-12 https://www.wellingtonfl.gov/2161/Private-Utility-Companies

Q23 Where does the utility sit in the sequence? Core Utility interconnection

After permit / before energization — FPL's tariff requires 'the Customer ... provide Local Building Code Official inspection and certification of installation' (Sheet 9.050 §3.4) confirming the installation 'was permitted, has been approved, and has met all electrical and mechanical qualifications,' and the customer must notify FPL at least 10 calendar days before initially placing the system in service (§3.5)

Why the confidence is not higherVerbatim from FPL's PSC-filed electric tariff, Customer-Owned Renewable Generation Tier 1 Interconnection Agreement, Sheets 9.050-9.051

FPL PSC-filed electric tariff, Section 9, eff. 1 Jan 2026 checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Q24 Is a HOA or architectural approval required first? Overlays & special cases

No — the Village does NOT consult or require sign-off from private Homeowners Associations before issuing a permit, and says so explicitly, though the applicant remains contractually responsible for their own HOA/deed-restriction compliance separately from the permit

Why the confidence is not higherVerbatim from the Village's own 'Miscellaneous Improvements Affidavit/Checklist' (which every principal/accessory-structure building permit, including solar per its inclusion of 'Solar heating panels ... Section 6.4.1.A.9 of the LDR', must include): 'Wellington will not consult private Homeowners Associations prior to issuing a permit. The applicant, and not Wellington, is responsible for determining whether any private deed restrictions exist'

Village Miscellaneous Improvements Affidavit/Checklist checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4935/Miscellaneous-Improvements-Form_FINAL-es

Q25 Is there a historic-district review? Overlays & special cases

No — no historic-district review is published for Wellington

Why the confidence is not higherSite search for 'historic district' on wellingtonfl.gov returned zero results; controls in the same session: positive control 'electrical' = 10 results (nonzero, search functioning), fabricated control 'zzqqx' = 0 results. Wellington was incorporated in 1996 as a planned community and has no known historic-district overlay

site search with controls checked 2026-09-12 https://www.wellingtonfl.gov/Search?searchPhrase=historic%20district

Q26 Is a wind or windstorm certification required? Overlays & special cases

Yes — the mounting system must be site-specifically engineered to a Design Wind Speed of 170vult MPH, Exposure B or C

Why the confidence is not higherVerbatim qualifier certification on the Village's Solar PV Installation Checklist / Policies & Procedures document: 'The Design Wind Speed for the project is 170vult MPH; Exposure B or C' and 'The Mounting System is Site-Specifically Engineered to 170vult MPH wind-load pressures'; the Village's separate Wind Speeds page confirms Palm Beach County generally sits in the Wind-Borne Debris Region

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q27 Is a Specific Use Permit or Council approval ever required? Overlays & special cases

No specific-use permit or Council approval is published for ordinary residential rooftop PV; Wellington's Equestrian Overlay Zoning District (EOZD, adopted 2003) governs a separate ~9,000-acre Equestrian Preserve Area but is not invoked by the Village's own rooftop-solar checklist/affidavit route

Why the confidence is not higherSite searches for 'special use permit solar' and 'solar farm' returned only unrelated equestrian/floodplain hits and the Village's own solar checklist itself (no SUP/Council-approval item on it); this is an inference from the checklist's silence plus the EOZD's stated geographic scope, not an exhaustive LDR-text review (LDR text sits behind Municode, which disallows automated access)

Village FAQ (Equestrian Overlay Zoning District) checked 2026-09-12 https://www.wellingtonfl.gov/faq.aspx?qid=142

Q28 Is there a system-size cap on residential generation? Overlays & special cases

Nothing published by this authority.

Where we lookedVillage's solar permit packet, fee schedule, Building Code Amendments page, and site searches for 'kilowatt cap'/'system size' for a stated residential system-size (kW) cap; found only a design constraint (max 4 series strings per inverter), no kW ceiling on residential generation anywhere in the Village's own documents

https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Install 5 steps · 20 questions
  1. Build to the code editions actually in force here

    The NEC edition a jurisdiction enforces is often a cycle behind the newest one published, and local amendments sit on top of it. Rapid shutdown, conductor sizing and labelling all change between editions, so the edition in force is the first thing to establish, not the last.

    • Which NEC edition is in force? Not specified by name/edition in any of Wellington's own solar, electrical, or code-amendment documents — all of them cite only 'FBC 8th Edition (2023)' and never name an NFPA 70/NEC year. The solar checklist's busbar/breaker sizing table matches the format of NEC 705.12(B)(3)(2) (120% rule), consistent with either the 2020 or 2023 NEC, but the edition itself floats 45% · Village electrical permit checklist (rev. 5/24)
    • Which building code edition is in force? Florida Building Code, 8th Edition (2023), effective 31 December 2023 97% · Village department page (Building)
    • Which fire code edition is in force? Fire code sits with Palm Beach County Fire Rescue (PBCFR), not the Village. PBCFR's own document library carries a file titled 'Local-Amendments-FFPC-8th.pdf', which by title alone indicates the Florida Fire Prevention Code, 8th Edition is the currently-adopted base fire code for PBCFR's service area (which includes Wellington); the document's body text could not be retrieved (see method note) 60% · Palm Beach County Fire Rescue document index (filename only; PDF body unreachable)
    • Are there local amendments to any of the above? Yes — local amendments exist. The Village's own Building Code Amendments page lists 'Amendments to the Florida Building Code 2023 8th Edition' among the currently adopted code documents, alongside amendment sets for every FBC cycle back to 2010 78% · Village department page (Building Code Amendments)
    • What is the installation judged against? FBC 8th Edition (2023) plus Wellington's own local amendments to it, an edition-unspecified NEC, and (for fire-related aspects) the Florida Fire Prevention Code as enforced by Palm Beach County Fire Rescue 75% · Village department page (Building)
  2. Fire access, setbacks and pathways

    Ridge setbacks and roof access pathways are fire-service requirements and they constrain the array layout. They are the most common cause of a redesign after the fire department comments on a plan set.

    • What ridge setback and access pathways are required? The Village's own document states a general roof-edge setback of at least 3 feet for the array (not a separately labelled 'ridge setback'), plus the cantilever (≤6") and under-module gap (≤12") limits above; no distinct fire-access-pathway width/route requirement is stated in the Village's own solar document (that would sit with Palm Beach County Fire Rescue, whose local PV/rooftop-access standard could not be retrieved — see q31 method note) 70% · Village solar permit packet
  3. Rapid shutdown

    Which rapid-shutdown rule applies follows directly from the NEC edition in force, and the initiation device has to be at a location the fire service can reach and identify. This is inspected, and it is labelled.

    • Is rapid shutdown required, and to which NEC edition? Not named by the Village. Rapid shutdown (NEC 690.12) is not mentioned anywhere in Wellington's Solar PV Installation Checklist, Policies & Procedures, or Electrical checklist, and because Wellington never names an NEC edition (see q29), the applicable rapid-shutdown text and boundary (module-level vs array-boundary) cannot be pinned down from local documents alone 55% · site search with controls
  4. Labels and placards

    The NEC sets a baseline for permanent markings at the service equipment and the disconnecting means. On top of that, an authority may specify its own wording, and the utility may specify more again. Where any of them writes its own text, a generic off-the-shelf label set will not pass — this is the detail most often fixed on a return visit.

    • Which placards does this authority require at the service equipment? At the utility (FPL) level, two placards are required: at the interconnecting meter can, a warning placard reading 'WARNING / MULTI POWER SOURCES / ENTER SOURCES HERE / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'; at the DER/generation AC disconnect switch, 'GENERATION SYSTEM AC DISCONNECT / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. If a battery is installed, a third placard reading 'Battery storage utilized in this facility' must be permanently affixed to the meter enclosure. Wellington's own solar checklist does not add any placard of its own beyond requiring listed/labeled equipment generally 88% · FPL Electric Service Standards, rev. 10-30-25, Section XIII (OCR'd)
    • Does the authority specify placard wording of its own? No — Wellington's own documents specify no placard wording of their own; all specific placard wording found is FPL's (utility), not the Village's 68% · Village solar permit packet (absence)
    • Does it specify letter height, colour or material? Only the utility (FPL) specifies material: 'permanent and weatherproof/UV resistant placard with engraved letters.' No numeric letter-height or colour is given anywhere found (Village or utility); Wellington itself specifies nothing on letter height/colour/material 65% · FPL Electric Service Standards, rev. 10-30-25 (OCR'd)
    • Does the UTILITY specify placards beyond the AHJ's? Yes, extensively — FPL's Electric Service Standards Section XIII specifies meter-can and DER-disconnect placards, a battery-storage placard, disconnect-switch mechanical specs (visible-open, lockable, FPL 3/8" padlock shank, NEC 404.6(C) de-energized-blade requirement), and a 10-foot maximum separation from the meter socket, none of which are restated by the Village's own solar checklist 90% · FPL Electric Service Standards, rev. 10-30-25 (OCR'd)
    • Where must the labels be placed? At the interconnecting meter can, and at the DER/generation AC disconnect switch (which itself must sit within 10 feet of, and separate from but adjacent to, the meter socket, with no locked gate/door/fence in between) 88% · FPL Electric Service Standards, rev. 10-30-25 (OCR'd)
  5. Disconnect, storage and listed equipment

    Where the AC disconnect must sit relative to the meter is usually the utility's rule, not the building department's. Battery storage frequently carries its own permit, its own inspection and its own fire conditions.

    • Where must the AC disconnect be, relative to the meter? The AC/DER disconnect switch must be mounted separate from, but adjacent to, the FPL meter socket, within 10 feet of it, with no locked gates, doors or fences between the meter socket and the disconnect switch, and it must remain unrestricted and accessible to FPL personnel at all times 90% · FPL Electric Service Standards, rev. 10-30-25 (OCR'd)
    • Must equipment be on a specific approved list? Yes — all modules, inverters, combiner boxes, etc. must be identified, listed and labeled for use in PV systems, and the system must be 'FSEC Certified or ... designed by an appropriate licensed professional'; separately FPL requires UL 1741 SA / IEEE 1547-certified, NRTL-tested inverters for interconnection 85% · Village solar permit packet + FPL ESS
    • Are batteries permitted, and under what conditions? At utility level, FPL permits customer-side battery storage under conditions: UL 1741-certified (NRTL tested) or DC-coupled behind a UL 1741 device; a placard 'Battery storage utilized in this facility' permanently affixed to the meter enclosure; batteries paired with a renewable-generation system may not export to the grid; stand-alone backup batteries need no interconnection agreement but the customer bears all liability for back-feed. Wellington's own building/fire documents have NO published battery/ESS-specific permit item — the only 'Generator' packet found is fossil-fuel generators (no battery content), and searches for 'battery'/'energy storage' returned no relevant building-code hits 65% · FPL Electric Service Standards, rev. 10-30-25 (OCR'd) + Village site-search absence
    • Is there a separate ESS permit or inspection? No dedicated ESS permit type or inspection was found — the Village's Plan Review Time-Frame Chart and Building Forms & Applications list have no 'Battery'/'ESS'/'Energy Storage' row alongside the 'Solar Panel Installation' and 'Generator' rows that do exist 62% · Village Plan Review Time-Frame Chart (absence)
    • Is a ground mount treated as a structure? Not explicitly addressed — Wellington's only PV-specific checklist is written for ROOF-mounted arrays on a detached SFD or free-standing residential accessory structure (it discusses roof trusses, roof edges, roof surface gap); no ground-mount PV checklist or document exists on the Village's site. A ground-mount array would most likely be permitted through the general 'Detached Accessory Unit'/structural permit route and would be treated as a structure, but this is an inference, not a stated Village rule 55% · Village Building Forms & Applications list (absence) + inference
    • Is there a local rule on service upgrades or busbar sizing? Yes — Wellington's own Solar PV Installation Checklist reproduces a busbar-ampacity/main-breaker sizing table (matching NEC 705.12(B)(3)(2)'s 120% supply-side/load-side connection rule) as a required field the qualifier must select and certify, tying inverter output current directly to allowed busbar/breaker combinations 85% · Village solar permit packet
    • Is a specific mounting system or attachment spacing required? Yes, in detail: mounting/bracket manufacturer must carry product approval; attachment details engineered for ALL components/attachments in the wind-load path; roof must be framed with wood trusses/rafters at ≤24" on center; array set back ≥3' from all roof edges; array must not cantilever over perimeter anchors by more than 6"; gap under modules to roof surface must not exceed 12"; anchor-to-roof flashing/sealing method and products must be identified and listed for the use 92% · Village solar permit packet

20 questions answered against Village of Wellington’s own published documents

Q29 Which NEC edition is in force? Core Code editions in force

Not specified by name/edition in any of Wellington's own solar, electrical, or code-amendment documents — all of them cite only 'FBC 8th Edition (2023)' and never name an NFPA 70/NEC year. The solar checklist's busbar/breaker sizing table matches the format of NEC 705.12(B)(3)(2) (120% rule), consistent with either the 2020 or 2023 NEC, but the edition itself floats

Why the confidence is not higherChecked the Solar (Electric/Plumbing) Checklist, the Electrical & Low Voltage Checklist, and the Building Code Amendments page — none names an NEC edition (only FBC editions are listed by year); FPL's own Electric Service Standards also refer only to 'National Electric Code (NEC)' generically with no year

Village electrical permit checklist (rev. 5/24) checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/5072/Electrical-and-Low-Voltage_FINAL-es

Q30 Which building code edition is in force? Core Code editions in force

Florida Building Code, 8th Edition (2023), effective 31 December 2023

Why the confidence is not higherVerbatim from the Village's Building department page: 'The Florida Building Code, 8th Edition (2023) takes effect on December 31, 2023. Permit applications and plans submitted on or after December 31, 2023, must demonstrate compliance...'; every solar/electrical checklist masthead repeats 'FBC 8th Edition 2023'

Village department page (Building) checked 2026-09-12 https://www.wellingtonfl.gov/214/Building

Q31 Which fire code edition is in force? Code editions in force

Fire code sits with Palm Beach County Fire Rescue (PBCFR), not the Village. PBCFR's own document library carries a file titled 'Local-Amendments-FFPC-8th.pdf', which by title alone indicates the Florida Fire Prevention Code, 8th Edition is the currently-adopted base fire code for PBCFR's service area (which includes Wellington); the document's body text could not be retrieved (see method note)

Why the confidence is not higherPBCFR's CRRD Plan Review document list (discover.pbcgov.org/pbcfr/CRRD/Pages/Plan-Review.aspx) shows the filename 'Local-Amendments-FFPC-8th.pdf'; however direct downloads of PBCFR PDFs were reset by the server for both curl and urllib, headless-Chrome print-to-pdf produced a blank capture, and archive.org/Wayback returned 'Temporarily Offline' at time of check (12 Sep 2026) — an infrastructure failure, not an absence. Confidence capped because the body text (and hence confirmation beyond the filename) was unreachable

Palm Beach County Fire Rescue document index (filename only; PDF body unreachable) checked 2026-09-12 https://discover.pbcgov.org/pbcfr/CRRD/Pages/Plan-Review.aspx

Q32 Are there local amendments to any of the above? Core Code editions in force

Yes — local amendments exist. The Village's own Building Code Amendments page lists 'Amendments to the Florida Building Code 2023 8th Edition' among the currently adopted code documents, alongside amendment sets for every FBC cycle back to 2010

Why the confidence is not higherVerbatim list from wellingtonfl.gov/301/Building-Code-Amendments; the underlying ordinance text is hosted on library.municode.com, which disallows automated/ClaudeBot access in its robots.txt (confirmed: 'User-agent: ClaudeBot / Disallow: /'), so the amendment TEXT itself could not be quoted — only the Village's own listing that the amendment document exists

Village department page (Building Code Amendments) checked 2026-09-12 https://www.wellingtonfl.gov/301/Building-Code-Amendments

Q33 What is the installation judged against? Core Electrical

FBC 8th Edition (2023) plus Wellington's own local amendments to it, an edition-unspecified NEC, and (for fire-related aspects) the Florida Fire Prevention Code as enforced by Palm Beach County Fire Rescue

Why the confidence is not higherComposite of q29-q31/q32 answers above

Village department page (Building) checked 2026-09-12 https://www.wellingtonfl.gov/214/Building

Q34 Is there a local rule on service upgrades or busbar sizing? Electrical

Yes — Wellington's own Solar PV Installation Checklist reproduces a busbar-ampacity/main-breaker sizing table (matching NEC 705.12(B)(3)(2)'s 120% supply-side/load-side connection rule) as a required field the qualifier must select and certify, tying inverter output current directly to allowed busbar/breaker combinations

Why the confidence is not higherVerbatim table on the Village's Solar PV Installation Checklist Form, page 1 of 2

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q35 Is a specific mounting system or attachment spacing required? Structural & mounting

Yes, in detail: mounting/bracket manufacturer must carry product approval; attachment details engineered for ALL components/attachments in the wind-load path; roof must be framed with wood trusses/rafters at ≤24" on center; array set back ≥3' from all roof edges; array must not cantilever over perimeter anchors by more than 6"; gap under modules to roof surface must not exceed 12"; anchor-to-roof flashing/sealing method and products must be identified and listed for the use

Why the confidence is not higherVerbatim qualifier-certification bullet list on the Village's Policies & Procedures for Solar Photovoltaic document

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q36 What ridge setback and access pathways are required? Core Fire pathways & setbacks

The Village's own document states a general roof-edge setback of at least 3 feet for the array (not a separately labelled 'ridge setback'), plus the cantilever (≤6") and under-module gap (≤12") limits above; no distinct fire-access-pathway width/route requirement is stated in the Village's own solar document (that would sit with Palm Beach County Fire Rescue, whose local PV/rooftop-access standard could not be retrieved — see q31 method note)

Why the confidence is not higherThe 3' figure is a generic 'set back from all roof edges' rule in Wellington's Policies & Procedures for Solar PV, not phrased as a fire-code access pathway; Palm Beach Fire Rescue's own fire-code amendments (which would carry any NFPA 1/rooftop-access-pathway specifics) were unreachable at time of check

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q37 Is rapid shutdown required, and to which NEC edition? Core Rapid shutdown

Not named by the Village. Rapid shutdown (NEC 690.12) is not mentioned anywhere in Wellington's Solar PV Installation Checklist, Policies & Procedures, or Electrical checklist, and because Wellington never names an NEC edition (see q29), the applicable rapid-shutdown text and boundary (module-level vs array-boundary) cannot be pinned down from local documents alone

Why the confidence is not higherSite search for 'rapid shutdown' returned 2 hits, both false positives (an equestrian-crossing solar-flasher document and an unrelated market study) — controls in the same session: positive 'electrical' = 10, fabricated 'zzqqx' = 0, so the search was functioning and this is a genuine absence

site search with controls checked 2026-09-12 https://www.wellingtonfl.gov/Search?searchPhrase=rapid%20shutdown

Q38 Which placards does this authority require at the service equipment? Core Labels Signage & labelling

At the utility (FPL) level, two placards are required: at the interconnecting meter can, a warning placard reading 'WARNING / MULTI POWER SOURCES / ENTER SOURCES HERE / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'; at the DER/generation AC disconnect switch, 'GENERATION SYSTEM AC DISCONNECT / RATED AC OUTPUT CURRENT ** AMPS / NOMINAL OPERATING VOLTAGE ** VOLTS'. If a battery is installed, a third placard reading 'Battery storage utilized in this facility' must be permanently affixed to the meter enclosure. Wellington's own solar checklist does not add any placard of its own beyond requiring listed/labeled equipment generally

Why the confidence is not higherOCR'd directly from FPL's Electric Service Standards (rev. 10-30-25), Section XIII 'Distributed Generation', pages 162 and 170 of 173 — this section uses an embedded Type 3 font that defeats pdftotext (garbled Caesar-shift-like output), so pdftoppm+tesseract OCR was used on those specific pages per method

FPL Electric Service Standards, rev. 10-30-25, Section XIII (OCR'd) checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Q39 Does the authority specify placard wording of its own? Core Labels Signage & labelling

No — Wellington's own documents specify no placard wording of their own; all specific placard wording found is FPL's (utility), not the Village's

Why the confidence is not higherAbsence inferred from a full read of Wellington's Solar PV Installation Checklist and Policies & Procedures document, which discuss labeling only in the general sense ('all modules, inverters, combiner boxes ... identified, listed and labeled for use in PV systems') and never quote specific placard text

Village solar permit packet (absence) checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q40 Does it specify letter height, colour or material? Core Labels Signage & labelling

Only the utility (FPL) specifies material: 'permanent and weatherproof/UV resistant placard with engraved letters.' No numeric letter-height or colour is given anywhere found (Village or utility); Wellington itself specifies nothing on letter height/colour/material

Why the confidence is not higherVerbatim from FPL Electric Service Standards Section XIII (OCR'd, page 162/169); no Village document was found addressing placard material/height/colour

FPL Electric Service Standards, rev. 10-30-25 (OCR'd) checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Q41 Is a site plan / facility map placard required, and what must it show? Core Labels Signage & labelling

Nothing published by this authority.

Where we lookedVillage's Solar PV Installation Checklist and Policies & Procedures for Solar PV pages for a site-plan/facility-map placard requirement (NEC 705.10-style); the document discusses equipment listing/labeling generally but never a facility map/placard, and no separate document addressing this was found on the Village's site

https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q42 Does the UTILITY specify placards beyond the AHJ's? Core Labels Signage & labelling

Yes, extensively — FPL's Electric Service Standards Section XIII specifies meter-can and DER-disconnect placards, a battery-storage placard, disconnect-switch mechanical specs (visible-open, lockable, FPL 3/8" padlock shank, NEC 404.6(C) de-energized-blade requirement), and a 10-foot maximum separation from the meter socket, none of which are restated by the Village's own solar checklist

Why the confidence is not higherSee q38/q40/q48 sourcing

FPL Electric Service Standards, rev. 10-30-25 (OCR'd) checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Q43 Where must the labels be placed? Core Labels Signage & labelling

At the interconnecting meter can, and at the DER/generation AC disconnect switch (which itself must sit within 10 feet of, and separate from but adjacent to, the meter socket, with no locked gate/door/fence in between)

Why the confidence is not higherVerbatim from FPL Electric Service Standards Section XIII.A.4 and A.6 (OCR'd)

FPL Electric Service Standards, rev. 10-30-25 (OCR'd) checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Q44 Must equipment be on a specific approved list? Equipment listing

Yes — all modules, inverters, combiner boxes, etc. must be identified, listed and labeled for use in PV systems, and the system must be 'FSEC Certified or ... designed by an appropriate licensed professional'; separately FPL requires UL 1741 SA / IEEE 1547-certified, NRTL-tested inverters for interconnection

Why the confidence is not higherVillage's Policies & Procedures for Solar PV (qualifier-certification bullets) plus FPL Electric Service Standards Section XIII.A.1 (OCR'd)

Village solar permit packet + FPL ESS checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q45 Are batteries permitted, and under what conditions? Core Battery / ESS

At utility level, FPL permits customer-side battery storage under conditions: UL 1741-certified (NRTL tested) or DC-coupled behind a UL 1741 device; a placard 'Battery storage utilized in this facility' permanently affixed to the meter enclosure; batteries paired with a renewable-generation system may not export to the grid; stand-alone backup batteries need no interconnection agreement but the customer bears all liability for back-feed. Wellington's own building/fire documents have NO published battery/ESS-specific permit item — the only 'Generator' packet found is fossil-fuel generators (no battery content), and searches for 'battery'/'energy storage' returned no relevant building-code hits

Why the confidence is not higherFPL text OCR'd from Electric Service Standards Section XIII.D, page 170/173; Wellington absence proven with controls in the same session: 'battery' and 'energy storage' searches returned only unrelated hits (equestrian/floodplain/waste pages), fabricated control 'zzqqx' = 0, positive control 'electrical' = 10

FPL Electric Service Standards, rev. 10-30-25 (OCR'd) + Village site-search absence checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Q46 Is there a separate ESS permit or inspection? Battery / ESS

No dedicated ESS permit type or inspection was found — the Village's Plan Review Time-Frame Chart and Building Forms & Applications list have no 'Battery'/'ESS'/'Energy Storage' row alongside the 'Solar Panel Installation' and 'Generator' rows that do exist

Why the confidence is not higherAbsence inferred from the complete Plan Review Time-Frame Chart and Building Forms & Applications page, both fully enumerated in this session; no separate ESS line exists on either

Village Plan Review Time-Frame Chart (absence) checked 2026-09-12 https://www.wellingtonfl.gov/228/Plan-Review-Time-Frame-Chart

Q47 Is a ground mount treated as a structure? Core Ground mount

Not explicitly addressed — Wellington's only PV-specific checklist is written for ROOF-mounted arrays on a detached SFD or free-standing residential accessory structure (it discusses roof trusses, roof edges, roof surface gap); no ground-mount PV checklist or document exists on the Village's site. A ground-mount array would most likely be permitted through the general 'Detached Accessory Unit'/structural permit route and would be treated as a structure, but this is an inference, not a stated Village rule

Why the confidence is not higherConfirmed absence: searches for 'ground mount solar' returned only the roof-oriented solar packet and unrelated hits (equestrian, curb details); the Village's Building Forms & Applications list (fully enumerated) has no ground-mount PV item

Village Building Forms & Applications list (absence) + inference checked 2026-09-12 https://www.wellingtonfl.gov/1011/Building-Forms-Applications

Q48 Where must the AC disconnect be, relative to the meter? Core Utility equipment

The AC/DER disconnect switch must be mounted separate from, but adjacent to, the FPL meter socket, within 10 feet of it, with no locked gates, doors or fences between the meter socket and the disconnect switch, and it must remain unrestricted and accessible to FPL personnel at all times

Why the confidence is not higherVerbatim, FPL Electric Service Standards Section XIII.A.4 and the standalone 'DER Disconnect Switch Utility Requirements' page (both OCR'd)

FPL Electric Service Standards, rev. 10-30-25 (OCR'd) checked 2026-09-12 https://www.fpl.com/partner/pdf/electric-service-standards.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

Inspection 5 steps · 14 questions
  1. Book it

    Booking is a portal, a phone call or an email depending on the authority, and the notice required is rarely zero. Book before the work is finished rather than after — the lead time, not the work, is usually what sets the date.

    • How is an inspection booked? Portal (Tyler EnerGov Self Service) is the primary route; phone (561-753-2430) is used to confirm/inquire about time-of-arrival the morning of an inspection 82% · Village department page (Building Inspections)
    • How much notice is required? No fixed 'X business days' figure is published; inspections 'may be scheduled 24 hours a day for any business day or up to 5pm for the following business day' — i.e., a request made by 5:00 pm can be booked for the next business day 75% · Village department page (Building Inspections)
    • Are same-day or AM/PM windows offered? No fixed AM/PM window is offered; instead, an approximate time of arrival is emailed to the applicant once the inspector routes their day, and the applicant can call between 7:00-7:30 a.m. the morning of the inspection if that email doesn't arrive 78% · Village department page (Building Inspections)
  2. Know who turns up

    Some authorities inspect their own solar work; some delegate it, and a few do not inspect the PV equipment itself at all. Who is coming determines what they will look at.

    • Does this AHJ perform its own final solar inspection? Yes — the Village performs its own final building/electrical solar inspections using its own named inspectors (e.g., David Bardin, Building Inspector/Electrical); a private-provider alternative is separately available under FS 553.791/553.7913 if the applicant elects it 82% · Village department page (Building Inspections)
    • If delegated, to whom? Fire-related inspection is delegated to Palm Beach County Fire Rescue (Jeffrey Miller listed as the PBC Fire Inspector on the Village's own Building Inspections contact page); the private-provider inspection option (if elected by the applicant) can be delegated to any FS 553.791-qualified private provider firm the applicant retains, subject to Wellington's 12%/28%/40% fee-credit schedule for that route 80% · Village department page (Building Inspections) + Fee Schedule
  3. Work the stages in order

    A rough-in or mid-roof inspection, where one is required, has to happen before the work it covers is closed up. Missing a stage means opening something back up, and it is the most expensive kind of correction.

    • Which inspections are required, and in what order? A single combined 'In-Progress' site visit covering both the structural in-progress inspection and the electrical rough inspection (contractor must be present and provide access for both), followed by a Final inspection to close the permit 82% · Village solar permit packet, Policies & Procedures page
    • Is a rough-in or mid-roof inspection required? Yes — a combined structural in-progress / electrical rough inspection is explicitly required before final sign-off 90% · Village solar permit packet, Policies & Procedures page
  4. Have the paperwork on site

    The approved plan set, the permit, and the equipment listings should be on site and reachable. Inspectors routinely verify that installed equipment matches what was approved, and that the labels are the ones the plan set promised.

    • Is there a published inspection checklist? Yes — the 'Solar PV (Photovoltaic) Installation Checklist Form' itself is exactly that: a published, form-based inspection/compliance checklist covering structural and electrical items with a qualifier sign-off 90% · Village solar permit packet
    • What must be on site at inspection? The printed permit card and one printed set of the approved plans (legible size, printed in color if the plans contain markups) available in a Permit Box or on the job site; the recorded Notice of Commencement (if the value triggers Fla. Stat. Ch. 713) must be posted on the job site before the first inspection; any supplemental inspection paperwork (e.g. photographic evidence, per the solar Policies & Procedures) should be pre-uploaded to the 'Inspection Documentation Folder' in ProjectDox 82% · Village department pages (Guide to Permitting + Building Inspections)
    • Does the inspector verify labels and listings? Yes, inferentially — the Qualifier must certify at permitting that 'all modules, inverters, combiner boxes, etc. are identified, listed and labeled for use in PV systems,' and the in-progress inspection is where this would be field-verified alongside the structural/electrical rough work 60% · Village solar permit packet
  5. Sign-off, and permission to operate

    Passing gives you a final or an equivalent sign-off. That is not the same as permission to operate: PTO comes from the utility, and who tells the utility the inspection passed varies. A system left switched off for weeks is usually waiting on this handover.

    • What is issued on pass? Final (a passed final inspection closes out the permit on an existing dwelling retrofit); a Certificate of Occupancy/Completion is a separate, distinct request used for new construction or completion agreements, not the ordinary route for a rooftop PV retrofit on an existing home 58% · Village Building Forms & Applications list (inference)
    • Who notifies the utility for PTO? Installer/Customer — FPL's tariff places the notification duty on the Customer, who must provide FPL with the local Building Code Official's inspection/approval certification and must notify FPL at least 10 calendar days before initially placing the system in service; FPL does not initiate this itself and the AHJ does not push it to FPL 78% · FPL PSC-filed electric tariff, Section 9, eff. 1 Jan 2026
    • Is there a re-inspection fee? $60 (1st re-inspection), $120 (2nd, same type), $180 (3rd, same type), $300 (4th, same type); a contractor-requested partial inspection is also $60 95% · Village Permit Fee Schedule (live page)
    • How are corrections issued and cleared? Via ProjectDox: the applicant is emailed a corrections notice, logs in and accepts the 'Applicant Resubmit' task, reviews 'Review Comments' (must respond in writing to each comment marked 'unresolved'), uploads revised or newly-versioned files as directed, then submits the task back for review 85% · Village department page (Guide to Permitting)

14 questions answered against Village of Wellington’s own published documents

Q49 How is an inspection booked? Core Booking & scheduling

Portal (Tyler EnerGov Self Service) is the primary route; phone (561-753-2430) is used to confirm/inquire about time-of-arrival the morning of an inspection

Why the confidence is not higherVillage's Building Inspections page: 'Schedule your next inspection here' linking to the EnerGov Self-Service app; separately, 'contact your inspector between 7:00 and 7:30 a.m. ... by dialing 561-753-2430'

Village department page (Building Inspections) checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q50 How much notice is required? Core Booking & scheduling

No fixed 'X business days' figure is published; inspections 'may be scheduled 24 hours a day for any business day or up to 5pm for the following business day' — i.e., a request made by 5:00 pm can be booked for the next business day

Why the confidence is not higherVerbatim from the Village's Building Inspections page

Village department page (Building Inspections) checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q51 Are same-day or AM/PM windows offered? Booking & scheduling

No fixed AM/PM window is offered; instead, an approximate time of arrival is emailed to the applicant once the inspector routes their day, and the applicant can call between 7:00-7:30 a.m. the morning of the inspection if that email doesn't arrive

Why the confidence is not higherVerbatim from the Village's Building Inspections page

Village department page (Building Inspections) checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q52 Does this AHJ perform its own final solar inspection? Core Who inspects

Yes — the Village performs its own final building/electrical solar inspections using its own named inspectors (e.g., David Bardin, Building Inspector/Electrical); a private-provider alternative is separately available under FS 553.791/553.7913 if the applicant elects it

Why the confidence is not higherVillage's Building Inspections contact directory names in-house structural/electrical/mechanical inspectors; the same page separately describes the private-provider notice procedure as an opt-in alternative, not the default

Village department page (Building Inspections) checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q53 If delegated, to whom? Core Who inspects

Fire-related inspection is delegated to Palm Beach County Fire Rescue (Jeffrey Miller listed as the PBC Fire Inspector on the Village's own Building Inspections contact page); the private-provider inspection option (if elected by the applicant) can be delegated to any FS 553.791-qualified private provider firm the applicant retains, subject to Wellington's 12%/28%/40% fee-credit schedule for that route

Why the confidence is not higherVillage's Building Inspections page contact list; Fee Schedule item 30 'Private Provider Credits'

Village department page (Building Inspections) + Fee Schedule checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q54 Which inspections are required, and in what order? Core Stages & sequence

A single combined 'In-Progress' site visit covering both the structural in-progress inspection and the electrical rough inspection (contractor must be present and provide access for both), followed by a Final inspection to close the permit

Why the confidence is not higherVerbatim from the Village's Policies & Procedures for Solar PV: 'Contractor to request In-Progress inspection with Building Department ... Contractor to be on site during In-Progress Inspection and provide access for BOTH the structural in-progress as well as the Electrical Rough inspection'; a terminal Final inspection is inferred from the general Wellington permit-closure structure (fee schedule's CO/permit-renewal language) rather than stated by name on the solar document itself

Village solar permit packet, Policies & Procedures page checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q55 Is a rough-in or mid-roof inspection required? Stages & sequence

Yes — a combined structural in-progress / electrical rough inspection is explicitly required before final sign-off

Why the confidence is not higherSame verbatim source as q54

Village solar permit packet, Policies & Procedures page checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q56 Does the inspector verify labels and listings? Core What is checked

Yes, inferentially — the Qualifier must certify at permitting that 'all modules, inverters, combiner boxes, etc. are identified, listed and labeled for use in PV systems,' and the in-progress inspection is where this would be field-verified alongside the structural/electrical rough work

Why the confidence is not higherInference — the Village's document does not use the word 'inspector verifies' explicitly; it is the qualifier's certification obligation, checked in the ordinary course of the in-progress inspection

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q57 Is there a published inspection checklist? Core What is checked

Yes — the 'Solar PV (Photovoltaic) Installation Checklist Form' itself is exactly that: a published, form-based inspection/compliance checklist covering structural and electrical items with a qualifier sign-off

Why the confidence is not higherSame solar permit packet, page headed 'SOLAR PV (PHOTOVOLTAIC) INSTALLATION CHECKLIST FORM'

Village solar permit packet checked 2026-09-12 https://www.wellingtonfl.gov/DocumentCenter/View/4958/Solar-Panel_FINAL-es

Q58 What must be on site at inspection? Core Documents on site

The printed permit card and one printed set of the approved plans (legible size, printed in color if the plans contain markups) available in a Permit Box or on the job site; the recorded Notice of Commencement (if the value triggers Fla. Stat. Ch. 713) must be posted on the job site before the first inspection; any supplemental inspection paperwork (e.g. photographic evidence, per the solar Policies & Procedures) should be pre-uploaded to the 'Inspection Documentation Folder' in ProjectDox

Why the confidence is not higherComposite from the Village's Guide to Permitting (Step 5, printing requirements), the bundled Notice of Commencement form's warning language, and the Building Inspections page's 'Inspection Documents' section

Village department pages (Guide to Permitting + Building Inspections) checked 2026-09-12 https://www.wellingtonfl.gov/249/Building-Inspections

Q59 Is there a re-inspection fee? Corrections & re-inspection

$60 (1st re-inspection), $120 (2nd, same type), $180 (3rd, same type), $300 (4th, same type); a contractor-requested partial inspection is also $60

Why the confidence is not higherVerbatim, Permit Fee Schedule item 6 'Re-Inspection Fee'

Village Permit Fee Schedule (live page) checked 2026-09-12 https://www.wellingtonfl.gov/282/permit-fee-schedule

Q60 How are corrections issued and cleared? Corrections & re-inspection

Via ProjectDox: the applicant is emailed a corrections notice, logs in and accepts the 'Applicant Resubmit' task, reviews 'Review Comments' (must respond in writing to each comment marked 'unresolved'), uploads revised or newly-versioned files as directed, then submits the task back for review

Why the confidence is not higherVerbatim from the Village's Guide to Permitting, Step 3 'Corrections Required'

Village department page (Guide to Permitting) checked 2026-09-12 https://www.wellingtonfl.gov/269/Guide-to-Permitting

Q61 What is issued on pass? Core Final sign-off & PTO

Final (a passed final inspection closes out the permit on an existing dwelling retrofit); a Certificate of Occupancy/Completion is a separate, distinct request used for new construction or completion agreements, not the ordinary route for a rooftop PV retrofit on an existing home

Why the confidence is not higherInference from the existence of a separate 'Request for Certificate of Occupancy/Completion' form (distinct from the ordinary building-permit closure) and the fee schedule's CO-fee section, which is written around new/altered occupancy rather than PV retrofits specifically; no document states 'Final' by name for solar

Village Building Forms & Applications list (inference) checked 2026-09-12 https://www.wellingtonfl.gov/1011/Building-Forms-Applications

Q62 Who notifies the utility for PTO? Core Final sign-off & PTO

Installer/Customer — FPL's tariff places the notification duty on the Customer, who must provide FPL with the local Building Code Official's inspection/approval certification and must notify FPL at least 10 calendar days before initially placing the system in service; FPL does not initiate this itself and the AHJ does not push it to FPL

Why the confidence is not higherVerbatim, FPL PSC-filed tariff Sheets 9.050-9.051, §§3.4-3.5

FPL PSC-filed electric tariff, Section 9, eff. 1 Jan 2026 checked 2026-09-12 https://www.fpl.com/content/dam/fplgp/us/en/rates/pdf/electric-tariff-section9.pdf

Lines marked with a percentage were read off this authority’s own published documents. Unmarked guidance is general good practice, not this jurisdiction’s rule — always confirm against the authority before you submit.

No change record for this authority yet. Values arrive here as they are researched, and each one is dated.

Labels & placards for this authority

Wording 68%

No — Wellington's own documents specify no placard wording of their own; all specific placard wording found is FPL's (utility), not the Village's

Size, colour & material 65%

Only the utility (FPL) specifies material: 'permanent and weatherproof/UV resistant placard with engraved letters.' No numeric letter-height or colour is given anywhere found (Village or utility); Wellington itself specifies nothing on letter height/colour/material

Where they go 88%

At the interconnecting meter can, and at the DER/generation AC disconnect switch (which itself must sit within 10 feet of, and separate from but adjacent to, the meter socket, with no locked gate/door/fence in between)

What the utility wants on top 90%

Yes, extensively — FPL's Electric Service Standards Section XIII specifies meter-can and DER-disconnect placards, a battery-storage placard, disconnect-switch mechanical specs (visible-open, lockable, FPL 3/8" padlock shank, NEC 404.6(C) de-energized-blade requirement), and a 10-foot maximum separation from the meter socket, none of which are restated by the Village's own solar checklist

Each figure above is sourced and dated in the full answer set below (questions 38–43). Where an authority’s own published sheet is older than the code it has adopted, the answer says so.

Their website
Solar Requirements
Average approval time — application to PTO

From the CPUC interconnection record. Bars show the average days taken each year; a year with no recorded projects is left blank rather than drawn as zero.